HomeMy WebLinkAbout1996-02-01 City CouncilCity of Palo Alto
City Manager’s Report
TO:HONORABLE CITY COUNCIL
FROM:CITY MANAGER DEPARTMENT: PLANNING
DATE:February 1, 1996 CMR:134:96
SUBJECT:Caltrans Project to Install a New Southbound On-ramp to U.S.
Route 101 at San Antonio Road, Related Changes .to the
Charleston Road/San Antonio Road Intersection, and Ramp
Metering Along U.S. Route 101 in the Southbound Direction
REQUEST
This is an informational report, and no Council action is requested. Caltrans has had a
proposed project (a) to install a new sonthbound on-ramp to U.S. Route 101 at San
Antonio Road along with related changes to the Charleston Road/San Antonio Road
intersection, and (b) to install ramp metering along U.S. Ronte 101 in the southbound
direction.
Recently, Caltrans has decided to delete the portion of the project that involves the new
southbound on-ramp at San Antonio Road and related changes to the Charleston
Road/San Antonio Road intersection and to proceed with only the portion of the project
that involves the installation of ramp metering along U.S. Ronte 101 in the southbound
direction (Attachment 1).
Whereas Caltrans would have needed City approval of a revised Freeway Agreement in
order to install the new southbound on-ramp at San Antonio Road, Caltrans does not need
City approval for the ramp metering, as long as it does not involve any work witlfin the
City’s fight-of-way and does not conflict with the existing freeway agreement. Therefore,
Caltrans has not requested formal .approval of ramp metering from Palo Alto or other
similarly affected cities (Mountain View, Santa Clara and Stmnyvale).
The i~urpose of this report is to share information regarding the evolution of this project.
RECOMMENDATIONS
No Council action is required or recommended.
CMR:134:96 Page 1 of 7
POLICY IMPLICATIONS
The project, as originally proposed, is consistent with efforts to maintain and improve
traffic conditions in major travel corridors and on regional roadway facilities. These are
important considerations, in view of efforts to improve air quality and meet the objectives
and requirements of the Santa Clara County Congestion Management Program. The
deletion of the proposed new on-ramp at San Antonio Road, and closure of the existing
Charleston on-ramp diminishes, but does not negate, some operational improvement for
fi’eeway traffic flow.
In 1982, when Caltrans proposed a set of operational improvements for southbound Route
101 it was referred to as the "Congestion Relief Project" and included both ramp metering
and a new on-ramp at San Antonio Road and closure of the existing Charleston Road on-
ramp. The City Council reviewed and approved that project, subject to several
conditions. The current project, as originally proposed, includes essentially the same
operational improvements proposed in the earlier Congestion Relief Project, and
incorporates measures that address the conditions raised by the City of Palo Alto, during
the review of the earlier (1982) proposed project.
EXECUTIVE SUMMARY
Background
Caltrans has had a proposed project that would make certain operational improvements
along U.S. Route 101 (San Mateo County line to Route 880). The proposed changes in
Palo Alto would include the following items:
Construction of a new southbound entrance ramp to Route 101 from San Antonio
Road, in conjunction with
the concurrent closure of an existing southbound Charleston Road entrance
ramp, at the Rengstorff Avenue interchange;
the installation of a traffic signal at the new intersection of the new freeway
entrance ramp and San Antonio Road; and
the minor widening of Charleston Road to provide two southbound left-
turn lanes onto San Antonio Road.
CMR:134:96 Page 2 of 7
Installation of ramp metering [including High Occupancy Vehicles (HOV)
preference at some locations] on southbound entrance ramps to Route 101 at:
Embarcadero Road,
Oregon Expressway, and
San Antonio Road (new entrance ramp).
In order for Caltrans to proceed with the new on-ramp at San Antonio Road (part A),
Caltrans needs, and has requested that the City of Palo Alto approve, a new Freeway
Agreement, as well as a related Cooperative Agreement and two Utility Agreements.
However, regarding ramp metering (Part B), Caltrans does not need City approval for the
ramp metering, as long as it does not involve any work within the City’s right-of-way and
does not conflict with the existing freeway agreements. Therefore, Caltrans has not
requested formal approval of agreements with the City of Palo Alto, or other similarly
affected cities (Mountain View, Santa Clara and Sunnyvale).
The Council, at its regular meeting on Monday, March 22, 1993 considered the subject
project and decided to continue the item until the April 12, 1993 City Council meeting.
The item was then removed from the April 12th agenda, for the purpose of further
evaluation. Subsequently, Caltrans put the prdject on hold pending completion and
approval of required air quality analyses and other priority projects..
Included as Attachment 2 is an earlier staff report (CMR: 186:93; March 18, 1993) that
provides more detail regarding the project. Additional information on three issues
discussed at the March 1993 meeting is provided as Attaclmaent 3.
Current Status
During the intervening three years since this topic was last before the Council, Caltrans
has completed a study to evaluate the air quality impacts on receptors near metered ramps.
The Metropolitan Transportation Commission (MTC) has reviewed the study and
concluded that the project meets air quality conformity requirements (Attachment 4).
In August 1995, Caltrans advised City staffthat they were prepared to proceed with the
advertisement and construction of the project and requested final Palo Alto City Council
action on elements that require approval of the City of Palo Alto.
CMR:134:96 Page 3 of 7
In the process of final staff review and preparation of information for Council review, a
concern regarding the adequacy of the length of the proposed double left-turn lane, to be
installed on the southbound approach of Charleston Road at the San Antonio intersection,
arose. Several discussions with Caltrans staff established that the proposed length of the
double let~-mm lane is insufficient and would, thereby, cause a negative impact on a local
City street. Measures to resolve the negative impact, by extending the length of the
double left-turn lane, are either insufficient and/or result in further negative impacts at the
Charleston/Fabian intersection.
Further discussions with Caltrans staff led to consideration of several other possibilities,
all predicated upon the new assumption that the Charleston on-ramp to Route 101 would
remain open, rather than closing it. This would redistribute traffic on Charleston Road in
a manner that renders the proposed length of the double left-turn lane sufficient.
