HomeMy WebLinkAbout1997-07-21 City Council (22)TO:
Manager’s
City of Palo Alto
Summary Report
HONORABLE CITY COUNCIL
7
FROM:
AGENDA DATE:
CITY MANAGER
July 21, 1997
DEPARTMENT: Community Services
CMR:327:97
SUBJECT:GOLF COURSE MASTER IMPROVEMENT PLAN
CONSTRUCTION, FINANCING, BUDGET AMENDMENT
ORDINANCE, PARKS IMPROVEMENT ORDINANCE, AND
MUNICIPAL FEE SCHEDULE AMENDMENT
Staff requests that Council authorize staff to proceed with construction of a significant
portion of the Golf Course Master Improvement Plan (MIP), as outlined in this report. Staff
also requests that Council approve the attached Budget Amendment Ordinance (BAO) in the
amount of $5.4 million to allow staff to begin to award contracts for the MIP, a Park
Improvement Ordinance which includes all construction phases of the Golf Course
Improvement Project, an amendment to the Golf Services section of the Municipal Fee
Schedule, and give staff authorization to fund the project through the issuance of bonds in
approximately spring of 1998.
RECOMMENDATIONS
Staff recommends that Council:
Approve the attached Budget Amendment Ordinance:to appropriate an additional $5.4
million to the existing capital improvement project 19624, "Golf Course Improvements"
to fund construction costs. Funding will come out of bond proceeds, anticipated to be
issued in spring of 1998, when the major construction occurs. Repayment of the bonds
will come from golf revenues. The driving range work will begin this fall, with the
contract for the remained of the work to be awarded by January 1998.
Direct staffto pursue issuance of revenue bonds to fund the project. The timing of the
sale will depend _on interest rates and the actual cash outlays for project construction.
Estimated bond proceeds, to cover construction costs, design costs already incurred,
issuance costs, and a debt service reserve fund as part of the financing, will total
approximately $7.4 million. The final amount issued will depend on the bond rating the
City receives and the actual interest rates in effect when the bonds are sold.
3.Approve the attached amendment to the Municipal Fee Schedule.
CMR:327:97 Page 1 of 13
4.Approve and adopt the Park Improvement Ordinance and Plan for the improvements to
the Municipal Golf Course.
There are a number of policy issues inherent in staff’s proposal for the Golf Course
improvements and financing. They include: ,
O
O
Level of subsidy, if any, from the General Fund for the course improvements.
Staff recommends that Golf Course revenues fund the course improvements and
that there should be no subsidy from the General Fund to provide staff support
for the project. While the.Golf Course is an important community asset, as a fee-
for-use recreational facility, it is appropriate for user fees to cover the cost of the
facility rather than diverting funds from other General Fund programs. Staff has
therefore sized the bond financing in accordance with the amount of debt
financing that can be funded from the expected future green fee revenue. Staff
will continue to recommend green fees that will fall within the average of Bay
Area public courses. Consequently, staff believes that the financial burden of
paying for the improvements overtime will not be onerous for users.
Assumption 0frisk by the City: There exists a risk that, in the event of future
economic downturn, demographic changes, or increased competition from
surrounding courses, that there would be insufficient green fee revenues to pay
for the debt service costs of these improvements. In that event, the General Fund
would be expected to make up any revenue shortfalls so that debt service
payments could be made. Staff believes, however, that the fee revenue
projections are prudent and conservative, and that projected fee increases will not
drive away customers. Furthermore, staff believes there is a larger risk to the
golf course revenue stream from a.9.I improving the course. If the Golf Course
continues to deteriorate, it is expected that bow the level of customer satisfaction
and the amount of public use will continue to decline, along with revenue.
ARY
Since 1985, preparations have been under way to perform significant renovation work to the
Palo Alto Municipal Golf Course. These preparations included the development of a ~
Course Master Improvement Plan, which Council approved in 1995. At that time, the cost
to implement the plan_ was estimated at $7-8 million. In 1996, Council was presented with
a preliminary draft of an implementation plan to address the goals of the ~I~ (CMR: 123:96).
Using Golf Course revenue potential as the controlling factor, the plan recommended $5
million in construction, which is partial implementation of the full ~. The balance of the
]~LE would be completed by the tenants, City Golf Course staff, and future capital projects,
as funding is available.
CMR:327:97 Page 2 of 13
Since the presentation of the preliminary MIP, staff and the consultants have been working
toward f’malizing construction plans and a financing plan, which are now complete. With
Council’s approval, it is staffs intent to begin construction of this project in fall of 1997,
which requires awarding a contract in August. The project will be completed by summer
1999.
This recommended construction project not ohly addresses the most pressing issues
identified in the ]EKE, but completes the necessary infrastructure which will be built upon
with future, continued improvements of the Golf Course. To keep within projected budget
restraints, the proposed project will not include all of the elements that were described in the
preliminary implementation plan presented to Council in 1996 (CMR:123:96). Certain
independent elements, including a storm reservoir, improvements to the parking lot,
including a bike path and entrance road, and an irrigation storm lake adjacent to fairway 18,
have been excluded from the proposed project and may be implemented when funds become
available.
Proposed Construction Project
The additional funds needed for the proposed project total $5.4 million. The project elements
are detailed in Attachment 1, and include:
o Construction of a master drain system ($830,000)
°Replacement of the irrigation system ($1;644,000)
¯Reconstruction of five fairways, eight greens, six tees, seven bunkers and various
roughs ($2,310,000)
°Repair/enhancement of cart paths ($68,000)
¯Renovation of the driving range ($548,000)
Completion of these elements of the ~ will help create a Golf Course that drains properly,
is efficiently irrigated, has healthy vegetation, is playable year-round and can compete with
courses throughout the Bay Area.
Municipal Fee Schedule Changes
Staff is requesting that Council approve an amendment to the Golf Services section of the
Municipal Fee Schedule. Because at times customers will not find the course in a fully
playable condition as an 18-hole course, some changes are proposed to the Municipal Fee
Schedule. During the construction period there will be three types of green fees in force.
Regular fees will apply when the normal 18-hole course is in play. When a shortened 18-
hole course will be in play, interim fees will apply. When the number of holes is reduced to
CMR:327:97 Page 3 of 13
15 holes or less, special application fees will apply. Activation of the different levels of fees
will be at the direction of the Director of Community Services.
Park Improvement Ordinance
The Charter and Municipal Code require that a Park Improvement Ordinance and a Plan be
approved and adopted prior to any construction or~ land held by the City for park purposes.
