HomeMy WebLinkAbout1997-10-27 City Council (23)City Manager’s Report
TO:HONORABLE CITY COUNCIL
FROM:CITY MANAGER DEPARTMENT:ADMINISTRATIVE
SERVICES
AGENDA DATE: OCTOBER 27, 1997 CMR:442:97
SUBJECT:REQUEST FROM MUSEUM OF AMERICAN HERITAGE FOR
COST ASSISTANCE WITH STRUCTURAL REPAIR OF
WILLIAMS PROPERTY, 351 HOMER AVENUE
RECOMMENDATION
The Museum of American Heritage (Museum) has requested City assistance with costs up
to a maximum of $65,000 for co~ecting recently discovered structural problems with the
Williams House at 351 Homer Avenue. Past Council action has directed that use and
improvement of the Williams property be at no cost to the City. Therefore, staff requests
Council direction and recommends that:
1)If Council wishes to assist the Museum with costs for correcting structural problems
with the stucco and sheathing up to a maximum of $65,000, staffbe directed to work
with the Museum to identifymore precisely the extent of the problem and estimated
costs, and proceed in one of the following ways:
return to Council for approval of a Budget Amendment Ordinance to cover the
entire cost, not to exceed $65,000.
return to Council for approval of a Budget Amendment Ordinance to cover a
portion of the cost, as determined by Council;
return to Council for approval of a Budget Amendment Ordinance and a loan
to the Museum to cover the costs, not to exceed $65,000, with a term of 5
years and an interest rate equal to the City’s average portfolio rate of return,
plus .25 percent.
CMR:442 Page 1 of 4
If Council prefers that the Museum retain responsibility for all costs associated with
the project, direct staff to take no action.
BACKGROUND
On June 10, 1996, Council awarded the Museum an option to lease the Williams property
at 351 Homer Avenue for the purpose of developing and operating a park and museum open
to the public. Over the next year, the Museum fulfilled the required conditions of the option
including receiving the necessary city approvals and raising funds for the development of
its project. On May 7, 1997, the lease between the Museum and City was executed, and
construction on the project was begun.
On September 15, 1997, the Museum sent a letter (Attachment A) to the Council requesting
City funding in an amount not to exceed $65,000 to be used to cover the costs of correcting
structural problems and re-plastering the Williams house. The Museum has completed 60 to
70 percent of its Education Center building; seismically improved the garage and installed
a rear fire wall; and installed a new roof on both the garage and the Williams house. The
project is scheduled to be completed in November 1997. While attempting to obtain bids
for patching the Williams house exterior stucco, the Museum recently discovered that the
stucco may need to be entirely replaced rather than patched as was originally planned and
budgeted for. In addition, a patch of stucco which recently came loose near the building
grade level has revealed wood sheathing showing signs of significant dry rot. As of its
September 15, 1997 letter, the Museum had received cost estimates for replacing the stucco
and the sheathing totaling $58,000 to $63,000. The Museum has raised over $500,000 for
architectural and construction costs for the Williams project; however, unaware of these
building conditions at the time the lease was negotiated, it never contemplated replacement
of the stucco and sheathing and has budgeted only $15,000 for patching and painting the
exterior of the house. Therefore, the Museum has requested that the City Council authorize
funding assistance in an amount not to exceed $65,000, to be used solely for enhancing the
structural integrity of and for plastering costs for the Williams house.
DISCUSSION
City inspections of the Williams house conducted prior to soliciting proposals for the
prope~y revealed the necessity for patching but not replacing the stucco. In general, the
house was found to bc in good structural condition considering its age, and a termite report
obtained in 1989 and updated in 1994 found no evidence of significant dry rot or termite
damage. Since receiving the Museum’s September 15, 1997 letter, City staff has inspected
the stucco and sheathing and recommends that the Museum contact contractors experienced
in plaster testing and restoration regarding the exterior stucco and investigate further the
condition and costs of repairing the sheathing. In response to this recommendation, the
CMR:442 Page 2 of 4
Museum has solicited additional opinions and cost estimates but has not yet received them.
Although specific costs are not available at this time, the Museum requires a timely response
from the City in order not to delay the scheduled opening date, and has therefore requested
a maximum allocation of $65,000.
The Request for Proposals (RFP) for the Williams property identified general improvements
required for use of the property and noted that proposers would be responsible for identifying
any additional improvements that may be necessitated _by a specific use. In accordance with
Council direction, the RFP and option to lease for the Williams property require that
restoration and improvements necessary for the use and operation of the property be done at
no cost to the City. However, the Museum points out that the condition of the sheathing was
not possible to detect without doing destructive inspection, and the magnitude of the stucco
repair that may be necessary is not something the Museum could have anticipated. In an
October 6, 1997 letter to the City Manager (Attachment B), the architect for the project notes
that the Museum has already paid for other significant improvements which were unknown
to the Museum when it entered into the option to lease, such as strengthening of the roof
structure and full fire sprinkling of all structures, and that it would be difficult for the
Museum to raise additional funds for significant improvements at this late point in the
" project.