Alternatives
During these discussions, Caltrans indicated a willingness to consider three options
regarding the new on-ramp and related changes to the Charleston Road!San Antonio Road
intersection. In all cases, installation of ramp metering on all southbound on-ramps would
proceed as proposed.
Option 1:Build the San Antonio on-rmnp, close the Charleston on-ramp, and modify_.
City_ streets as proposed.
This plan is the proposed project reviewed by Council at the March 1993
meeting, and is clearly Caltrans’ preference. This plan includes the closure
of the Charleston on-ramp, which is one of the primary freeway
operational improvements which this project is intended to achieve.
However, it results in a negative impact in the area of the
Charleston~abian intersection that calmot be satisfactorily resolved.
Option 2:Build the San Antonio on-ramp, leave the Charleston on-ramp open, and
do not make any changes to City, streets.
This plan forgoes one of the primary freeway improvements that the
project is intended to achieve, namely the closure of the Charleston on-
ramp. In addition, the existing left-ram storage on southbound Charleston
at San Antonio would be insufficient to handle some increment of
additional left-turning vehicles, attracted to the new San Antonio on-ramp.
CMR:134:96 Page 4 of 7
This plan would also require some type of formal legal agreement between
Caltrans and Palo Alto, as well as Mountain View (the jurisdiction within
which the existing Charleston on-ramp is located), in order to ensure that
the Charleston 0n-ramp is not closed at some future time, without the
concurrence of Palo Alto.
Option 3:Do not build the San Antonio on-ramp, leave the Charleston on-ramp open,
and make no changes to City. streets.
While this option also forgoes one of the primary freeway improvements
that the project is intended to achieve (closure of the Charleston on-ramp),
it has little or no impact on Palo Alto’s streets and intersections.
No agreement between Caltrans and Palo Alto and no further action by the
Council would be required for this alternative. While problematic, there
may come a time in the future when Caltrans again proposes the
construction of a new southbound on-ramp at San Antonio Road, in
conjunction with other actions.
In addition to these three options, City staff felt that there was another and better option.
Option 4:Build the San Antonio on-ramp, leave the Charleston on-ramp open, and
modify. City streets as proposed.
This plan would satisfactorily resolve the negative impact in the area of the
Charleston/Fabian hatersection associated with Option 1, while still
achieving some, albeit not all, of the freeway operational improvement
associated with the closure of the existing Charleston on-ramp. By not
closing the Charleston on-ramp to Route 101, traffic on Charleston Road,
on the southbound approach to the San Aa~tonio intersection, would be
redistributed in a manner that renders the proposed length of the double
left-turn lane sufficient.
This option would also require some type of formal legal agreement
between Caltrans and Palo Alto, as well as Mountain View (the
jurisdiction within which the existing Charleston on-ramp is located), in
order to ensure that the Charleston on-ramp is not closed at some future
time, withont the concurrence of Palo Alto.
CMR:134:96 Page 5 of 7
Conclusion
Caltrans clearly prefers to proceed with the project as originally proposed (Option 1),
which is to include the construction of a new San Antonio on-ramp and close the existing
Charleston on-ramp. However, without resolving the identified associated negative impact
on a local City street and preparation of appropriate environmental documentation, City
staff does not support Option 1.
Caltrans indicated some willingness to proceed with Option 2, which they feel addresses
and resolves the concern regarding the negative impact on a local City street, provided
Palo Alto agrees to support the closure of Charleston Road, if and when some undefined
criteria are met in the future. City staff does not believe that the existing left-turn storage
along Charleston Road at San Antonio Road is sufficient and, therefore, a negative impact
is likely to occur. Furthermore, it appeared that the intent and content of a potential
agreement regarding the future closure of Charleston Road was viewed quite differently
by Caltrans staff and City staff.
Caltrans indicated that they believe there is not sufficient justification from a traffic
operations standpoint to support Option 4, which includes the improvements at the
Charleston Road!San Antonio Road intersection and did not agree that a negative impact
would occur on City streets if Option 2 were built. Therefore, they would not support
Option 4.
Subsequently, Caltrans has now advised City staffthat they are proceeding with Option 3,
which provides for the installation of ramp metering along U.S. route 101 in the
southbound direction, and deleting the portion of the project that involves the new
southbound on-ramp at San Antonio Road. They are revising their plans for submittal to
their headquarters office for approval and advertisement.
Whereas Caltrans’ would have needed City approval of a revised Freeway Agreement in
order to install the new southbound on-ramp at San Antonio Road, Caltrans’ position is
that they already have the necessary authority to fully implement ramp metering; and,
therefore, have not requested formal approval of ramp metering from Palo Alto or other
similarly affected cities (Mountain View, Santa Clara and Suunyvale).
City staffhad offered to bring the issue of the various options before the Council for some
policy direction, and was prepared to do so on January 16, 1996, Caltrans indicated that
they did not wish to bring the item to the Council without City staff support and agreement
with Caltrans regarding a recommended option.
CMR: 134:96 Page 6 of 7
In summary, Caltrans is proceeding with the implementation of a project that includes
installation of ramp metering on the southbound lanes of U.S. Route 101 at Embarcadero
and Oregon in Palo Alto. Work on this project is likely to begin in the late spring or
summer of this year (1996). No changes (additions or closures) are to be made to the
ramp configuration that now exists at San Antonio Road and Charleston Road and no
changes will be made to the Charleston Road!San Antonio Road intersection.
FISCAL IMPACT
There is no fiscal impact to the City of Palo Alto.
ENVIRONMENTAL ASSESSMENT
Caltrans has indicated that they have completed the necessary environmemal analysis to
proceed with this project.
ATTACHMENTS
1:Letter from Caltrans (January 5, 1996) regarding options and intent.
2:Staff Report (CMR:186:93; dated March 18, 1993).
3:Additional information regarding three topics discussed at March 22, 1993 Council
meeting.
4: Letter from Caltrans (September 12, 1995) regarding air quality conformity.
