HomeMy WebLinkAbout1996-03-14 City CouncilCity of Palo Alto City Manager’s Report TO:HONORABLE CITY COUNCIL ATTENTION: FINANCE COMMITTEE FROM:CITY MANAGER DEPARTMENT: ADMINISTRATIVE SERVICES DATE:MARCH 14, 1996 CMR:174:96 SUBJECT:MIDYEAR CAPITAL IMPROVEMENT PROJECTS STATUS REPORT REQUEST This is an informational report and no Council action is required. EXECUTIVE SUMMARY This report provides an update on the status of each of the City’s Capital Improvement Program (CIP) projects as of midyear 1995-96. Project managers have summarized the status of the capital projects for which they were responsible, placing an emphasis on any issues which might cause a change in the scope or timing of the projects. With the City’s aging infrastructure and the resulting increase in CIP funding requests, the midyear status report will keep Council abreast of the current progress of all open projects and aid in the decision to fund new priorities. All projects outstanding as of the beginning of fiscal year 1995-96 are summarized in this report by fund. Within each fund, the projects are ordered by project number, in order to allow quick cross-referencing to the CIP Budget document. In prior years, for the General Fund, this report contained accumulated budget and actual information, from the inception of each project through the midyear reporting date. This year the report has been changed to show only the available, or remaining budget for each project at the beginning of the fiscal year, compared to the actual expenditures for the first two quarters of 1995-96. With this change, Council will have meaningful information about the actual financial status of each CIP project. CMR:174:96 Page 1 of 2 PREPARED BY: Jennifer Chang, Senior Accountant DEPARTMENT HEAD APPROVAL: CITY MANAGER APPROVAL: CC: rda Harrison Deputy City Manager, Administrative Fleming Manager CMR:174:96 Page 2 of 2 CAPITAL IMPROVEMENT PROGRAM (CIP) PROJECT STATUS REPORT DECEMBER 1995 GENERAL FUND 18508 -18514 pUBLIC BUILDING STRUCTURAL IMPROVEMENTS This project provides for the design and construction of structural improvements to public buildings. The structural retrofit of the Senior Center will be completed by summer of 1996. A seismic study of the Municipal Service Center (MSC) is expected to start in spring 1996 and be completed within six months. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $1,888,615 $ 665,904 FIRST QUARTER 1997-98 18614 FINANCIAL DATABASE UPGRADE This project provides for upgrades to the City’s automated financial system. Enhancements to the Stores/Inventory System and the Payroll/Human Resources System, as well as a new Cash Receipting System with integration into the City’s Integrated Financial Accounting System (’IFAS) are anticipated in t 995-96. The acquisition of the PayrollfHuman Resources System is a separate CIP project, but enhancements and the interface with IFAS are included within the scope of this project. Bar coding of warehouse inventory is also anticipated. AVAILABLE BUDGET AS OF JULY 1, 1995 $ 347,855 ACTUAL EXPENSE FOR 1995-96 $801 EXPECTED COMPLETION ONGOING 18617 ART IN PUBLIC....pL, .-.2ES This project supports commissioning or purchasing works by living artists for interior or exterior public spaces and obtaining professional consultants to assist the Public Art Commission in their efforts. The installation of the Seyed Alavi sculpture in the Civic Center lobby has been completed and the Public Art Commission is preparing a public reception for the artist. The Greg Brown mural Roofhoppers II, located at 300 Hamilton Avenue is complete; Rooflaoppers I was destroyed with the renovation of 281 University Avenue. Presently, the Public Art Commission is holding a competition for artists for the gateway at California Avenue and E1 Camino Real. The artist who is selected will be expected to complete the project by September 1996. The Public Art Commission is also planning, along with the Architectural Review Board, a forum that will address the nature of architectural design projects and the integration of public art in such projects. AVAILABLE BUDGET AS OF JULY 1, 1995 $47,292 ACTUAL EXPENSE FOR 1995-96 $3,500 EXPECTED COMPLETION ONGOING 18812 INFORMATION SYSTEM ..DEVELOPMENT This project supports the acquisition of computer hardware required for the successful processing of the City’s centralized applications. The funds will be used to buy disks and memory for the HP9000 servers. The project will be completed by the end of the fiscal year. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $ 10,870 $ 0 4TH QUARTER 1995-96 18822,,,,,~EOG~HIC INFORMATION SYSTEM The purpose of this multi-year project is to create a computerized map of the City’s infrastructure. The aerial base map of the City has been completed and all City utility information will be digitized into the computer by June 1996. Purchase of customer service- oriented software for accessing the orthophoto, the Pavement Maintenance Management System and utility information will be purchased by summer, after coordination with the affected departments. AVAILABLE BUDGET AS OF JULY 1, 1995 $252,090 ACTUAL EXPENSE FOR 1995-96 $ 35,462 EXPECTED COMPLETION ONGOING 2 18,~,03 SIDEWALK REPAI~:, This project provides for the repair and replacement of City sidewalks and the construction of curb ramps to comply with Americans with Disabilities Act (ADA) requirements. Bids for sidewalk replacements in District No. 23 are currently under evaluation and construction will occur during the spring and early summer of 1996. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $1,020,124 $ 338,2O3 FIRST QUARTER 1996-97 .18~...!.6 FII~ STATION......DORMITORY MODIFICATION This project provides for the remodeling of the dormitory and locker room facilities at five fire stations to provide private facilities for male and female ftrefighters. The remodeling of all five stations is complete. A contract has been approved to fabricate and install cabinets for Fire Station No. 2. The cabinet work is expected to be completed in 1995-96. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $ 161,321 $ 3,284 3P~ QUARTER 1995-96 18918 HARBOR IMPROVEMENTS Three elements of the Harbor Improvement Project were completed at the end of 1993. They included a 4.5-acre marsh created along Harbor Point, a new sailing station for hand-carried craft near Mayfield Slough, and the restoration of the harbor master’s cottage to its original Spanish Colonial Revival style. Other improvements included the installation of new paths, picnic areas and landscaping. Funding for restoration of the remaining seven-acre marsh will be proposed with the 1997-98 budget. Staffis evaluating the possibility of San Mateo County Transportation Authority paying for the restoration, as a mitigation to a freeway project. AVAILABLE BUDGET AS OF JULY 1, 1995 $492,410 ACTUAL EXPENSE FOR 1995-96 $455 EXPECTED COMPLETION FY 1997-98 18971,18670,19610 STILE_, MAINTEN~CE This project provides for the annual resurfacing of streets, identified by the City’s Pavement Maintenance Management System as needing improvement. The 1995 project was completed and included resurfacing approximately 22 miles of streets and the construction of bike lanes on Los Robles Avenue. A street condition survey of all the streets will be completed in the spring of 1996, and information from the survey will be used to determine future work. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 - EXPECTED COMPLETION $3,818,557 $1,230,986 ONGOING 19001, 18803 AIRPORT TANK REMOVAL AND CLEAN UP Ground contamination was found at the tank removal site at 1901 Embarcadero Road (Palo Alto Airport). The extent of contamination was identified and a risk analysis was submitted to the Santa Clara Valley Water District for review. A favorable response for site closure is expected from the District in mid 1996-97. AVAILABLE BUDGET AS OF JULY 1, 1995 $581,685 ACTUAL EXPENSE FOR 1995-96 $37 EXPECTED COMPLETION ONGOING 19009 FINANCE VAULT REMODELING This project provided for the remodeling of the Finance vault area located on the second floor of the Civic Center. This project is complete. AVAILABLE BUDGET AS OF JULY 1, 1995 $23,914 ACTUAL EXPENSE FOR 1995-96 $3,873 EXPECTED COMPLETION COMPLETED 19011 RECORDS MANAGEMENT This project provides document imaging and storage for records within the Police, Fire, Planning, and Utilities Departments. The Police and Planning Departments have installed and implemented hardware and software solutions. The hardware consists of document scanners, personal computer workstations, and CD ROM drives for document storage. The documents are managed by software developed by CDB Infotek. New optical disk drives are on order, along with scannners and personal computer workstations for installation in February 1996. In March 1996, new software for all four departments will be delivered and implemented, which will complete the project. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $ 165,352 $ 0 3RD QUARTER 1995-96 4 19012 PAYROLL/HUMAN.SOURCES SYSTEM This project implements an automated Payroll/Human Resources System for integration with the City’s automated financial system. The system was live on July 1, 1995, with most of the basic payroll functions operational at that time. Several of the functions that existed in the old system still need to be developed. A new version of the software, Lawson Version 6.1, will be installed in 1995-1996, providing much of the remaining system functionality. A number of the Human Resources modules remain to be implemented. