City of Palo Alto
Summary Report
TO:HONORABLE CITY COUNCIL
ATTENTION: FINANCE COMMITTEE
FROM:CITY MANAGER DEPARTMENT: Community Services
DATE:FEBRUARY 13, 1996 CMR: 123:96
SUBJECT:Implementation Plan for the Development of the Golf Course Master
Improvement Plan
This report is a follow up to CMR:298:95, Implementation and financJngd~ms_fox
development of the Golf Course_Master Improvement Plan. This report gives Council an
overview of the progress made toward implementing the Golf Course Master Improvement
Plan.
This is an informational report and there are no recommendations for action at this time.
POLICY IMPLICATIONS
This report is consistent with City policy.
The Golf Course Master Improvement Plan is a conceptual proposal to upgrade various
components of the Golf Course, as addressed in CMR: 248:95. The Master Improvement
Plan’s objectives were designed to address existing problems and to create a format that takes
advantage of opportunities permitting long-term cost savings and increased value. Council
approved a Site and Design Application in May 1995.
The Master Improvement Plan originally called for approximately $8 million of
improvements and the developement of an action plan for completion of the project. After
much study, and with participation from the departments of Administrative Services, Public
Works, and Community Services, staff developed a modified Implementation Plan to fit
within budgeting constraints.
The Implementation Plan ;~cludes $5 million for construction prolects, including design, a
project manager and a con, _gency, a long-term accelerated maim ~nce program, and a plan
to execute some Master Plan improvements at a later date due to financial constraints. The
benefits of the proposed project are considerable, including irrigation, drainage, fairway, and
driving range improvements. These enhancements will provide for a high quality Golf
Course that will facilitate maintenance, ensure water savings by using reclaimed water more
efficiently, significantly improve playing conditions, and solidify long-term revenues through
a satisfied customer base.
To finance this project, staff is formulating a plan that involves issuing bonds and a possible
subsidy to the Golf Course from the General Fund, as Golf Course revenue will not cover all
costs during the construction phase. Staff is also exploring potential partnerships with
tenants that would result in customer service improvements, and long-term enhancements to
the restaurant and pro shop. Tenant improvements are not included in the $5 million. Tax
law changes regarding the use of tax exempt bonds for portions of the Golf Course
improvements, have raised issues that require additional research and discussion. A separate
staff report recommends retaining a financial advisor to assist staff in studying these
questions with bond counsel, supporting discussions on tenant lease negotiations, and
structuring a financing package.
FISCAL IMPACT
No fiscal impact at this time.
ENVIRONMENTAL AS~tESS31EN~
1. Environmental Assessment recommended adoption of a negative declaration.
Council approved a Mitigated Negative Declaration that determined that any potential
impacts can be mitigated to levels of less than significance.
ATTACHMENTS
CMR:298:95
Golf Course Project Schedule
Prepared by: Richard James, Department of Community Services
Department Head Review:
PAUL THILTGEN
Director of Community Services
City Manager Approval:
City
CMR: 123:96 Page 2 of 8
City of Palo Alto
City Manager’s Report
SUBJECT:Implementation Plan for the Development of the Golf Course Master
Improvement Plan
RECOMMENDATIONS
This report is a follow-up to CMR:298:95, Implementation and financing plans for
development of the Golf Course Master Improvement Plan. The report gives Council an
overview of the progress made toward implementing the Golf Course Master Improvement
Plan.
BACKGROUND
The Golf Course Master Improvement Plan is a conceptual proposal developed to upgrade
various components of the Golf Course, as addressed in CMR: 248:95. Council approved
a Site and Design Application and a Mitigated Negative Declaration for this plan in May
1995.
The Master Improvement Plan objectives were designed to address existing problems and
to create a format to take advantage of opportunities permitting long-term cost savings and
increased value. The Master Improvement Plan cites the following as its objectives:
-Address critical irrigation and drainage problems;
-Optimize the use of reclaimed water;
-Maintain affordable green fee structure and provide quality golf;
-Minimize environmental impacts relative to areas of potential renovations;
-Ensure the safety of golfers, staff and neighbors;
-Balance long-term maintenance and budgetary requirements;
-Improve parking, restaurant, golf shop and driving range facilities to meet
safety issues and enhance revenue production; and
-Improve the maintenance and storage facilities to address associated
environmental concerns.
