HomeMy WebLinkAbout1998-08-03 City Council (13)City of Palo Alto,
City Manager’s Report
TO:HONORABLE CITY COUNCIL
6
FROM:CITY MANAGER DEPARTMENT: PUBLIC WORKS
DATE:AUGUST 3, 1998 CMR:335:98
SUBJECT:AWARD OF CONTRACT TO ANDY’S ROOFING COMPANY, INC.,
FOR CUBBERLEY COMMUNITY CENTER CLASSROOMS "A" AND
"B" AND COVERED HALLWAYS RE-ROOFING PROJECT- CIP
19018
RECOMMENDATION
Staff recommends that Council:
Approve and authorize the Mayor to execute the attached contract with Andy’s Roofing
Company, Inc., in the amount of $174,000 for the Cubberley Community Center
Classrooms A and B and Covered Hallways Re-roofing Project.
Authorize the City Manager or her designee to negotiate and execute one or more
change orders to the contract with Andy’s Roofing Company, Inc., for related,
additional but unforeseen work which may develop during the project, the total value
of which shall not exceed $17,400.
DISCUSSION
Project Description
The built-up roofs on Units A and B, the covered hallways attached to Buildings R and S,
and the remaining covered hallways at the perimeters of the buildings are being replaced as
part of an ongoing roofing repair and replacement program at the Cubberley site. Plywood
decking and sheetmetal gutters and flashings will be replaced as requiredi Roof replacements
at the Cubberley site are being accomplished according to an established priority over
multiple years with an average of two roofs scheduled per year for replacement.
Bid Process
A notice inviting formal bids for the Cubberley Community Center Classrooms A, B and
Covered Hallway Re-Roof Project was sent on June 24, 1998, to five builders’ exchanges
and 11 contractors. The bidding period was 27 days. A pre-bid meeting was held on June
30, 1998; six bidders attended the meeting. Bids were received from two qualified
contractors on July 21, 1998, as listed on the attached bid summary (Attachment A). Bids
CMR:335:98 Page 1 of 2
ranged from a ~high of $187,796 to a low bid of 174,000. Contractors not responding
indicated that they did not submit a bid because they were too busy.
Staff has reviewed all bids submitted and recommends that the bid of $174,000 submitted
by Andy’s Roofing Company, Inc., be accepted and that Andy’s Roofing Company, Inc.,
be declared the lowest responsible bidder. The bid is 14 percent below the engineer’s
estimate of $203,500.
Staff checked references supplied by the contractor for previous work performed and found
no significant complaints. Staff also checked with the Contractor’s State License Board and
found that the contractor has an active license on file.
RESOURCE IMPACT
Funds for this project are available in Capital Improvement Project 19018, Cubberley Code
and Roof Repairs.
POLICY IMPLICATIONS
This award does not represent any change to existing City policies.
ENVIRONMENTAL REVIEW
This project is categorically exempt from California Environmental Quality Act and no
further environmental review is necessary.
ATTACHMENTS
Attachment A:Bid Summary
Attachment B:Contract
PREPARED BY:Karen Smith, Facilities Manager
DEPARTMENT HEAD:./~----,.,
~GLENN £.
,lic Works
CITY MANAGER
EMILY HARRISON
Assistant City Manager
CMR:335:98 Page 2 of 2
0
r7
E
00
0
00 00
000
00
00
00
00
00
000
00
000
00
00
00
ATTACHMENT A
ATTACHMENT B
FORMAL CONTRACT SECTION 500
CONTRACT
(Public Work)
Public Works Department
This Contract, dated x..~_, is entered into by and between the City of Palo Alto, a chartered city and a municipal corporation
of the State of California ("City"), and Andy’s Roofing Company, Inc., a California Corporation, ("Contractor").
For and in consideration of the covenants, terms, and conditions ("the provisions") of this Contract, City and Contractor
("the parties")agree:
1.Term. This Contract shall commence and be binding on the parties on the Date of Execution of this Contract, and
shall expire on the date of recordation of the Notice of Substantial Completion, or, if no such notice is required
to be filed, on the date that final payment is made hereunder, subject to the eadier termination of this Contract.