Past Council policy requiring the property be used and improved at no cost to the City and
the recent discovery of possible significant conditions not anticipated nor budgeted for by
the Museum, require staff to seek Council direction. Staff has identified the following four
options for responding to the Museum’s request, which~ are reflected in the staff
recommendation and discussed below under Resource Impact and Policy Implications: 1)
City pays full cost of necessary repairs to stucco and sheathing; 2) City and Museum share
the cost; 3) City loans the Museum funds to cover costs; and 4) Museum pays full cost of
repairs.
.RESOURCE IMPACT
City funds have not been budgeted for Williams house improvements or repairs. If Council
chooses to participate in the costs as requested by the Museum, staff would return with a
Budget Amendment Ordinance. Funds would come from the Budget Stabilization Reserve.
For the loan option, staff recommends a term of five years and an interest rate equat to the
City’s average portfolio rate of return for the last fiscal year, plus .25 percent (the interest
rate on the loan would be 6.24 percent for fiscal year 1997-98). The five-year term is
consistent with. the longest term the City would normally utilize when investing City funds.
Furthermore, a term of more than five years would increase risk to the City. By using the
average portfolio rate of earnings, the City would not forego interest earnings on the loaned
CMR:442 Page 3 of 4
funds. The additional .25 percent would compensate the City for the administrative effort
involved in handlin.g the loan.
POLICY IMPLICATIONS
Based on Policy and Procedures 1-11 (Leased Use of City Land/Facilities) and past Council
action, both the RFP and the option to lease for the Williams property include provisions
requiring that restoration and improvements necessary for the use and operation of the
property be done at no cost to the City. City participation in the cost of improvements
would be an exception to this policy.
The City has no official policy for loaning City funds to outside groups, and has not made
such loans in the past. Should Council select this option, it could set a precedent for the
future. It is possible that other community groups or interests would look to this action as
a signal about a new City policy regarding loans.
ENVIRONMENTAL REVIEW
An environmental impact assessment determined that the project would have a less than
significant impact on the environment and a negative declaration was adopted by the City
Council on June 10, 1996. No further environmental review for the project is necessary
under the requirements of the California Environmental Quality Act (CEQA).
ATTACHMENTS
Attachment A:September 15, 1997 letter to City Council from Museum of American
Heritage
Attachment B:October 5, 1997 letter from project architect to City Manager.
PREPARED: Janet Freeland, Senior Financial Analyst
DEPARTMENT HEAD APPROVAL:
CITY MANAGER APPROVAL:
CC: Museum of American Heritag
Meliss)a Cavallo
Acting Directors,....~~ministrative Servlces
/( ~r~Fleming ;~/}
[~ i(y Manager ~M]
CMR:442 Page 4 of 4
THE MUSEUM
of AMERICAN
HERITAGE
BOARD OF
DIRECTORS
J. Robert Beck
Chairman
George Zimmerntan
Vice-chairman
Charles L. Pack
Treasnrer
Beverly J. Nelson
Secretary/Exec. Dir.
R~ger D. Broussal
Kathleen A. Craig
Joseph Ehrlich
Crystal D. Gamage
Charles M. Gillis
Kenoeth Kormanak
Marshall Mathews
Carl B. Moerdyke
Roxy Rapp
Tony K. Svensson
OFFICERS
Carl B. Moerdyke
Preside n t
Frank l,ivermore
Founder/Vice-pr, es.
Sozanoe H. Beaver
Vice-president
Theotlora Nelson -
Vice-president
COMMUNITY
ADVISORY BOARD
Jaotes L. Adams
Robert E. Bond
Allan Chin
Marybelle Cody
Joseph J. Corn
Joan Cnnneen ¯
"Wallace V, Cunneert
Leonard W. Ely
Margc Gratiot
Loretta Green
Carroll Harrington
Charles C. Boage
Carl Holvlck
Ralph Igler
David M. Kelley
Jacques Littlefield
T. Kevin Mallen
Jeantte McDonnell
Shelley Monfort
Barbara Newton
Carroll Notthoff
Rixford K. Snyder
Sara C. Spang
Steve Staiger
Eleanor J. Watanabe
Gall Woolley
RECEIVED
SEP 1 7 1997
CITY h~.NAGER’S OFFICE
ATTACHMENT A
97SEP!7 AHI0:01
September 15, 1997
To:
Subject:
All Membei’s of the Palo Alto.City Council
Condition of the Exterior Stucco on tiae Williams House
Dear Honorable Council Members:
There is much good news to report on the progress of the Williams House and
Garden project. The Educa,~tion Center building and the attendant Handicapped
Toilet Faciiil~ies are currently 60% to 70% complete. The garage has been
seismically improved, a fire resistant rear wall has been installed, a new roo~f has
been put on both the garage and the Williams House proper, and the overall
schedule for completion of the project is ea’rly November, 1997.
