HomeMy WebLinkAbout1998-03-17 City Council (6)City of Palo Alto City Manager’s Report TO:HONOI~BLE CITY COUNCIL ATTENTION: FROM: FINANCE COMMITTEE CITY MANAGER DEPARTMENT: ADMINISTRATIVE SERVICES DATE:MARCH 17, 1998 CMR:168:98 SUBJECT:1997-98 MIDYEAR PROGRESS REPORT ON KEY PLANS AND IMPACT MEASURES REOUEST Periodic performance reporting to the Council by City departments is an integral part of Mission Driven Budgeting (MDB). The status of key plans and impact measures is reported to Council at midyear and at the close of the fiscal year. City departments have submitted reports on the status of their key plans and impact measures for the first six months of 1997-98. Progress is reported for all key plans. Impact measures are only reported on an exception basis. Exceptions consist of: a variance of 20 percent in the projected year end result for an impact measure; or a variance of 20 percent based on the first six months of the fiscal year. In addition, an impact measure would be reported if there is significant information about which the Council should be informed. The majority of the key plans for 1997-98 are under way or are expected to be accomplished in 1997-98. Some key plans have experienced delays due to a shift in departmental priorities. Reprioritization is often required as a result of Council actions. City staff has been doing a comprehensive quality control evaluation of impact measures and, in the 1998-99 Proposed Budget, will include some changes to impact measures to try and improve clarity and provide more meaningful information. CMR:168:98 Page 1 of 2 PREPARED BY: Robin Spencer, Staff Accountant ’ APPROVED BY: CITY MANAGER APPROVAL: CC:n/a Melis~a Cavallo Acting Director Administrative Services CMR:168:98 Page 2 of 2 Status report from the City Attorney’s office not received. FUNCTIONAL AREA: INTERNAL AUDITS AND REVIEWS KEY PLANS 1. Utilize the Internet to more fully describe audit services provided. 2. Work with departments in developing control assessment programs. 3. Coordinate a peer review of the City Auditor’s Office. PROGRESS 1. Currently examining other, web sites for government audit functions for reference in how to design the appearance and content of our web page. 2. Completed a control assessment questionnaire for the City’s record management program. 3. In progress. Completion date uncertain. 4. Issue a report to Council reflecting the status of all audit recommendations. The City Manager will complete the current status section of this report. 4. Completed, pending receipt of City Manager’s response. 5. Utilize programs and activities described in the City’s Mission Driven Budget in completing a risk assessment model to be used as a tool for identifying potential areas for audit. 5. Completed, pending receipt of information regarding financial results. Major Activity: Annual External Audit IMPACT MEASURES 1.To complete 100 percent of the audit assignments as reflected on the Audit Plan. 1996-97 ACTUALS 100% 1997-98 SIX 1997-98 1997-98 MONTH ESTIMATED ADOPTED ACTUALS ACTUALS 100%n/a 80% 1. Continuation of vacancies prevented us from achieving this goal. FUNCTIONAL AREA:.PROFESSIONAL ASSISTANCE AND SERVICES KEY PLANS 1. Develop and issue a Request for Proposal (RFP) for external audit services. PROGRESS 1. In progress. Draft RFP has been completed and will be issued to prospective firms on Feb .ruary 23, 1998. Major Activity: Annual External Audit IMPACT MEASURES 2. Perform a post audit survey of Cit~ /management and staff to evaluat~ /performance of audit firm. 1997-98 SIX 1997-98 1996-97 1997-98 MONTH ESTIMATED ACTUALS ADOPTED ACTUALS ACTUALS 0 Yes n/a 2. Not applicable: this will be goingout to bid. City management and staff will be part of the selection team. 4 FUNCTIONAL AREA: PUBL~ ~,; INFORMATION KEY PLANS 1. Develop a contingency plan for local cable programming. PROGRESS 1. Fifty percent complete. 2. Display the results of the November 4, 1997,, General Municipal Election on television and via the Internet. 2. Complete. Major Activity: Public Outreach IMPACT MEASURES 4, Cablecast a minimum of 12 hours o~n/a new programming per month on th~ cable government channel. (revised) [ 1997-98 SIX 1997-98 1996-97 1997-98 MONTH ESTIMATED ACTUALS ADOPTED ACTUALS ACTUALS 12 19.5 4. Informational/promotional videos from the U.S.G.S., the Utilities Department, and the Missing Children’s organization resulted in higher new programming hours. FUNCTIONAL AREA: COUNCIL SUPPORT SERVICES’ Major Activity: Board/Commission Recruitment IMPACT MEASURES 1997-98 SIX 1997-98 1996-97 1997-98 MONTH ESTIMATED ACTUALS ADOPTED ACTUALS ACTUALS Ensure vacancies on a Board/Commission have at least 2 applicants. (Revised) Increase the total number of Boards and Commissions applicants by 10 (revised from 15) percent. 2 17% -2 10 4.5 0% 5 10% 5 1. Advertising and recruiting efforts have resulted in increased interest from the community to apply for boards and commissions. 2. The majority of recruitments will occur during the 2nd half of the fiscal year. Major Activity: Council Events IMPACT MEASURES Coordinate 5 Council events per year, e.g., annual Council reorganization, annual meeting with legislators, sistei city functions, retreats, State of the City, and Town Hall meetings. 1997-98 SlX 1997-98 1996-97 1997-98 MONTH ESTIMATED ACTUALS ADOPTED ACTUALS ACTUALS 5 0 1. These activities will occur during the 2nd half of the fiscal year. Major Activity: Council Committee Meetings/Minutes IMPACT MEASURES 1996-97 1997-98 ACTUALS , ADOPTED Transcribe Council Standing Committee minutes within 10 days of the meeting. (new) Finalize Council minutes in 8 Weeks ot the meeting. (revised) n/a 10 8 1997-98 SiX 1997-98 MONTH ESTIMATED ACTUALS ACTUALS 15 5.8 10 ~8 1. Due to additional Council meetings in the P’ quarter, the contract secretary transcribed Council meeting minutes which impacted the turnaround time. 2. A reallocation of staff and contract secretary transcr.iption resulted in a faster turnaround time for Council meeting minutes. 6 FUNCTIONAL AREA: ELECTIONS/CONFLICT OF INTEREST KEY PLANS PROGRESS 1. Conduct the November 4, 1997, General Municipal Election. 1. Complete. The General Municipal and Special Elections of November 4, 1997, were held. Five four-year seats and one two- year seat were filled and an initiative and Council measure were voted upon. 2. Implement and monitor changes to Conflict of Interest/Campaign Disclosure as a result of Proposition 208, including, but not limited to, monitoring the period in which campaign funds may be received. 