The Master Plan originally called for approximately $8 million of improvements and
developed an action plan for completion of the project. After much study, and with
participation from the departments of Administrative Services, Public Works and
Community Services, staff developed a modified Implementation Plan to fit within budgeting
constraints. The objectives of the modified Implementation Plan are:
CMR: 123:96 Page 3 of 8
-Address the most pressing recommendations of the Master Improvement Plan,
-Develop a viable financial plan, and
-Maintain revenue flow by not closing the Golf Course during construction periods.
The modified Implementation Plan includes $5 million for construction projects, including
design, a project manager and a contingency, a long-term accelerated maintenance program,
and a plan to execute Master Plan improvements that are being deferred due to financial
constraints. The benefits of the proposed project are considerable, including irrigation,
drainage, fairway, and driving range improvements. These enhancements allow for a high
quality Golf Course that will facilitate maintenance, ensure water savings by using reclaimed
water more efficiently, significantly improve playing conditions, and solidify long-term
revenues through a satisfied customer base.
To fmance this project, staffis formulating a plan that involves issuing bonds and a subsidy
to the Golf Course from the General Fund, as golf course revenue will not cover all operating
and debt service costs during the construction phase. Staff is also exploring potential
parmerships with tenants that would result in customer service improvements, and long-term
enhancements to the restaurant and pro shop. Tenant improvements are not included in the
$5 million. Tax law changes regarding the use of tax exempt bonds for portions of the Golf
Course improvements, have raised issues that require additional research and discussion. It
is anticipated that bonds will not need to be sold until 1997-98.
POLICY IMPLICATIONS
This report is consistent with current City policy.
DISCUSSION
IMPLEMENTATION PLAN
The proposed Implementation Plan is the result of a collaborative effort by City staff to
design a program that balances customer needs with the need for horticultural and drainage
improvements to the Course, regulatory agency requirements, and available funding. This
Implementation Plan is grouped into ten areas consisting of: Project Management, Consultant
Selection, Project Design, Interim Improvements, Project Schedule, Proposed Construction,
City Staff Implemented Improvements, Tenant Improvements, Enhanced Maintenance
Program and Financial Plan.
Project Management
Project management will be accomplished using a unique, team concept, composed of staff
from the Public Works and Community Services Departments. This team approach will take
advantage of each Department’s strengths and expertise. Community Services staff possesses
knowledge and experience in Golf Course design, operation and maintenance, and works
closely with the golf community. Public Works’ expertise lies in project planning, document
CMR: 123:96 Page 4 of 8
preparation and contra,..legotiations. All aspects of the prt.j..ct will be monitored and
appropriate decisions made using the knowledge and background contained within each
Department. Staff is confident that this team approach to project management will be a
blueprint for future projects of this nature.
Consultant Selection
The Master Plan consultants, Amphion Environmental, Inc. and Halsey Daray Golf, will
provide the design and construction services for this project. The 1994 Golf Course Master
Improvement Plan "Request for Proposals" included a provision to retain the consultant for
future design work, if the initial work were deemed successful. The firrns selected to prepare
the Master Plan were successful in working with the community and City staff, and
developed a quality product. Subsequently, staff is commencing negotiations with Amphion
Environmental, Inc. and Halsey Daray Golf to have them continue to supply the services
necessary to carry out the Master Plan.
Project Design:
The proposed Implementation Plan includes all of the recommended Master Improvement
Plan Golf Course renovations. Although there are not sufficient funds to pay for all of these
renovations, staff proposes that all greens, tees and fairways proposed to be rebuilt, be
designed now with some as add-alternates to the bid. This would allow them to be included
in the construction project, should estimates come in lower than anticipated. Designing all
of the Course improvements at this time will also allow for consistency of design, create cost
efficiencies, and provide opportunities to proceed with the balance of the improvements
should resources become, available in future years.
Interim Improvements:
To allow continued golf play during the project, City staff will make necessary interim
improvements to the Golf Course before construction. These include building temporary
greens and tees, erecting safety barriers around the modified tee areas, and performing minor
irrigation changes to help maintain the temporary greens and tees. Staff will return to
Council following the design process with recommendations for temporary staffmg, and
supplies and materials for interim improvements.
Project Schedule
This element of the project is scheduled to begin its design phase in April 1996 and be
completed in April 1997. Interim construction (temporary tees and greens) would commence
no later than July 1997 and reach completion in time for course demolition, grading and
renovation beginning in March 1998. Bonds would most likely be sold during this time. The
initial construction project would be completed between March 1999 and June 1999. (A
detailed project schedule is attached.)
Proposed Construction:
The work that will be accomplished during the initial construction period includes:
Golf Course:
CMR: 123:96 Page 5 of 8
0
Construction of a master drain system and storm reservoir.
Replacement of the irrigation system.