The Municipal Golf Course is in this category. The Park Improvement Ordinance and Plan,
Attachments five and six respectively, authorizes the improvements to the golf course.
EISCAL/MPACT
As reported in CMR: 140:96, the Golf Course improvement project will be fmanced through
issuing revenue bonds. The debt service will be paid for out of golf revenue, which includes
green fees and tenant r~ntal revenue. Community Services and Administrative staff have
projected a schedule of annual green fees over the years that will support these higher debt
servicecosts, without negatively impacting customer demand. The City’s current green fees
are below the market, and raising them to the proposed levels will bring the fees to within
the average for public golf courses in the Bay Area.
The total financing package, including construction, design and interim improvements, the
services of a f’mancial advisor and bond counsel, and a debt service reserve totals
approximately $7,400,000. Debt service payments on the bonds will be approximately
$600-650,000 annually, depending on the interest rates in effect when the bonds are actually
taken to market.
The total project f’mancing is projected as:
Construction Budget (if approved by Council via
BAO, attached)
Funds already appropriated:
Design and Interim Improvements
Financial Advisor
Financing Costs, to be:paid through bond proceeds, and
which will not needto be budgeted for:
Bond Counsel, Underwriter Fees, Other Issuance
Costs (est.)
$5,400,000
$660,000
$40,0O0
$400,000
Debt Service Reserve $900,000.
Total Estimated Financing Package $7,400,000
CMR:327:97 Page 4 of 13 ~
Staff has plans to incur most of the construction expenditures in the late spring and early
summer of 1998. To save on interest expenses during the first year, staff believes that the
sale of bonds should occur in the spring/summer of next year. The exact timing of the
project would depend on interest rates at that time, and the timing of the actual construction
payments. Staff therefore proposes that Council approve conceptually a bond sale for the
spring/summer of 1998, and authorize staff to determine the optimum timing with its
financial advisor. ’
The Budget Amendment Ordinance is for the full amount of the capital improvement project
because staffplans to award contracts for the entire project between now and the spring of
1998, when the debt is issued. The budget authorization needs to be in place for the contracts
to be awarded, and, rather than propose several incremental BAOs, it is proposed to authorize
the entire project at this time. The issuance of the debt, as stated above, is intended to
coincide with the first payment for the first stages of construction.
ENVIRONMENTAL ASSESSMENT
The City Council approved a Mitigated Negative Declaration for this project in May 1995
(CMR:248:95). The Mitigated Negative Declaration determined that any potential impacts
can be mitigated to levels of less than significance and are incorporated into the design of the
project.
CMR:327:97 Page 5 of 13 /
C ty
City of Palo Alto
Manager’s Report
SUBJECT: GOLF COURSE MASTER IMPROVEMENT PLAN CONSTRUCTION,
FINANCING, BUDGET AMENDMENT ORDINANCE, PARKS
IMPROVEMENT ORDINANCE, AND MUNICIPAL FEE SCHEDULE
AMENDMENT
Staff recommends that Council:
Approve the attached Budget Amendment Ordinance to appropriate an additional $5.4
million to the existing capital improvement project 19624, "Golf Course
Improvements" to fund construction costs. Funding will come out of bond proceeds
in Spring of 1998 when the major construction occurs. Repayment of debt service
will come from golf revenues. The driving range work will begin this fall, with the
contract for the remainder of the work to be awarded by January 1998.
Direct staffto pursue issuance of bonds in approximately spring of 1998 to fund the
project. The timing of the sale will depend on interest rates and the actual cash
outlays for project construction. Estimated total bond proceeds, to cover construction
costs, design costs already incurred, issuance costs, and a debt service reserve fund
as part of the financing will total approximately $7.4 million. The final amount issued
will depend on the bond rating the City receives and the actual interest rates in effect
when the bonds are sold.
3.Approve the attached amendment to the Municipal Fee Schedule.
o Approve and adopt the Park Improvement Ordinanceand Plan for the improvements
to the Municipal Golf Course.
Since 1985, preparations have been under way with the goal of performing significant
renovation work to th~ Palo Alto Municipal Golf Course. A brief history of those
preparations is as follows:
1985 - 1991: Starting in 1985, staff begin studying a number of customer service and
operational concerns that were emerging at the Golf Course. These included
irrigation and drainage problems, safety issues arising from errant balls leaving the
Golf Course, and revenue loss due to the limited size of the restaurant and pro shop.
Some of these issues were addressed through capital project proposals that were
CMR:327:97 Page 6 of 13 : ,
delayed pending development of a. comprehensive plan to address all Golf Course
issues.
1992 - Council approved the preparation of a ]EilE with the objective of addressing
existing problems and taking advantage of opportunities for long-term cost savings.
1993 - 1994 - The ~ was developed by consultants, Amphion Environmental, Inc.
and Halsey Daray Golf, working closely with City staffand the local golf community.
May 1995 - Council approved the ]~j~. Additionally, Council approved a Site and
Design Application and a Mitigated Negative Declaration for this project
(CMR:248:95). The plan was estimated to cost between $7 million and $8 million in
1995 dollars.
February 1996 - City Manager’s Report (CMR: 123:96) outlined a preliminary draft
of an implementation plan to address the goals of the ]kl!E. Using Golf Course
revenue potential as the controlling factor, the plan recommended $5 million in
construction, representing partial implementation of the full ]~Jd~. The balance of the
~ would be completed by the tenants, City Golf Course staff, and future capital
projects. This report also approved a contract extension to Amphion Environmental
Inc. to perform construction design work. Council also approved hiring a Financial
Advisor to examine options for financing the ]kllE. (CMR: 140:96).
February 1997 - Council approved funding for construction of interim greens and tees
in preparation for major construction to begin in spring 1998 (CMR: 146:97).
June 1997 - The 1997/98 budget adopted by Council included funds for materials and
staffing to begin implementing the fairway top-dressing program.
Since February 1997, staff and the consultants have been working toward fmalizing
construction plans and a financing plan, which are now complete. With Council approval,
it is staffs intent to begin construction of this project in fall of 1997 and complete the project
by summer 1999.
There are a number Of policy issues inherent in
improvements and financing. They include:
staff’s proposal for the Golf Course
O Level of subsidy, if.any, from the General Fund for the course improvements.
