HomeMy WebLinkAbout1997-10-27 City Council (29)City of Pa!o Alto
City Manager’s Report
TO:HONORABLE CITY COUNCIL
FROM:
DATE:
CITY MANAGER
OCTOBER 27, 1997
DEPARTMENT: Utilities
CMR:437:97
SUBJECT:AWARD OF CONTRACT TO TESTING ENGINEERS, INC.
FOR SOIL TESTING SERVICES
RECOMMENDATION
Staff ~ecommends that Council approve and authorize the Mayor to execute the attached
three year contract with Testing Engineers, Inc. In the amount of $45,000 annually for
soil testing services.
DISCUSSION
Project Description
The work to b.e performed under the contract is for soil compaction testing related to
Utilities Engineering Capital Improvement Projects (CIP). These compaction tests are
required to measure soil compaction density and to comply with city construction
standards.
The project is designed to operate for three years, subject to council approval of the
budget.
The estimated quantity of pipe to be installed for Water, Gas, and Wastewater CIP
projects is 46,000 linear feet per fiscal year. The approximate duration tO construct
46,000 linear feet of utility mains is 307 work days. The average time spent at the job site
for a soil testing technician is 3 hours per day at $47/hour. In addition, one Maximum
Moisture Density Curve Test is required per project location at $195/test.
.Bid Process
Requests for bids for soft testing services were sent by Purchasing to five soil testing
firms. The bidding period was twenty-one days. No pre-bid meeting was held. Bids
were received from four qualified contractors on September 16, 1997, as listed on the
CMR:437:97 Page 1 of 2
attached bid summary (Attachment A). Bids ranged from a high of $67.50/hour to a low
bid of $47.00/hour (based on the average price over three years). The only testing firm
that did not respond was not interested in bidding.
---°Staff has reviewed all bids submitted and recommends that the low bid of $47/hour
(based on the average price over three years) submitted by Testing Engineers, Inc. be
determined by Council to be the lowest responsible bid and that the contract be awarded
accordingly. The low bid is approximately twenty-two percent below the engineer’s
estimate of $60/hour.
Staff checked references supplied by the testing firm for previous work performed by
Testing Engineers, Inc. and found no complaints.
RESOURCE IMPACT
The bid included vendor pricing for a thirty-six (36) month (3-year) agreement. Funds for
the first year-of this project are available in the FY 1997-98 Capital Improvement
Program (CIP) under the following projects, Water Main Replacement (8016), Gas Main
Replacement (8018), and Wastewater Collection Rehabilitation/Augmentation 9173).
ENVIRONMENTAL REVIEW
This project was considered to be categorically exempt as part of the Council approval of
the Utilities Engineering CIP and no further environmental review is necessary.
ATTACHMENTS
Attachment A:
Attachment B:
Bid Summary
Contract
PREPARED BY: Roger Cwiak
DEPARTMENT HEAD REVIEW:
CITY MANAGER APPROVAL:
j. vnuzzr:
Director of Utilities
Assistant City Manager
CMR:437:97 Page 2 of 2
FORMAL CONTRACT - Utilities Department SECTION 500
CONTRACT No.
(Public Work)
This Contract, number dated , is entered into by and between the City of Palo Alto, a chartered
city and a municipal corporation of the State of California (’City’), and ..Testing Engineers, Inc. , a California
Corporation ,
For and in consideration of the covenants, terms, and conditions (’the provisions") of this Contract, City and
Contractor (’the parties’) agree:
Term. This Contract shall commence and be binding on the parties on the Date of Execution of this
Contract, and shall expire on the date of recordation of the Notice of Substantial Completion, or, if no such
notice is required to be filed, on the date that final payment is made hereunder, subject to the earlier
termination of this Contract. This Contract may be terminated for convenience by the City upon ten (10)
days’ prior written notice.
General Scope of Project and Work. Contractor s~hall furnish labor, services, materials and equipment in
connection with the construction of the Project and complete the Work in accordance with the covenants,
terms and conditions of this Contract to the satisfaction of City. The Project and Work is generally
described as follows:
Title of Project:
Total Bid:
Soil Testing Services No. #37600
$ 135.000
Contract Documents. This Contract shall consist of the documents set forth below, which are on file with
the City Clerk and are hereby incorporated by reference. For the purposes of construing, interpreting and
r~solving inconsistencies between and among the provisions of this Contract, these documents and the
provisions thereof are set forth in the following descending order of precedence.
f.
g.
h.