Reconstruction of five fairways, approximately nine greens and fourteen bunkers.
Grading and leveling six tees and renovating various rough areas throughout the Golf
Course.
Driving Range:
¯ Reposition the driving range away from Embarcadero Road. Install higher fencing to
contain errant balls from entering Embarcadero Road, office buildings, and the tenth
fairway.
.Grade, sand cap, install irrigation, and plant turf on the range.
Parking Lot/Access Road:
o Enlarge parking lot and provide a new exit to Embarcadero Road to improve traffic flow.
¯Improve the Golf Course/Airport access road.
°Improve restaurant delivery service entry and employee parking area.
City Staff Implemented Improvements:
The Parks and Golf Division can complete the balance of the deferred improvements through
a combination of in-house work, outside contracts and capital improvement projects. The
deferred components could be funded when cash flow allows, which staff estimates to be in
the fiscal year 2005-06. Completion of deferred components may include:
Repairing and enhancing the cart path system;
Planting trees for safety and esthetics;
-Improving the fairways, greens and tees that were not part of the initial
project;
-Maintaining facility improvements; and
-Other items as defined in the Master Improvement Plan.
Tenant Improvements:
Several improvements recommended in the Master Improvement Plan included customer
service enhancements to Golf Course tenant facilities. Implementing such improvements
is contingent upon future lease contracts with the restaurant and pro shop operators.
Potential tenant improvements include:
Pro shop expansion allowing increased retail space, retail storage, and
potential increases in revenue;
Installation of driving range lighting allowing for limited night use and
increased revenues;
-Additional restaurant seating capacity enabling large tournament and meeting
groups to use the facility, thus increasing potential revenue sources; and
CMR: 123:96 Page 6 of 8
-Outside restaurant seating and a pass-through service window to provide
quick and easy access for golfers and non-golfers to obtain food and beverage
service.
Enhanced Maintenance Program
The Golf Course consultant and the Master Improvement Plan recommend an enhanced
maintenance program. Accomplishing this will require an increase in present levels of
maintenance expenditures, which involves augmentations in staffing, equipment and
materials. Noting that present staffmg levels are considerably below comparable courses,
the Master Plan recommends at least three full time staff be added to the operating budget.
This implementation proposal recommends the addition of two full time maintenance "
personnel. The additional personnel will facilitate the Master Plan’s recommended increase
in turf maintenance and aid in the completion of deferred maintenance and Master Plan
projects.
The Master Plan also recommends an accelerated topdressing program to improve existing
turf conditions and to reduce future capital costs for improvements. This topdressing
program is designed to improve the soil structures and medium for those fairways deferred
or not designated for sand capping. Periodic light layers of sand, approximately 1/4" thick,
will be applied to the fairways to improve existing soil conditions and drainage in the surface
of the soil structure. The sand will be applied monthly during the growing season. The long-
term goal is to raise the existing surface of the fairways 12 to 18 inches, over a 7 to 10 year
period, creating a medium suitable to growing turf and better utilization of reclaimed water.
Implementation of this program calls for an increase to the operation budget of $150,000 for
supplies and materials.
Financial Plan
To finance the Implementation Plan, staff has been formulating a financial plan that involves
funding from a bond issuance for construction projects and a subsidy from the General Fund
to maintain golf operations during the construction period, when green fee revenue will
decline due to an anticipated decline in golf rounds played. In exploring bond fmancing, a
number of issues arose which affect the type and amount of debt that can be issued and also
affect the City’s Golf Course’s contractual arrangements with its tenants. Because staff is
still working with bond counsel and the Golf Course tenants on these issues, a reasonably
accurate pro forma cannot be prepared at this time. However, staff is able to provide
background information into the questions at hand and into the essential features of Master
Plan fmancing.
Bond Financing Issues
A nonprofit Golf Course Corporation was formed in 1977 to facilitate Golf Course
improvements. Since the Corporation last issued debt in 1978, tax laws have changed. These
changes center on the extent to which a tax-exempt bond issuance for a public facility can
CMR: 123:96 Page 7 of 8
benefit a private, for profit business. The City also has the option of issuing taxable bonds
for Master Plan improvements. Use of taxable bonds allows the City to enter into any type
of contractual agreement with lessees and make any improvements Council approves, but
that method of financing is more costly. The type of bonds issued, therefore, has an impact
on the amount of debt that can be incurred, and on the terms of the leases with tenants. The
role of the financial advisor will be to help staff study these questions with bond counsel,
support discussions on tenant lease negotiations, and structure a financing package. Based
on a conservative, tax-exempt rate of 6.3 percent and anticipated project and issuance costs
of $5.6 million, the Golf Course’s annual debt service would equal $501,000 per year. At a
higher, taxable bond rate of 8.3 percent for the same project, an annual debt service of
$584,000 would be required. The rate spread, between the types of bonds issued, requires
staff to carefully assess options and altematives in financing the Master Plan and in
developing contracts with lessees. In addition, staff will explore with bond counsel whether
the issuance of new debt requires the Golf Course to refinance the remaining debt from the
1978 bond issuance.