Staff recommends that Golf Course revenues fund the course improvements
and that there should be.no subsidy from the General Fund to provide staff
support for the project. While the Golf Course is an important community
asset, as a fee-for-use recreational facility, it is appropriate for user fees to
CMR:327:97 Page 7 of 13 l
cover the cost of the facility rather than diverting funds from other General
Fund programs. Staffhas therefore sized the bond financing in accordance with
the amount of debt financing that can be funded from the expected future green
fee revenue. Staffwill continue to recommend green fees that will fall within
the average of Bay Area public courses. Consequently, staff believes that the
financial burden of paying for the improvements overtime will not be onerous
for users. ’
O Assumption of risk by the City: There exists a risk that, in the event of future
economic downturn, demographic changes, or increased competition from
surrounding courses, that there would be insufficient green fee revenues to pay
for the debt service costs of these improvements. In that event, the General
Fund would be expected to make up any revenue shortfalls so that debt service
payments could be made. Staff believes, however, that the fee revenue
projections are prudent and conservative, and that projected fee increases will
not drive away customers. Furthermore, staffbelieves there is a larger risk to
the golf course revenue stream from l19_t improving the course. If the Golf
Course continues to deteriorate, it is expected that both the level of customer
satisfaction and the amount of public use will continue to decline, along with
revenue.
This recommended construction project not only addresses the most pressing issues
identified in the MIP, but completes the necessary infrastructure which will be built upon
with future improvements of the Golf Course. To keep within projected budget constraints,
the proposed project will not include all of the elements that were described in the
preliminary implementation plan presented to Council in February 1996 (CMR:123:96).
Certain independent elements, including a storm reservoir, improvements to the parking lot,
including a bike path and entrance road, and a reclamation irrigation lake adjacent to fairway
18 have been excluded from the proposed project, to be implemented when funds become
available.
Proposed Construction Project
The funds required for the proposed construction project total $5.4 million and are detailed
in Attachment 1. The major elements of the project are as follows:
Construction of a master drain system ($830,000): This is a storm drain system
which will reduce flooding and "standing water" on the rough areas outside of the fairways,
and on the course during the winter months, allowing for increased quality of play.
Additionally, this system, working in concert with the irrigation system and sand-capping,
will allow for the continual use of reclaimed water and will reduce salt buildup in the root
zone areas of the fairway grass plants.
CMR:327:97 Page 8 of 13 ~’
Replacement of the irrigation system ($1,644,000): The proposed irrigation system
will replace the current, failing system which is a combination of a 1955 and 1977
installation. It is designed to economically and precisely distribute reclaimed water to
fairways, tees and roughs (a State requirement), and potable water to the greens. Through
the ]EKE process and through discussions with other golf facilities using reclaimed water,
staff and the consultants agree that to minimize potential maintenance problems and enhance
customer service and the quality of play, it is essential to apply potable water to the greens.
Reconstruction of five fairways, eight greens, six tees, seven bunkers and various
roughs ($2,310,000): This construction will renovate the most critical areas of the course
with the highest toxicity levels in the soil and the poorest drainage. Drainage and growing
conditions will be vastly improved through sand-capping and grading.
Repair/enhancement of cart paths ($68,000): This element will provide cart paths
at the tees which are scheduled for renovation, and repair sections of the paths and service
roads that are damaged during construction. Path replacement in the new fairway areas will
be installed at a later date when funding becomes available.
Renovation of the driving range ($548,000): Repositioning the driving range and
installing higher fencing will mitigate a continuing safety issue by preventing errant balls
from going out onto Embarcadero Road, the office buildings adjacent to the range, and the
tenth fairway. During this process, the natural tmfarea of the driving range will be replaced
with a synthetic turf. The synthetic turf will reduce future maintenance costs associated with
mowing and irrigation, greatly improve its appearance, and minimize the substantial dust
problem that develops during most windy days.
Proposed Municipal Fee Schedule
Staff is requesting that Council approve an amendment tb the Golf Services section of the
Municipal Fee Schedule. Because, at times, customers will not find the course in a fully
playable condition as a 18-hole course, some changes are proposed to the Municipal Fee
Schedule. During the construction period there will be three types of green fees in force.
Regular fees will apply when the normal 1 g-hole course is in play. When a shortened 18-
hole course will be in play, interim fees will apply. When the number of holes is reduced to
15 or less, special application fees will apply. Activation of the different levels of fees will
be at the direction 0fthe Director of Community Services.
Park Improvement Ordinance
The Charter and Municipal Code require that a Park Improvement Ordinance and a Plan be
approved and adopted prior to any construction on land held by the City for park purposes.
The Municipal Golf Course is in this category. The Park Improvement Ordinance and Plan,
Attachments five and six respectively, authorizes the improvements to the golf course.
CMR:327:97 Page 9 of 13
Expected Results
During summer months the Golf Course is plagued with areas of turf that are hard pan and
brown, not due to lack of water, but due to the high salinity content of the soil. On many
fairways, salt from the underground bay water leaches through the soil making growing
conditions poor at best. This project will reduce salt intrusion and create favorable growing
conditions through increased irrigation, drainage, and a growing medium consisting of 10
inches of sand. ’
During winter months, standing water and large ponds form on fairways and in rough areas,
creating difficult to impossible playing conditions. Through sand-capping and the
installation of a master drain system, water will be carried offthe Golf Course at an increased
rate, and fairways scheduled for renovation may remain playable during the winter months.
Many rough areas, which are now void of vegetation, will become growing mediums for turf
and natural vegetation, giving the course a new look, with an expanse of vegetation instead
of brown areas, dust and mud. Siltation and runoff from these areaswill be reduced to
minimal amounts, benefiting the environment in and around the golf facility.
Underneath the visible improvements will be the infrastructure that will give the Golf Course
a solid base to be adequately maintained for the next twenty-year-period. The invisible miles
of pipe and wire, and the tons of sand and fill dirt will help create a Golf Course that drains
properly, is efficiently irrigated, has healthy vegetation, is playable year-round and can
compete with courses throughout the Bay Area,
Construction Schedule
This project will be completed in three phases (see Attachment 2 for a complete construction
schedule). Phase one, which will begin in July of 1997, will create new greens and tees that
will be used as an interim course while the major construction is done in Spring of 1998.
Phase two will implement construction of the driving range element. This element is being
done prior to the main course construction to provide some immediate and visible benefits
to the golfing community, and to allow for a more reliable revenue stream to the tenants (the
Golf Shop and the restaurant) and the City. During the driving range closure period of
approximately two months, the Golf Course will still be fully operational, and once the
driving range is complete, the Course will undergo construction.
Phase three, the major construction, will begin in the spring of 1998, at which time the
interim greens and tees will be ready for use. Total construction and turf grow-in time is
approximately one year, allowing the renovated course to be open to the public in late spring
of 1999.