Prepared By: Marvin L. Overway, Chief Transportation Official
Department Head Review:
KENNETH R. SCHREIBER
Director of Plmming
and Community Environmem
City Manager Approval:
City
CO:Caltrans (Stewart Ng)
City of Mountain View (Dennis Belluomini)
James Dinkey
Larry Barone
Walt Bailey
Leanne Bryant
Jack Woodson
Owner/managers
835 & 851 San Antonio
830, 849, & 870 Charleston
CMR: 134:96 Page 7 of 7
STATE OF CAUFORNIA--BUSINESS, TRANSPORTATION AND HOUSING AGENCY
DEPARTMENT OF TRANSPORTATION
DISTRICT 4, OFFICE OF PROJECT DEVELOPME~f
SANTA CLARA COUNTY
1754 Technology Drive, Suite 200
San Jose, CA 95110
ATTACHMENT1
PETE WIL~ON, Governor
January 5, 1996
Mr. Marvin L. Overway
Chief Transportation Official
City of Palo Alto
P. O. Box 10250
Palo Alto, CA 94303
Dear Mr. Overway:
The purpose of this letter is to confirm our understanding of the current status of the
proposed project to construct a new southbound on-ramp to Route 101 at the San Antonio
interchange and to install ramp metering along southbound Route 101 from the San Mateo county
¯ line to the De La Cruz Boulevard!Trimble Road Interchange.
In the meeting with you on December 6, 1995, our staff discussed three options:
Option 1
Build the Route 101 southbound on-ramp at the San Antonio Interchange, close the
Charleston Road on-ramp to southbound Route 101 and provide street improvements at
the San Antonio Road/Charleston Road intersection. This option provides:
Two metered mixed-flow lanes at the new on-ramp to provide maximum storage
of 44 vehicles (maximum demand is 30 vehicles.
250 feet double left turn lanes from southbound Charleston Road to eastbound San
Antonio Road. The demand for these.left turns requires 900 feet of left turn
storage length. Due to the close proximity with the Fabian/Charleston
intersection, the required storage length cannot be met.
This option was reflected on the Plans Specifications and Estimate (PS&E) transmitted to
the City on September 21, 1995 for review and comments.
Mr. Marvin L. Overway
January 5, 1996
Page 2
Option 2
Build the new Route 101 southbound on-ramp at the San Antonio Interchange. The
existing Charleston Road to southbound Route 101 on-ramp remains open. This on-ramp
will not be metered under this project due to limited space for storage. There are no city
street improvements under this option.
Option 3
Not build the new on-ramp, at San Antonio Interchange. The existing Charleston Road
on-ramp to southbound Route 101 remains open. The proposed project will move
forward with ramp metering on other southbound on-ramps, except the Charleston Road
on-ramp to southbound Route 101.
In the meeting with our staffon November 21, 1995, you indicated your opposition to the
Option 1 because of potential impacts on city streets due to lack of storage length for lef~ turn
movements at the San Antonio Road/Charleston Road intersection.
In the December 6, 1995 meeting, you again confirmed your position not to support
Option 1. You also requested Caltrans to revise Option 2 to include the improvements at the San
Antonio Road/Charleston Road Intersection as called out in the PS&E under Option 1. Without
those improvements included, you were opposed to Option 2.
We have considered your proposal, but there is not sufficient justification from a traffic
operations standpoint to support the improvements at the San Antonio Road/Charleston Road
intersection. We believe the majority of the traffic currently using the Charleston Road on-ramp
will continue to use that on-ramp. Only a portion of that traffic will use the new on-ramp at San
Antonio Road Interchange, since this ramp will be metered. Therefore, Caltrans will be
proceeding ahead with Option 3.
We are making corrections on the project’s PS&E to remove all works at the Route
10 I/San Antonio Road Interchange as well as street improvements at Charleston Road/San
Antonio Road Intersection. As you are aware, this project is in the CTC’s 1995 Allocation Plan
and it is critical that there be no further delays to the project. The final project’s PS&E will then
be submitted to our Headquarters in the later part of January, 1996 for approval and
advertisement.
Mr. Marvin L. Overway
January 5, 1996
Page 3
If you have any questions, please contact Paul Mai, Senior Transportation Engineer, at
(408) 452-7331.
Sincerely,
JOE BROWNE
Distric~!~irector
STEWART D. NG, 0ffice~
Division of Design West
Project Development, Santa Clara "B"
sta o,t
March 18, 1993
ATTACHMENT 2
12
HONORABLE CITY COUNCIL
Palo Alto, California
APPROVAL OF AGREEMENTS BETWEEN THE STATE OF CALIFORNIA AND CITY OF
PALO ALTO IN CONNECTION WITH U.S. ROUTE i01 NEW ON-RAMP AT SAN
ANTONIO ROAD,RELATED CHANGES TO CHARLESTON ROAD/SAN ANTONIO ROAD
INTERSECTION,AND RAMP METERING ALONG U.S. ROUTE i01 IN SOUTHBOUND
DIRECTION
Members of the Council:
REPORT IN BRIEF
The California Department of Transportation (Caltrans) has proposed
a project that will make certain operational improvements along
U.So Route i01 (San Mateo County line to Route 880)° The proposed
changes in Palo Alto, as illustrated in Figures 1 and 2, include
the following items:
Part A
Construction of a new southbound entrance ramp to Route i01
from San Antonio Road, in conjunction with:
the concurrent closure of an existing southbound
Charleston Road entrance ramp at the Rengstorff Avenue
interchange,
the installation of a traffic signal at the new
intersection of the new freeway entrance ramp and San
Antonio Road, and
the minor widening of Charleston Road to provide two
southbound left-turn lanes onto San Antonio Road.
CMR:186:93
Part B
Installation of ramp metering (includlng High Occupancy
Vehicles (HOV) preference at some locations) on southbound
entrance ramps to Route I01 at:
Embarcadero Road,
Oregon Expressway, and
San Antonio Road (new entrance ramp)
In order for Caltrans to proceed with the new on-ramp at San
Antonio Road (Part A), Caltrans needs and has requested that the
City of Palo Alto approve a new Freeway Agreement, as well as two
Utility Agreements° However, regarding ramp metering (Part B),
Caltrans, position is that it already has the necessary authority
to fully implement ramp metering; therefore, Caltrans has not
requested formal approval or agreements with the City of Palo Alto,
or other similarly affected cities (Mountain View, Santa Clara, and
Sunnyvale). The City Attorney agrees that Caltrans does not
specifically need Palo Alto’s approval for the ramp metering
project° However, the Attorney’s office has requested, and
Caltrans has agreed, that the two agencies also enter into a
Cooperative Agreement that would supplement the Freeway Agreement
by delineating the rights and responsibilities of.each party with
respect to the on-ramp project and the ramp metering project. The
Cooperative Agreement does not mandate that either project be done.