ALTERNATIVES
Alternatives are not addressed in this report.
FISCAL IMPACT
The recommendations in this report have no direct fiscal impact.
ENVIRONMENTAL ASSESSMENT
Council approved a Mitigated Negative Declaration for this project in May 1995
(CMR:248:95). Major issues that were discussed included biotic resources, hazardous
materials, reclaimed water, flooding, lighting and glare, and traffic and circulation. The
Mitigated Negative Declaration determined that any potential impacts can be mitigated to
levels of less than significance.
STEPS FOLLOWING APPROVAL
1. Develop Request for Proposal for financial advisor services.
2. Award contract to Financial Advisor.
3. Begin contract negotiations with Amphion Environmental, Inc., and Halsey Daray
Golf.
4. Return to Council for approval of an amended consultant contract including a Budget
Amendment Ordinance.
5. Create a Capital Improvement Project for construction design services.
6. Initiate design work for the project.
ATTACHMENTS/EXHIBITS
CMR:298:95
Golf Course Project Schedule
CMR: 123:96 Page 8 of 8
City of Palo Alto
City Manager’s Report
TO:HONORABLE CITY COUNCIL
FROM:CITY MANAGER DEPARTMENT: Community Services
AGENDA DATE:
SUBJECT:
June 12, 1995 CMR: 298:95
Implementation and financing plans for development of the Golf
Course Master Improvement Plan
REQUEST
This is an informational report and no Council action is requested.
RECOMMENDATIONS
There are no recommendations at this time. Staff will submit to the Finance Committee a
recommendation for implementation, development and financing, for the Golf Course Master
Improvement Plan, late this Summer. A Committee recommendation could then be given to
Council in the Fall.
POLICY IMPLICATIONS
This project does not represent any change to existing City policies.
EXECUTIVE SUMMARY
The Golf Course Master Improvement Plan is a conceptual proposal to upgrade various
components of the golf course, as addressed in the Planning and Community Environment Site
and Design CMR: 248:95. Staff, the Consultant Team and the Golf Advisory Committee will
continue to refine the technique for developing and financing the Master Improvement Plan.
Finance, Community Services and Public Works Departments are in the process of reworking
the pro forma financial statements and the development of work schedules, so that this project
can be accommodated within fiscal constraints, and allow the Golf Course to remain open in
some manner during the construction phase to minimize public disruption.
FISCAL IMPACT
There is no fiscal impact at this time.
CMR: 298:95 Page 1 of 2
ENVIRONMENTAL ASSESSMENT
There is no environmental assessment or impact associated with this report.
Related CMR:248:95 Site and Design Application
(Copies available in City Manager’s Office)
PREPARED BY: Paul Dias, Parks and Golf Division
DEPARTMENT HEAD REVIEW:
PAUL
Director of Community Services
CITY MANAGER APPROVAL:
er
CC:Golf Advisory Committee
Golf Course Corporation
CMR:298:95 Page 2 of 2
GOLF CbdRSE PROJECT S HEDULE
February 6, 1996
Construction Start July 97
WORK ITEM
Council review RFP for Financial Advisor
Negotiate Consultant Agreement
Council approve Consultant Agreement
Amendment.
Prepare preliminary Plans (10%)/Review by
Staff
Golf Advisory Board/ARB
Prepare 50% Plans/Review by staff
Prepare 95% Plans!Review by staff
Council approve financial plan
Golf Advisory Board
Prepare !00% Plans/Solicit Bids
Award Construction Contract
Start Construction
Storm Drainage
Irrigation
Parking Lot and Entrance Road
Rough and Final Grading
ACTION
DATE
February 96
April 96
August 96
February 97
April 97
July 97
July 97
START
March 96
May 96
September 96
¯ January 97
April 97
July 97
July 97
July 97
March 98
Landscaping
Driving Range
End Construction June98
April 98
March 98
FINISH
April 96
August 96
December 96
April 97
May 97
October 98
October 98
October 98
April 98
June 98
June 98
>.
>.
0
<>
~0