Master Improvement Plan Elements Not Addressed in this Project:
Many of the improvements discussed in the ~ are not addressed in this project. These
include improvements that can be considered as independent or stand alone projects, and may
CMR:327:97 Page 10 of 13
be implemented through a combination of in-house work, capital projects, or tenant financed
improvements.
It is important to note here that, although most of the critical issues affecting the Golf Course
are being addressed, an integral part of the ]~[]~ Kes in the implementation of an enhanced
maintenance program, which includes, a long-term fairway top dressing program. The
enhanced maintenance program is necessary because this project will change the
maintenance standards of the course by adding approximately 20 percent more turf to
fertilize, irrigate, and mow. The top-dressing program will enhance drainage and growing
deficiencies on the balance of the Golf Course, by slowly building a sand base that will
isolate the turf roots from salt intrusion from underground bay water. This enhanced
maintenance and top-dressing program is not addressed by the construction project, but will
be included in the 1998-00 budget request.
The ~ elements that need to be completed in the future along with possible approaches for
implementation include:
Through the use of in-house staff and contracted services:
Improving drainage and growing conditions throughout the balance of the Golf Course
with a top-dressing program and additional drainage installations.~
¯Renovating remaining bunkers, greens and tees not addressed in this project
¯Planting trees lost through attrition for safety and esthetics
Through the use of capital projects, developed when funding is available:
¯Constructing a reservoir that will act as a holding pond for excess water
¯Constructing a reclaimed water storage area for irrigation (Presently, there is only a 15
minute reserve of water should the system fail.)
, Parking lot expansion ~
¯ Expanding the cart paths
Through tenant-funded improvements:
o Expanding the pro shop to allow for increased retail space, retail storage, and potential
increases in revenue
Expanding the restaurant seating capacity, enabling large tournaments and meeting
groups to use the facility and increasing potential revenues
Creating outside restaurant seating and a pass-through service window to provide quick
and easy access for golfers and non-golfers to obtain food and beverage service.
As reported in CMR: 140:96, the Golf Course improvement project will be fmanced through
issuing revenue bonds. This use of financing is consistent with the recently approved City
debt policy (CMR:210:97): "It is appropriate to consider debt financing.., when the project
CMR:327:97 Page 11 of 13 ! .~
financing can be paid for directly by the users of the facility" over time. The debt service
will be paid for out of golf revenue, which includes green fees and tenant rental revenue.
Community Services and Administrative staff have projected a schedule of annual green fees
over the years that will support these higher debt service costs without negatively impacting
customer demand. The City’s green fees are below market, and raising them to the levels
projected will mean that the City"s fees are within the average of public golf courses in the
Bay Area.
The total project f’mancing is projected as:
Construction Budget (if approved by Council via $5,400,000
BAO, attached)
Funds already appropriated:
Design and Interim Improvements $660,000
Financial Advisor $40,000
Financing Costs, to be paid through bond proceeds, and
which will not need to be budgeted for:
Bond Counsel, Underwriter Fees, Other Issuance $400,000
Costs (est.) "
Debt Service Reserve $900,000
Total Estimated Financing Package $7,400,000
This will result in annual debt service payments on the bonds of approximately
650,000, depending on the interest rates in effect when the bonds are actually sold.
$600-
Staffhas projected that the bulk of the construction expenditures will occur in the late spring
and early summer of 1998. In order to reduce interest expense the first year, staff believes
that the bond sale should optimally occur in the spring/summer of 1998. The exact timing
of the project would d~pend on interest rates at the time, and the timing of the actual
construction payments. Staff therefore proposes that Council approve conceptually a bond
sale for the spring/summer of 1998, and allow staff to determine the optimum timing with
its financial advisor.
Cash flow projections for the project expenditures indicate that about $.7 million will be
spent over the next six months on the first phase of construction, the driving range, and on
CMR:327:97 Page 12 of 13
the interim improvements approved by Council in CMR: 146:97 on February 24, 1997. With
previously spent design work, the City will have advanced a total of about $1.2 million for
the Golf Course project by next Spring. The City has been able to absorb these cash outlays
through its healthy cash flow situation.
The Budget Amendment Ordinance is for the full amount of the capital improvement project
because staffplans to award contracts for the entire project between now and the spring of
1998, when the debt is issued. The budget authorization needs to be in place for the contracts
to be awarded, and, rather than propose several incremental BAOs, it is proposed to authorize
the entire project at this time. The issuance of the debt, as stated above, is intended to
coincide with the first payment for the first stages of construction.
The California Constitution limits local governments from increasing general bonded
indebtedness without a 2/3 vote of the electorate. Therefore, absent a vote, one of the only
financing vehicles available for this type of project is the issuance of Certificates of
Participation (COPs). COPs are technically a long-term lease arrangement, not "debt," and
are therefore exempt from the Constitution’s voter requirements. This form of financing has
become a common, if not the predominant form of financing in California for projects that
are not either assessments, redevelopment related, or utility revenue bonds. It is the same
vehicle used for the existing golf financing done in 1978, as well as the method used to
finance Civic Center garage seismic improvements in the early 1980’s, as well as the
subsequent Civic Center seismic improvements-and fu’e alarm system.
Under COPs, the City sets up a separate legal entity, a nonprofit corporation, for a period
of time to coincide with the long-term lease, typically 20 years. The corporation leases the
Golf Course from the City. The "corporation," (i.e., the City), issues certificates .of
participation, and the proceeds are used to finance the capital improvements. Investors in
the bond market are, in effect purchasing a share of the fUture stream of lease payments that
the City will make to the corporation for leasing the golf course back for 20 years. The City
then uses green fee revenue to make the lease payments, and the General Fund stands behind
the lease payments in the event that fee revenue declines. While the City does not have to
stand behind the certificates, the interest rate charged would be quite expensive otherwise,
as the bonds would be more risky. Staff believes the risk of a significant golf market
downturn, particularly in the municipal market, is fairly remote.
~AL ASSESSMENT
The City Council approved a Mitigated Negative Declaration for this project in May 1995
(CMR:248:95). The Mitigated Negative Declaration determined that any potential impacts
can be mitigated to levels of less than significance and are incorporated into the design of the
project.