2.General Scobe of Project and Work. Contractor shall furnish labor, services, materials and equipment in.
connection with the construction of the Project and complete the Work in accordance with the covenants, terms
and conditions of this Contract to the satisfaction of City. The Project and Work is generally described as fol lows:
PROJECT TITLE:Cubberley Community Center Classrooms A, B and Covered Hallway Re-roof
Invitation For Bids (IFB) # 107292
Base Bid:$174,000.00
Contract Documents. This Contract shall consist of the documents set forth below, which are on file with the City
Clerk and are hereby incorporated by reference. For the purposes of construing, interpreting and resolving
inconsistencies between and among the provisions of this Contract, these documents and the provisions thereof
are set forth in the following descending order of precedence.
This Contract.
Notice Inviting Formal Bids.
Project Specifications.
Drawings.
Change Orders.
Bid.
Supplementary Conditions.
General Conditions. .
Standard Drawings and Specifications (1992).
Certificate of Insurance, Performance Bond, Labor & Materials (Payment) Bond.
Affirmative Action Guidelines and Compliance Report.
Other Specifications, or part thereof, not expressly incorporated in the Contract Specifications or the
Standard Drawings and Specifications (1992).
Any other document not expressly mentioned herein which is issued by City or entered into by the parties.
4.Compensation. In consideration of Contractor’s performance of its obligations hereunder, City shall pay to
Contractor the amount set forth in Contractor’s Bid in accordance with the provisions of this Contract and upon
CITY OF PALO ALTO: FORMAL CONTRACT {107292)PAGE 1 OF 8
FORMAL CONTRACT SECTION 500
the receipt of written invoices and all necessary supporting documentation within the time set forth in the Contract
Specifications and the Standard Drawings and Specifications (1992), or, if no time is stated, within thirty (30) Days
of the date of receipt of Contractor’s invoices.
Insurance. On or before the Date of Execution, Contractor shall obtain and maintain the policies of insurance
coverage described in the Notice Inviting Formal Bids on terms and conditions and in amounts as may be required
by the Risk Manager. City shall not be obligated to take out insurance on Contractor’s personal property or the
personal property of any person performing labor or services or supplying materials or equipment under the
project. Contractor shall furnish City with the certificates of insurance and with original endorsements affecting
coverage required under this Contract on or before the Date of Execution. The certificates and endorsements for
each insurance policy shall be signed by a person who is authorized by that insurer to bind coverage in its be half.
Proof of insurance shall be mailed to the Project Manager to the address set forth in Section 15 of this Contract.
Indemnification. Contractor agrees to protect, defend, indemnify and hold City, its Council members, officers,
employees, agents and representatives harmless from and against any and all claims, demands, liabilities, losses,
damages, costs, expenses, liens, penalties, suits, or judgments, arising, in whole or in part, directly or indirectly,
at any time from any injury to or death’ of persons or damage to property as a result of the willful acts or the
negligent acts or omissions of Contractor, or which results from Contractor’s noncompliance with any Law
respecting the condition, use, occupation or safety of the Project site, or any part thereof, or which arises from
Contractor’s failure to do anything required under this Contract or for doing anything which Contractor is required
not to do under this Contract, or which arises from conduct for which any Law may impose strict liability on
Contractor in the performance of or failure to perform the provisions of this Contract, except as may arise from
the sole willful acts or negligent acts or omissions of City or any of its Council members, officers, employees,
agents or representatives. This indemnification shall extend to any and all claims, demands, or liens made or filed
by reason of any work performed by Contractor under this Contract at any time during the term of this Contract,
or arising thereafter.
To the extent Contractor will use hazardous materials in connection with the execution of its obligations under this
Contract, Contractor further expressly agrees to protect, indemnify, hold harmless and defend City, its City Council
members, officers and employees from and against any and all claims, demands, liabilities, losses, damages,
costs, expenses, liens, penalties, suits, or judgments City may incur, arising, in whole or in part, in connection with
or as a result of Contractor’s willful acts or negligent acts or omissions under this Contract, under the ¯
Comprehensive Environmental Response, Compensation and Liability Act (42 U.S.C. §§9601-6975, as amended);
the Resource Conservation and Recovery Act (42 U.S.C. §§6901-6992k, as amended); the Toxic Substances
Control Act (15 U.S.C. §§2601-2692, as amended); the Carpenter-Presley-Tanner Hazardous Substance Account
Act (Health & Safety Code, §§25300-25395, as amended); the Hazardous Waste Control Law (Health & Safety
Code, §§25100-25250.25, as amended); the Safe Drinking Water and Toxic Enforcement Act (Health & Safety
Code, §§25249.5-25249.13, as amended); the Underground Storage of Hazardous Substances Act (Health &
Safety (;ode, §§25280-25299.7, as amended); or under any other local, state or federal law, statute or ordinance,
or at common law.