I.j.
k.
I.
This Contract.
Notice inviting Formal Bids.
Project Specifications.
Drawings.
Change Orders.
Bid.
Supplementary Conditions.
General Conditiohs.
Standard Drawings and Specifications (1992).
Certificate of Insurance, Performance Bond, Labor & Materials (Payment) Bond.
Affirmative Action Guidelines and Compliance Report.
Other Specifications, or part thereof, not expressly incorporated in the Contract Specifications or
the Standard Drawings and Specifications (1992).
Any other document not expressly mentioned herein which is issued by City or entered into by the
parties.
CITY OF PALO ALTO: SAMPLE CONTRACT IFB SECTION 500-1 OF 8
FORMAL CONTRACT - Utilities Department SECTION 500
Compensation. In consideration of Contractor’s performance of its obligations hereunder, City shall pay to
Contractor the amount set forth in Contractor’s Bid in accordance with the provisions of this Contract and
upon the receipt of written invoices and all necessary supporting documentation within the time set forth
in the Contract Specifications and the Standard Drawings and Specifications (1992), or, if no time is stated,
within thirty (30) Days of the date of receipt of Contractor’s invoices.
Insurance. on or before the Date of Execution, Contractor shall obtain and maintain the policies of
insurance coverage described in the Notice Inviting Formal Bids on terms and conditions and in amounts
as may be required by the Risk Manager. City shall not be obligated to take out insurance on Contractor’s
personal property or the personal property of any person performing labor or services or supplying materials
or equipment under the Project. Contractor shall furnish City with the certificates of insurance and with
odginal endorsements affecting coverage required under this Contract on or before the Date of Execution.
The certificates and endorsements for each insurance policy shall be signed by a person who is authorized
by that insurer to bind coverage in its behalf. Proof of insurance shall be mailed to the Project Manager
to the address set forth in Section 15 of this Contract.
Indemnification. Contractor agrees to protect, defend, indemnify and hold City, its Council members,
officers, employees, agents and representatives harmless from and against any and all claims, demands,
liabilities, losses, damages, costs, expenses, liens, penalties, suits, or judgments, arising, in whole or in
part, directly or indirectly, at any time from any injury to or death of persons or damage to property as a
result of the willful acts or the negligent acts or omissions of Contractor, or which results from Contractor’s
noncompliance with any Law respecting the condition, use, occupation or safety of the Project site, or any
part thereof, or which arises from Contractor’s failure to do anything required under this Contract or for
doing anything which Contractor is required not to do under this Contract, or which arises from conduct
for which any Law may impose strict liability on Contractor in the performance of or failure to perform the
provisions of this Contract, except as may arise from the sole willful acts or negligent acts or omissions of
City or any of its Council members, officers, employees, agents or representatives. This indemnification
shall extend to any and all claims, demands, or liens made or filed by reason of any work performed by
Contractor under this Contract at any time during the term of this Contract, or arising thereafter.
To the extent Contractor will use hazardous materials in connection with the execution of its obligations
under this Contract, Contractor further expressly agrees to protect, indemnify, hold harmless and defend
City, its City Council members, officers and employees from and against any and all claims, demands,
liabilities, losses, damages, costs, expenses, liens, penalties, suits, or judgments City may incur, arising,
in whole or in part, in connection with or as a result of Contractor’s willful acts or negligent acts or
omissions under this Contract, under the Comprehensive Environmental Response, Compensation and
Liability Act (42 U.S.C. § §9601-6975, as amended); the Rbsource Conservation and Recovery Act (42
U.S.C. § §6901-6992k, as amended); the Toxic Substances Control Act (15 UoS.C. § §2601-2692, as
amended); the Carpenter-Presley-Tanner Hazardous Substance Account Act IHealth & Safety Code,
§ §25300-25395, as amended); the Hazardous Waste Control Law (Health & Safety Code, §§25100-
25250.25, as amended); the Safe Drinking Water and Toxic Enforcement Act (Health & Safety Code,
§ §25249.5-25249;13, as amended); the Underground Storage of Hazardous Substances Act (Health &
Safety Code, § §25280-25299.7, as amended); or under any other local, state or federal law, statute or
ordinance, or at common law.