CMR:327:97 Page 13 of 13 ~
NEXT STEPS
1. Award contract for the Golf Course Driving Range
2. Develop and distribute RFP for Golf Course construction project
3. Award contract
ATTACHMENTS
Attachment 1: Project Elements and Budget "
Attachment 2: Project Schedule
Attachment 3: CMR: 123:96
Attachment 4: Budget Amendment Ordinance, with Exhibit A
Attachment 5: Parks Improvement Ordinance
Attachment 6: Golf Course Improvement Plans
Prepared by: Richard James, Administrator, Community Services Department
Jim Steele, Manager of Investments and Debt, Administrative
Department
Department Head Review~
PAUL THILTGEN
City Manager Approval:_~ctor, Commun~ervices
Palo Alto Golf Course Corporation "
Palo Alto Golf Advisory Committee ~
Services
CMR:327:97 Page 14 of 13 ] -
GOLF COURSE AMENDED BUDGET (5/13/97)Attachment I
,~OLF COURSE
IMPLEMENTATION PLAN
’"-’I Estimated Cost -i~I Construction T ~ilrrigation System
,,"Piping/heads
i!Irrigation System Total
IIStorm Drain System . -
Drainage System
Pump
Storm Drain System Total
Golf Course Surface Improvements
Fairways & Roughs*
#s 3, 4, 7, 10, 13, 15, 16, 18
Greens
Traps
Tees
#s4, 5, 7, 8, 11, 13, 15, 16
#s 4, 5, 6, 7, 10, 13, 15, 16
#s 3, 4, 10,13, 15, 18
’i Trees
Golf Course Surface Improvements Total
I Cart Path Repair/Expansion
IDriving Range
Fencing
Realignment
Driving Range Total
Construction Phase Subtotal
Construction Contingency
Construction Consultant Services
Const. Consultant Cont.
Construction Phase Total
,iPre’Construction Costs
Interim Improvements and Design Costs
TOTAL PROJECT COSTS _
$1,371,969
$1~_371~969
$361,260
$331,793
$693~052
$1,613,108
$203,207
$34,001
$77,450
$o
$1,927~766
$56~446
$197,125
$260,690
¯ " $457,8!5
$4,507,049
$676,057
$180,282
$36,056
$660,000
~6~444
$1_, 644,0001
$830,000
$2~310~000
$68~000
$548~000
$5,4o0,ooo
$660,000
$ ,os0,0oo
06/20/97, 10:52 AM FILE:GOLF$2.WK4
Attachment 2
GOLF COURSE PROJECT SCHEDULE
June 8, 1997
Interim Improvements
a.Award construction contract
b.Complete Construction
June 2, 1997
September 1997
°Driving Range
Solict bids
Open bids
Award contract & Park Improvement Ordiannce
Start construction
Complete construction "
June 18, 1997
July 22, 1997
August 4, 1997
September 1997
November 1997
°Purchase Sand
a.Solict bids
b.Open bids
c.Award contract
July 1997
September 1997
October 1997
o Golf Course Improvements
a.Solict bids
b.Open bids .
c.Award contract
d.Start construction
e.Complete construction
October 1997
December 1997
January 1998
March 1998
June - August 1998
Attachment 3
City Manager’s
City of Palo Alto
Summary Report
TO:HONORABLE CITY COUNCIL
ATTENTION:
FROM:
FINANCE COMMITTEE
CITY MANAGER DEPARTMENT:Community Services
DATE:FEBRUARY 13, 1996 CMR: 123:96
SUBJECT: Implementation Plan for the Development of the Golf Course Master
Improvement Plan
This report is a follow up to CMR:298:95, Implementation and financing plans for
development of the Golf Course Master Improvement Pdan. This report gives Council an
overview of the progress made toward implementing the Golf Course Master Improvement
Plan.
RECOMMENDATIONS
This is an informational report and there are no recommendations for action at this time.
This report is consistent with City policy.
EXECUTIVE SUMMARY
The Golf Course Master Improvement Plan is a conceptual proposal to upgrade various
components of the Golf Course, as addressed in CMR: 248:95. The Master Improvement
Plan’s objectives were designed to address existing problems and to create a format that takes
advantage of opportunities permitting long-term cost savings and increased value. Council
approved a Site and Design Application in May 1995.
The Master Improvement Plan originally called for approximately $8 million of
improvements and the developement of an action plan for completion of the project. Atter
much study, and with participation from-the departments of Administrative Services, Public
Works, and Community Services, staff developed a modified Implementation Plan to fit
within budgeting constraints.
The Implementation Plan includes $5 million for construction projects, including design, a
project manager and a contingency, a long-term accelerated maintenance program, and a plan
to execute some Master Plan improvements at a later date due to financial constraints. The
benefits of the proposed project are considerable, including irrigation, drainage, fairway, and
driving range improvements. These enhancements will provide for a high quality Golf
Course that will facilitate maintenance, ensure water savings by using reclaimed water more
efficiently, significantly improve playing conditions, and solidify long-term revenues through
a satisfied customer base.
To finance this project, staff is formulating a plan, that involves issuing bonds and a possible
subsidy to the Golf Course from the Gerieral Fund, as Golf Course revenue will not cover all
costs during the construction phase. Staff is also exploring potential partnerships with
tenants that would result in customer service improvements, and long-term enhancements to
the restaurant and pro shop. Tenant improvements are not included in the $5 million. Tax
law changes regarding the use of tax exempt bonds for portions of the Golf Course
improvements, have raised issues that require additional research and discussion. A separate
staff report recommends retaining a financial advisor to assist staff in studying these
questions with bond counsel, supporting discussions on tenant lease negotiations, and
structuring a financing package.
FISCAL IMPACT
No fiscal impact at this time.
ENVIRONMENTAL ASSESSMENT
1. Environmental Assessment recommended adoption of a negative declaration.
2. Council approved a Mitigated Negative Declaration that determined that any potential
impacts can be mitigated to levels of less than significance.
ATTACHMENTS
CMR:298:95
Golf Course Project Schedule
Prepared by: Richard James, Department of Community Services
Department Head Review:
Director of Community Services
City Manager Approval:
CMR: 123:96 Page 2 of 8 :.
City of Palo Alto
City Manager’s Report
Implementation Plan for the Development of the Golf Course Master
Improvement Plan
This report is a follow-up to CMR:298:95, J~plementation and financing plans for
development of the Golf Co~. The report gives Council an
overview of the progress made toward implementing the Golf Course Master Improvement
Plan.
The Golf Course Master Improvement Plan is a conceptual proposal developed to upgrade
various components of the Golf Course, as addressed in CMR: 248:95. Council approved
a Site and Design Application and a Mitigated Negative Declaration for this plan in May
1995.