The Contractor, Jack & Cohen, has been attempting to secure bids for the patching
of the exterior stucco. The original intent, when establishing our budget for the
project, was to put in $15,000 for patching and painting the exterior of the
Williams House.
I’m enclosing copies of a letter from McVey Plastering Inc. dated August ’15,
1997. The key point of his letter was the 3’d sentence that states "when the walls
were originally stuccoed, an interior material was used on the, exterior walls." This
means the substrate plaster is a gypsum material rather than a Portland cement
material,, which is proper for exterior use.
We’re also enclosing a copy of McVey Plastering Inc. "’Memo-Letter" dated
September 5, 1997, with ~.n estimate of some $32,200 to replace the existing
exterior latent plaster with a three coat cement plaster application.
The revelation that the substrate of the existing building was "an interior material"
was completely unknown to us during the negotiations with the Palo Alto staff in
securing the opt!on on the lease and ultimately the lease itself.
The Museum has raised over $500,000 for architectural and construction’cost,
whidh never contemplated stripping the Williams House down to the wood
sheathing, replacing sheathing subject to dry rot and putting a brand newcomplete
skin on the building.
3401 El Carnino Real ¯ Palo Alto, California 94306-2805 ¯ Phone 415/321-1004 ¯ Fax 4151494-6183
Founded 1985 By The Frank ’Liverraore Trust
A California Non-pro(it Corporation Fed It) #77-9106732 State |D 111’2.80035
All Members of the Palo Alto City Council
September 15, 1997
Page 2
We should not proceed with the short-term patch and paint process originally
contemplated. Our plastering contractor is not even certain that the new materials,
presently in use will adhere to the existing interior material referred to earlier.
When we consider that the Williams House b.nd Garden were willed to the City for
ownership in perpetuity we’re asking the Council to consider a one time long-term
solution rather than the short-term fix referred to earlier. The costs for the long-
term approach which will preserve the Williams House for perpetuity are as
follows:
1.Demolition (removal of existing stucco $8,000
substrate and lath, no~i included in McVey
Plastering’s estimate)
2.Scaffolding 3,000
3.McVey’s estimate (includes two layers
of building paper wire lath, 3 coats of
cement plaster)
Total
32,200
$43,200
In addition, recently a patch stucco came loose close to the grade level of the
building revealing that the wood sheathing, which is below the existing outside
grade displays significant dry rot caused by many years of being located below the
outside grade. Once again, this was a condition that could not be readily
ascertained during our initial lease negotiations. If the sh,~eathing condition we
observed in this one small area, is typical around the entire perimeter of the house
the long-term structural integrity of the house may be called into question. It is
impossible to determine the extent.of this dry rot condition without removing the
stucco around the entire base of the house. The cost to replace the damaged
portion of the sheathing with sound moisture resistant materials (assuming the mud
sills are in sound condition) will run between $15,000 and $20,000, bringing the
total additioiaal cost of this issue to some $58,000 to $63,000.
So here’s the dilemma: Should the Museum, the Tenants, and Palo Alto, the
Landlord, close our collective eyes to what we now know are serious conditions,
we can cover-up the dlN ’rot, patch over the loose stucco and hope for the best?
Or should the Landlord make the significant investment for the long-term benefit
of the Community?
All Members of the Palo Alto City Council
September 15, 1997
Page 3
The decision on how to proceed should be made by the end of September or early
October so that the project completion schedule will not be significantly impacted.
We respectfully request you authorize an allocation not to exceed $65,000 to be
used solely for the structural integrity and plastering costs of the Williams House.
We anxiously and eagerly await your decision on this important issue.
\ ~e Ehr’lTch
",Board Member and Chair of the Design Committee
cc: June Fleming, City Manager
JE/cm:ccncl.doc
August.15, 1997
Robert M. Bybee
Project Manager
Jack & Cohen Builders, Inc.