The purpose of this report is to recommend, with respect to Part A
(construction of a new southbound entrance ramp to Route i01 from
San Antonio Road, and related changes to Charleston Road), that the
Council:
(1)
(2)
(3)
(4)
find that Part A of the proposed Caltrans project is
consistent with the Comprehensive Plan,-and the Negative
Declaration prepared by Caltrans is adequate;
approve Part A of the proposed Caltrans project;
approve a resolution (Attachment i) authorizing the Mayor
to sign a Cooperative Agreement (Attachment 2) and a new
Freeway Agreement (Attachment 3) with the State of
California for Route I01 within the City of Palo Alto;
authorize the Mayor to sign a Utility Agreement with the
State of California for relocation of electric facilities
(Attachment 4); and
(5)authorize the Mayor to sign a Utility Agreement with the
State of California for relocation of gas facilities
(Attachment 5).
C~R:186:93 3118193
Page 2
Staff also recommends, with respect to Part B (installation of ramp
metering, including HOV preference, on southbound entrance ramps to
.Route i01), that the Council:
(6)underscore the importance of a commitment by Caltrans to
(a) ongoing monitoring of the operations; (b) a thorough
operational evaluation, inclusive of before and after
conditions; and (c) remedial actions/projects to address
any adverse impacts on local city streets.
BACKGROUND AND DESCRIPTION OF PROJECT
In 1982, Caltrans proposed a set of operational improvements for
southbound Route I01 that was referred to as the "Congestion Relief
Project,,. The City reviewed and approved that project (subject to
several conditions); however, Caltrans never implemented the
project, due to a number of factors. The current proposed project
includes, essentially, the same operational improvements previously
proposed in the earlier Congestion Relief Project, and incorporates
measures that address the conditions raised by the City of Palo
Alto, during the review of the earlier proposed project.
Purpose of New San Antonio Road Entrance RamD CPart A)
The purpose of closing the existing southbound Charleston Road
entrance ramp and replacing it with a new entrance ramp at San
Antonio Road is to reduce the repetitive delays and conflicts at
the Rengstorff interchange. The congestion at this location is
caused by vehicles entering Route i01 from Charleston Road and
exiting Route I01 to Rengstorff Avenue (compounded by the close
proximity of another entrance ramp from Rengstorff Avenue and the
relatively high volumes of traffic making these maneuvers).
Closure of the Charleston Road entrance ramp will significantly
reduce the weaving maneuvers and conflicts that presently occur at
this location, thereby improving traffic flow in the through travel
lanes, as well as the entrance and exit ramps of Route i01o The
proposed new southbound entrance ramp at San Antonio Road will
serve much the same traffic as the existing Charleston Road
entrance ramp, without many of the operational shortcomings and
negative impacts.
The closure of the Charleston Road entrance ramp at Rengstorff and
the addition of the new ramp at San Antonio Road will cause a re-
orientation of southbound traffic, that will create the heed for a
second left-turn lane on the southbound Charleston Road approach to
San Antonio Road°
CMR:186:93 3/18/93
Page 3
Purpose of Ramp Meterinq ~Part B)
When the traffic volume on a freeway is low-to-moderate, the
intrusion of traffic from freeway ramps has little or no adverse
impact on the overall flow of traffic. However, during the periods
of peak traffic flow, as the traffic volume on freeways approaches
the capacity of the roadway, the intrusion of traffic entering from
freeway ramps becomes increasingly noticeable. As the volume of
entering traffic increases, the effect on freeway traffic flow
becomes increasingly pronounced to a point where entering traffic
can, and often does, cause freeway traffic flow to deteriorate to
a stop and go condition° This reduces the actual volume of traffic
that the freeway can serve to a level well below its potentia!
capacity°
The primary purpose of ramp metering is to regulate the flow of
ramp traffic entering the freeway traffic stream during the period
of peak traffic flow, so that it has a minimal effect on the
ability of the freeway to operate at its full capacity° By
converting platoons of traffic into individual units, the merging
process can be accomplished more efficiently with less disruption
to traffic flow on the freeway, which preserves the full capacity
of the freeway and reduces accidents and delay normally encountered
in congested stop and go conditions°
Actual experience with ramp metering in Denver has resulted in a i0
to 15 percent increase in the volume-carrying capability of the
freeway° In Minneapolis, ramp metering has resulted in a 26
percent reduction in travel time and a 38 percent reduction in the
accident rate°
More Detailed Description of Proposed Project (Parts A and B)
A March 20, 1992 staff report to the Planning Commission
(Attachment 6) provides useful background information, as wel! as
a more detailed description and discussion of the various
components of the current proposed Caltrans project.
PLANNING COMMISSION REVIEW
The previous project (1982) received extensive review by the
Planning Commission° Since the current proposed project will widen
an existing roadway and is considered to have some effect on the
physical development of the City, it was brought before the
Planning Commission for its review and comments in accordance with
Section 19o04o050 of the Palo Alto Municipal Code.
The proposed Caltrans project was reviewed by the Planning
Commission on March 25, 1992 (minutes included as Attachment 7).
The Planning Commission passed a motion (7-0), finding that the
project is consistent with the Comprehensive Plan and the negative
CMR:186:93 3/18/93
Page 4
declaration is adequate, and recommending approval of the project
to the City Council. The motion also included the importance of a
commitment by Caltrans to: (a) ongoing monitoring of operations,
(b) a thorough operational evaluation, inclusive of before and
after conditions, and (c) remedial actions/projects to address any
adverse impacts on local City streets° Finally, the Commission
added a condition that Caltrans work with City staff, along with
Planning Commissioner Tony Carrasco,to explore additional
landscaping along Charleston Road.