Assumption of Risk. Contractor agrees to voluntarily assume any and all risk of loss, damage, or injury to
the property of Contractor which may occur in, on, or about the Project sit~ at any time and in any manner,
excepting such loss, injury, or damage as may be caused by the sole willful act or negligent act or
CITY OF PALO ALTO: SAMPLE CONTRACT IFB SECTION 500-2 Or: a
FORMAL CONTRACT - Utilities Department SECTION 500
omissionof City or any of its Council members, officers, employees, agents or representatives.
o
=
Waiver. The acceptance of any payment or performance, or any part thereof, shall not operate as a waiver
by City of its rights under this Contract.. A waiver by City of any breach of any part or provision of this
Contract by Contractor shall not operate as a waiver or continuing waiver of any subsequent breach of the
same or any other provision, nor shall any custom or practice which may arise between the parties in the
administration of any part or provision of this Contract be construed to waive or to lessen the right of City
to insist upon the performance of Contractor in strict compliance with the covenants, terms and conditions
of this Contract.
Compliance with Laws. C~ntractor shall comply with all Laws now in force or which may hereafter be in
force pertaining to the Project and Work and this Contract, with the requirement of any bond or fire
underwriters or other similar body now or hereafter constituted, with any discretionary license or permit
issued pursuant to any Law of any public agency or official as well as with any provision of all recorded
documents affecting the Project site, insofar as any are required by reason of the use or occupancy of the
Project site, and with all Laws pertaining to nondiscrimination and affirmative action in employment and
hazardous materials.
10.Bonds. As a condition precedent to City’s obligation to pay compensation to Contractor, and on or before
the Date of Execution, Contractor shall furnish to the Project Manager the Bonds as required under the
Notice Inviting Formal Bids.
11.R. epresentations and Warranties. In the supply of any materials and equipment and the rendering of labor
and services during the course and scope of the Project and Work, Contractor represents and warrants:
Any materials and equipment which shall be used during the course and scope of the Project and
Work shall be vested in Contractor;
Any materials and equipment which shall be used during the course and scope of the Project and
Work shall be merchantable and fit to be used for the particular purpose for which the materials are
required;
Any labor and services rendered and materials and equipment used or employed during the course
and scope of the Project and Work shall be free of defects in workmanship for a period of one (1)
year after the recordation of the Notice of Substantial Completion, or, if no such notice is required
to be filed, on the date that final payment is made hereunder;
d=Any manufacturer’s warranty obtained by Contractor shall be obtained or shall be deemed obtained
by Contractor for and in behalf of City.
Any information submitted by Contractor prior to the award of Contract, or thereafter, upon request,
whether or not submitted under a continuing obligation by the terms of the Contract to do so, is
true and correct at the time such information is submitted or made available to the City;
Contractor has not colluded, conspired, or agreed, directly or indirectly, with any person in regard
to the terms and conditions of Contractor’s Bid, except as may be permitted by the Notice Inviting
Formal Bids;
CITY OF PALO ALTO: SAMPLE CONTRACT IFB SECT|ON 500-3 OF 8
FORMAL CONTRACT - Utilities Department SECTION 500
Contractor has the power and authority to enter into this Contract with City, that the individual
executing this Contract is duly authorized to do so by appropriate resolution, and that this Contract
shall be executed, delivered and performed pursuant to the power and authority conferred upon the
person or persons authorized to bind Contractor;
h~Contractor has not made an attempt to exert undue influence with the Purchasing Manager or
Project Manager or any other person who has directly contributed to City’s decision to award the
contract to Contractor;
There are no unresolved claims or disputes between Contractor and City which would materially
affect Contractor’s ability to perform under the Contract;
Contractor has furnished and will furnish true and accurate statements, records, reports, resolutions,
certifications, and other written information as may be requested of Contractor by City from time
to time during the term of this Contract;
Contractor and any person performing labor and services under this Project are duly licensed by the
State of California as required by California Business & Professions Code Section 7028, as
amended; and
Contractor has fully examined and inspected the Project site and has full knowledge of the physical
conditions of the Project site.