The Master Improvement Plan objectives were designed to address existing problems and
to create a format to take advantage of opportunities permitting long-term cost savings and ¯
increased value. The Master Improvement Plan cites the following as its objectives:
Address critical irrigation and drainage problems;
-Optimize the use of reclaimed water;
-Maintain affordable green fee structure and provide quality golf;
-Minimize environmental impacts relative to areas of potential renovations;
-Ensure the safety of golfers, staff and neighbors;
-Balance long-term maintenance and budgetary requirements;
-Improve parking, restaurant, golf shop and driving range facilities to meet
safety issues and enhance revenue production; and
-Improve the maintenance and storage facilities to address associated
environmental concerns.
The Master Plan originally called for approximately $8 million of improvements and
developed an action plan for completion of the project. After much study, and with
participation from the departments of Administrative Services, Public Works and
Community Services, staffdeveloped a modified Implementation Plan to fit within budgeting
constraints. The objectives of the modified Implementation Plan are:
CMR: 123:96 Page 3 of 8
Address the most pressing recommendations of the Master Improvement Plan,
Develop a viable financial plan, and
Maintain revenue flow. by not closing the Golf Course during construction periods.
The modified Implementation Plan includes $5 million for construction projects, including
design, a project manager and a contingency, a long-term accelerated maintenance program,
and a plan to execute Master Plan improvements that are being deferred due to financial
constraints. The benefits of the proposed project are considerable, including irrigation,
drainage, fairway, and driving range improvements. These enhancements allow for a high
quality Golf Course that will facilitate maintenance, ensure water savings by using reclaimed
water more efficiently, significantly improve playing conditions, and solidify long-term
revenues through a satisfied customer base.
¯To finance this project, staffis formulating a plan that involves issuing bonds and a subsidy
to the Golf Course from the General Fund, as golf course revenue will not cover all operating
and debt sei’vice costs during the construction phase. Staff is also exploring potential
partnerships with tenants that would result in customer service improvements, and long-term
enhancements to the restaurant and pro shop. Tenant improvements are not included in the
$5 million. Tax law changes regarding the use of tax exempt bonds for portions of the Golf
Course improvements, have raised issues that require additional research and discussion. It
is anticipated that bonds will no[ need to be sold until 1997-98.
POLICY IMPLI~
This report is consistent with current City policy.
IMPLEMENTATION PLAN
The proposed Implementation Plan is the result of a collaborative effort by. City staff to
design a program that balances customer needs with the need for horticultural and drainage
improvements to the Course, regulatory agency requirements, and available funding. This
Implementation Plan is grouped into ten areas consisting of: Project Management, Consultant
Selection, Project Design, Interim Improvements, Project Schedule, Proposed Construction,
City Staff Implemented Improvements, Tenant Improvements, Enhanced Maintenance
Program and Financial Plan.
Project Management
Project management will be accomplished using a unique, team concept, composed of staff
from the Public Works and Community Services Departments. This team approach will take
advantage of each Department’s strengths and expertise. Community Services staffpossesses.._
knowledge and experience in Golf Course design, operation and maintenance, and works
closely with the golfcornmunity. Public Works’ expertise lies in project planning, document
CMR: 123:96 Page 4 of 8
preparation and contract negotiations. All aspects of the project will be monitored and
appropriate decisions made using the knowledge and background contained within each
Department. Staff is confident that this team approach to project management will be a
blueprint for future projects of this nature.
Consultant Selection
The Master Plan consultants, Amphion Environmental, Inc. and Halsey Daray Golf, will
provide the design and construction services for this project. The 1994 Golf Course Master
Improvement Plan "Request for Proposals" included a provision to retain the consultant for
future design work, if the initial work were deemed successful. The firms selected to prepare
the Master Plan were successful in working with the community and City staff, and
developed a quality product. Subsequently, staff is commencing negotiations with Amphion
Environmental, Inc. and Halsey Daray Golf to have them continue to supply the services
necessary to carry out the Master Plan.
Project Design:
The proposed Implementation Plan includes all of the recommended Master Improvement
Plan Golf Course renovations. Although there are not sufficient funds to pay for all of these
renovations, staff proposes that all greens, tees and fairways proposed to be rebuilt, be
designed now with some as add-alternates to the bid. This would allow them to be included
in the construction project, should estimates come in lower than anticipated. Designing all
of the Course improvements at this time will also allow for consistency of design, Create cost
effieiencies, and provide opportunities to proceed with the balance of the improvements
should resources become available in future years.
Interim Improvements:
To allow continued golf play during the project, City staff will make necessary interim
improvements to the Golf Course before construction. These include building temporary
greens and tees, erecting safety barriers around the modified tee areas, and performing minor
irrigation changes to help maintain the temporary greens and tees. Staff will return to
Council following the design process with recommendations for temporary staffing, and
supplies and materials for interim improvements.
Project Schedule
This element of the project is scheduled to begin its design phase in April 1996 and be
completed in April 1997. Interim construction (temporary tees and greens) would commence
no later than July 1997 and reach completion in time for course demolition, grading and
renovation beginning in March 1998. Bonds would most likely be sold during this time. The
initial construction project would be completed between March 1999 and June 1999. (A
detailed project schedule is attached.)
Proposed Construction:
The work that will be accomplished during the initial construction period inelude~:
Golf Course."
CMR: 123:96 Page5of8 ,~ ~
Construction of a master drain system and storm reservoir.
Replacement of the irrigation system.
Reconsm~ction of five fairways, approximately nine greens and fourteen bunkers.
Grading and leveling six tees and renovating various rough areas throughout the Golf
Course.
Reposition the driving range away from Embarcadero Road. Install higher fencing to
contain errant balls from entering Embarcadero Road, office buildings, and the tenth
fairway.
Grade, sand cap, install irrigation, and plant turf on the range.
¯
_ a
Enlarge parking lot and provide a new exit to Embarcadero Road to improve traffic flow.
Improve the Golf Course/Airport access road.
Improve restaurant delivery service entry and employee parking area.
City Staff Implemented Improvements:
The Parks and Golf Division can complete the balance of the deferred improvements through
a combination of in-house work, outside contracts and capital improvement projects. The
deferred components could be funded when cash flow allows, which staff estimates to be in
the fiscal year 2005-06. Completion of deferred components may include:
Repairing and enhancing the cart path system;
Planting trees for safety and esthetics;
-Improving the fairways, greens and tees that were not part of the initial
project;
-Maintaining facility improvements; and
-Other items as defined in the Master Improvement Plan.
Tenant Improvements:
Several improvements recommended in the Master Improvement Plan .included customer
service enhancements to Golf Course tenant facilities. Implementing such improvements
is contingent upon future lease contracts with the restaurant and pro shop operators.