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION. $ 36,675 $ 3,957 4TH QUARTER 1996-97 19018 CUBBERLEZ....BUILDING CODE MODIFICATION This project will accomplish necessary repairs required to comply with current building, f~re safety, and disabled access regulations, as well as on going operational maintenance. As part of this ongoing project, restroom upgrades for ADA and several reroofing projects have been completed. AVAILABLE BUDGET AS OF JULY 1, 1995 $ 658,263 ACTUAL EXPENSE FOR 1995-96 $1,599 EXPECTED COMPLETION ONGOING 19073 MAJOR INTERSECTION.!MPROVEMENTS This project provides for improvements of several intersections identified in the 1989 Citywide Land Use Transportation Study. The design of Page Mill Road!Foothill Expressway intersection improvements will be completed in 1996, with construction expected in 1997. Work includes adding new turning and bicycle lanes and rephasing the signals. The project has been delayed, due to a sound wall study being performed by Stanford University. Completion of the study is expected by spring of 1996. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $1,812,201 $ 23,5O0 2ND QUARTER 1997-98 19101 TANK INVESTIGATION......AND..REMOVAL This project includes the investigation, testing, design and removal of underground tanks discovered on City property or within the City right-of-way. Over the last year, two underground tanks were removed from the sidewalk area at 291 Alma Street. AVAILABLE BUDGET AS OF JULY !, 1995 $100,244 ACTUAL EXPENSE FOR 1995-96 $0 EXPECTED COMPLETION ONGOING 191,02 AgA. STRADERO L,__._E DAM This project replaces the Arastradero Dam spillway to adequately handle overflow waters during heavy storms and to repair the dam face to withstand earthquake forces. A final scope of work is currently being developed before proceeding with the design. Construction is anticipated for summer of 1997. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $ 159,828 $ 952 1 ST QUARTER 1997-98 19108 CIVIC CENTER FIRE SPRINKLER...SYSTEM This project provided for the installation of a new fire sprinkler and fire alarm system in the Civic Center office building. This project is complete. AVAILABLE BUDGET AS OF JULY 1, 1995 $ 78,407 ACTUAL EXPENSE FOR 1995-96 $ 22,789 EXPECTED COMPLETION COMPLETED 19109 POLICE,,,COMPUTER SYSTEMS This multi-phase project improves police and dispatching information management processes. Work completed includes: an integrated, single access to law enforcement data bases; upgrade of the minicomputer; upgrade of the police records management system; access to law enforcement data bases and car-to-car communications from computers in twenty patrol vehicles. Staff anticipates providing access to law enforcement data bases in ten additional vehicles, and to complete the purchase, installation and implementation of a computer aided dispatch system in 1997-98. AVAILABLE BUDGET AS OF JULY 1, 1995 $344,688 ACTUAL EXPENSE FOR 1995-96 $75,812 EXPECTED COMPLETION 1997-98 19119 CIVIC CENTER REMODEL AND RELOCATION This project provided for the remodeling of the second, third, and fourth floors of the Civic Center office building. This project is complete. AVAILABLE BUDGET AS OF JULY 1, 1995 $244,484 ACTUAL EXPENSE FOR 1995-96 $7,670 EXPECTED COMPLETION COMPLETED 19205 & 19520 FUEL STOR ~E TANK UPGRADE AND SITE IMt.~.OVEMENTS These two projects are closely related and have been combined for procurement purposes. These projects provide for upgrades to Underground Fuel Storage Tanks and Replacement of ten fuel dispensers at various City fire stations and facilities. Bids open in February and will be submitted for Council approval in March. Work is scheduled to be completed within 90 days after the contract is awarded. Staff estimates the contract amount will be approximately $125,000. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $ 125,000 $ 0 4TH QUARTER 1995-96 19206 WATER RESCUE. EQUIPMENT This project involved the purchase of water rescue equipment and training for personnel for a joint water rescue task force between Palo Alto and Menlo Park Fire P~otection District. All major equipment purchases have been made. All training has been conducted with assigned personnel. The project is complete. AVAILABLE BUDGET AS OF J-SLY 1,1995 $5,501 ACTUAL EXPENSE FOR 1995-96 $2,905 EXPECTED COMPLETION COMPLETED 19212 BRYANT STREET BIKE BOULEVARD This project involves the implementation of the extension of the Bryant Street Bicycle Boulevard from Churchill Avenue to Palo Alto Avenue. The extension was completed in 1992. In September 1994, Council approved the installation of a permanent traffic circle at Bryant and Addison Streets. In January 1996, the City Council approved a prototype design for the traffic circle. Construction is scheduled to be completed in fall 1996. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSES FOR 1995-96 EXPECTED COMPLETION $ 37,898 $ 1,395 2NDQUARTER 1996-97 19213 CALIFORNIA AVENUE PARKING ,,STRUCTURE This project provided for the construction of a two-story parking structure on Cambridge Avenue and was completed in January 1995. AVAILABLE BUDGET AS OF JULY !, 1995 $155,243 ACTUAL EXPENSE FOR 1995-96 $5,905 EXPECTED COMPLETION COMPLETED 19214 HAZARDOUS MA.._~RIAL RESPONSE EOUIPMENT This project involved the purchase of hazardous materials response equipment to provide safety personnel the capability to enter into areas containing hazardous materials. All disposable equipment has been ordered and/or received. All assigned personnel have been trained and certified to the necessary level. The trailer to carry the equipment has been received and outfitted. AVAILABLE BUDGET AS OF JULY 1,1995 $16,356 ACTUAL EXPENSE FOR 1995~96 $45 EXPECTED COMPLETION COMPLETED 19301 BAYLANDS ATHLETIC CENTER CIRCUIT REPLACEMENT This project will replace the conduit and wiring of the ballpark lights at the Athletic Center and restore the field, as required. No work has been done on this project to date. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $ 50,000 $ 0 4TH QUARTER 1995-96 19304 BAYLANDS AMENITIES IMPROVEMENTS This project provides forthe renovation and installation of basic park facilities within the Baylands Nature Preserve. The design and installation of the Baylands entry gate and associated signage is complete. The replacement of regulatory signage throughout the Baylands Nature Preserve is expected to be complete by mid-1996. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $ 21,075 $ 0 2ND QUARTER 1995-96 19305 FOOTHILLS PARK PICNIC FACILITY REPLACEMENT This project provided for the replacement of picnic tables, BBQ stands and garbage cans in picnic areas in Foothills Park. All purchases have been made. The picnic tables and garbage cans have been assembled and installed. Only fifteen BBQ stands remain to be installed, which will occur prior to June 30, 1996. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $ 5,790 $ 4,843 4TH QUARTER 1995-96 19306 PARK IMPROVEMEN l S AND REPAIRS This is an ongoing project that includes the replacement of old and nonaccessible playground equipment. This project also includes the replacement and upgrade of park benches, signs, picnic area improvements and other amenities. Improvements in 1995-96 will be made at Cameron, Werry, and Weisshaar Parks (bench and sign replacement). After FY 1995-96, ongoing park improvements will continue to be funded through CIP project No. 19415. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $ 3,853 $ 0 4TH QUARTER 1995-96 19307 BICYCLE BRIDGE REHABILITATION This project involves the renovation of the wooden deck on the bicycle bridge on Wilkie Way over Adobe Creek. Staff prepared the specifications and evaluated a number of alternatives. It appears that the most cost effective approach would be a poured, in-place decking. However, the estimated cost may exceed the available budget. Due to budget constraints, the Department of Public Works has recommended that this project be cancelled. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSES FOR 1995-96 EXPECTED COMPLETION $ 30,000 $ 0 4TH QUARTER 1995-96 19308 FACILITIES REROOFING This project involved the refoofmg of the flat roof section of the Mitchell Park Community Center and the maintenance building at Foothill Park. The project is complete. AVAILABLE BUDGET AS OF JULY 1, 1995 $25,064 ACTUAL EXPENSE FOR 1995-96 $4,925 EXPECTED COMPLETION COMPLETED 1,,,~309 AMERICANS WITH DISABILITIES ACT COMPLIANCE This project provides for the implementation of the transition plan and self evaluation study which was developed to meet the requirements of ADA. The transition plan study completed in March 1992 identified physical obstacles, described in detail methods to make facilities accessible, and specified a schedule of actions to be implemented. External pathways, parking structures, and curb work at all City facilities have been corrected. An architectural consultant was retained to design and prepare construction documents. The survey and schematic design for ADA improvements at the main library have been concluded. Construction of ADA improvements to the Main Library will occur between February and May 1996. Elevators, restrooms and drinking fountains at other public facilities will be modified to comply with ADA standards over a four year period beginning in FY 1996-97. AVAILABLE BUDGET AS OF JULY 1, 1995 $704,163 ACTUAL EXPENSE FOR 1995-96 $40,929 EXPECTED COMPLETION ONGOING 19310 EMBARCADERO PEDESTRIAN/BIKE BRIDGE AND BIKE PATH EXTENSION This project provides for design and construction of a bike path on the westerly side of the Caltrain railroad tracks from Churchill Avenue to the southerly end of the Joint Powers Board (JPB) parking lot, including a bridge over Embarcadero Road. The path passes through properties owned by the JPB, the Palo Alto Unified School District (PAUSD) and Stanford University, and fiber optics lines belonging to MCI, Sprint and Wiltel exist in the area. The necessary agreements have been executed with all parties. The design portion is 95 percent complete. ~onstmction has been delayed, due to design changes as a result of review by various agencies. Construction is expected to start in July 1996 and to be completed in the fourth quarter of 1996-97. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $ 513,778 $ 1,800 4TH QUARTER 1996-97 19.311 MSC SECURITY IMPROVEMENTS This project provides for improved security at the MSC complex. Improvements to the lighting have been made in selected areas. A new gate security system has been installed. Additional lighting, video surveillance, an intrusion alarm for the warehouse, and the design of a warehouse enclosure is planned in 1996. AVAILABLE BUDGET AS OF JULY 1, 1995 $86,374 ACTUAL EXPENSE FOR 1995-96 $0 EXPECTED COMPLETION FY 1997-98 10 19312 FIRE COMMUNICA 1 IONS COMPUTER SYSTEM This project involves the replacement of the current fire computer system with a state-of- the-art integrated fire management and Computer Assisted Dispatch (CAD) computer application system, which is compatible with the Police Communications Computer System capital project. Specifications have been developed for hardware needs. Evaluation of several specialized fire software programs has been undertaken. The CAD portion of the project has been delayed, due to problems in selecting a qualified vendor within the project’s funding range. Staff will be returning to Council with a detailed report on plans to reassess this portion of the project. This project is expected to be concluded by June 1997. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $400,506 $ 5,770 4TH QUARTER 1996-97 19313 BICYCLE LANE IMPROVEMENTS This project involves installing new bicycle lanes on E1 Camino Way between El Camino Real (at Maybell Avenue) and West Meadow Drive, and replacing existing bicycle and vehicular lanes with standard width bike and vehicular lanes on East Meadow Drive east of Alma Street. The improvements on East Meadow Drive were implemented in conjunction with the 1995 Street Resurfacing Project last summer. During the next six months, staff will pursue discussions with the school community, local business and property owners regarding the design of the improvements along E1 Camino Way. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSES FOR 1995-96 EXPECTED COMPLETION $47,254 $ 0 2ND QUARTER 1996-97 19401 CALIFORNIA AVENUE UNDERPASS IMPROVEMENTS This project is to retain a consultant to conduct a feasibility study to improve the California Avenue pedestriardbicycle underpass, to bring it into compliance with 1990 ADA requirements. Staff intends to retain one consultant to conduct both this study and the Pedestrian/Bicycle Grade Separation Feasibility Study (CIP 19502), because the issues involved in conducting these studies are similar. A study advisory committee will be established in mid-1996, and a Request for Proposal (RFP) for consultant selection will be completed by fall 1996. The study will be completed by fall 1997. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $30,000 $ 0 2ND QUARTER 1997-98 11 19402 CIVIC CENTER LOBBY RENOVATION This project will be completed in two phases. The first includes upgrades to the interiors of Level A and the fast floor lobbies, including paint, carpet and furniture. Phase I is complete, Phase II involves development and maintenance of the Information Management System (Internet). The installation of personal computers to provide access to the Internet is complete. The workstations need securing to prevent tampering by the using public. The project will be complete in 1995-96. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $ 763 $ 0 3~ QUARTER 1995-96 19403 RADIO REPLACEMENT This ongoing project replaces all existing City-owned two-way radio communications equipment and systems, in accordance with a ten-year replacement schedule. Replacement of this equipment at the end of its normal service life ensures reliability and provides vital two-way radio communications for nearly every department within the City, including Police, Fire, Utilities and Public Works Departments. Purchases for 1994-95 have been completed, except for a small amount of carryover that will be utilized during fiscal year 1995-96. The remaining funds for this multi-year project have been moved into the Communications Division operating budget beginning fiscal year 1995-96. The original replacement plan was scheduled to continue into fiscal year 2002. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $21,034 $18,767 1995-96 (FUNDSMOVEDINTO OPERATING BUDGET) 19406 RINCONDADA POOL SITE IMPROVEMENTS This project provides for replacement of pool infrastructure piping and valving, resurfacing of the pool deck, construction of a new pool storage house, improvement of deck drainage and other electrical/mechanical/civil improvements. The consultant agreement was awarded in December 1995. Design on the project is just beginning, and construction is scheduled to begin September 1996. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $529,533 $ 0 2ND QUARTER 1996-97 12 19407 FACILITIES WATER BACKFLOW DEVICE This project provides for the installation of back_flow devices on water services to City facilities and buildings to prevent contamination of the City’s water supply. In December 1995, Council awarded a contract for the installation of twenty water backflow devices at key City facilities. This initial phase of the project will be completed byApril 1996. Staff has requested $70,000 in the FY 1996-97 budget to install back_flow devices at twenty-one remaining City facilities. This final project phase would be designed during the fall of 1996 and constructed in spring of 1997. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $60,000 $ 280 3~ QUARTER 1996-97 19409 PARAMEDIC AMBULANCE This project involves the purchase of a paramedic ambulance and all necessary paramedic equipment for the use of the Fire Department on a rotational service basis. The third ambulance has been purchased and placed in service. The project is complete. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $13,860 $10,520 COMPLETED " 19410 CIVIC CENTER GARAGE IMPROVEMENTS This project provided improvements to the garage, including painting, lighting repairs, and new signage and graphics. The painting and lighting portions are complete; however, the contractor’s payment is being held, pending final inspection of the work. Graphics and striping design are also complete and signage will be completed in 1995-96. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $199,956 $135,910 3RDQUARTER 1995-96 19411 ALMA STREET BIKE BRIDGE This project provides for the design and construction of a new bike/pedestrian bridge over San Francisquito Creek at Alma Street and short bike path segments between Alma Street in Palo Alto and Alma Street in Menlo Park. The design will be completed in spring 1996 and will be jointly selected in conjunction with the City of Menlo Park, the Santa Clara Valley Water District and the State of California. Construction is expected to be completed by fall 1996. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $208,665 $ 4,261 1ST QUARTER 1996-97 13 19412 UNIVERSITY, CALIFORNIA, AND MIDTOWN LANDSCAPE This is an ongoing beautification project for business district areas. It includes landscaping, sidewalk and other improvements. In the California Avenue and University Avenue Business Districts, seasonal flowers were planted 2-3 times, the Midtown Business Area was improved by increasing the size of existing tree wells, and ivy was planted in the larger tree wells. Bicycle racks were replaced with a new loop style rack. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $38,311 $12,131 4TH QUARTER t995-96 19413 ATHLETIC FIELDS RENOVATION This is an ongoing project to provide quality playing fields at City park locations. Work has been completed at Terman, Greer, and E1 Camino Parks. This year funds were used to fill and grade low areas at the Baylands Athletic Center. When the CIP funding is depleted in this fiscal year, this project will continue to be funded from the Community Service Department operating budget. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION: $9,037 $ 676 4TH QUARTER 1995-96 19414 PARK IRRIGATION AND BACKFLOW IMPROyEMENTS This project consists of ongoing improvements for irrigation at City facilities. This year a new irrigation system will be installed at Peers Park. Backflow devices will continue to be installed at City facilities. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $470,999 $ 64,789 2NDQUARTER 1996-97 1 ~ 15 PARK FACILITIES IMPROVEMENTS This is an ongoing project that includes the replacement of old and non-accessible playground equipment. This project also includes replacement and upgrade of park benches, signs, picnic area improvements and other amenities. New playground equipment will be installed at Rinconada Park. Picnic area improvements will be made at Seale and Scott Parks. This project is very simildr in scope to CIP project No. 19306; however, for budgetary reasons; they are maintained as two separate projects. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $199,199 $16,653 2NDQUARTER 1996-97 14 19417 INTERNATIONAL TEcEPHONE AND TELEGRAPH SITE EASEMENT PURCHASE The purchase agreement between the City and the owner of the easement is subject to approval by the Federal Communications Commission ~CC) of relocation of the owner’s transmitter facility. The owner must first find a new site and then get FCC approval. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $412,000 $ 0 2ND QUARTER 1996-97 19418 LIBRARY AUTOMATION SERVIC.ES This project develops the Library’s computer system into an information network that can deliver new and emerging products and services to selected library facilities and remote users. The replacement of the central computer with a new Unix-based machine was completed in 1993-94. Upgrading the network that links Main, Mitchell Park, and Children’s Libraries by connecting these facilities to the City’s wide area network (WAN) was completed in 1995-96. Networking the Library’s computer to the City’s existing Inter-net connection will occur in late 1995-96 after network security issues are resolved. The automated telephone-based book renewal system was installed in 1994-95. Replacement of existing old catalog terminals and the addition of public use computer equipment, including Internet workstations, are scheduled for completion by the end of 1995-96. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSEFOR 1995-96 EXPECTED COMPLETION $348,341 $ 61,889 2ND QUARTER 1995-96 19420 CHUCK THOMPSON SITE POOL ~MOVAL The project includes removal and backfilling of the pool on the City-owned property at 3005 Middlefield Road. Work will occur after the rainy season and should be completed within two months. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $29,550 $ 210 4TH QUARTER 1995-96 15 19502 PEDESTRIAN/BIKE ORADE SEPARATION FEASIBILITy STUDY This project provides for a feasibility study to assess the various options for providing pedestrian!bike grade separations at the Caltrain railroad tracks and Alma Street at four different cross street locations: Meadow Drive, Charleston Road, Churchill Avenue, and Palo Alto Avenue. A study advisory committee will be established in mid-1996, and the consultant selection process will be completed by fall 1996. The consultant study will be completed by fall 1997. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $150,000 $ 0 4TH QUARTER 1995-96 1 ~.503. SAND HILL ROAD BRIDGE - BIKE LANES This is a design and construction project to widen the Sand Hill Road Bridge. The existing two-lane bridge will be widened to install on-road bicycle lanes over San Francisquito Creek along Sand Hill Road, and the bicycle lanes will be Continued west to the intersection of Sand Hill Road!Santa Cruz Avenue. The City of Menlo Park is the lead agency for this project. It plans to proceed with the selection of a design consultant in the summer of 1995. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $40,000 $ 0 4TH QUARTER 1995-96 1 ~505 .REVENUE COLLECTION I~MODEL This project will be accomplished in two phases. The first phase provides for improvements to the office layout. This phase will be completed in the third quarter of 1995/96. The second phase will remove non-supporting walls, replace the security doors, and remodel the customer service counter. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $85,000 $1,455 2ND QUARTER 1996-97 1~,506,,P~S QFFSTREET TREE TRIMMING This project provided for the pruning of designated trees in City parks and around City facilities. All park and facility trees were previously surveyed and rated according to pnming needs. Two contractors performed work on trees rated as most in need of pruning. Three hundred and ninety six trees in 16 parks, along with 30 trees at five facilities were pruned. This project provided much-needed pruning for improved tree health and hazard reduction. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $85,000 $ 0 3RD QUARTER 1995-96 16 19508 TENNIS AND BASK& l BALL COURT RENOVATION This project consists ofresurfacing four concrete surface and three asphalt concrete surface tennis courts at Mitchell Park and resuffacing on one asphalt concrete surface basketball court at Terman Park. The bid opening date for this project is scheduled for March 5, 1996. Work will begin immediately after the contractor is selected and the project will be completed this spring. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $25,000 $ 0 4TH QUARTER 1995-96 19509 PARK PATHWAY REPAIRS This project provides for pathway repairs at Eleanor Park. The project is complete. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $21,000 $18,900 COMPLETED 19510 PARKS SOFTSCAPE PLANT P~PLACEMENT This project provides for replacement of plants, shrubs, and ground cover at City facilities. This year, landscaping will be replaced at Peers Park and the arboretum islands. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $32,053 $18,584 1996 19511 LUCIE STERN PATHWAY LIGHTING This project installs lighting along two pathways from the street to the building complex. Work on this project has not been started. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $25,000 $ 0 1 ST QUARTER 1996-97 17 1,,,~512 CIVIC CENTER, PLAZA WATERPROOFING This project provides for the waterproofing of plaza planters and other areas leaking water through the plaza concrete slab. This project includes a study to determine the extent of damage which may have occurred due to water intrusion and structural cracking of the Civic Center plaza deck. Staffplans to issue an RFP and will award an agreement by March 1996. Design is expected to be completed by June 1997. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $50,000 $ 0 4TH QUARTER 1996-97 19513 POLICE LOCKER ROOM RENOVATION FEASIBILITY STUDY This project provides for a feasibility study/space utilization analysis for the renovation of the Police Department locker rooms and shower facilities. The study phase is complete. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $5,676 $ 376 COMPLETED 19514 FACILITIES ROOF REPLACEMENTS This project is being accomplished in two phases. MSC-A,B and C, Fire Stations 1 and 4 were reroofed (Phase I) at the beginning of this fiscal year. The Civic Center, Council Chambers and Police Department roofs will be completed (Phase II) in the fourth quarter of this fiscal year. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $553,163 $436,101 4TH QUARTER 1995-96 19515 DOWNTOWN LIBRARY BEAM REPAIR This project includes the analysis and design of repairs to the roof support girders. Staff expects to award a design agreement within the next two months and anticipates completing design by November 1996. Construction of improvements is not yet funded and will not occur until after May 1997. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $25,000 $ 0 4TH QUARTER 1996-97 18 19516 PERMIT INFORMATItJN TRACKING SYSTEM This project provides for the design and implementation of an automated Permit Information Tracking System to track and monitor permits and activities such as applications, licenses, inspections, complaints and code enforcement. An interdepartmental committee worked to complete an RFP, which was sent to nine vendors. Responses were received at the end of January. It is anticipated that a vendor will be selected by late spring, with implementation of the chosen system beginning in early summer. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $90,000 $ 75 4TH QUARTER 1996-97 19519 MULTI-LINE TELEPHONE SYSTEM REPLACEMENTS This project is to replace telecommunications switching devices located at several of the City’s remote locations. The current systems are no longer supported by the manufacturer and spare parts are no longer readily available. The analysis and the definition of requirements are being finalized. Procurement will occur this fiscal year, with the installation and implementation of the telecommunications switches complete next fiscal year. AVAILABLE BUDGET THROUGH 06/30/96 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION ¯$140,000 $ 0 2ND QUARTER 1996-97 19521 WIRELESS VEHICLE MANAGEMENT SYSTEM This project provides for the installation of wireless monitoring devices on City vehicles to support maintenance requirements and usage monitoring. Secondary support provides for secure facility access control and automated fuel dispensing. The Interlink contract was awarded in the amount of $107,000 and work is due to begin in March 1996. This is the second phase of a three-phase project. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $109,374 $ 1,738 4TH QUARTER 1995-96 19 19522 MSC GARAGE IMPROVEMENTS This project provides for upgrades to garage doors, the modification of an existing in-ground exhaust system to an overhead exhaust system, and a portable vehicle lift for heavy vehicles. Six portable column rifts were ordered and installed in the second quarter. Major retrofitting work has been completed and a vendor has been selected to install an overhead exhaust system. All remaining project work should be completed by year-end. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $104,202 $ 78,222 4TH QUARTER 1995-96 19523 EL CAMINO I~AL INTERSECTION IMPROVEMENTS This project provides for traffic signal modifications and pedestrian!bike improvements at Arastradero Road, Maybell Avenue, and Los Robles Avenue along E1 Camino Real, including modifying traffic signals at Maybell and Los Robles Avenues to an eight phase operation. Since E1 Camino Real is a State highway, Caltrans is the lead agency. Staffhas received confirmation from Caltrans that the State is willing to participate financially and will design and construct the improvements in FY 1996/97, subject to executing the necessary agreements with the City. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSES FOR 1995-96 EXPECTED COMPLETION $160,000 $ 0 4th Quarter 1996-97 19524 B!KE SYSTEM IMPROVEMENTS This project provides for improvements in Palo Alto bike routes, including extension of bike routes along Park Boulevard and Montrose Avenue, elimination of the sidewalk bike paths at Park Boulevard and Montrose Avenue, and replacement of bike racks at City facilities. Staff will pursue preparation of plans for these improvements during the next six months, with project completion scheduled by the end of 1996. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $30,000 $o 2ND QUARTER 1996-97 2O 19525 TECHNOLOGY IMPROVEMENTS FOR RECREATION, ARTS AND CULTURE This project provided for the purchase and installation of computer hardware and software to create a computerized, multi-facility class registration and facility scheduling system for two divisions of the Community Services Department. All purchases have been made and the class registration module is operational. Implementation of the facility scheduling module has been deferred until staff has adequate experience with class registration. Implementation of the facility reservation module is scheduled for summer 1996. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $18,042 $ 6,525 1 ST QUARTER 1996-97 19530 DOWNTOWN PARKING STRUCTURE FEASIBILITY STUDY This project involves retaining a consultant to conduct a study to investigate the overall feasibility of the development of a parking structure or structures on one or more sites in the downtown area. A consultant agreement with Watry Design Group was approved by the Council in August 1995 to conduct the study, subject to the City Attorney’s Office resolving a conflict of interest issue, which was raised by a member of the public at the Council meeting. This issue was resolved recently and the consultant is now proceeding with the study. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $79,990 $ 0 2ND QUARTER 1996-97 19531 CUBBERLEY DANCE STUDIO L-WING CONVERSION This project will provide for the conversion of a 3,500 square-foot auto shop building into a dance studio at Cubberley Community Center. The converted space will then be rented for dance instructions. Work is expected to start early next fiscal year. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $40,000 $ 0 2ND QUARTER 1996-97 21 1,953.2 DEMOLITION OF,,,,At<ASTRADERO MAIN HOUSE & C~T&KER COTTAGE The project will demolish the main and caretaker’s houses on the Arastradero Preserve, remove asbestos in the houses and remm the property to its natural condition, as part of the Arastradero Open Space Preserve. The demolition will include the swimming pool, propane tank, pool equipment and concrete foundations. The project has been put on hold, pending Council review of options regarding utilization of the existing main and caretaker houses. AVAILABLE BUDGET AS OF JULY 1, 1995 $90,000 ACTUAL EXPENSE FOR 1995-96 $0 EXPECTED COMPLETION NOT SET 19535 CITYWIDE TIMEKEEPING SYSTEM This project provides for the temporary data entry and programming services necessary for the implementation of an interim timekeeping database, until the final timekeeping system is completed. Funding for the final timekeeping system is requested in the FY 1996-97 Budget. The final timekeeping solution will automate the City’s timekeeping needs, replace paper time cards, and will be required to accurately determine the cost of City services for the City’s Mission Driven Budget (MDB). In 1997-98, the system will be expanded to field personnel. The system will be fully integrated with the City’s financial data base and the Payroll/Human Resources system. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $36,446 $12,439 4TH QUARTER 1997-98 19601 CIVIC CENTER ASBESTOS ..REMOVAL This project removes sprayed-on acoustical ceiling material containing asbestos in the Civic Center restrooms, elevator lobbies and Police Department records area. After removal, ceilings will be retextured and the main lobby’s high ceiling will be encapsulated. Consultant selection will begin in the third quarter of 1995-96. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $235,000 $ 0 4TH QUARTER 1995-96 22 19602 CIVIC CENTER CHILLER REPLACEMENT This project designs and replaces the 300-ton Civic Center chiller. Work will include removal and installation of the chiller, material disposal, all system ductwork and mechanical room modifications, seismic and structural improvements, and a leak alarm system. Consultant selection will begin in the third quarter of 1995-96. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $100,000 $ 0 3RD QUARTER 1996-97 19603 CULTURAL CENTER COURTYARD REPAIR This project will repair the brick surface and benches in the Cultural Center courtyard. A courtyard tree will also be removed and replaced with a different tree species. Bids for this project are currently under evaluation. This project will be completed this spring. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $60,000 $80,000 4TH QUARTER 1995-96 19604 MSC BUILDING A HVAC IMPROVEMENTS This project will expand the heating, ventilating and air conditioning system in the MSC building which houses Parks and Golf personnel. Work on this project has not started. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $34,000 $ 0 1 ST QUARTER 1996-97 19605 FOOTHILLS PARK WATER MANAGEMENT SYSTEM This project develops and implements a long-range water management system for Foothills Park. It includes design and replacement of the turf irrigation system, and installation of backflow devices in Foothills Park. Staff will focus on Phase I of the design and installation of lower turf irrigation system within the next few months. The installation of backflow devices will follow next year. Phase II of the remaining installation will be completed by mid-1998. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $240,000 $ 0 DURING 1997-98 23 19606 FIRE STATION 3,,DRIVEWAY EXTENSION This project will widen the driveway of Fire Station No. 3, located at the comer of Newel and Embarcadero Roads to accommodate the mining around of fire vehicles. The project also includes installation of vehicle washing facilities at all City fire stations to comply with new City non-point source regulations for commercial vehicle washing. The vehicle washing equipment will be located at the comer of Fire Station No. 3, where the driveway is to be widened. Environmental mandate may require an oil/grease-water separator to be installed. Because the cost to construct the separator may exceed the project budget, staff is evaluating feasible alternatives. Specifications for the driveway and equipment work are in the process of being finalized contingent upon the decision. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $35,000 $ 0 4TH QUARTER 1995-96 19607 CUBBERLEY RESTROOM/CONCESSION UTILITIES This project provides for the design and installation of utility services for a proposed new restroom!concession facility to be located adjacent to the Cubberley football field. Initiation of this project is dependent upon development of a public-private partnership to secure funding needed to build the concession facilities. Community and user group negotiations, which were expected to be completed by June of 1995, are still in progress. The building design is currently being developed by community volunteers and will be finalized in FY 1996-97.. It is anticipated that utility services installation and building construction will begin in 1997-1998. AVAILABLE BUDGET AS OF JULY 1, 1995 $150,000 ACTUAL EXPENSE FOR 1995-96 $0 EXPECTED COMPLETION 1997-98 1 ~.608..DOWNTO~....UI~AN DESIGN IMPROVEMENT This project is to implement several design improvements in the Downtown area. The first step of the multi-phased program is the preparation of a schematic design and feasibility study to develop aesthetically pleasing and functional designs and determine the construction and maintenance costs of each project. The recommended projects would then be prioritized over a five-year period with future CIP funding. City staff and acommittee of downtown merchants and property owners developed an RFP and have selected a firm to prepare the design plan. A contract is currently being negotiated. The plan is expected to be completed by November of 1996. Implementation will follow over a five-year period. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $100,000 $0 2ND QUARTER 1996-97 24 19618 GIS APPLICATION This is a multi-departmental project to develop application software, and provides for associated hardware needs, which will allow easy and quick access to City data and maps. The Planning Division has begun development of customer service applications, and has purchased a plotter to enhance the City’s ability to produce map products. In 1996-97, Planning will coordinate hardware acquisition, and the Utilities, Public Works and other Deparmaents will begin application development. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $462,000 $11,390 ONGOING 19620 CIyIC CENTER LAN UPGRADE This project will replace the existing Civic Center local area network. The specifications for this project have been defined. Implementation is on hold, pending approval of City- wide network upgrades proposed in 1996-97. It is anticipated that work on this will occur during the first quarter of FY 96-97, with implementation in the second quarter. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $160,000 $ 0 2ND QUARTER 1996-97 1 ~,621 PAUSD FIELD EQUIPMENT This project was established for the purchases of vehicles and turf maintenance equipment which are necessary to implement the PAUSD and City Athletic field program. The co- operative agreement provides for the joint funding for the maintenance efforts between PAUSD and the City during the period January 1, 1996 through June 30, 1997. Work is scheduled to begin in the third quarter this year. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $218,000 $ 24,000 4TH QUARTER 1995-96 19622 POLICE SECURITY IMPROVEMENTS This project provides for the remodel of the Administrative Services area of the Police Department, located on the first floor of the Civic Center. The selection process for the design consultant is in progress. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $95,000 $ 0 1 ST QUARTER 1996-97 25 ENTERPRISE FUNDS WATER FUND 8013 WATER SYSTEM EXTENSIONS This project constructs system extensions that are required to provide service to new customers and to satisfy increased demands of existing customers. These improvements include new mains, valves, domestic services, meters on upgraded existing services, fire services, and hydrants. AVAILABLE BUDGET AS OF JULY 1, 1995 $ 143,000 ACTUAL EXPENSE FOR 1995-96 $96,476 EXPECTED COMPLETION ONGOING 8014 SERVICE AND HYDRANT REPLACEMENTS This project replaces old, deteriorated, galvanized water service lines and lead goose necks, upgrades non-standard fire hydrant assemblies, and replaces existing deteriorated copper water services lines. AVAILABLE BUDGET AS OF JULY 1, 1995 $ 137,000 ACTUAL EXPENSE FOR 1995-96 $9,153 EXPECTED COMPLETION ONGOING 8015 WA~R METERS This project includes purchasing meters for new customers, upgrading meters for current customers and replacing obsolete meters that are no longer repairable. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $ !32,247 $ 99,130 ONGOING 27 8016 WATER MAIN REPLACEMENTS This project replaces water mains that are inadequate in size to supply required fire flows and pressures for fire protection and construction materials. This project completed 15,800 linear feet of water main replacements in 1995-96. The Phase IX Water Main Replacement will be bid in April 1996. The project will reach its goal of 16,000 linear feet of main replacements for 1995-96. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $3,585,539 $ 895,300 ONGOING 8636 WATER WELL SITES ~HABILIT~TION This project reviews the City’s well system for potential abandonment and provides for refurbishment of the City’s six remaining wells. Artesian flow has been stopped at the Meadows Well site. The Meadows Well site has been recommended for abandonment. The Matadero Well and Fernando Well sites remain to be studied. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $148,036 $ 437 ONGOING 8749 WATER,,,RESERVOIRS IMPROVEMENTS This project provides for the recoating of the interior and exterior of the City’s steel reservoirs in the foothills. The project also includes the rehabilitation of Boronda Reservoir in Foothills Park, which is a prestressed concrete reservoir. In 1995-96, the Montebello Reservoir will be recoated on the interior and exterior. The Montebello Reservoir is the fourth of four steel reservoirs to be recoated. The Montebello Reservoir recoating contract has been awarded by Council and the work will start in spring 1996. Work remaining for this project includes Boranda Reservoir repairs, maintenance work on the fences around the sites, and repairing asphalt roads into and surrounding the reservoirs. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $ 542,283 $ 126 DURING 1997-98 28 8923 WATER STA~ON IMPROVEMENTS This project will update the City’s water receiving stations monitoring and control equipment. The work will be carried out in conjunction with the development of the water, gas, and storm station Supervisory Control and Data Acquisition (SCADA) System. The SCADA system design and construction contracts have been awarded by Council and the software development phase of the project is in progress. The field construction portion of the project will start after the software development is complete. AVAILABLE BUDGET AS OF JULY 1, 1995 $104,504 ACTUAL EXPENSE FOR 1995-96 $0 EXPECTED COMPLETION 1996-97 29 ELECTRIC FUND 8741 ELECTRIC LOAD RESEARCH The load research system is a computer-based system that records electricity and gas use on a time-interval basis for selected customers. This load profile data is used for load forecasting, rate design, gas purchase balancing, and commodity purchase billing validation. Recent activities include migrating the system to the local area network, upgrading the software to the latest release and installing recorders at 20 additional sites. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $ 57,437 $ 25,208 4TH QUARTER 95-96 885~,,,,,,,,,,ELECTRIC 4/12 KV CONVERSION This ongoing project converts the 4 KV distribution system to 12 KV in areas that will facilitate utilization of 12KV capacity, available at Park Boulevard, Maybell, Quarry, and Colorado Substations, and allow the retirement of old 4KV equipment. To date, approximately 60 percent of the conversions in the Alma/Churchill and the Middle- field!Louis area have been completed. The remaining work in these areas will be completed by the end of the fiscal year. AVAILABLE BUDGET AS OF JULY 1, 1995 $247,000 ACTUAL EXPENSE FOR 1995-96 $89,002 EXPECTED COMPLETION ONGOING 8918 ELECTRIC EAST BAYSHORE TO PADMOUNTED SWITCHES Underground switches near the Baylands are subject to damage from submersion. Several switches were replaced and moved to above ground locations to improve reliability and prevent further damage. This project is now complete. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $ 125,686 $ 41,059 COMPLETED 30 8928 ELECTRIC CUSTOM]_ DESIGN AND CONNECTION SER¥~ ~ES This is an ongoing project to design and connect customer services, purchase service equipment, and to replace deteriorated distribution facilities. To date, approximately 40 customers have been connected to the electrical system. Unused funding is returned to reserves at the end of the fiscal year. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $2,362,663 $ 761,704 ONGOING 8929 ELECTRIC STREET LIGHTING CONVERSION This project converts all street lights to high pressure sodium. To date, 446 of the 1200 remaining series street lights have been converted to high pressure sodium. In the remainder of the year, 87 more series street lights and approximately 300 mercury vapor streetlights will be converted to high pressure sodium. The remaining street lights will be converted in 1996-97. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $ 880,000 $ 95,307 2ND QUARTER 96-97 8930 ELECTRIC TRAFFIC SIGNALS This project upgrades existing traffic signals to increase safety, reliability, and to .meet current standards. Five traffic signal controllers in the downtown area have been replaced to date and one additional controller will be replaced by yearend. AVAILABLE BUDGET AS OF JULY 1, 1995 $ 508,419 ACTUAL EXPENSEFOR 1995-96 $ 71,571 EXPECTED COMPLETION ONGOING 8931 COMMUNICATIONS SYSTEM IMPROVEMENTS This project installs hardwire and coaxial cable, as necessary, to provide communications services for traffic signal coordination, telephone links, and other computer data transmission activity. The library cable communication links have been installed, and installation of a utility radio channel is in progress. AVAILABLE BUDGET AS OF JULY 1, 1995 $100,651 ACTUAL EXPENSE FOR 1995-96 $21,848 EXPECTED COMPLETION ONGOING 31 8,937 QUARRY’,, RD 12 KV . ~F_,DERS This project installs 12KV feeders at Quarry Road to increase system capacity in the downtown and Stanford Shopping Center area. This project is now complete. AVAILABLE BUDGET AS OF JULY 1, 1995 $15,055 ACTUAL EXPENSE FOR 1995-96 $ 11,518 EXPECTED COMPLETION COMPLETED 8938 SUBSTATION PROTECTION IMPROVEMENT This project funds various improvements to the protective equipment in electric substations. Improvements include relay and fuse replacements and replacement of obsolete and failed controls. AVAILABLE BUDGET AS OF JULY 1, 1995 $102,000 ACTUAL EXPENSE FOR 1995-96 $38,511 EXPECTED COMPLETION ONGOING 8940 UNDERGROUND SWITCH REPLACEMENT This project funded the purchase of new switches to replace deteriorated subsurface oil switches. All the switches have been purchased and the project is complete. Switch installation will be completed on CIP No.8928. AVAILABLE BUDGET AS OF JULY 1, 1995 $35,440 ACTUAL EXPENSE FOR 1995-96 $ 31,755 EXPECTED COMPLETION COMPLETED 8944 SUBSTATION IMPROVEMENTS This project includes replacement of batteries and battery chargers, based upon their life expectancy, renovation of security fences and entry gates, and upgrading of the substation drainage system and miscellaneous other improvements. In the fourth quarter of 1995-96, a paved driveway will be installed in Hansen Way Substation. AVAILABLE BUDGET AS OF JULY 1, 1995 $109,668 ACTUAL EXPENSE FOR 1995-96 $0 EXPECTED COMPLETION ONGOING 32 9102 SWITCHGEAR SEISI~ RESTRAINT This project provides for seismic retrofits to substation switchgear. Civil design has been started and is expected to be completed by the end of the third quarter. Construction should be completed by the end of the fiscal year. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $ 74,629 $ 2,404 4TH QUARTER 95-96 9250 ALMA STREET 12 KV ADDITION This project replaces the 4 KV switchgear and transformers at the Alma Substation with new 12 KV transformers and switchgear. 4KV equipment has been removed and the new substation transformers have been ordered. This project will be completed in the third quarter of 1996-97. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $1,004,292 $ 17,145 3RDQUARTER 96-97 9252 DOWNTOWN UG DISTRICT 34 This underground conversion project covers the area from Cowper to Alma and Forrest to Addison. This project is now complete. AVAILABLE BUDGET AS OF JULY 1, 1995 $ 88,991 ACTUAL EXPENSE FOR 1995-96 $ 88,748 EXPECTED COMPLETION COMPLETED 9254 PADMOUNTED TRANSFORMER SEISMIC RESTRAINT This project installs seismic restraints on the padmounted transformers in the City. All the transformers in the City have been inspected to determine transformer layout for design engineering. Engineering design will begin in the third quarter of 1995-96. Project construction will begin in the fourth quarter of 1995-96, and the project will be completed in the fourth quarter of 1996-97. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $ 117,463 $ 10,554 4TH QUARTER 1996-97 9350 CHANNING/ADDISt_ . AVENUE UNDERGROUND This underground conversion project covers the area from Channing to Addison Avenue in downtown Palo Alto. This project is now complete. AVAILABLE BUDGET AS OF JULY 1, 1995 $ 50,000 ACTUAL EXPENSE FOR 1995-96 $ 18,495 EXPECTED COMPLETION COMPLETED 9354 STREET LIGHT IMPROVEMENTS This project funds the replacement of street light poles, pole foundations, luminaries, and wiring, as needed to maintain or improve street lighting. AVAILABLE BUDGET AS OF JULY 1, 1995 $ 90,000 ACTUAL EXPENSE FOR 1995-96 $0 EXPECTED COMPLETION ONGOING 9356 AUTOMATIC METER READING PROGRAM This project funds a feasability study to analyze the benefits of an automated meter reading system. The consultant’s report was accepted by staffand an RFP for the design and implementation of a pilot program is in progress. AVAILABLE BUDGET AS OF JULY 1, 1995 $ 104,886 ACTUAL EXPENSE FOR 1995-96 $0 EXPECTED COMPLETION ONGOING 9357 UTILITIES BILLING SYSTEM This project will provide a client/server-based utility billing and customer information system to the Utilities Department. The project is critical to the Utilities Department as competition in the industry continues to increase. The system will provide more timely and facilitated access to utility rate, usage and customer information. To date, development has delivered five years of historical data for user access and the new utility billing statement. The system will include rate change and billing update modules, online update customer information, and ad hoc reporting capabilities. Additional funding in the amount of $186,200 was requested and approved by Council this year. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $ 361,641 $ 104,624 4TH QUARTER 96-97 34 9453 SOUTHGATE UNDEi .~O~ This project converts overhead electric lines to underground electric lines in the Southgate area. Substructures have been completed, and electrical construction will begin in the third quarter of 1995-96, with project completion in the first quarter of 1996-97. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $1,665,386 $ 609,558 1 ST QUARTER 96-97 9509 COLORADO SUBSTATION 60 KV BUS TIE B~AKER This project installs a second bus tie breaker at Colorado Power Station to improve reliability. Design is complete and construction will be completed in the fourth quarter of 1995-96. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION 9510 SUBSTATION TRANSFQRMER REPLACEMENT $ 37,340 $ 30,394 4TH QUARTER 95-96 This project replaces old and under-capacity substation transformers to maintain electric system reliability. One transformer will be replaced at the Hanover Substation in 1995-96. AVAILABLE BUDGET AS OF JULY 1, 1995 $393,437 ACTUAL EXPENSE FOR 1995-96 $3,819 EXPECTED COMPLETION ONGOING 9511 FUTURE UNDERGROUND DISTRICTS Project planning for the underground conversion of District 36 All new work on District 36 will be done on CIP Project No. 9610. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $ 26,934 $ 22,957 COMPLETED has been completed. 9515 SCADA SYSTEM UPGRADE This project replaces obsolete SCADA master station equipment that was originally installed in 1984. Proposals ~om vendors will be reviewed and a contract wil! be awarded in the third quarter of 1995-96. Construction of the master station will begin in the fourth quarter of 1995-96, with completion of the project in the second quarter of 1996-97. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $1,007,600 $ 37,209 2ND QUARTER 96-97 35 9610 COMMERCIAL STREET/CORPORATE WAY UG CONVERSION (DIST~CT 36) This underground conversion project covers the area bounded by Commercial Street, Transport Street and Industrial Avenue. Initial planning and design will be completed in the third quarter of 1995-96; substructure work will be completed in the first quarter of 1996-97; and final construction will be completed by the third quarter of 1996-97. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $2,300,000 $ 29,168 4TH QUARTER 96-97 9611 EMBARCADERO/MIDDLEFIELD UNDERGROUND CONVERSION This underground conversion project covers the area roughly bounded by Middlefield Road, Seale Avenue, and Embarcadero Road. Engineering on this project will start in the fourth quarter of 1995-96; design and coordination will be completed in 1996-97; and final construction will begin in the first quarter of 1997-98. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $ 80,000 $ 0 4TH QUARTER 97-98 9612 UTILITY CUSTOMER INFORMATION SYSTEM (PREVIOUSLY THE BILL PROCESSING SYSTEM) This project was funded to develop a new Utility Billing System. A five-year billing history has been established on-line. A new statement folder was purchased and a new bill statement was designed and introduced in February 1996. Application development has been funded through CIP project No. 9357, with the continued involvement of the Utility Customer Service staff. Staff recommends this project be consolidated with CIP project No. 9357 prior to yearend. AVAILABLE BUDGET AS OF JULY 1, 1995 $85,000 ACTUAL EXPENSE FOR 1995-96 $0 EXPECTED COMPLETION ONGOING 36 GAS FUND 8017 GAS SYSTEM EXTENSIONS This project extends the gas distribution system to provide services to new customers and augment service to customers with increased demands. Improvements constructed under this project include new mains, valves, services and appurtenances. AVAILABLE BUDGET AS OF JULY 1, 1995 $ 162,500 ACTUAL EXPENSE FOR 1995/96 $ 126,963 EXPECTED COMPLETION ONGOING 8018. GAS MAIN I~PLACEMENTS This project replaces leaking, inadequately sized and structurally-deficient existing gas mains and services. These gas mains must be replaced when leaks present a potential safety hazard or when leak repair is no longer cost effective. Deteriorated steel mains and thin wall plastic mains are given the highest priority for replacement. This project has replaced approximately 20,000 linear feet of deficient gas mains in 1995-96. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $2,978,790 $ 767,970 ONGOING 8019 GAS METERS AND REGULATORS This project installs new meters and regulators to serve new customers or to replace existing meters and regulators when required. This project replaces approximately 2,200 gas meters and regulators per fiscal year. New flow regulators, controls and site improvements at the City’s gas receiving stations will be installed to meet federal Department of Transportation regulations. AVAILABLE BUDGET AS OF JULY 1, 1995 $451,439 ACTUAL EXPENSE FOR 1995-96 $ 157,260 EXPECTED COMPLETION ONGOING 37 8919 GAS STATION IMP,.OVEMENTS This project includes improvements to four gas receiving stations and pressure sensing points in the gas distribution system. These facilities will be upgraded to state of the art, explosion- proof equipment and connected to the water, gas, and storm SCADA system which is currently under design and will be consmacted in 1996 (CIP No. 9515). AVAILABLE BUDGET AS OF JIJLY 1, 1995 $181,958 ACTUAL EXPENSE FOR 1995-96 $15,334 EXPECTED COMPLETION 1996-97 9230 NATURAL GAS VEHICLE CONVERSION 104 light-duff compressed natural gas (CNG) buming vehicles were planned for purchase during 1995-96 by the City’s Fleet Manager. The compressed natural gas original equipment manufacturers (OEM) are not building the vehicles as quickly as they had planned, so this project was approved to mitigate any operating delays. The project will ultimately convert one third of the light duty vehicle fleet from gasoline fuel to CNG. 35 vehicles will be converted and a CNG compressor station will be installed at the MSC. The remaining 69 CNG vehicles will be purchased as OEM CNG fuel bttming vehicles. AVAILABLE BUDGET AS OF JULY 1, 1995 $ 319,594 ACTUAL EXPENSE FOR 1995-96 $25,265 EXPECTED COMPLETION 1997-98 38 WASTEWATER FUND 8020 SEWER SYSTEM EXTENSIONS This project provides for the installation of sewer lateral connections and appurtenances for new or existing customers on existing