Assumption of Risk. Contractor agrees to voluntarily assume any and all risk of loss, damage, or injury to the
property of Contractor which may occur in, on, or about the Project site at any time and in any manner, excepting
such loss, injury, or damage as may be caused by the sole willful act or negligent act or omission of City or any
of its Council members, officers, employees, agents or representatives.
8.Waiver. The acceptance of any payment or performance, or any part thereof, shall not operate as a waiver by
City of its rights under this Contract. A waiver by City of any breach of any part or provision of this Contract by
Contractor shall not operate as a waiver or continuing waiver of any subsequent breach of the same or any other
CITY OF PALO ALTO: FORMAL CONTRACT (107292)PAGE 2 OF 8
FORMAL CONTRACT SECTION 500
provision, nor shall any custom or practice which may arise between the parties in the administration of any part
or provision of this Contract be construed to waive or to lessen the right of City to insist upon the performance of
Contractor in strict compliance with the covenants, terms and conditions of this Contract.
Compliance with Laws. Contractor shall comply with all Laws now in force or which may hereafter be in force
pertaining to the Project and Work and this Contract, with the requirement
of any bond or fire underwriters or other similar body now or hereafter constituted, with anydiscretionary license
or permit issued pursuant to any Law of any public agency or official as well as with any provision of all recorded
documents affecting the Project site, insofar as any are required by reason of the use or occupancy of the Project
site, and with all Laws pertaining to nondiscrimination and affirmative action in employment and hazardous
materials.
10.Bonds. As a condition precedent to City’s obligation to pay compensation to Contractor, and on or before the Date
of Execution, Contractor shall furnish to the Project Manager the Bonds as required under the Notice Inviting.
Formal Bids.
11.Representations and Warranties. In the supply of any materials and equipment and the rendering of labor and
services during the course and scope of the Project and Work, Contractor represents and warrants:
Any materials and equipment which shall be used during the course and scope of the Project and Work
shall be vested in Contractor;
Any materials and equipment which shall be used during the course and scope of the Project and Work
shall be merchantable and fit to be used for the particular purpose for which the materials are required;
Any labor and services rendered and materials and equipment used or employed during the course and
scope of the Project and Work shall be free of defects in workmanship for a period of one (1) year after
the recordation of the Notice of Substantial Completion, or, if no such notice is required to be file d, on the
date that final payment is made hereunder;
Any manufacturer’s warranty obtained by Contractor shall be obtained or shall be deemed obtained by
Contractor for and in behalf of City.
Any information submitted by Contractor prior to the award of Contract, or thereafter, upon request,
whether or not submitted under a continuing obligation by the terms of the Contract to do so, is true and
correct at the time such information is submitted or made available to the City;
Contractor has not colluded, conspired, or agreed, directly or indirectly, with any person in regard to the
terms and conditions of Contractor’s Bid, except as may be permitted by the Notice Inviting Formal Bids;
Contractor has the power and authority to enter into this Contract with City, that the individual executing
this Contract is duly authorized to do so by appropriate resolution, and that this Contract shall be
executed, delivered and performed pursuant to the power and authority conferred upon the person or
persons authorized to bind Contractor;
Contractor has not made an attempt to exert undue influence with the Purchasing Manager or Project
Manager or any other person who has directly contributed to City’s decision to award the contract to
Contractor;
CITY OF PALO ALTO: FORMAL CONTRACT (107292)PAGE 3 OF 8
FORMAL CONTRACT SECTION 50O
There are no unresolved claims or disputes between Contractor and City which would materially affect
Contractor’s ability to perform under the Contract;
Contractor has furnished and will furnish true and accurate statements, records, reports, resolutions,
certifications, and other written information as may be requested of Contractor by City from time to time
during the term of this Contract;
ko Contractor and any person performing labor and services under this Project are duly licensed by the State
of California as required by California Business & Professions Code Section 7028, as amended; and
Contractor has fully examined and inspected the Project site and has full knowledge of the physical
conditions of the Project site,
12.Assignment. This Contract and the performance required hereunder is personal to Contractor, and it shall not be
assigned by Contractor. Any attempted assignment shall be null and void.