2. Complete. Currently, Proposition 208 has been suspended, with respect to implementation. Major Activity: Conflict of Interest Code IMPACT MEASURES 1.Ensure that 95 percent of the economic interest filings by designated employees, including elected an~ appointed officials, be filed by the official deadlines. 1997-98 SIX 1997-98 1996-97 1997-98 MONTH ESTIMATED ACTUALS ADOPTED ACTUALS ACTUALS 95%95%5O%85% 1. The high percentage of staff turnover and difficulty in obtaining Leaving Office Statements from existing employees resulted in a large number oflate filings. Major Activity: Elections IMPACT MEASURES 3. Increase the number of absentee voter~ by 1 percent at all municipal elections.I 1996-97 1997-98 ACTUALS ADOPTED n/a 1% 1997-98 SIX 1997-98 MONTH ESTIMATED ACTUALS ACTUALS I 7 3. Absentee ballot applications were made available to every resident through the Palo Alto Weekly. Council candidates, opponents, and proponents of measures were encouraged to participate in the absentee ballot process, thus increasing over expectations. FUNCTIONAL AREA: LEGISLATIVE RECORDS MANAGEMENT KEY PLANS 1. Test the Records and Information Management (RIM) Program Disaster Recovery Plan. This will require significant participation by Department Records Coordinators whose records are stored in the Records Center. Due to the potential impact to City departments, this project may be done in stages. PROGRESS 1. Delayed due to unanticipated priority changes by other departments. 2. Where necessary, reclassify all records in the City Clerk’s system filed and indexed as miscellaneous documents. 2.Thirty-five percent complete. Completion expected in second half of fiscal year. 3. Review the retention 1995. schedules approved in 3. Twenty-five percent completed.. Anticipated completion in second half of fiscal year and is dependent upon participation of other depa~ments. Major Activity: Citywide Records Management IMPACT MEASURES 1. Ensure request for access to the Record~ Center be filled by 5 p.m. the followin~ business day. (new) | 1997-98 SIX 1997-98 1996-97 1997-98 MONTH ESTIMATED ACTUALS ADOPTED ACTUALS ACTUALS n/a 16 hours 1 3 1. Average time to f!ll request for accessing records in the Records Center has been 1 hour. Staff strives to be responsive and customer service oriented Major Activity: Clerk Record Management IMPACT MEASURES 3. Provide for an internal assessment to determine whether accurat~ classification and .indexing method., have been applied to 10 percent of th~ records that were filed in the Cit~ Clerk’s Office prior to January 1995. (new) 1997-98 SIX 1997-98 ,1996-97 1997-98 ~MONTH ESTIMATED ACTUALS ADOPTED ACTUALS ACTUALS n]a 10%5%10% 3. A change in procedure io quality check incoming contracts shifted the time allocated for this measure. Major Activity: Palo Alto Municipal Code IMPACT MEASURES 1997-98 SIX 1997-98 1996-97 1997-98 MONTH ESTIMATED ACTUALS ADOPTED ACTUALS ACTUALS 1.Transmit newly adopted ordinances electronically to publisher for codification within two business days after receipt of ordinance from the City Attorney. (new) 2 1.. Ability to transmit ordinances electronically has enabled staff to do this in one day. 2 9 FUNCTIONAL AREA: CITY MANAGEMENT KEY PLANS 1. Continue the implementation of the changes approved in the citywide Organizational Review. PROGRESS 1. Staff continues to implement recom- mendations. 2. Manage Utility Department implementation of the selected telecommunications strategy . and strategies to respond to deregulation. 3. Develop, a plan for implementing the recommendations contained in the Utilities organizational review. 2. Council adopted the Telecommunication Policy in November 1997, 3. Implementation plan has been developed and the progress reported to the City Council. Major Activity: Interdepartmental Coordination IMPACT MEASURES 1996-1997 ACTUALS 1997-1998 SIX 1997-1998 1997-1998 MONTH ESTIMATED ADOPTED ACTUALS ACTUALS Assure that City departments have access to current relevant Policy and Procedures Manual and other citywide procedural guidelines as needed, but no less frequently than twice a year. 2 2 2 4 3. The Policy and Procedures Manual has been updated to the City wide network, As policies change they are updated immediately. 10 FUNCTIONAL AREA: CITY COUNCIL RELATIONS KEY PLANS 1. Oversee programs throughout the City organization to assure successful progress on the Council’s three priorities for 1997-98: the Infrastructure Plan, Traffic Management and Safety, and Revitalization of Neighborhood Business Districts. 2. Following adoption of the Comprehensive Plan, implement a strategy for assuring that the Plan’s goals, policies and programs are instilled into the entire City organization. PROGRESS 1. Regarding Traffic Management and Safety, a speed survey has been conducted and its findings will be presented to the Council in the Spring of 1998. Other efforts to manage traffic, such as motorcycle traffic enforcement and neighborhood traffic officers and speed watch programs, have continued. Regarding the Revitalization of Neighborhood Business Districts, a Longs Drug Store has been approved in the Midtown neighborhood and other development projects ~e being reviewed. 2. The Comprehensive Plan is scheduled for final adoption in the Fall of 1998. Major Activity: Council & City Manager Interaction IMPACT MEASURES ]1. Respond to Council Member calls an.1 inquiries within 8 hours. (revised). 1996-1997 ACTUALS 1997-1998 SIX 1997-1998 1997-1998 MONTH ESTIMATED ADOPTED ACTUALS ACTUALS n/a 8 1. It has been possible to make at least an initial response to the majority of Council calls immediately, thus reducing the average response time. 11 Major Activity: Council Agendas and Meetings IMPACT MEASURES 1996-1997 ACTUALS 1997-1998 ADOPTED Develop City Council agendas that result in an average meeting time of four hours (revised) 4 1997-1998 SIX MONTH ACTUALS 1997-1998 ESTIMATED ACTUALS 1. Through careful meeting scheduling, average Council meeting duration has been lower than target. FUNCTIONAL AREA: COMMUNITY/INTERGOV. RELATIONS KEY PLANS 1. Continue to work with the school district to identify opportunities, such as the Building for Excellence program, where cooperation could result in more efficient or effective, provision of services. PROGRESS 1. A Citywide School Commute Safety Study was developed and will be brought to the Council in April 1998 after community input is obtained. 2. Coordinate the successful introduction and enactment of one item of legislation of specific importance to Palo Alto. 2. Staff worked with Senator Byron Sher to introduce SB682 to provide 60 days notice to tenants facing a rent increase. Unfor- tunately, this legislation was vetoed by the Governor in October 1997. Major Activity: Public Relations IMPACT MEASURES 1.Provide information to the media or~ City programs and activities on monthly basis." 