LANDSCAPING PLAN
At the time of the Planning Commission review, the project, as
proposed, required the removal of a total of II trees (4 mature
trees [10-13 inches] and 7 young trees [2-3 inches]), all along
Charleston Road. The proposed plan was to plant 12 new trees
within the private, adjacent landscaped area belonging to Sun
Microsystems. Figure 3 illustrates the locations of trees that are
to be removed and the location of the new trees.
The Planning Commission discussion reflected a strong interest in
having additional trees included as part of the proposed project,
including the possibility of a landscaped median° The action of
the Planning Commission was to ask Caltrans, City staff and
Commissioner Carrasco (having expressed an interest), to work
together to explore additional landscaping possibilities.
On April 2, 1992~ City staff (Transportation Division, City
Arborist, and a staff representative of the Architectural Review
Board) met with Commissioner Carrasco at the Charleston Road site,
to discuss what would be an appropriate landscape treatment for the
section of Charleston Road between San Antonio Road and Fabian Way.
The individuals present reached the following conclusions:
The provision of a landscaped median, albeit desirable, is not
practical, due to through lane off-sets, dual turning lanes,
and right-of-way limitations, and
°A total of 26 new trees should be planted along Charleston
Road, as illustrated in Figure 4. The tree replacement plan
includes the planting of 16 pistachio trees, 9 sycamore trees,
and 1 oak tree (at locations that are compatible with existing
trees which will not be removed) as part of the roadway
widening project°
Caltrans has approved a request to incorporate the 26 tree
replacement plan (Figure 4) as part of the overall Caltrans
project, rather than the previous proposed plan (Figure 3). The
project plans and specifications have been modified accordingly°
CMR:186:93 3/18/93
Page 5
NEW FREEWAY AGREEMENT
Caltrans has an established practice of executing a freeway
agreement with each jurisdiction through which its freew~ays
traverse. The agreement is a general statement of intent by
appropriate parties regarding local streets, costs, and rights-of-
way as they relate to a particular freeway alignment and
configuration, including interchanges and ramps.
The existing Freeway Agreement for the portion of Route i01 within
the City .of Palo .Alto is dated May 12, 1958. At that time,
portions of Route i01 were outside the then existing corporate
limits of the City of Palo Alto and within the jurisdiction of
Santa Clara County. Therefore, there presently exists a similar
freeway agreement between the State and the County, dated
September 17, 1958, covering the portion of Route i01 which, at
that time, fell within the jurisdiction of Santa Clara County.
In order for Caltrans to proceed with the portion of the proposed
project that involves the new southbound entrance ramp from San
Antonio Road to Route i01, Caltrans is requesting that the City of
Palo Alto execute a new Freeway Agreement. The new Freeway
Agreement would supersede the existing agreement executed in 1958
between the State and the City, as well as the one between the
State and the County, since intervening annexation has caused
portions of Route i01 previously within the County to now lie
within the jurisdiction of the City of Palo Alto. The new Freeway
Agreement incorporates a configuration for Route i01 and its
interchanges and ramps, similar to what exists today, with the
inclusion of a new freeway entrance ramp at. San Antonio Road. A
copy of the proposed new Freeway Agreement is included as
Attachment 3.
COOPERATIVE AGREEMENT
During discussions between Caltrans and City staff regarding the
Freeway Agreement, City staff raised several issues which, due to
limitations on format and content imposed by Caltrans, could not be
fully resolved within the Freeway Agreement document itself.
Therefore, a Cooperative Agreement between Caltrans and the City
was developed, as a means to resolve Palo Alto’s concerns. A copy
of the Cooperative Agreement is included as Attachment 2.
UTILITY AGREEMENTS
As part of the minor modifications to Charleston Road, there is a
need for relocation of existing above and below ground utilities.
As part of this proposed project, the City of Palo Alto will
perform the necessary work to relocate electric and gas utilities;
and Caltrans will reimburse the City for all costs related to such
work. Other utility work will be done by the project contractor to
the specifications and approval of the City of Palo Alto.
CMR:186:93 3/18/93
Page 6
The estimated costs for the utility work to be done by the City,
and fully reimbursed by Caltrans, is approximately $62,000 and
$5,000 for electric and gas facilities, respectively. A copy of
the Utility Agreement for electric related work is included as
Attachment 4, and a copy of the Utility Agreement for gas related
work is included as Attachment 5o
STATUS OF PROJECT
The plans and specifications for this project have been fully
prepared by Caltrans and the project is ready for implementation°
However, due to a new "post-CEQA" requirement from the Metropolitan
Transportation Commission (MTC) Caltrans is currently preparing
supplementa! air quality analyses and information for the project.
This will eventually be submitted to MTC for its review and
approval. In the meantime, further major progress on project
implementation is on hold.
Once Caltrans makes a firm decision to proceed with the project,
Palo Alto staff will then do the necessary electric and gas
relocation work, prior to the time that the project contractor
implements the proposed physica! changes to Charleston Road. The
portion of the project through Palo Alto is expected to take about
four months to complete and the entire project is expected to take
about ten months to fully complete°
ENVIRONMENTAL ASSESSMENT
An Environmental Assessment/Initial Study with a Negative
Declaration was prepared by the California Department of
Transportation, as lead agency, for the project and was approved by
the U.So Department of Transportation, Federal Highway
Administration, in November 1982o A copy of the Negative
Declaration and Finding of No Significant Impact are included as
attachments to the March 20, 1992 staff report to the Planning
Commission (Attachment 6).
In 1990, Caltrans completed a supplemental environmental
review/report and concluded that "changes which have occurred in
the proposal and in the surrounding conditions since the approval
of the negative declaration have been reviewed, and no evidence of
significant environmental impacts have been found°"
In addition to the Caltrans environmental assessments, the proposed
widening of Charleston Road, in conjunction with the closure of the
existing Charleston Road entrance ramp and the provision of a new
southbound entrance ramp from San Antonio Road (Part A), was
included in the City’s environmenta! analysis for the City Wide
Land Use and Transportation Study (87-EIA-50), as well as the San
Antonio/west Bayshore Area CS/GM Zone Study (85-EIA-7).