13.Claims of Contractor. All claims pertaining to extra work, additional charges, or delays within the Contract Time
or other disputes arising out of the Contract shall be submitted by Contractor to City in writing by certified or
registered mail within ten (10) Days after the claim arose or within such other time as may be permitted or required
by law, and shall be described in sufficient detail to give adequate notice of the substance of the claim to City.
14.Audits by City. During the term of this Contract and for a period of not less than three (3) years after the expiration
or earlier termination of this Contract, City shall have the right to audit Contractor’s Project-related and
Work-related writings and business records, as such terms are defined in California Evidence Code Sections 250
and 1271, as amended, during the regular business hours of Contractor, or, if Contractor has no such hours,
during the regular business hours of City.
15.Notices. All invoices, agreements, appointments, approvals, authorizations, claims, demands, Change Orders,
consents, designations, notices, offers, requests and statements given by either party to the other shall be in
writing and shall be sufficiently given and served upon the other party if (1) personally served, (2) sent by the
United States mail, postage prepaid, (3) sent by private express delivery service, or (4) in the case of a facsimile
transmission, if sent to the telephone FAX number set forth below during regular business hours of the receiving
party and followed within two (2) Days by delivery of a hard copy of the material sent by facsimile transmission,
in accordance with (1), (2) or (3) above. Personal service shall include, without limitation, service by delivery and
service by facsimile transmission.
To City:City of Palo Alto
City Clerk
250 Hamilton Avenue
P.O. Box 10250
Palo Alto, CA 94303
CITY OF PALO ALTO: FORMAL CONTRACT (107292)PAGE 4 OF 8
FORMAL CONTRACT
Copy to:City of Palo Alto
ATT.: Bill Shaddle, Project Manager
Public Works Department, Facilities Management Division
3201 East Bayshore Road
Palo Alto, CA 94301
To Contractor:Andy’s Roofing Company, Inc.
140 S. Whisman Road
Mountain View, CA 94041
SECTION 500
PHONE:(650), 967-2789
FAX: (650) 967-2741
16.
ATT.: THERESE ENGQUIST
Appropriation of City Funds. This Contract is sul~ject to the fiscal provisions of Article III, Section 12 of the Charter
of the City of Palo Alto. Any charges hereunder for labor, services, materials and equipment may accrue only
after such expenditures have been approved in advance in writing in accordance with applicable Laws. This
Contract shall terminate without penalty (I) at the end of any fiscal year in the event that funds are not appropriated
for the following fiscal year, or (ii) at any time within a fiscal y ear in the event that funds are only appropriated for
a portion of the fiscal year and funds for this Contract are no longer available. This Section 16 s hall control in the
event of a conflict with any other provision of this Contract.
17.Miscellaneous.
Bailee Disclaimer. The parties understand and agree that City does not purport to be Contractor’s bailee,
and City is, therefore, not responsible for any damage to the personal property of Contractor.
Consent. Whenever in this Contract the approval or consent of a party is required, such approval or
consent shall be in writing and shall be executed by a person having the express authority to grant such
approval or consent.
Controlling Law.’ The parties agree that this Contract shall be governed and construed by and in
accordance with the Laws of the State of California.
Definitions. The definitions and terms set forth in Section 1 of the Standard Drawings and SpecificatiOns
(1992) of this Contract are incorporated herein by reference.
Force Majeure. Neither party shall be deemed to be in default on account of any delay or failure to
perform its obligations under this Contract which directly results from an Act of God or an act of a superior
governmental authority.
Headings. The paragraph headings are not a part of this Contract and shall have no effect upon the
construction or interpretation of any part of this Contract.