mains or extensions of mains. This project also constructs new service laterals to comply with new infrastructure requirements resulting from the redevelopment of existing City lots. AVAILABLE BUDGET AS OF JULY 1, 1995 $138,000 ACTUAL EXPENSE FOR 1995-96 $30,608 EXPECTED COMPLETION ONGOING 8021 PLANT EQUIPMENT REPLACEMENT This ongoing project provides for scheduled replacement of the Regional Water Quality Control Plant (RWQCP) equipment for maintaining treatment reliability. Replacement of aeration tank blower No. 5 is in progress. Installation and construction is expectedto be complete by June 1996. AVAILABLE BUDGET AS OF JULY 1, 1995 $745,080 ACTUAL EXPENSE FOR 1995-96 $0 EXPECTED COMPLETION ONGOING 8022 SYSTEM FLOW METERING REPLACEMENT PROGRAM This project provides for ongoing replacement of system flow meters. As magnetic flow meters have a useful life of five years, staff has followed a periodic replacement schedule to ensure meter reliability and accuracy. One electromagnetic meter has been purchased. Staff has scheduled bid openings for the installation and reconditioning of the Los Altos meter station in February of 1996. AVAILABLE BUDGET AS OF JULY 1, 1995 $141,294 ACTUAL EXPENSE FOR 1995-96 $6,772 EXPECTED COMPLETION ONGOING 39 8865 LABORATORY FAt. _~ITIES AND EQUIPMENT 8926 This project provides laboratory facility improvements and minor equipment replacements to comply with Regional Water Quality Control Board requirements. All of the facility improvements fume hoods and ventilation fans are complete. Minor equipment replacements will be completed by end of 1996. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $ 110,616 $ 0 2ND QUARTER 96-97 PLANT WATER SYSTEM IMPROVEMENTS This project provides improvements to the WQCP No. 4 water system. Final modifications are in process. This project expected to be completed in June of 1996. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $ 21,000 $ 0 4TH QUARTER 95-96 9.!73 WASTEWATER COLLECTION SYSTEM REHABILITAtION/AUGMENTATION This project will construct high priority rehabilitation work, which reduces inflow of rain- water and groundwater into the City’s wastewater collection system. This project will also repair or replace mink sewers with capacity deficiencies, in order to handle existing and future wastewater flows. The project provides for the video taping and cleaning of large diameter collection system mains. Two projects, Phase IV and V, are currently under construction. Phase VI will start construction later this fiscal year. Approximately 34,000 linear feet of wastewater collection mains will be repaired in 1995-96. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $7,136,664 $1,038,660 ONGOING 9260 INSTRUMENTATION AND ALARM. DIST~BUTI.ON CONTROL SYSTEM This multi-year project includes a development and installation of a standardized distribution control system for Plant-wide alarm system, pumping control system (three locations), filtration, chlorination, dechlorination, incineration, polymer and a lime/caustic control system. Programmable Logic Controllers for the Main Pumping Plant and equipment room have been installed and are operational. Installation for the other buildings is in progress. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $ 14,719 $ 2,249 4th QUARTER 96-97 40 9454 INDUSTRIAL WAS2.,AB RELOCATION.. This project will add space to the WQCP Administration Building or the Industrial Waste lab by building out to the existing foundation line. Design is in progress, and construction is scheduled to begin in July 1996. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $ 175,000 $ 0 4th QUARTER 96-97 9504 INTERCEPTOR MAINTENANCE, CLEANING AND REPAIR This multi-year project includes cleaning and joint repair of the large "72" interceptor sewer line that carries over half the total in-flow to the WQCP from Mountain View and Los Altos. Continued build up of dirt and sand could restrict the flow to the Plant. The leaking joints are a cause of salt water infiltration and must be sealed to reduce plant flows and reduce high salt content in plant effluent. Inspection and engineering for the project is underway; cleaning and repair work is expected to begin in the summer of 1996. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $ 350,000 $ 0 4TH QUARTER 98-99 9505 INCINERATOR SLUDGE CONVEYANCE SYSTEM This project includes engineering, design, fabrication and installation of new sludgecon- veyance equipment. Installation and construction has begun, and the project is expected to be completed in September 1996. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $ 400,000 $ 361,000 4th QUARTER 96-97 9513 AERATION TANK INLET STRUCTURE MODIFICATIONS This project will double the size of the existing aeration tank inlet diversion box and add control valves and baffles, in order to allow the rerouting and control of wastewater into the aeration basins. Engineering and design has been completed and construction is expected to begin in the summer 1996. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $100,000 $ 0 FOURTH QUARTER 96-97 41 9514 SECONDARY CLAR~. ~ER MODIFICATIONS This project will modify the existing clarifiers to provide improved solids capture, scum removal and allow chemical additions to increase metal removal. To determine the appropriate clarifier modifications needed, a number of modifications are being investigated and tested. The investigations are expected to be completed by October 1996, after which engineering and design will begin. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $ 200,000 $ 0 FOURTH QUARTER 97-98 42 STORM DRAINAGE FUND 8870 COLLECTION SYSTEM IMPROVEMENTS This project provides improvements to the storm drain system, as identified in the Storm Drainage Master Plan and Condition Assessment Studies completed in 1993. In September 1995, Council awarded a contract to upgrade the City’s six storm water pump stations; construction will be completed in summer 1996. In spring 1996, staffwill bid a project to repair damaged storm drain system pipelines and infrastructure. Staff will issue an RFP during spring 1996 for design off Barron Park neighborhood storm drain improvements; repair/rehabilitation of deteriorated storm drains; and a project to correct recurrent street flooding at locations throughout the City. Curb and gutter replacement was incorporated into the annual street resurfacing project and performed by separate contract in 1995. Additional curb and gutter repairs will be made during 1996. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $6,740,341 $ 399,072 ONGOING 9508 ARASTRADERO CREEK EROSION REPAIRS This project will design, environmentally assess and construct improvements to Arastradero Creek between the darn and Arastradero Road. Improvements include repairing or replacing culverts and the eroded creek embankment at four culvert locations to prevent further creek erosion. A final scope of work is currently being developed before proceeding with the design. Construction is anticipated for summer 1997. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $ 165,070 $ 220 1 ST QUARTER 97-98 43 MULTI- ENTERPRISE FUND PROJECTS 8915 ARASTRADERO CREEK/FOOTHILL ROAD ACCESS This project will complete the landscape mitigation work for the utilities access road constructed on the Arastradero property from the Corte Madera water pump station to the Foothill Park boundary gate. A landscape restoration plan has been recommended to Council. Landscape work designed under this plan will be installed by community volunteers later this year. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $ 44,550 $ 409 2ND QUARTER 95-96 8945 AUTOMATED MAPPING This project was funded to acquire a highly detailed, high accuracy basemap of the City and its utility infrastructure. During the current fiscal year, the following occurred: 1) implementation of the basemap project; 2) quality control procedures were implemented and updated; 3) corrective feedback was provided to the vendor; 4) corrective iterations were provided to both the vendor and City staff. The basemap project should be completed by the end of this fiscal year. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $ 422,059 $ 52,879 4TH QUARTER 95-96 9352. CIVIC CENTER BUILD-OUT This project provides for the Civic Center 8th floor and mezzanine office space additions. The construction is now complete. AVAILABLE BUDGET AS OF JULY 1, 1995 $129,551 ACTUAL EXPENSE FOR 1995-96 $7,549 EXPECTED COMPLETION COMPLETED 44 9451 WATER, GAS, AND ~JRM STATION IMPROVEMENTS This project funds improvements required by the design of the Water, Gas, and Storm Stations SCADA project. The construction project has been awarded by Council and the SCADA software development has begun. The construction portion of the SCADA project will be completed in 1996. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $ 965,273 $ 4,808 2ND QUARTER 95-96 9506 MUNICIPAL SERVICE CENTER BULK STORAGE IMPROVEMENTS Construction of the bulk storage improvements at the MSC has been completed. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $ 132,102 $ 115,999 COMPLETED 9539 NEW VEHICLE PURCHASES This project provides for the purchase of three vans (dedicated Compressed Natural Gas models) to support three new positions for field inspectors. Orders will be placed in February 1996, and the vehicles should be delivered by August 1996. AVAILABLE BUDGET AS OF JULY 1, 1995 ACTUAL EXPENSE FOR 1995-96 EXPECTED COMPLETION $ 60,000 $ 0 1ST QUARTER 96-97 45