1997-1998 SIX 1997-1998 1996-1997 1997-1998 MONTH ESTIMATED ACTUALS ADOPTED ACTUALS ACTUALS 16 12 27 4O 1. Implementation of the City Manager’s Office Public Information function has encouraged an increase in press releases. 12 FUNCTIONAL AREA: ECONOMIC RESOURCES KEY PLANS 1. Act as a liaison to the Midtown residents on theMidtown revitalization process: PROGRESS 1. As part of the Comprehensive Plan review process, staff informed the Council that proactive efforts by staff in this area would be discontinued. 2. Conduct six meetings for commercial property owners, tenants, and other interested parties to identify individual needs, retail gaps, and impediments to economic health. 2. Due to staffing vacancies, no progress has been made on this key plan. It is not anticipated that staffing will be in place until fiscal year 1998-99. 3. Work with the Plarming Department to develop a plan for assessing commercial redevelopment options for south E1 Camino. 3. Due to staffing vacancies, no progress has been made on this key plan. ¯4. Support as appropriate the Planning Department’s area wide planning processes. 4. Due to staffing vacancies, limited progress has been made on this key plan. Major Activity: Process Facilitation IMPACT MEASURES 1996-1997 ACTUALS 1997-1998 SIX 1997-1998 1997-1998 MONTH ESTIMATED ADOPTED ACTUALS ACTUALS 1.Respond to all business with questions concerning City processes, and provide guidance for not less than 20 new/existing businesses .requiring in- depth assistance with City processes. (revised) 21 20 n/a n/a 1. Staff vacancy prevented achievement of this impact measure. 13 FUNCTIONAL AREA: FINANCIAL SUPPORT SERVICES KEY PLANS 1. Pursue implementation of Automatic Payment System (APS) for customer direct transfer of payments for utilities and other City services. PROGRESS 1. Delayed until the Utilities Customer Information System is implemented. 2. Solicit and select a vendor to automate timekeeping tO support time tracking under Mission Driven Budgeting (MDB). 3. Automate the preparation of the Comprehensive Annual Financial Report. 4. Evaluate the availability and applicability of new Window based IFAS modules and modify the City’s financial system to improve its user friendliness. 2. Delayed until technical infrastructure is upgraded to support client-server technology. 3. Partial automation completed in 1997. Full automation on hold pending reporting changes proposed by the Government Accounting Standards Board. 4. Modification of purchasing ’module underway and evaluation of Windows based IFAS modules in progress. 5. Participate in the evaluation and development of specifications for a job’costing system for the City’s utilities. 5. Specifications under development. 6. Consolidate the purchasing section at a single location to facilitate communication anal improve effectiveness within the group. 7. Review, identify and begin imPlementation of recommendations of the Steering Committee for the Purchasing Process that will provide more efficient and effective processing of customer requests, and more control and accountability in the procurement process. 6. Interim solution completed in 1997. Consolidation plan pending completion of Citywide space needs study. 7. In process, expect completion by December 1998. 14 KEY PLANS 8. Continue the training of contracting and customer staff in the re-engineered purchasing process and procedures completed in 1996-97. PROGRESS 8. Developing the curriculum for the new training process. Major Activity: Accounting Services IMPACT MEASURES Achieve an average satisfaction rating of 80 percent or higher using an annual internal accounts payable customer satisfaction survey.(revised) 1996-97 ACTUALS 1997-98 SIX 1997-98 1997-98 MONTH ESTIMATED ADOPTED ACTUALS ACTUALS n/a 80%n/a 80% 3. This activity occurs during the second half of the fiscal year. Major Activity: Purchasing and Contract Administration IMPACT MEASURES 1996-97 ACTUALS 1997-98 ADOPTED 1997-98 SIX MONTH ACTUALS o Save 5 percent of the division’s annual purchase volume through effective purchasing techniques. Increase inventory turns to 3 per year to minimize cash held in inventory. 1%5%1% 1997-98 ESTIMATED ACTUALS 2% 2 1. Completion of this impact measure was" dependent upon staffing vacant contract m~tnager positions. Vacant positions f!lled in September 1997. 3. A plan to dispose of non-moving stock is being developed 15 FUNCTIONAL AREA: PROPERTY MANAGEMENT KEY PLANS 1. Establish and manage contract with tenant for "White and Bright" program at the Webster/Cowper garage. 2. Assist leaseholders of Williams property in obtaining necessary City approvals and County grant funds to meet required conditions of leases. 3. Facilitate renovation of the University Avenue Train Depot. 4. Develop a waiting list for the art studio space at the Cubberley Community Center. PROGRESS 1. Completed. Contract has been established and new lighting has been installed. 2. Williams property leaseholders have received all required approvals, and project is under construction. Documentation required to obtain the $40,000 in grant funds has been submitted and approved by County, and check for the funds is forthcoming.. 3. Renovations are underway; interim !andscaping, tunnel cleaning/painting and directional signs have been installed. -Depot to be painted in latter part of this fiscal year. 4. Completed. The waiting list has been developed and is being maintained. FUNCTIONAL AREA: MONEY MANAGEMENT KEY PLANS PROGRESS 1. Obtain debt financing for Golf Course improvements. If debt is appropriate,, obtain debt financing for development of the former Los Altos Treatment plant site. 1. The Golf Course project is on schedule, and the debt issuance is planned in the second half of the fiscal year. No decision has been made by the City on acquiring the former Los Altos treatment plant site, and so it is not clear ¯ yet if financing will be needed. 16 KEY PLANS 2. Acquire consulting, services to facilitate financing efforts for downtown parking structure(s); and to guide the City through new assessment _ district requirements under Proposition 218. PROGRESS 2. Acquired a financial advisor to assist with financing issues, including financing the proposed downtown parking structure. 3. Assist in the implementation of charitable giving program for utilities customers. 4. Complete the implementation of the new cash receipting system, and begin implementing a new collection management system. 