CITY OF PALO ALTO: FORMAL CONTRACT {107292)PAGE 5 OF 8
FORMAL CONTRACT SECTION 500
Incorporation of Documents. All documents constituting the Contract documents described in Section
3 hereof and all documents which may, from time to time, be referred to in any duly executed amendment
hereto are by such reference incorporated in this Contract and shall be deemed to be part of this Contract.
Integration. This Contract and any amendments hereto between the parties constitute the entire
agreement between the parties concerning the Project and Work, and there are no other prior oral or
written agreements between the parties that are not incorporated in this Contract.
Modification of Agreement. This Contract shall not be modified or be binding upon the parties, unless
such modification is agreed to in writing and signed by the parties.
Provision. Any agreement, covenant, condition, clause, qualification, restriction, reservation, term or
other stipulation .in the Contract shall define or otherwise control, establish, or limit the performance
required or permitted or to be required of or permitted by either party. All provisions, whether covenants
or conditions, shall be deemed to be both covenants and conditions.
Resolution. Contractor shall submit with its Bid a copy of any corporate or partnership resolution or ot her
writing, which authorizes any director, officer or other employee or partner to act for or in behalf of
Contractor or which authorizes Contractor to enter into this Contract.
Severability. If a court of competent jurisdiction finds or rules that any provision of this Contract is void
or unenforceable, the provisions of this Contract not so affected shall remain in full force and effect.
Status of Contractor. In the exercise of rights and obligations under this Contract, Contractor acts as an
independent contractor and not as an agent or employee of City. Contractor shall not be entitled to any
rights and benefits accorded or accruing to the.City Council members, officers or employees of City, and
Contractor expressly waives any and all claims to such rights and benefits.
Successors and Assigns. The provisions of this Contract shall inure to the benefit of, and shall apply to
and bind, the successors and assigns of the parties.
Time of the Essence. Time is of the essence of this Contract and each of its provisions. In the calculation
of time hereunder, the time in which an act is to be performed shall be computed by excluding the first
Day and including the last. If the time in which an act is to be performed falls on a Saturday, Sunday, or
any Day observed as a legal holiday by City, the time for performance shall be extended to the following
Business Day.
Venue. In the event that suit is brought by either party hereunder, the parties agree that trial of such
action shall be vested exclusively in the state courts of California in the County of Santa Clara in the City
of San Jose or in the United States District Court for the Northern District of California in the City of San
Jose.
Recovery of costs. The prevailing party in any action brought to enforce the terms of this Contract or
arising out of this Contract may recover its reasonable costs, including reasonable attorney’s fees,
incurred or expended in connection with such action against the non-prevailing party.
CITY OF PALO ALTO: FORMAL CONTRA’CT ~07292) ....PAGE 6 OF 8
FORMAL CONTRACT
IN WITNESS WHEREOF, the parties have by their duly appointed representatives executed this Contract
in the city of Palo Alto, county of Santa Clara, State of California on the date first stated above.
A]-I’EST:
SECTION 500
City Clerk
CITY OF PALO ALTO
By:
Its Mayor
CONTRACTOR:
By:
Name:
Title:
Taxpayer I.D. No.
APPROVED:
Assistant City Manager
Director of Public Works
Director of Administrative Services
Insurance Review
APPROVED AS TO FORM:
Senior Assistant City Attorney
’CITY OF PALO ALTO: FORMAL coNTRACT (107292)"’PAGE 7 OF 8
FORMAL CONTRACT SECTION 500
CERTIFICATE QF ACKNOWLEDGMENT
(Civil Code § 1189)
STATE OF )
COUNTY OF )
On , before me,
for said County, personally appeared
, a notary public in and
personally known to me (or proved to me on the basis of satisfactory evidence) to be the person(s) whose
name(s) is/are subscribed to the within instrument and acknowledged to me that he/she/they executed
the same in his/her/their authorized capacity(ies), and that by his/her/their signature(s) on the instrument
the person(s), or the entity upon behalf of which the person(s) acted, executed the instrument.
WITNESS my hand and official seal.
Signature (Seal)
END OF SECTION
CITY OF PALO ALTO: FORMAL CONTRACT (107292) .......PAGE 8 OF 8