HomeMy WebLinkAbout1998-12-14 City Council (32)TO:
FROM:
DATE:
SUBJECT:
City of Palo Alto
City Manager’s Report
HONORABLE CITY COUNCIL
CITY MANAGER
DECEMBER 14, 1998
DEPARTMENT: PUBLIC WORKS
CMR:466:98
AWARD OF CONTRACT TO JIM DUFFY CONSTRUCTION FOR
THE CONSTRUCTION OF THE ENVIRONMENTAL COMPLIANCE
LABORATORY AND OFFICES AT THE WATER QUALITY
CONTROL PLANT
RECOMMENDATION
Staff recommends that Council:
Approve and authorize the Mayor to execute the attached contract with Jim Duffy
Construction in the amount of $538,698 for the construction of the Environmental
Compliance Division laboratory and office space at the Water Quality Control Plant
(RWQCP).
Authorize the City Manager or her designee to negotiate and execute one or more
change orders to the contract with Jim Duffy Construction for additional but
unforeseen work which may develop during the project, the total value of which shall
not exceed $53,870.
DISCUSSION
Project Description
The project involves relocation of the Environmental Compliance Division laboratory and
modification of related office space at the RWQCP. An additional 1520 square feet will be
added to the back side of the existing Administration Building in an adjacent abandoned
structure. The new space will house the laboratory and new office space. Approximately
4620 square feet of existing Administration Building interior space will be improved.
Improvements will include the addition of a conference room, fire suppression system,
upgraded and wheel chair accessible bathrooms and entryways, and a basement storage
room. Construction will require nine months to complete.
Bid Process
The project was first issued for bid to five contractors on September 28, 1998. The bidding
period was 29 days, and bids were received from three contractors on October 27, 1998.
Because of a wide bid spread ($933,000 to $553,272) and irregularities in the bids, Council
CMR:466:98 Page 1 of 2
rejected all bids on November 23, 1998 (CMR:439:98).
Staff added clarifications to the bid document and the project was issued for rebid. On
November 24, 1998, the notice for rebid was issued to four contractors. The rebid period
was 14 days. Bids were received from three contractors on December 8, 1998, as listed on
the attached bid summary (Attachment A). The bids ranged from a high of $662,110 to a
low bid of $538,698.
Staff has reviewed all bids submitted and recommends that the bid of $538,698 submitted
by Jim Dully Construction be accepted, and that Jim Duffy Construction be declared the
lowest responsible bidder. The bid is ten percent below the Engineer’s estimate of $600,000.
A change order amount of $53,870 which equals ten percent of the total contract, is
requested.
Staff checked references supplied by the contractor for previous work performed and found
no significant complaints. Staff also checked with the Contractors State License Board and
found that the contractor has an active license on file.
RESOURCE IMPACT
Funds for the project have been appropriated in the FY 1998-99 projects, Industrial Waste
Lab Relocation (CIP #9454) and Laboratory Facilities and Equipment (CIP #8865).
POLICY IMPLICATIONS
Recommendations of this staff report are consistent with City policies.
ENVIRONMENTAL REVIEW
This project is categorically exempt from CEQA.
ATTACHMENTS
Attachment A: Bid Summary
Attachment B: CMR:439:98
PREPARED BY: Phil Bobel, ~,anager Fcpvironrn~e~atal Compliance Division
DEPARTMENT HEAD: /z~~ //~. ~ff~/~
GLENN S. ROBERTS "
Director of Public Works
CITY MANAGER APPROVAL:
EMILY HARRI~
Assistant City Manager
CMR:466:98 Page 2 of 2
ATTACHMENT A
ATTACHMENT B
TO:
FROM:
City of Palo Alto
City Manager’s Report
HONORABLE CITY COUNCIL
CITY MANAGER DEPARTMENT: PUBLIC WORKS
6
DATE:NOVEMBER 23, 1998 CMR:439:98
SUBJECT:REJECTION OF BIDS FOR THE CONSTRUCTION OF THE
ENVIRONMENTAL COMPLIANCE LABORATORY AND OFFICES
AT THE WATER QUALITY CONTROL PLANT
RECOMMENDATION
Staff recommends that Council reject all bids for the construction of the Environmental
Compliance Division laboratory and office space at the Water Quality Control Plant
(RWQCP).
DISCUSSION
Project Description
The project involves relocation of the Environmental Compliance Division laboratory and
modification of related office space at the RWQCP. An additional 1520 square feet will be
added to the back side of the existing Administration Building in an adjacent abandoned
structure. The new space will house the laboratory and new office space. Approximately
4620 square feet of existing Administration Building interior space will be improved.
Improvements will include the addition of a conference room, fire suppression system,
upgraded and wheel chair-accessible bathrooms and entryways, and a basement storage
room. Construction will require nine months to complete.
Bid Process
A notice inviting formal bids for the construction of the laboratory and office space was sent
on September 28, 1998 to five contractors. The bidding period was 29 days. A mandatory
pre-bid meeting was held on October 8, 1998; four bidders attended the meeting. One bidder
did not attend the pre-bid meeting because their predicted worker availability was very low.
Bids were received from three contractors on October 27, 1998, as listed on the attached bid
summary (Attachment A). Bids ranged from a high of $933,000 to a low bid of $553,272.
Staffhas reviewed all bids submitted and recommends that Council reject all bids. Staff’s
recommendation is based on two reasons. First, the two lowest bidders contain some minor
irregularities in the listing of subcontractors. Secondarily, the day before the bid opening,
some discrepancies in the bid documents were identified. Staff believes that there was
CMR:439:98 Page 1 of 2
insufficient time to provide clarifications so that the bidders could prepare a good bid, which
may have led to the wide bid spread ...........................
Staffrecommends that Council reject all bids. Staffwill make certain that the discrepancies
are addressed and the bidders are given sufficient timeto prepare accurate bids.
RESOURCE IMPACT
Funds for the project have been appropriated in the FY 1998-99 CIP project #9454 and
FY 1998-99 CIP project #8865.
POLICY IMPLICATIONS
Recommendations of this staff report are consistent with City policies.
ENVIRONMENTAL REVIEW
This project is categorically exempt from California Environmental Quality Act.
ATTACHMENT
Environmental Compliance Laboratory - Bid Summary
PREPARED BY: Phil Bobel, Manager, Environmental Compliance Division
DEPARTMENT HEAD:.
GLENN S. ROBERTS
Director of Public Works
CITY MANAGER APPROVAL:
EIMILY H--ARRI SON ~
Assistant City Manager
CMR:439:98 Page 2 of 2