Potential tenant improvements include:
-Pro shop expansion allowing increased retail space, retail storage, and
potenti~il increases in revenue;
-Installation of driving range lighting allowing for limited night use and
increased revenues; .
-Additional restaurant seating capacity enabling large tournament and meeting
groups to use the facility, thus increasing potential revenue sources; and"
CMR: 123:96 Page 6 of 8 ~.~., "~
-Outside restaurant seating and a pass-through service window to provide
quick and easy access for golfers and non-golfers to obtain food and beverage
service.
Enhanced Maintenance Program
The Golf Course consultant and the Master Improvement Plan recommend an enhanced.
maintenance program. Accomplishing this will "require an increase in present levels of
maintenance expenditures, which involves augmentations in staffing, equipment and
materials. Noting that present staffing levels are considerably below comparable courses,
the Master Plan recommends at least three full time staff be added to the operating budget.
This implementation proposal recommends the addition of two full time maintenance
personnel. The additional personnel will facilitate the Master Plan’s recommended increase
in turf maintenance and aid in the completion of deferred maintenance and Master Plan
projects.
The Master Plan also recommends an accelerated topdressing program to improve existing
turf conditions and to reduce future capital costs for improvements. This topdressing
program is designed to improve the soil structures and medium for those fairways deferred
or not designated for sand capping. Periodic light layers of sand, approximately 1/4" thick,
will be applied to the fairways to improve existing soil conditions and drainage in the surface
of the soil structure. The sand will be applied monthly during the growing season. The long-
term goal is to raise the existing surface of the fairways 12 to 18 inches, over a 7 to 10 year
period, creating a medium suitable to growing tuff. and better utilization of reelairned water.
Implementation of this program calls for an increase to the operation budget of $150,000 for
supplies and materials.
Financial Plan
To finance the Implementation Plan, staffhas been formulating a financial plan that involves
funding from a bond issuance for construction projects and-a subsidy from the General Fund
to maintain golf operations during the construction period, when green fee revenue will
decline due to an anticipated decline in golf rounds played. In exploring bond financing, a
number of issues arose which affect the type and amount of debt that can be issued and also
affect the City’s Golf Course’s contractual arrangements with its tenants. Because staff is
still working with bond counsel and the Golf Course tenants on these issues, a reasonably
accurate pro forma cannot be prepared at this time. However, Staff is able to provide
background information into the questions at hand and into the essential features of Master
Plan financing.
A nonprofit Golf Course Corporation was formed in 1977 to facilitate Golf Course
improvements. Since the.Corporation last issued debt in 1978, tax laws have changed. These
changes center on the extent to which a tax-exempt bond issuance for a public facility can
CMR: 123:96 Page 7 of 8 ~ ~-
benefit a private, for profit business. The City also has the option of issuing taxable bonds
for Master Plan improvements. Use of taxable bonds allows the City to enter into any type
of contractual agreement with lessees and make any improvements Council approves, but
that method of financing is more costly. The type of bonds issued, therefore, has an impact
on the amount of debt that can be incurred, and on the terms of the leases with tenants. The
role of the financial advisor will be to help staff study these questions with bond counsel,
support discussions on tenant lease negotiations, and structure a financing package. Based
on a conservative, tax-exempt rate of 6.3 percent and anticipated project and issuance costs
of $5.6 million, the Golf Course’s annual’debt service would equal $501,000 per year. At a
higher, taxable bond rate of 8.3 percent for the same project, an annual debt service of
$584,000 would be required. The rate spread, between the types of bonds issued, requires
staff to carefully assess options and alternatives in financing the Master Plan and in
developing contracts with lessees. In addition, staffwill explore with bond counsel whether
the issuance of new debt requires the Golf Course to refinance the remaining debt from the
1978 bond issuance.
ALTERNATIVES
Alternatives are not addressed in this report.
FISCAL IMPACT
The recommendations in this report have no direct fiscal impact.
ENVIRONMENTAL ASSESSMENT
Council approved a Mitigated Negative Declaration for this project in May 1995
(CMR:248:95). Major issues that were discussed included biotic resources, hazardous
materials, reclaimed water, flooding, lighting and glare, and traffic and circulation. The
Mitigated Negative Declaration determined that any potential impacts can be mitigated to
levels of less than significance.
STEPS FOLLOWING APPROVAl,.."
1. Develop Request for Proposal for financial advisor services.
2. Award contract to Financial Advisor.
3. Begin contract negotiations with Amphion Environmental, Inc., and Halsey Daray
Golf.
4. Return to Council for approval of an amended consultant contract including a Budget
Amendment Ordinance.
5. Create a Capital Impiovement Project for construction design services.
6. Initiate design work for the project.
ATTACHMENTS/EXHIBITS
CMR:298:95
Golf Course Project Schedule
CMR: 123:96 Page 8 of 8 ’ f
City
City of Palo Alto
Manager’s Report
TO:HONORABLE CITY COUNCIL
FROM:CITY MANAGER DEPARTMENT: Community Services
AGENDA DATE: June 12, 1995 CMR: 298:95
SUBJECT:Implementation and financing plans for development of the Golf
Course Master Improvement Plan
REQUEST
This is an informational report and no Council action is requested.
RECOMMENDATIONS"
There are no recommendations at this time. Staff will submit to the Finance Committee a
recommendation for implementation, development and financing, for the Golf Course Master
Improvement Plan, late this Summer. A Committee recommendation could then be given to
Council in the Fall.
POLICY IMPLICATIONS
This project does not represent any change to existing City policies.
EXECUTIVE SUMMARY
The Golf Course Master Improvement Plan is a conceptual proposal to upgrade various
components of the golf course, as addressed in the Planning and Community Environment Site
and Design CMR: 248:95. Staff, the Consultant Team and the Golf Advisory Committee will
continue to refine the technique for developing and financing the Master Improvement Plan.
Finance, Community Services and Public Works Departments are in the process of reworking
the pro forma financial statements and the development of work schedules, so that this project
can be accommodated within fiscal eonslraints, and allow the Golf Course to remain open in
some manner during the=construction phase to minimize public disruption.
FISCAL IMPACT
There is no fiscal impact at this time.
CMR: 298:95 Page 1 of 2
ENVIRONMENTAL ASSESSMENT
There is no environmental assessment or impact associated with this report.