3. The utilities customer charitable giving program (ProjectPledge) is complete. 4. Implementation of the cash receipting project is scheduled to begin in February 1998. Implementation of the collections management system will take place after the cash receipting system is operational. Major Activity: General Billing and Collections IMPACT MEASURES 4.Collect at least 90% of outstandin~ accounts for false alarms receivable. | 1997-98 SIX 1999-97 1997-98 MONTH ACTUALS ADOPTED ACTUALS 100%90%64% 1997-98 ESTIMATED ACTUALS 90% 4. Second quarter billings were much higher than in previous quarters. Most invoices were issued towards the end of the quarter therefore, collection activity will not begin until January 1998. Staff expects that the yearly total will still meet the target of 90%. 17 FUNCTIONAL AREA: FINANCIAL PLANNING, ANALYSIS, AND REPORTS KEY PLANS 1. Support the implementation of the Utilities Organizational Review. PROGRESS 1. Assisted with the implementation during the 1997-98 budget process. 2. Facilitate the delivery and write financial sections of the Infrastructure Management reports for Council review. 3. Automate the process for collecting key plans and impact measures. Review and recommend improvements to existing departmental impact measures. 2. Modules II (Traffic and Transportation) and III (Parks and Open Space) were presented for review to the Finance Committee in July and October 1997, respectively. The proposed prioritization and financial options are expected to be presented in the spring of 1998. 3. The City’s current budget document publishing vendor will have a product to automate the collection of key plans and impact measures for review late in 1997- 98. After obtaining feedback from Council and reviewing the current departmental impact measures, staff decided to hire a consultant during 1998- 99 to assist in the process of improving and setting benchmarks for impact measures. Major Activity: Consulting and Special Studies IMPACT MEASURES 1.Identify a minimum of $100,000 i~ potential savings-through analytica~ projects and special studies.. | 1997-98 1996-97 1997-98 ESTIMATED ACTUALS ADOPTED ACTUALS $50,000 $100,000 1997-98 SIX MONTH ACTUALS $100,000 1. Potentialsavingsareidentifiedduring the budgetprocess anaYortowardsthe endofthefiscal year. 18 FUNCTIONAL AREA: CENTRALIZED APPLICATION SUPPORT KEY PLANS 1. Expand the access to data for ad hoc inquiry and reporting through the acquisition and implementation of a user friendly report writing tool. 2. Complete the implementation of Geographic Information System counter applications, in conjunction with the Planning, Public Works, and Utilities departments. 3. Assist in the implementation of an automated timekeeping system to facilitate the entry and greatly improve the accuracy of time card data for employees. PROGRESS 1. A report writing tool, Crystal Reports, has been acquired and is being utilized in. the Information Technology Division. 2. The GIS Counter Applications have been installed at the Public Works engineering counter as a beta site.. Implementation at a number of other locations will take place following the completion of the hardware and software upgrades currently underway. 3. Due to the technical limitations, staff delayed the timekeeping acquisition and implementation until the technical infrastructure upgrade is complete. Estimated completion of the infrastructure upgrade is June 1998. A Request for Proposals will be re- issued in 1998-99. 4. Select architectural environment and. initiate the development of the required architecture to support the computer systems implementation of the Citywide Timekeeping System. 5. Acquire database management tools that help identify and assist in improving the response time of existing systems. Using these tools, provide quarterly reports on the status of the City’s databases. 4. An environment has been selected and is being implemented. The two major architectural elements are the NT Operating System and Intranet capability. 5. A Request for Proposals has been issued and four responses have been received. The review process is underway. 19 KEY PLANS 6. Work with the selected vendor to install and implement the initial portion of the Utilities Customer Information Syste.m. PROGRESS 6. A contract for the new Utilities’ CIS was approved by Council in September 1997. The baseline software has been installed and tested. Training of the Core Team is in progress.. Implementation of the project is scheduled in December 1998.. 7. Participate in the implementation of Permit Tracking System, working with Planning and other associated departments. 7. Continued to work on the evaluation of Permit Tracking Systems. Major Activity: Data Base & Application Management 1997-98 SIX 1997-98 1996-97 1997-98 MONTH ESTIMATED ACTUALS ADOPTED ACTUALS ACTUALS 2.Manage user response time by n/a ensuring that no data bases exceed 85 percent capacity. (new) 85%n/a 85% 2. Procedures have not been defined due to the inability to staff a full time- data base administrator position and the lack.of system management tools currently in the acquisition process. FUNCTIONAL AREA: CENTRAL COMPUTER SUPPORT KEY PLANS 1. Acquire production support tools that monitor and manage Central Processing Unit (CPU) utilization and disk space, and assist in problem resolution for the Hewlett Packard and NT PROGRESS ~1. A Request for Proposals has been issued and four responses have been received. The review process is underway. servers. 20 KEY PLANS 2. Upgrade the processing capability of the server used by Finance personnel, as well as citywide staff entering purchasing requisitions and accessing budget information. PROGRESS 2. A new server has been acquired and installed. Plans are being prepared for the migration of Finance and Human Resources Applications to the new server. Major Activity: Production Control IMPACT MEASURES 1.Produce and print utility invoices o~ schedule with 98 percent accuracy.[ (2500 statements each day by 9:00am) l 1997-98 SIX 1997-98 1996-97 1997-98 MONTH ESTIMATED ACTUALS ADOPTED ACTUALS ACTUALS 98%98%50%72% 1. Did not meet measure due to printer jamming caused by electricai power problems in the computer room and part malfunctions. The bill statements have been available by 11:00am each day, approximately 95% of the time. FUNCTIONAL AREA: PERSONAL COMPUTER KEY PLANS 1 .Implement a software solution that provides electronic mail, personnel calendaring, meeting and conference room scheduling and assists in routing of internal documents among City staff. PROGREss 1. Requirements are being developed by a cross functional team. 2. Implement the Internet Master Plan including developing policies and making improvements in Internet servers to make service more responsive and reliable. Home page development and updating will be contracted. 