CMR:186:93 3/18/93
Page 7
CONCLUSION
Staff believes that the proposal to: (a) replace the existing
Charleston Road ramp with a new ramp at San Antonio Road, along
with minor widening of Charleston Road to provide two left-turn
lanes (Part A) and (b) install ramp metering with HOV preference,
where practical (Part B), will individually and collectively
contribute to improved traffic flow on Route i01 without
significant adverse impact on other streets. Experience indicates
that the freeway will be able to serve a higher volume of traffic
with improved travel speed, smoother traffic flow, fewer and less
severe accidents, and reduced congestion attributable to
disruptions from platoons of traffic entering from freeway ramps,
accidents, and other incidents.
Furthermore, the proposed project is consistent with efforts to
maintain and improve traffic conditions in major travel corridors
and on regional roadway facilities. These are important
considerations, in view of efforts to improve air quality and meet
the objectives and requirements of the Congestion Management
Program for Santa Clara County.
RECOMMENDATION
Staff recommends, with respect to Part A (construction of a new
southbound entrance ramp to Route i01 from San Antonio Road, and
related changes to Charleston Road) that the Council:
find that -Part A of the proposed Caltrans project is
consistent with the Comprehensive Plan and that the
Negative Declaration prepared by Caltrans is adequate;
(2)approve Part A of the proposed Caltrans project;
(3)approve a resolution (Attachment i) authorizing the Mayor
to sign a Cooperative Agreement (Attachment 2) and a new
Freeway Agreement (Attachment 3) with the State of
California for Route i01 within the City of Palo Alto;
(4)
(5)
authorize the Mayor to sign a Utility Agreement with the
State of California for relocation of electric facilities
(Attachment 4); and
authorize the Mayor to sign a Utility Agreement with the
State of California for relocation of gas facilities
(Attachment 5).
C51R:186:93 3/18/93
Page 8
Staff also recommends, with respect to Part B (installation of ramp
metering, including HOV preference, on southbound entrance ramps to
Route I01) that the Council:
(6)underscore the importance of a commitment by Caltrans to
(a) ongoing monitoring of the operations; (b) a thorough
operational evaluation, inclusive of before and after
conditions; and (c) remedial actions/projects to address
any adverse impacts on local city streets.
Respectfully submitted,
MARVIN OVERWAY
Chief Transportation official
City Manager
KENNETH R. SCHREIBER
Director of Planning and
Community Environment
Attachments:
These attachments are
available for reference in the
Transportation Division, sixth
floor, City Hall
io Resolution
2.Cooperative Agreement
3o Freeway Agreement
4°Utility Agreement (Electric)
5°Utility Agreement (Gas)
6.March 20, 1992 staff report to the Palo Alto
Planning Commission
7o March 25, 1992 Planning Commission minutes
cc:Caltrans (Dennis Bosler, Rodney Oto)
City of Mountain View
City of Menlo Park
City of East Palo Alto
City of Sunnyvale
Stanford University
Palo Alto Chamber of Commerce
Walt Bailey, Space Systems Loral
Larry Barone, Sun Microsystems
James Dinkey
Businesses in 800 block of Charleston Road
CMR:186:93 3/18/93
Page 9
ATTACHMENT 3
ADDITIONAL INFORMATION ON THREE ISSUES
DISCUSSED AT THE MARCH 1993 COUNCIL MEETING
Additional information regarding the following three topics:
o Letter commitment from Caltrans
o Ramp storage and vehicle cues
o New traffic signal at entrance ramp and San Antonio Road
LETTER COMMITMENT FROM CALTRANS
Caltrans has stated that they already have the necessary authority to
fully implement ramp metering and do not intend to seek formal
approval or formal agreements with the City of Palo Alto or other
similarly affected cities(Mountain View, Santa Clara, and Sunnyvale)
for that purpose. However, they have stated that they will work
cooperatively with the city to address impacts to local street
operation that occur after this project is implemented and,
furthermore, that the costs of such mitigation wil! be covered by the
State. Caltrans has provided a letter to the Mayor, dated April 7,
1993, reiterating their commitment to resolve any adverse impacts to
local streets and to fund, if necessary, any such actions. Short of
a formal agreement with Caltrans, staff believes this is a reasonable
basis upon which future action, if necessary, can be expected to
occur.
RAMP STORAGE AND VEHICLE CUES
Following is a summary description of the available ramp storage and
related anticipated peak vehicle queues for each of the southbound
on-ramps within Palo Alto.
Embarcadero Road EB - Caltrans information indicates that the
anticipated maximum number of vehicles in the queue will be 20, based
upon a metering rate of 7.5 sec/veh. The distance from the metering
light back to the gore area of the ramp is approximately Ii00 feet
which provides sufficient storage for 40 vehicles. This ramp
includes a narrow overpass structure that separates it from an
existing Route i01 exit ramp and makes it impractical to widen to
provide a second lane for HOV preference or other use.
CMR:Page 8 of
Embarcadero Road WB - Caltrans information indicates that the
anticipated maximum number of vehicles in the queue will be i0, based
upon a metering rate of 5.2 sec/veh. The distance from the metering
light back to the gore area of the ramp is 300 feet which provides
sufficient storage for ii vehicles. In addition, the project
includes widening the existing ramp to two lanes with one lane
designated for HOV preference. If the HOV designation were ever
removed, the additional storage area (300 feet) would accommodate ii
additional vehicles.
Oreqon Expressway - Caltrans information indicates that the
anticipated maximum number of vehicles in the queue will be 20, based
upon a metering rate of 8.0 sec/veh. The distance from the metering
light back to the gore area of the ramp is 700 feet (sufficient
storage for 25 vehicles) plus an additional 400 feet back to the
intersection of West Bayshore Road. In addition, the project
includes widening the existing ramp to two lanes with one lane
designated for HOV preference. If the HOV designation were ever
removed, the additional storage area (550 feet) would accommodate 20
additional vehicles.