Related CMK:248:95 Site and Design Application
(Copies available in City Manager’s Office)
PREPARED BY: Paul Dias, Parks and Golf Division
DEPARTMENT HEAD REVIEW:
PAUL THILTGE~
Director of Community Services
CITY MANAGER APPROVAL:
CC:Golf Advisory Committee
Golf Course Corporation
CMR:298:9~Page 2 of 2
Attachm~
ORDINANCE NO.
ORDINANCE OF THE COUNCIL OF THE CITY OF PAL0 ALTO
AMENDING THE BUDGET FOR THE FISCAL YEAR 1997-98 TO
PROVIDE AN ADDITIONAL APPROPRIATION AND TO AMEND THE
MUNICIPAL FEE SCHEDULE FOR THE’GOLF COURSE IMPROVEMENTS
CAPITAL IMPROVEMENTS PROJECT, NUMBER 19624
WHEREAS, pursuant to the provisions of Section 12 of Article
III of the Charter of the City of Palo Alto, the Council on June
23, 1997 did adopt a budget and a Municipal Fee Schedule for fiscal
year 1997-98; and
WHEREAS, on May 15, 1995, Council approved a Golf Course Master
Plan; and
WHEREAS, in order to preserve its long-term viability,
improvements to the Golf Course are needed, including work to
enhance drainage, upgrade the irrigation system, improve fairways
and greens, and renovate the driving range; and
WHEREAS, the estimated cost of the proposed improvements is
$5,400,000; and
WHEREAS, the Council has adopted Resolution 7581, declaring its
intent to issue debt financing in the form of tax exempt bonds in
the future to fund the improvements to the Golf Course; and
WHEREAS, the bonds will be sold in spring or early summer of
1998 to coincide with the timing of actual cash outlays for,project
construction and obtain the most advantageous interest rates; and
WHEREAS, CIP 19624, Golf Course Improvements, needs to be
increased now so that construction of driving range improvements can
begin in the fall and so that the contract for the major
improvements can be awarded in January 1998;and
WHEREAS, upon the sale of the bonds, the General Fund will be
reimbursed for all expenses incurred up to the date of the sale
which are related-to the Golf Course project; and
WHEREAS, the 1997-98 Municipal Fee Schedule needs to be amended
to allow for fee reductions during times when the course will not
be in a fully playable condition due to interim improvements and
construction; and
WHEREAS, City Council authorization is needed to amend the
1997-98 budget and the Municipal Fee Schedule as hereinafter set
forth.
NOW, THEREFORE, the Council of the City of Palo Alto does
ORDAIN as follows:
SECTION i. The sum of Five Million Four Hundred Thousand
Dollars ($5,400,000) is hereby appropriated to Capital Improvement
Project No. 19624, Golf Course Improvements, which will be funded
from the anticipated sale of bonds.
SECTION 2. This transaction will have no impact on the Budget
Stabilization Reserve.
SECTION 3. The Municipal Fee Schedule is hereby amended to
reflect changes shown in Exhibit A, which is attached hereto and
incorporated herein by reference.
SECTION 4. As specified in Section 2.28.080(a) of the Palo
Alto Municipal Code, a two-thirds vote of the City Council is.
required to adopt this ordinance.
SECTION 5. The City Council approved a Mitigated Negative
Declaration for this project in May 1995 (CMR:248:95) . The
Mitigated Negative Declaration determined that any potential impacts
can be mitigated to less than significance, and have been
incorporated into the design of the project.
SECTION 6. As provided in Section 2.04.350 of the Palo Alto
Municipal Code, this ordinance shall become effective upon adoption.
INTRODUCED AND PASSED:
AYES:
NOES:
ABSTENTIONS:
ABSENT:
ATTEST:APPROVED AS TO FORM:
City Clerk Senior Asst. City Attorney
APPROVED:
Mayor
City Manager
Acting Director, Administrative
Services Department
Director of Community Services
Department
ORDINANCE NO.
ORDINANCE OF THE COUNCIL OF THE CITY OF PALO ALTO
APPROVING AND ADOPTING A PLAN FOR IMPROVEMENTS TO
MUNICIPAL GOLF COURSE
WHEREAS, Article VIII of th~ Charter of the City of Palo
Alto and Section 22.08.005 of the Palo Alto Municipal Code require
that before any substantial building, construction, reconstruction
or development is commenced or approved, upon or with respect to
any land held by the City for park purposes, the Council shall
first cause to be prepared and by ordinance approve and adopt a
plan therefor; and
WHEREAS, the Municipal Golf Course is dedicated to park
purposes; and
WHEREAS, the City intends to construct certain capital
improvements to the Municipal Golf Course, including, without
limitation: the reconstruction of various fairways, greens, roughs,
tees, bunkers and golf cart paths; the construction of an electric
utility system; the installation of a new irrigation system; the
installation of a new storm drain system and drainagepumping
system; and the realignment and renovation of the driving range
("Plan"); and
WHEREAS, the site and design review of the Plan has been
conducted and the Plan has been recommended for approval by the
City boards and commissions having jurisdiction over such matters,
because it conforms to the provisions of Chapter 18.82 of the Palo
Alto Municipal Code and the Palo Alto Comprehensive Plan; and
WHEREAS, the Council desires to approve the Plan and to
adopt it as part of the official plan for the construction of
improvements at the Municipal Golf Course;
NOW, THEREFORE, the Council of the City of Palo Alto does
ORDAIN as follows:
SECTION I. The Plan, a copy of which is on file in the
office of the Division of Planning, Department of Planning and
Community Environment, and to which copy reference is hereby made
concerning the full particulars thereof, is hereby approved and
adopted.
SECTION 2. TheCity Council hereby finds that this project
is categorically exempt under Section 15304 of Title 14 of the
California Code of Regulations.
970715 syn 0071241
SECTION 3. This ordinance shall become effective upon the
commencement of the thirty-first day after the day of its adoption.
INTRODUCED :
PASSED:
AYES :
NOES :
ABSENT:
ABSTENTIONS :
ATTEST :APPROVED:
City Clerk Mayor
City Manager
APPROVED AS TO FORM:
Senior Asst. City Attorney
City Manager
Director of Public Works
Director of Planning and
Community Environment
Director of Community Services
Director of Parks and Golf
Course
2
970715 syn 0071241
Attachment 6
Construction Item Legend
:.:i’;’ili.!.ii~.!’ Rough Reconstruction Areas
Fairways
Greens and Bunkers
Fairway Bunkers
Driving Ranl~
Realign &
Renovate
Driving
Range
Existing
Club House
& Pro Shop
Enhance
WetLands
’.:.:.:..,Oo o o od
New Irrigation
Entire Course
Existing
Restroom
Existing
Parking Lot