HomeMy WebLinkAbout1996-04-04 City CouncilTO:
City of Palo Alto
City Manager’s Repor
HONORABLE CITY COUNCIL
FROM:CITY MANAGER DEPARTMENT: Public Works
DATE:
SUBJECT:
April 4, 1996 CMR:216:96
Construction Impact of New Project at 424 University Avenue.
REQUEST
This is an informational report on a private development project located at 424 University
Avenue. The purpose of the report is to make Council aware of the construction impacts
this project will have on University Avenue.
POLICY IMPLICATIONS
This informational report does not contain any changes to existing City policies.
EXECUTIVE SUMMARY
On September 21, 1995 the Architectural Review Board (ARB) approved, with
conditions, a private development project for a new 18,497 square foot retail and
commercial building at 424 University Avenue. The project will involve demolishing the
existing seismically deficient building and constructing a new four story structure on the
site. One of the development conditions requires the submittal of a logistics plan to
address construction impacts and corresponding measures to eliminate or minimize these
impacts.
A critical element of the logistics plan deals with access to the site for demolition and
construction activities. The owner initially submitted a plan to stage demolition and
construction activities using access from the rear of the site. However, in order to provide
such access, it was necessary to obtain an agreement with Union Bank, the owner of the
property adjacent to the rear of the 424 University Avenue site (See Exhibit A). To date,
Bank representatives and the owners of 424 University Avenue have been unable reach
such an agreement. Although 424 University Avenue has an existing 10 foot wide
CMR:216:96 Page 1 of 4
ingress/egress access easement across Union Bank’s parking lot, it is legally questionable
as to whether it can be used for construction access activities. In any event, the easement
is neither large enough nor in a suitable location for accommodating construction storage
and circulation.
Having failed to reach agreement with the Bank after several weeks of negotiations, the
owner of the 424 University Avenue property recently requested approval of a street work
permit in order to proceed with construction as soon as possible. As a necessary second
choice to the rear access, the Public Works Department is proceeding to issue the street
permit with construction access from University Avenue, the only other option available.
If for some reason the parties are able to reach agreement on the easements necessary to
construct the building from the side and rear of 424 University Avenue, City Council will
be advised.
Following is a description of the work under the street permit which is divided into three
phases:
Demolition and Excavation Phase (5-6 weeks)
Trucks will remove demolition and excavated material from the site at the rate of
3-4 trucks per day. These occurrences should not detain traffic or pedestrians on
University Avenue for more than five minutes at a time while the truck driver backs
a vehicle into the building floor area to accept debris and spoils. (The process will
be reversed upon leaving the site.) Pedestrians will be routed through a protected
canopy area at all times except when trucks are entering or leaving the site. Four
parking spaces will be used by the contractor during this phase.
Concrete Pouring Phase (approximately 1 week)
During this phase, approximately 400 cubic yards of concrete will be poured for the
foundation and floors, utilizing concrete delivery trucks at the rate of 15 per day.
Trucks will be located within the four space parking lane adjacent to the curb.
Pedestrians will continue to be routed within a canopy area, along a portion of the
sidewalk area, similar to demolition and excavation phase.
Steel Erection Phase (8 weeks)
Initially, a mobile crane will be located within the foot-print area of the new
building and the structure will be erected from this position. Steel will be unloaded
from a delivery trailer parked on University Avenue. For safety reasons,
CMR:216:96 Page 2 of 4
pedestrians will be temporarily rerouted across the street, but only during the three
to four hour unloading period. During the unloading, traffic on University Avenue
will be rerouted toward the north side of the street. Parking spaces on the north
side of the street will be removed to accommodate the realigned traffic flow.
Unloading of the steel will be scheduled between 5:00a.m. and 9:00a.m. For the
remainder of the time, pedestrians will utilize the canopy area located within the
existing sidewalk area.
Later during the steel erection phase of the project, the crane will be located clear
of the building, and a portion of the machine will extend into the existing travel
lanes. This new crane position will permit the facade of the building to be
constructed. As before, the sidewalk area will be closed between the hours of
5:00a.m. and 9:00a.m. during the actual unloading of the steel, and pedestrians will
be rerouted to the opposite side of the street. Steel will be stockpiled onto the
sidewalk area. At this point, pedestrians will return to the south side of University
Avenue and be rerouted safely around the crane. During the entire two to three day
unloading and steel erection process, traffic on University Avenue will be
temporarily rerouted toward the north side of University Avenue. Existing parking
spaces on the north side of the street will be removed in order to accommodate the
realigned traffic flow of University Avenue. At night, parking and the pedestrian
canopy will be restored. The contractor will be required to follow a City approved
traffic control plan which regulates the location of signs, cones and flagpersons.
Work is expected to start in early April and finish by December 1996. The Public Works
Department will require the contractor to restore the sidewalk area before the start of the
Christmas shopping season and maintain a six foot wide pedestrian canopy along the
frontage. The contractor advises that the front of the building will be substantially
complete by then and offsite traffic impacts, such as rerouting traffic flow will not be
required. Merchants nearby will be notified periodically by way of a bulletin, informing
them of ongoing construction activities.
FISCAL IMPACT
There is no fiscal impact to the City. The contractor is required to post a bond for
$10,000 to protect the City against any accidental damage to City improvements such as
curb and gutter, sidewalks,and pavement.
CMR:216:96 Page 3 of 4
ENVIRONMENTAL ASSESSMENT
An environmental assessment is not required for this informational report.
ATTACHMENT
Plan of site
PREPARED BY: George Bagdon, Assistant Director of Public Works
DEPARTMENT HEAD REVIEW:
CITY MANAGER APPROVAL:
GLENN S. ROBERTS
Director of Public Works
as~~r
cc: Susan Frank, Chamber of Commerce
CMR:216:96 Page 4 of 4
Exhibit
UNIVERSITY AVENUE
!/////I /I /!/I II/I IIII///I /I I//II/
#400
Union Bank
A
SCALE1 0 1 2 3 4 5
Feet