San Antonio (New Ramp) - Caltrans information indicates that the
anticipated maximum number of vehicles in the queue will be 30, based
upon a metering rate of 7.0 sec/veh, and assuming two lanes of ramp
metering. The distance from the metering light back to the gore area
of the ramp is approximately 560 feet which provides sufficient
storage space for 20 vehicles on one lane and an addition 20 vehicles
on a second lane.
Caltrans’ original proposal, at this location, was to have two lanes
of ramp metering without provision for HOV preference, city staff had
requested that Caltrans.initially designate one of the lanes for HOV
preference. If actual queuing of single occupant vehicles becomes
excessive, then other options (including the designation of both
lanes for single occupant vehicles) could be pursued. Caltrans
agreed to initially designate one lane as HOV preference but
continues to believe it will not work, and the HOV preference wil!
need to be removed.
More recently, Caltrans has provided information that indicates that
a single lane would be inadequate to handle the volume of single
occupant vehicles, therefore, the second lane is needed as well. For
example, with only one mixed flow lane and one HOV bypass lane, the
anticipated maximum number of vehicles in the queue will be 135
vehicles, based upon a metering rate of 4.0 sec/veh, which is the
maximum metering rate possible for one lane. The distance from the
metering light back to the gore area of the ramp is sufficient to
accommodate only 20 vehicles and inadequate for the projected demand.
CMR:Page 9 of
Based upon further consideration of this matter, City staff concurs
with Caltrans’ assessment that both lanes of the new on-ramp will be
needed, in order to avoid excessive queues. Therefore, staff plans
to request that Caltrans modify their project to eliminate the HOV
preference at this location°
NEW TRAFFIC SIGNAL AT ENTRANCE RAMP AND SAN ANTONIO ROAD
The proposed new traffic signal at the location where the new freeway
entrance ramp connects to San Antonio Road, will operate as a simple
two-phase signal, providing green time for left turning vehicles°
Westbound traffic on San Antonio Road, coming from the freeway
overpass as well as traffic leaving Route i01 (southbound) and headed
in the direction of Charleston Road, will not be required to stop at
the new traffic signal under any situation. Eastbound traffic on San
Antonio Road, headed toward the overpass as well as headed toward the
new on-ramp, will be required to stop periodically in order to permit
left turning vehicles to safely access the new entrance ramp. During
the peak period of traffic flow in this area, eastbound traffic on
San Antonio Road will receive 90 percent of’ the green time with the
left turning vehicles receiving the remaining i0 percent.
CMR:Page 10 of
STATE OF CAUFORNIA--BUSINE~S, "fl~ANSPORTATION AND HOLI~ING AGENCY
DEPARTMENT OF TRANSPORTATION
DISTRICT 4, OFFICE OF PROJECT DEVELOPMENT
SANTA CLARA COUNTY
1754 Technology Drive, Suite 228
San Jose, CA 95110
April 7, 1993
PETE WILSON, Governor
(408) 452-7300
Honorable Jean McCown
Mayor
City of Palo Alto
P. Oo Box 10250
Palo Alto, CA 94303
Dear Mayor McCown:
At the March 22, 1993 Palo Alto City Council meeting, our
proposed project to construct a southbound on-ramp at San Antonio
Road and Route i01 and to install ramp metering on four ramps was
discussed. Questions were raised by the Council as to what
Caltrans actions and responsibilities would be if traffic on City
streets was adversely impacted by the ramp metering.
We expect our practices will be the same as those employed
in initiating and operating other metering systems in Santa Clara
County. One of the basic guidelines that we follow whenever we
begin operation of a new ramp meter is to cause no adverse
operational impacts to the local traffic on the streets adjacent
to the metered ramp. During the Initial implementation period,
Caltrans staff will closely monitor the operation of both the
meters and adjacent local streets and make adjustments to the
signal cycling rates as necessary. Our goal will be to achieve
effective ramp meter operation that benefits both freeway and
!ocal street traffic. There may be temporary impacts on local
street operation in the vicinity of the ramps during this start-
up period but we are confident that these impacts will be
negligible after we make the adjustments and as drivers become
accustomed to the ramp meters. If adverse local street operation
remains as a result of the ramp metering, Caltrans will work
cooperatively with the city and we will take the necessary steps
for correction. There are several ways that this can be
addressed. In the short term, we may be able to handle some of
the potentia! problems by adjustments to the ramp meter rates.
Other options also include converting an HOV bypass lane to mixed
flow or minor restriping or widening to provide greater storage
capacity.
Honorable Jean McCown
April 7, 1993
Page 2
Corrective actions costing less than $300,000 will be
financed directly by Caltrans. More costly solutions may require
some type of major capital improvements to the local street
system or the freeway. Under the recently implemented ISTEA
legislation, the procedure by which funding for these types of
capital improvements is secured has changed significantly. The
most likely source of funding for capital improvements is from
the Federal Congestion Mitigation/Air quality (CMAQ) program.
Although the State Transportation System Management (TSM) program
still exists as a source of funds for projects to improve traffic
operations, the number of new projects that will be funded from
it has been drastically reduced in order to support the CMAQ
program. Authority to allocate the CMAQ funds rests primarily
with the County Congestion Management Agency. Therefore, it is
likely that major improvements to address traffic congestion on
the loca! street system or freeway will require a joint effort
between the city and Caltrans to secure ISTEA funding. We will
work cooperatively with the city to pursue any needed
improvements.
We feel confident that any problems encountered can be
resolved to the satisfaction of both agencies. In the unlikely
event that an impasse occurs between Caltrans and the City, MTC
staff has agreed to act as a mediator to resolve any disputes not
resolved between us.
Our representatives will attend your Council meeting on
April 12, 1993 to respond to any further questions you might
have. If earlier information should be needed, please contact
either Dennis Bosler at (408) 452-7336 or Rod Oto at (510) 286-
4540.