12.Assignment. This Contract and the performance required hereunder is personal to Contractor, and it shall
not be assigned by Contractor. Any attempted assignment shall be null and void.
13.Claims of Contractor. All claims pertaining to extra work, additional charges, or delays within the Contract
Time or other disputes arising out of the Contract shall be submitted by Contractor to City in writing by
certified or registered mail within ten (10) Days after the claim arose or within such other time as may be
permitted or required by law, and shall be described in sufficient detail to give adequate notice of the
substance of the claim to City.
14.Audits by City. During the term of this Contract and for a period of not less than three (3) years after the
expiration or earlier termination of this Contract, City shall have the right to audit Contractor’s Project-related
and Work-related writings and business records, as such terms are defined in California Evidence Code
Sections 250 and 1271, as amended, during the regular business hours of Contractor, or, if Contractor has
no such hours, during the regular business hours of City.
15.Notices, All agreements, appointments, approvals, authorizations, claims, demands, Change Orders,
consents, designations, notices, offers, requests and statements given by either party to the other shall be
in writing and shall be sufficiently given and served upon the other party if(1 ) personally served, (2) sent
by the United States mail, postage prepaid, (3) sent by private express delivery service, or (4) in the case
of a facsimile transmission, if sent to the telephone FAX number set forth below during regular business
hours of the receiving party and followed within two (2) Days by delivery of a hard copy of the material sent
by facsimile transmission, in accordance with (1), (2) or (3) above. Personal service shall include, without
limitation, service by delivery and service by facsimile transmission.
~31"i-Y OF PALO ALTO: SAMPLE CONTRACT IFB ......SECTibN 500-40F’~
FORMAL CONTRACT - Utilities Department
To City:City of Palo Alto
City Clerk
250 Hamilton Avenue
P.O. Box 10250
Palo Alto, CA 94303
Copy to:City of Palo Alto
Utilities Engineering Department
250 Hamilton Avenue
P,O, Box 10250
Palo Alto, CA 94303
Phone: (650) 329-2126
FAX: (650) 329-2608
AT’I’N.: Edward Wu, Project Manager
To Contractor:"restin,q Enqineers, Inc. . .
2123 Berin.q Drive, Suite.,..E ......
San.Jose, CA 95131
Phone: (408) 451-2420
FAX: ~408~ 451-242~
ATTN.: Mr. Terry_ Chiccino
SECTION 500
16.
17.
Appropriation of City Funds. This Contract is subject to the fiscal provisions of Article III, Section 12 of the Charter
of the City of Palo Alto. Any charges hereunder for labor, services, materials and equipment may accrue only after
such expenditures have been approved in advance in writing in accordance with applicable Laws. This Contract
shall terminate without penalty (I) at the end of any fiscal year in the event that funds are not appropriated for the
following fiscal year, or (i~ at any time within a fiscal year in the event that funds are only appropriated for a portion
of the fiscal year and funds for this Contract are no longer available. This Section 16 shall control in the event of
a conflict with any other provision of this Contract.
Miscellaneous.
Bailee Disclaimer. The pa~es understand and agree that City does not purport to be Contractor’s bailee,
and City is, therefore, not responsible for any damage to the personal property of Contractor.
bJ Consent. Whenever in this Contract the approval or consent of a party is required, such approval or
consent shall be in writing an~l shall be executed by a person having the express authority to grant such
approval or consent.
Controlling Law. The parties agree that this Contract shall be governed and construed by and in
accordance with the Laws of the State of California.
do Definitions. The definitions and terms set forth in Section 1 of the Standard Drawings and Specifications
(1992) of this Contract are incorporated herein by reference.
e.Force Majeure. Neither party shall be deemed to be in default on account of any delay or failure to perform
CITY OF PALO ALTO" SAMPLE CONTRACT IFB SECTION 500-50~: 8
FORMAL CONTRACT - Utilities Department SECTION 500
its obligations under this Contract which directly results from an Act of God or an act of a superior
governmental authority.
fo Headings. The paragraph headings are not a part of this Contract and shall have no effect upon the
construction or interpretation of-any part of this Contract.
