HomeMy WebLinkAbout1997-10-06 City Council (25)City of Palo Alto
City Manager’s Report
TO:HONORABLE CITY COUNCIL
FROM:CITY MANAGER DEPARTMENT: PUBLIC WORKS
DATE:OCTOBER 6, 1997 CMR:419:97
SUBJECT:INFORMATIONAL REPORT ON THE SANTA CLARA VALLEY
WATER DISTRICT’S MATADERO/BARRON CREEK FLOOD
CONTROL PROJECT
This report conveys information on recent developments concerning the Santa Clara Valley
Water District’s (District) Matadero/Barron Creek flood control project. No Council action is
required.
BACKGROUND
In March 1996, staff provided updated information to Council on the Federal Emergency
Management Agency’s (FEMA) Special Flood Hazard Areas (SFHA) in Palo Alto
(CMR: 183:96). The report included information on the status of the Santa Clara Valley Water
District’s (District) flood control program in Palo Alto and an estimate of the number of
properties that would be removed from the SFHA as a result of the channel improvements. An
important component of the District’s program is the Matadero/Barron Creek flood control
project.
The fmal phase of the Matader0/Barron Creek flood dontrol project was completed in July 1996.
The project, implemented in five separate construction phases over an eight-year period, was
designed to protect approximately 5,900 flood-prone properties from flooding for up to the one
percent flood1. Of this total, approximately 200 properties were to be removed from the SFHA
on FEMA’s Flood Insurance Rate Map (see attached map). The remaining 5,700 properties
either remain in the SFHA because they continue to be subject to saltwater flooding or were
never included in the SFHA because they were subject to freshwater flooding less than one foot
in depth. In order to Officially remove the 200 properties from the SFHA, the District is
.required to apply to FEMA for a Letter of Map Revision (LOMR). The LOMR application
~The one percent flood has a one percent chance of occurring in any given year. It is
sometimes referred to as the 100-year flood, because it is the flood that would be equaled or
exceeded on an average of one time every one hundred years, measured over a long time period.
CMR:419:97 Page 1 of 3
consists of maps, calculations, and other background information documenting that the
channel improvements will provide protection from the one percent flood.
DISCUSSION
Upon completion of the flood control improvements in July 1996, District staff began
preparation of its LOMR application to FEMA and expected to submit it in June 1997.
District representatives have recently informed staffthat they have identified an error in the
design of the Matadero/Ba~ron Creek flood control project (at the Matadero Creek and Louis
Road bridge structure) that will prevent it from submitting a LOMR application to FEMA
at this time. District staff will notify its Board of Directors of this issue at the October 7
Board meeting. As a courtesy, District staff will provide City staffwith a copy of its staff
report. Since the District’s report was not fmalized prior to assembly of the Council packet,
it will be provided at Council Members’ places on Monday night.
Discovery of a design error in the flood control project has several implications for Palo Alto
residents and businesses. First of all, the 200 properties in the SFHA that were expected to
be removed will remain in the SFHA. District staff estimates a one and a half to two year
delay in obtaining the LOMR required to remove these properties from the SFHA. As a
result, property owners will continue to be required to carry flood insurance on their property
if it is mortgaged, at an annual cost of $500 or more. The second impact of the design error
is that there are a substantial number of properties that are not, in fact, protected against the
one percent .flood. District staff have determined that, under current conditions, residents
along Barron Creek have protection against the one percent (100-year) flood, but that
Matadero Creek residents have only two percent (50-year) flood protection. Furthermore,
the current conditions could induce flooding of properties that were not subject to flooding
prior to construction of the flood control project.
In its report, District staffprovides its Board with a list of alternative interim measures that
could be implemented to mitigate the impacts of the design error and recommends a
preferred alternative. The alternative recommended by District staff is to partially block the
intake structure of the Barron diversion culvert to allow it to accept a maximum flow of only
300 cubic feet per second (vs. 600 cubic feet per second per the original design). This
alternative will result in one percent (100-year) flood protection for Matadero Creek
¯ properties and five percent (20-year) flood protection for Barton Creek properties. The five
percent (20-year) level of protection for Barron Creek properties is higher than pre-project
conditions (20 percent/5-year protection), but lower than current conditions (one
percent/100-year protection). The recommended alternative was selected by District staff
because it eliminates the condition of causing flooding in new areas, provides improved flood
protection to all properties when compared with pre-project conditions, and minimizes the
total number of properties at risk of flooding. The District staff recommendation also
includes provisions for conducting District-hosted public meetings in the affected
neighborhoods to present information on the flood control project design error, interim
CMR:419:97 Page 2 of 3
measures to be implemented, and status of the LOMR application. City staffwill attend the
meetings.
District staff will proceed based upon direction given by the District Board at its October 7,
1997 meeting. It is expected that interim measures will be implemented and public meetings
will be conducted in late October. Staff will attend the October 7 District Board meeting and
then return to Council with updated information once it is available from the District.
FISCAL IMPACT
This report has no fiscal impacts to the City.
ENVIRONMENTAL ASSESSMENT
An environmental assessment is not required for this informational report.
ATTACHMENTS
Areas to be eliminated from the Special Flood Hazard Area as a result of the
Matadero/Barron Creek flood control project
PREPARED BY: Joe Teresi, Senior Engineer
DEPARTMENT HEAD REVIEW:
GLENN S.
Director of Works
CITY MANAGER APPROVAL:
City Manager
Stan Williams, Santa Clara Valley Water DistriCt
Kay Whitlock, Santa Clara Valley Water District
Dave Chesterman, Santa Clara Valley Water District
Randy Talley, Santa Clara Valley Water District
Gary Uenaka, Santa Clara Valley Water District
Susan Frank, Palo Alto Chamber of Commerce
Will Beckett, Barron Park Association
Kristen Johnson, Ventura Neighborhood Association
Cole Richmond, Chestnut-Wilton Homeowners Association
Debbie Mytels, Midtown Residents Association
CMR:419:97 Page 3 of 3
Areas to be eliminated from the Special Flood Hazard Area
as a result of the Matadero/Barron Creek flood control project
Polo Altc
Flood
Basin
~Areas to be eliminated from
Special, Flood Hazard Area Scale00.5 1 2
Miles
AB14901o