2. The Internet Master Plan is being implemented. New servers have been installed to make the Internet more reliable. The redesign and maintenance of the City’s Home Pages is underway. 21 KEY PLANS 3. Implement the personal computer portion of the Computer Replacement Fund, including determination of citywide configuration, acquisition, and installation. 4., In conjunction with the interdepartmental Computer Technical Advisory Group (CompuTAG), determine the next generation Office Productivity Suite, consisting of word processing, spreadsheet, graphics, presentation and project scheduling software tools. PROGRESS 3. Entered into a contract for the purchase of personal computers in January 1998. 4. This effort has not begun due to the time required for the NT Operating System implementation. Major Activity: New Personal Computer Project IMPACT MEASURES 1. Complete 80 percent of projec~ 1milestones according to schedule. (new~ 1996-97 1997-98 ACTUALS ADOPTED 80% 1997-98 SIX MONTH ACTUALS 1997-98 ESTIMATED ACTUALS 80% 1. This activity will occur during the second half of the fiscal year.. FUNCTIONAL AREA: TELEPHONE & DATA COMMUNICATION KEY PLANS 1. Develop a plan for funding the replacement of telephone instruments within the City. The models currently supplied areno longer manufactured or supported by the vendor. PROGRESS 1. Project is on hold pending a review of the City’s entire telephone system. 22 KEY PLANS 2. Continue the Citywide network improvements. This phase consists of network analysis hardware and software and the installation of additional personal computer servers for users to share files, printers, and software applications. PROGRESS 2. The three remaining facilities are Terman~ College Terrace and Downtown Libraries. The analysis phase is underway. 23 FUNCTIONAL AREA: ARTS AND CULTURE KEY PLANS 1. Initiate planning and seek outside funding opportunities for EC2, a program combining art and exploration for children. 2. Plan and implement Dominic di Mare, a traveling exhibition. 3.Initiate an artist-in-the-schools partnership program in the arts. 4. Complete the Arts Master Plan. 5. Implement Phase II of the Children’s Theatre Golden Anniversary project. 6. Implement Children’s Theatre Outreach Program at seven Palo Alto Unified School District schools.’ PROGRESS 1. Planning of the EC2 will proceed the second half of the fiscal year. 2. Organization of Dominic di Mare exhibition completed. 3. Four partnerships have been completed between eight schools. Five new partnerships (10 schools) will commence in February. 4. Steering committee is working with a professional research specialist to design a tool to collect important data from the Community. 5. This construction project is nearing completion. 6. Seven schools have been selected for implementation. FUNCTIONAL AREA: CUBBERLEY COMMUNITY CENTER KEY PLANS 1. Continue to promote public use of Cubberley through use of display advertisements, utility bill announcements, and brochures. PROGRESS 1. Promotional programs are ongoing, including advertising, posters, and use of the public access cable. 24 KEY PLANS 2. Continue development of landscape plans for non-landscaped and asphalt areas between building wings and begin planting. PROGRESS 2. Plans developed. for planter areas have been 3. Complete repairs to the athletic fields by filling low areas, aerating, re-seeding, and replacing sprinkler heads. 3. Repairs to the athletic fields are currently in progress, and will be completed in Spring of 1998. Major Activity: Cubberley Center Services IMPACT MEASURES Receiye an average rating of 3 or bette~1. (on a scale of 1 to 4) on Customeq Service surveys received from th~ public, tenants, and hourly users.(new)l 1996-97 ACTUALS 1997-98 SIX . 1997-98 1997-98 MONTH ESTIMATED ADOPTED ACTUALS ACTUALS laJa n/a >3 1. Customer Service Surveys are tabulated on an annual basis. Major Activity: Cubberley Maintenance IMPACT MEASURES 1.Receive an average rating of 3 or bette~ (on a scale of 1 to 4) on Custome~ Service surveys received from th~ public, tenants, and hourly users.(new)[ 1996-97 1997-98 ACTUALS ADOPTED n/a Customer Service Surveys are tabulated on an annual basis. 1997-98 MONTH ACTUALS 1997-98 ESTIMATED ACTUALS n/a >3 25 FUNCTIONAL AREA: GOLF SERVICES KEY PLANS l. Implement Golf Course Master Improvement Plan construction plan as approved by Council. At the same time, complete interim alternative " course construction, turf establishment, and maintenance for use in 1998-99. PROGRESS 1. Golf Master Plan implementation not underway due to delays in bid PaCkage issuance. Interim construction completed and the maintenance is on schedule. 2. Support Junior Golf Programs for local players, high schools, and East Palo Alto juniors. 3. In the spring of 1998, coordinate with the Public Works Department on the installation of an equipment wash facility in conjunction with the Golf Course Master Improvement Plan. 2. This activity occurs during the second half of the fiscal year. 3. Installation is proposed to start at the completion of golf course renovation work in Fall 1998.~ 4. Plan, develop, and implement golf marketing and public relations program to maximize customer service before, during, and after construction improvements. This will include promotions and special fee packages to enhance revenue flows during slow business periods. 5. Facilitate golf shop and restaurant operations during construction of improvements. 4. Marketing and public relations plan and implementation has been expedited through media advertising to defuse mis-information regarding the construction status of the golf course. Play rounds are up due to success of plans. 5. This will be coordinated with commencement of construction activities in the spring of 1998. 26 Major Activity: Business Operations IMPACT MEASURES 1.Generate revenue to exceed expense~ (including debt service and Cit~ overhead expenses) by 25 percent. | 1996-97 ACTUALS 31% 1. This activity is calculated at the end of the fiscal year. 1997-98 ADOPTED 25% 1997-98 SIX 1997-98 MONTH ESTIMATED ACTUALS ACTUALS n/a 25% FUNCTIONAL AREA: PARK SERVICES KEY PLANS 1. Design and install a new irrigation system at Rinconada Park. 2. Coordinate ajoint project between the Public Works and Community Services Departments to begin development of a conceptual master plan for Mitchell Park, which will include playground renovations, park infrastructure, and lighting improvements. 