975 High Street
Palo Alto, California 94301
Dear Bob:
PKOJ£CT:Palo Alto Historlcal.Museum
351 Homer Street
Palo AIrs, CA
After examining the existing exterior stucco walls, 1~ is my opinion
Iz is no~ feasible to repair them. I was ~nly able to examine areas where
~he finish coa~ had failed and had fallen off ~he walls due to :he deterioration
of the basacoa~. When ~h~ walls were ori~Inally stuccoed, an Interior material
was used on ~he ex=erlor walls, In my opinion, even though it has lasted for a
conside£able number of years, ~t. hag. re~9~gd ~he po~u~ where i= is no ion~er
advisable to repair...
Sincerely,
K. Edwin McVelgh
President
SEP 86 ’97 13:48 MCVEIGH PLASTERIMG P,i,i
TO:
P.O. Box 7149 ° REDWOOD CrrY, CA 94063-0149
memo-letter
Jack & Cohen Builders, Inc./Robert Bybee
975 High Street
Palo Alto, CA 94301
DATE Sep=ember 5, 1997
SUBJECT:...Palo Alto Historical ~[useum
351 Homer Street, £a!o Alto, CA
COST ESTIMATE:
Estimate ro ~eplace’existin~ exterior lath and plaster with three coat cement
plaster application.
LABOR & MATERIALS }3~2QQ.00
No=e! Scaffold for work over 13’0’ is not ~ncluded.
H. Edwin McVei~h,Dresiden~.
ATTACHMENT B
ARCHII’.
October 6, 1997
June Fleming
City Manager
City of Pale Alto
250 Hamilton Avenue
Pale Alto, CA 94301 "
Deal" June,
Thank you and Janet [br meeting with us last week to discuss the Will’iams house. I’m writing this
letter as an aside to that meeting. I see a real opporlun~,b, .here [kn’,the City to set an example of how
to respect the historic fabric of a struclure at a time when hislori~ prcsc~,ation issues are at the
forefronl of public debate. . , . , ,
Tile Williams house will soon open to ureat public fanfare. Undoubledly, the Museum’s opening will
be well-received and recognized as an impommt historic prcsc~walion project wilhin the communily.
The grand opening will provide an opporlunity Ibr the City to participate in the public events
surrounding the o~enin~ as a parmer in the project. This public-private partnership between the City’
and the Museum ~m s~wc to demonslratc what can be done when all parties contribute toward the
common goals. The incentives that can apply to prescrvalion projects are all illustratqd in this
project. Zoning relief granted by the City made it possible to prcse~we the gardens, the use of the
State Historic Building Code made it possible to save the garage. In essence, this project stands as a
billboard to the prese~walion values and goals I think tl~e City wanls to encourage.
People’s reaclions to lhe projecl will del)end on Ihe visual impressions they carry away with them.
l’m concerned that a patched stucco job will Ioo~ like just tllat -.a patch job. In order to really carry
off the project well, we should repair the stucco in a way that will loo~ good and also help prolong
the li[’c of the building by addressing tl~c. inadequacies of I]’lc existing inslallalion. To this end, the
Museum seeks your and the Council’s assistance.
Tile Museum has ah’cady tackled olher hidden problems encountered in the existing structure without
seeking additional funding from the Cily. When the main housewas rc-rool~d, the existing roof
structure was lk)und to be inadcquale {o resisl anlicipalcd lateral’ lbrces" fmmearlhquakes and required
strengthening. At the time the Museum was awarded the oplion to lease, il was not known that full
tim-sprinkling o[" all structures would be required.. These two ilems alone.cosl tens of thousands o["
dollars, which the Museum paid.
’Fun(lraising is dill]cull ill besl, all(I tile MtlsCtlm has done an incredihlc job of raising over a half a
inillion dollars loward this project. If you-remcmhcr, as I do, lhc long history of groups who
unsuccessfully at/cmplcd IO lackle lhis.prop~rly wilh ils really difficulties, including fund raising, then
you can apprecialc lhe organizalion and effort Ihc Museum has put forward to reach this point. The
magnitude of the stucco repair was no~ something we could have anticipaled, and its cost is difficult
Ik)r lhe Museum IO raise ftallds [k)r at this lalc poim in the project. We ask thai yotl look favorably
our us in findin~ a quick answer to this problem.upon ~~~.
Sinccl,~~Monlgomery Anderson, A
Principal
Cody Anderson Wasney Architects, Inc.
Janet Freeland, City, of Pill() Alto, Real Estale l)ivision
Joe Ehrlich, Eh rl ich-Rom in ge r Arch itec ts " "
Cody Anderson Wasney Architects Inc. ¯ 941 Emerson Street ¯ Pale Alto, CA 94301 ¯ Tel 415, :~28,181B ¯ Fax 415. 328.1888 ¯ Email cawarch@aol,com