Sincerely,
PRESTON W. KELLEY
District Director
GERALD E. DUCEY
Deputy District Director
Project Development "A"
South Bay Counties
STATE OF CAUFORNIA--BUSINESS, TRANSPORTATION AND HOUSING AGENCY
DEPARTMENT OF TRANSPORTATION
DISTRICT 4, OFFICE OF PROYECT DEVELOPMENT
SANTA CLARA COUNTY
1754 TechnololD’ Drive, Suite 200
San.rose, CA 95110
ATTACHMENT 4
September 12, 1995
PETE WILSON, Covemor
Mr. Marvin L. Overway
Chief Transportation Official
City of Palo Alto
P. O. Box 10250
Palo Alto, CA 94303-0862
Dear Mr. Overway:
SUBJECT: Route 101 Southbound Ramp Metering Project - Air Quality Conformity
Caltrans has completed a study to evaluate the air quality impacts on receptors near
metered ramps. The scope and the results of the study are included in a report entitled "Carbon
Monoxide Concentrations Adjacent to Ramp Meters", dated May 20, 1994.
The Metropolitan Transportation Commission (MTC) has reviewed the report and found
acceptable.
The project is now clear of air quality requirement and can proceed to advertisement and
construction.
Attached for your information are:
The June l, 1994 cover letter of the "Carbon Monoxide Concentrations Adjacent
to Ramp Meters", summarizing the findings and conclusion.
The September 15, 1994 review letter from MTC.
If you have any questions, please contact Paul Mai, Senior Transportation Engineer, at
(408) 452-7331.
Sincerely,
JOE BROWNE
District Director
Attachments
By
STEWART D. NG
Office Chief
Division of Design West
Project Development, Santa Clara "B"
STATE OF CALIFORNIA--BUSINESS, TRANSPORT,~ AND HOUSING AGENCY
D/::PARTMENT OF TRANSPORTATION
BOX 23660
OAKLAND, CA 94623-0660
(51o) 286-4.~4
TDD (510) 286-4-454
PETE WILSON,
June 1, 1994
Mr. Lawrence Dahms, Executive Director
Metropolitan Transportation Commission
Metro Center
101 Eighth Street
Oakland, CA 94607-4700
Attention: Marc Roddin, County Planning Coordinator
Dear Mr. Dahms:
Attached for your information are the results of our air quality assessment of
the State Route 101 ramp metering project at various locations from Guadalupe
River in San Jose to Moffett Boulevard Overcrossing in Mountain View in Santa
Clara Count),.
This project is identified as 04-0468, EA 396171, SC1-101-40.0/47.9, page 187,
1994 TIP, Volume II, Highway Element.
The assessment for this ramp metering project is based on actual field data
collection of carbon monoxide emissions at two currently metered ramps. They are:
1. DeAnza Boulevard on-ramp to southbound SC1-280 in Cupertino.
Two mixed-flow lanes plus one HOV lane.
Metered during afternoon peak period.
2. Blossom Hill on-ramp to northbound SC1-101 in San Jose.
One mixed-flow plus one HOV lane.
Metered during the morning peak period.
In order to evaluate the air quality impacts on receptors near metered ramps,
Caltrans initiated a CO monitoring study adjacent to the above described ramps
during the 1993-94 CO season. The scope and the results of the study are included in
the enclosed report entitled "Carbon Monoxide Concentrations Adjacent to Ramp
Meters’, dated May 20, 1994. Total Maximum 1-hour and 8-hour CO concentrations,
in parts per million (ppm) were as follows:
Mr. Lawrence Dahms
June 1,1994
Page Two
Ramp Location 1-hour 8-hour
DeAnza 6.9 ppm 4.8 ppm
Blossom Hill 7.3 ppm 6.1 ppm
The report suggests that ramp metering does not affect CO
concentrations at nearby receptors, but that there is a dear relationship between peak
driving periods and monitored CO levels. In addition, a CO burden analysis for the
freeway mainline was performed for the years 1995 and 2010. The burden analysis is
based on an operational analysis for both the BUILD and NO-BUILD scenarios. The
analysis revealed a 26 and 30 percent decrease of CO emissions for the years 1995 and
2010 during the peak period. Emission factors EMFAC7F were used for the analysis.
Based on the above analysis we conclude that there will be no violation of the
1-hour and 8-hour state or federal CO standards.
If you have any questions, please contact Mr. Victor Zeuzem of my staff at
(510) 286-5677.
Sincerely,
JOE BROWNE
District Director
Deputy District Director
Planning and Public Transportation
Attach
bcc:HYYahata
DSteinhauser
JSMcCrank
JJSpinello
DM ulli..,-~ n
DAOdell
VRZeuzem
RNOto
MEWelsh
PBcnson(NTM ~ R)
HPHensley
SChongchaikit
ASChow
DBosler
files
MTC
METROPOLITAN
TRANSPORTATION
COMMISSION
S=n M~t~ County
Wu.u*~ F. H~,~
Dianne Stei~hauser
Caltrans
Box 23660
Oakland, CA 94623-0660
De~~6irah~user:
September 15, 1994
¯ :.;:-T~ ! <9
MTC staff reviewed the Caltrans study, "Carbon Monoxide Concentrations
Adjacen~ to Ramp Meters", dated May 1994. "We understand that the
purpose of the study was to provide information on the air quality impacts
of ramp meters that ca.~ be used in project spedfic conformity
determinations. Caltrans gathered monitor data because, as explained in
the report, existing air quality models cannot predict these impacts
accurately. Monitors were placed at two ramp meter sites where worst case
conditions were considered to exist with regard to po~entiaI CO
concentrations. Because the study found no violations of the federal 8-
hour CO standard, Caltrans hopes to enable MTC to find that all ramp
meter projects do not create CO standard violations and thus meet
Resolution ~2270 requirements.
We agree that the study was well designed and implemented. -Therefore,
we agree to use the study’s conclusions to show that other ramp meter ¯
prqjects meet conformity requirements.
However, a concern is that the conclusions are based on limited data taken
at just two ramp meter sites. We recommend that Caltrans continue to
monitor at worst case ramp meter sites in order to add to the information
about CO impacts.
Thank you for undertaking this very useful study.
Sincerely,
William F. Hein
Deputy Executive Director-
¢c Mike Kim, BAAQMD
Jo~ee~ P. Bo~T ~OC~T~ ¯ 101 I:ICHTH 5;=eET " O~J~U~O, CA 94607-4700
510/464-7700 ¯ TDD/TTY 510/464.7769 ¯ FAX 510/464-7848