3. Design and in~tall a new irrigation system at Jordan Middle School. 4. Resurface six termis courts at Rinconada park 5. Repair pathways at Briones, Bowde.n, and Robles parks. 6. Improve field conditions and maintenance at Jordan and Walter Hayes elementary schools as part of the agreement with Palo Alto Unified School District. PROGRESS 1. Design and development. Specifications are under 2. In the process of requesting proposals from consultants to develop plans and specifications. It is expected that a contract will be awarded in 1997-98. 3. Deferred due to the P.A.U.S.D. Building for Excellence change in plans regarding redevelopment of school sites. 4. Contract has been awarded. Expect completion in Spring 1998. 5. In progress. Expect completion in Spring of 1998. 6. In progress. Expect completion in Spring of 1998. 27 KEY PLANS 7. Implement landscape improvements to Rinconada and Greer Parks, the Cultural Center, and the Main Library. PROGRESS 7. In progress. of 1998. Expect completion in Spring FUNCTIONAL AREA: HUMAN SERVICES KEY PLANS 1. Review and modify the Human Services Resource Allocation Process (HSRAP). 2. Develop additional shelter opportunities for people who are homeless in the region. 3. Administer the Homeless Work Program. 4. Produce and distribute a Tenant’s Rights and Responsibilities Handbook, and assist specific nonprofit organizations with educational outreach to tenants and landlords. PROGRESs 1. The 1998-99 modified. RFP was-reviewed and 2. Through 1998-99 HSRAP process, currently reviewing funding proposal which will provide additional shelter opportunities. 3. Completed phase two of the Homeless Workers Program; placed five workers in City positions. 4. The Department is reconsidering the feasibility of a Tenant’s Handbook being produced, either in-house or through contracting out. Working with nonprofit organizations to accomplish educational outreach. 5. Increase opportunities for the public to access human services information through the Internet. 6. Perform an annual evaluation of all Human Services Task Forces and Citizen Committees to determine whether they have met their objectives and are continuing to meet emerging community needs. 5. Completed updated information for the Human Services and Child Care web pages in October 1997. 6. Completed the annual evaluation and made recommendation to have Recreation, Open Space and Sciences Division assume staffing for the Palo Alto Youth Council. 28 KEY PLANS PROGRESS 7. Develop standards for a comprehensive assessment of the impact of proposed housing and non-residential projects on the supply of child care services in Palo Alto. 7. Currently working with the Department of Planning & Community Environment to incorporate child care into the PAMF / SOFA Coordinated Plan. Plan is still being developed. Major Activity: Human Services Contract Administration 1996-97 1997-98 IMPACT MEASURES ACTUALS ¯ADOPTED 1997-98 SiX 1997-978 MONTH ESTIMATED ACTUALS ACTUALS For 100 percent of funded agencies, conduct at least one on-site inspectior to ensure funds are spent appropriately and all contract requirements are fulfilled. lOO%100%0%100% 1. This activity is conducted during the second half of the fiscal year.. Major Activity: Community Partnership/Public Services IMPACT MEASURES 2.Staff will provide information an~ educational outreach to approximatel3~ 3,500 citizens and businesses in th~ community. (rex~ised) | 1997-98 SIX 1996-97 1997-98 MONTH ACTUALS ADOPTED ACTUALS 3,450 3,500_1. 893 1997-978 ESTIMATED ACTUALS 3,500 distribution of the Infor.mation & Referral directory. Major Activity: Child Care Services Seventy-five percent of the objective will be achieved in the second half of the fiscal year due to 1997-98 SIX 1997-978 1996-97 1997-98 MONTH ESTIMATED ACTUALS ADOPTED ACTUALS ACTUALSIMPACT MEASURES Ensure that 100 percent of City/PAUSD school age child care programs are meeting contract requirements. (new) n]a 100%0%100% 1. This activity is conducted during the second half of the fiscal year. 29 FUNCTIONAL AREA: LIBRARY SERVICES KEY PLANS 1. Finalize draft of the Library Master Plan and forward to City Council for review and adoption. Implementation of the Plan would include consideration of possible expansion at the Children’s Library in conjunction with other capital work being done there. PROGRESS 1. Draft complete and will be forwarded to City Council in late 1997-98. 2. Improve quality of book collections through identification of outdated subject areas, aggressive discarding of obsolete, worn, and unused materials, and targeted purchasing of new material to fill gaps. 2. Specific adult non-fiction in the humanities and science subject areas have been identified for discard. $5,000 in funds have been allocated for expenditure by June 1998. 3. Prepare. a revised Library Automation Plan. 3. Draft RFP completed to hire library automation consultant in preparation of plan. Major Activity: Library Outreach IMPACT MEASURES I2 .Through enrichment activities,reac1 20,000 children .annually. 1996-97 ACTUALS 30,424 I 1997-98 SIX 1997-98 MONTH ADOPTED ACTUALS 20,000 13,042 1997-98 ESTIMATED ACTUALS 2. The rise in attendance reflects population growth in this age group. Major Activity: Circulation IMPACT MEASURES 3.Rank fifth or better in California publiq libraries in similarly sized communitie~ in terms of per capita circulation rate.[ (new) | 1997-98 SIX 1997-98 1996-97 1997-98 MONTH ¯ ESTIMATED ACTUALS ADOPTED ACTUALS ACTUALS n/a 5 n/a 5 3. California State Library Statistical report is typically issued in February of each year. lt provides documentation for the measure. 30 FUNCTIONAL AREA: OPEN SPACE AND SCIENCES SERVICES KEYPLANS 1. Implement habitat restoration, removal of non-native vegetation, and trail repair and maintenance ~ictivities, as outlined in the Arastradero Preserve Management Plan. 2. With community involvement, begin the process for the design of a modest new facility on the Arastradero Preserve. 3. Expand on the pilot program to provide facilitators for the Junior Museum’s Exhibit Hall. PROGRESS 1. Restoration of the house and barn.site, planting of mature ’native oaks and acorn seeds on ten acres of property, preliminary design of a permanent trail system, and removal of non-native vegetation have been completed. 2. A design team has been contracted to facilitate task force meetings and public workshops to prepare a preliminary design. 3. Five new facilitators havebeen recruited and trained. 4. Expand interpretive program offerings at Lucy Evans Baylands Nature Interpretive Center, to better utilize the resources of the facility. 