Incorporation of Documents. All documents constituting the Contract documents described in Section 3
hereof and all documents which may, from time to time, be referred to in any duly executed amendment
hereto are by such reference incorporated in this Contract and shall be deemed to be part of this Contract.
Integrat~0n. This Contract and any amendments hereto between the parties constitute the entire agreement
between the parties concerning the Project and Work, and there are no other prior oral or written
agreements between the parties that are not incorporated in this Contract.
Modification of Agreement. This Contract shall not be modified or be binding upon the parties, unless such
modification is agreed to in writing and signed by the parties.
Provision. Any agreement, covenant, condition, clause, qualification, restriction, reservation, term or other
stipulation in the Contract shall define or otherwise control, establish, or limit the performance required or
permitted or to be required of or permitted by either party. All provisions, whether covenants or conditions,
shall be deemed to be both covenants and conditions.
Resolution. Contractor shall submit with its Bid a copy of any corporate or partnership resolution or other
writing, which authorizes any director, officer or other employee or partner to act for or in behalf of
Contractor or which authorizes Contractor to enter into this Contract.
Severability. If a court of competent jurisdiction finds or rules that any provision of this Contract is void or
unenforceable, the provisions of this Contract not so affected shall remain in full force and effect.
mo Status of Contractor. In the exercise of rights and obligations under this Contract, Contractor acts as an
independent contractor and not as an agent or employee of City. Contractor shall not be entitled to any
rights and benefits accorded or accruing to the City Council members, officers or employees of City, and
Contractor expressly waives any and all claims to such rights and benefits.
Successors and Assigns. The provisions of this Contract shall inure to the benefit of, and shall ’apply to and
bind, the successors and assigns of the parties.
Oo Time of the Essence. Time is of the essence of this Contract and each of its provisions. In the calculation
of time hereunder, the time in which an act is to be performed shall be computed by excluding the first Day
and including the last. If the time in which an act is to be performed falls on a Saturday, Sunday, or any
Day observed as a legal holiday by City, the time for performance shall be extended to the following
Business Day.
go Venue. In the event that suit is brought by either party hereunder, the parties agree that trial of such action
shall be vested exclusively in the state courts of California in theCounty of Santa Clara in the City of San
Jose or in the United States District Court for the Northern District of California in the City of San Jose.
qo Recovery of costs. The prevailing party in any action brought to enforce the terms of this Contract or arising
out of this Contract may recover its reasonable costs, including reasonable attorney’s fees, incurred or
expended in connection with such action against the non-prevailing party.
~I~’OF PALO ALTO; SAMPLE CONTRACT IFB SECTION 500-60~="’~
FORMAL CONTRACT - Utilities Department SECTION 500
IN WITNESS WHEREOF, the parties have by their duly appointed representatives executed this Contract in the
city of Palo Alto, County of Santa Clara, State of California on the date first stated above.
ATTEST:CITY OF PALO ALTO
By:
City Clerk Its: Mayor
APPROVED:CONTRACTOR:
City Manager
By:
Name:
Director of Utilities Title:
Director of Administrative Services
Taxpayer I.D. No.:
Manager, Contract Administration
(insurance review)
APPROVED AS TO FORM:
Senior Asst., City Attorney
CITY OF PALO ALTO: SAMPLE CONTRACT IFB SECTION 500-7 OF 8
FORMAL CONTRACT - Utilities Department
CERTIFICA~TE OF ACKNOWLEDGMENT
(Civil Code § 1189)
SECTION 500
STATE OF )
COUNTY OF )
On , before me,
for said County, personally appeared
, a notary public in and
personally known to me (or proved to me on the basis of satisfactory evidence) to be the person(s) whose
name(s) is/are subscribed to the within instrument and acknowledged to me that he/she/they executed
the same in his/her/their authorized capacity(ies), and that by his/her/their signature(s) on the instrument
the person(s), or the entity upon behalf of which the person(s) acted, executed the instrument.
WITNESS my hand and official seal.
Signature (Seal)
END OF SECTION
CITY OF PALO ALTO: SAMPLE CONTRACT IFB SECTION 500-8 OF 8