5. Develop and implement a mapping strategy to identify the extent of non-native, invasiveweeds in the City’s open space land, then develop and implement a plan for their control or removal. 6. Research and implement effective and appropriate strategies to evaluate the quality of programs offered by Open Space and Sciences. 7. Complete .Phase II of the Foothills Park Water Management Plan capital project. 4. Emphasis has been placed oia expanding nature and science programs by presenting tours and programs in Spanish. Program attendance has increased approximately ten percent. 5.A native plant specialist contracted by the Arastradero Preserve Steward is in the process of preparing a map outlining the present extent of non-native encroachment. 6. A survey was designed and distributed to 500 current program participants. Information gathered from the survey indicated a high customer satisfaction rate, and a desire for more programs offerings for school age children. 7. Work on Phase II is scheduled to begin September, 1998. 31 KEY PLANS 8. Initiate discussions for a capital campaign and building renovation of the Junior Museum and Zoo, consistent with the City’s infrastructure program. 9. Open a major thematic exhibit on "Language" at the Junior Museum and Zoo. 10. Comply with the requirements of Native American Grave Protection and Repatriation Act as it relates to the Junior Museum’s Native American Collection. This includes developing an inventory of affected items and subsequently estimating the cost of compliance. PROGRESS 8. A renovation chair has been selected by the Friends of the Junior Museum to determine scope of project. 9. ,A new exhibit producer was hired who conceived, designed, fabricated and installed an exhibition entitled "Construction Sight" in the record time of three months. 10. Artifact summaries identifying Native American contacts and organizing artifact data have been prepared. Project is currently on hold pending additional funding. Major Activity: Open Space/Sciences Education Services IMPACT MEASURES 2.Maintain an interpretive and scienc~ activities cancellation rate of less thar~ 10 percent by providing quali~ programs in a timely manner. | 1997-98 SlX 1997-98 1996-97 1997-98 MONTH ESTIMATED ACTUALS ADOPTED ACTUALS ACTUALS 11%10%2%2% 2. Previously this impact measure represented only classes listed in the ’Enjoy" catalog. Starting with the current fiscal year, all classes, Workshop, and outreach programs will be accounted for under this impact measure, in order to better represent the breadth of programs provided 32 Major Activity: Wildlife/Resource Management IMPACT MEASURES 1996-97 ACTUALS 1997-98 ADOPTED 1997-98 MONTH ACTUALS o Aggressively work with other agencies to protect and increase the population of the California Clapper Rails to 80 birds in the Palo Alto Baylands by removing non-native environmental quality of the Baylands. (new) Apply for all required State an~ Federal permits for new animal., acquired for the Junior Museum Zoc within 30 days of receipt of the animal. in order to develop an understanding ol the extent of the problem, annually survey 20 percent of the City’s 4,00C acres of open space land to identify and map the distribution of non-native. invasive weeds. (new) n/a 20% 80 30 20% lffa 15% 1997-98 ESTIMATED ACTUALS n/a n/a 15% This measure seems to be beyond the reasonable control of staff Staff continue to remove red foxes and feral cats, yet too many uncontrollable environmental factors directly affect and impact the breeding of this endangered species. 2. No new animals were acquired so far during the past fiscal year, no permits required 3. With the current staffing levels fifteen percent of the open space land has been mapped FUNCTIONAL AREA: RECREATIONAL SERVICES KEY PLANS l. Increase the number of teams participating in the adult basketball and softball leagues. PROGRESS 1. Participation increased by seven teams, plus a new 16 team summer basketball league program was added. 33 KEY PLANS 2. In partnership with the Police Department, Human Services, and outside agencies, including PAUSD, provide programming for teens and "at-risk" youth through the Positive Alternatives for Youth Program. PROGRESS 2. "i~he program has been successfully implemented with a new program coordinator. A Youth Activity Center has been opened at the Ventura site. 3. Develop and.distribute a citywide special events calendar and regularly update the special events information on the City’s Intemet page. 3. Calendars are available to the public, and web site content is now being updated on a quarterly basis. 4. Renovate the circular swimming pool and deck area at Rinconada Pool, and add new play elements for children. 4. Construction scheduled to begin in Spring of 1998. 5. Implement a strategy to increase volunteer support from community organizations and individuals. 5. As a result of staff outreach, volunteer support has increased by approximately twenty percent. 6. Implement a strategy to secure additional sponsors for youth programs and special events. 6. Funding sources are being solicited, with a focus on the Middle School Outlet program. Major Activity: Adult Programs IMPACT MEASURES 1.[Offer 200 adult special interest classet~ach year. (new) ~ 1. Fall is the busiest season for adult classes. 1996-97 ACTUALS n/a 1997-98 SIX 1997-98 MONTH ADOPTED ACTUALS 200 125 1997-98 ESTIMATED ACTUALS 200 34 Major Activity: Youth and Teen Programs IMPACT MEASURES 1997-98 SIX 1997-98 1996-97 1997-98 MONTH ESTIMATED ACTUALS ,ADOPTED ACTUALS ACTUALS Produce after school sports leagues 850 middle school students. (new) Enroll 2,900 children in summer swir~ classes. (new) Produce 65 sessions of youth sport., camps.(new) n/a n/a n/a 850 2,900 547 2,018 75 85O 2,500 76 1.Fall and Winter sports produce the largest participation numbers for the Middle School Athletics program. 2. The majority of swim lessons are conducted during the months of July and August. 3. All camps except for one are offered in the months of July and August. Major Activity: Programs for Persons with Special Needs IMPACT MEASURES 1997-98 1997-98 1996-97 1997-98 MONTH ESTIMATED ACTUALS ADOPTED ACTUALS ACTUALS o Offer programs for disabled populations that attract 400 participants. (revised) Recover 25 percent of program costs for persons with special needs. 722 32% 400 25% 547 6% 850 20% ¯ I. Programs have increased in popularity over past years. 3. Most of the program revenue is generated during the second half of the fiscal year. 35 Major Activity: Recreation Facilities IMPACT MEASURES 1.Increase the number of rentals by 3 percent. 2. Generate 2 percent increased program revenue through improved marketing and increased user fees. 1997-98 SIX ! 997-98 1996-97 1997-98 MONTH ESTIMATED ACTUALS ADOPTED ACTUALS ACTUALS -5%3% 12%2% 28% 25% 20% 20% 1. Demand for weddings, corporate events has continued to increase significantly. 2. Demand for weddings, corporate, events has continued to increase significantly. 36 FUNCTIONAL AREA: EMERGENCY RESPONSE KEYPLANS 1. Conduct public reviews, report to Council, and implement any Foothills Fire Management Master Plan changes resulting from evaluation during 1996-97. PROGRESS 1. Project is progressing. Public reviews will be conducted and a report will be presented to Council in 1998/99. 2. Based on Council direction, continue to implement Paramedic Master Plan operational measures and revise quality improvement program. 3. Implement with neighboring jurisdictions any approved mutual aid agreements for emergency medical responses. 2. Bids will be received for transport engines in February 1998. Once a vendor is chosen, it will take approximately one year to receive the apparatus. The quality improvement program has been revised. 3. Discussions are underway with Menlo Park Fire District. Uncertain when this program could be implemented (if approved by County EMS agencies) due to probability of having to cross~-certify all affected paramedics to function in both counties. Major Activity: Fire Suppression Services IMPACT MEASURES 1997-98 SIX 1997-98 1996-97 1997-98 MONTH ESTIMATED ACTUALS ADOPTED ACTUALS ACTUALS 3.Limit property loss to $0.15 per $1,00(~ market value of property protected. 5.Limit the incidence of fires in buildings to 2 or less per 1,000 people. $0.176 $0.15 2 $0.10 .60 $0.15 1 3.& 5. Six month actual figures were based on the structure of the property. During the first six months there has been little fire activity. 37 FUNCTIONAL AREA: ENVIRONMENTAL AND SAFETY MANAGEMENT -KEY PLANS 1. Continue joint meetings with representatives from Santa Clara County cities, Santa Clara County, the Environmental Health Department, and the California Environmental Protection Agency to meet the requirements of SB- 1082 which requires the streamlining of hazardous waste regulations. PROGRESS 1. Requirements have been met and participating agency agreement between Santa Clara County and the City of Palo Alto providing administration of the Unified Waste and Hazardous Materials Programs management program is complete. 2. Upon finfil legal review and Council approval of the Emergency Preparedness Plan, begin training City employees. 2. Emergency plan has been finalized during the first six months, with training to take place during the last six months of the fiscal year. Council is scheduled to approve this in late 1997-98. Major Activity: Fire Code Research, Development and Enforcement 1996-97 1997-98 IMPACT MEASURES ACTUALS ADOPTED 1997-98 1997-98 MONTH ESTIMATED ACTUALS ACTUALS Inspect 80 percent of all applicable high hazard occupancies every six months. Inspect 90 percent of all applicable ordinary hazard occupancies every twelve months. Inspect 100 percent of all applicable light hazard occupancies every 36 months. 93% 86% 99% 80% 90% lOO% 37.5% 39% 34% 80% 90% 100% 1. Staffing issues and other priorities prevented us from attaining this impact measure. 2. & 3. Inspections are arranged by street location to enable the most efficient use of the fire fighters time. As a result the remaining inspections will occur during the last half of the fiscal year. 38 Major Activity: Disaster Preparedness IMPACT MEASURES To conduct City employee training on disaster management for 20 percent of all employees annually. To conduct 6 community training talks to neighborhood associations on disaster survival techniques annually. To conduct 2 disaster management exercises for City staff members. (new) 1997-98 SIX 1997-98 1996-97 1997-98 MONTH ESTIMATED ACTUALS ADOPTED ACTUALS ACTUALS 18%20% 6 2% 2 n/a 20% 6 1. Emergency plan has been finalized during the first six months, with training to take place during the last six months of the fiscal year. 2. Approximately 10 community training talks have been conducted with 2 of them being to neighborhood associations. 4.. Emergency plan has been finalized during the first six months, with training to take place during the last six months of the fiscal year. FUNCTIONAL AREA: TRAINING AND PERSONNEL MANAGEMENT KEY PLANS 1. Conduct meetings with other agencies to determine feasibility of a joint entry level~ outreach and hiring process. PROGRESS 1. A consortium of 15 fire agencies was formed which conducted an outreach and entry level hiring process. Palo Alto Fire Department hired 5 recruits from the established eligibility list in October 1997. 39 FUNCTIONAL AREA: RECORD AND INFORMATION MANAGEMENT KEY PLANS 1. Continue to develop and implement an optical imaging records filing and management system. PROGRESS 1. Permanentstaff has assumed the workload .previously performed by temporary staff. Input of records proceeds as time permits. 40 FUNCTIONAL AREA: EMPLOYEE COMPENSATION AND BENEFITS KEY PLANS 1 .Work with Public Employee Retirement System, Public Agency Coalition, and League of California Cities to modify existing dental, vision, medical and long term care benefit plans to reduce the City’s benefit plan costs. 2. Negotiate agreement with Service Employees’ Intemational Union (SEIU) and Palo Alto Peace Officers’ Association (PAPOA). PROGRESS 1. Long term care is complete resulting in reduced benefit cost. Work has begun in the other areas with completion scheduled in fiscal year 98-99. 2. Negotiations with SEIU will begin in March, 1998; with PAPOA in June 1998. Major Activity: Classification and Salary Administration IMPACT MEASURES 1997-98 SIX 1996-97 1997-98 MONTH ACTUALS ADOPTED ACTUALS Assure classification system is currenl by reviewing 20 percent of positior descriptions annually. , Survey on an annual basis 75 percent ol all of benchmark classifications tc determine competitive rates of pay. 33% 50% 20% 75%n/a 1997-98 ESTIMATED ACTUALS 20% 75% 1, & 2. These impactmeasures will occur during the last six months of the fiscal year. Major Activity: Labor Contract Negotiation/Management IMPACT MEASURES 1.Negotiate agreements according_ toi Council authorization with all thre~ representation units within 60 days o~expiration of, contracts. . | 1997-98 SIX 1996-97 1997-98 MONTH ACTUALS ADOPTED ACTUALS 100 days 60 days 1. This impact measure will occur during the last six months of the fiscal year. n]a 1997-98 ESTIMATED ACTUALS 60 days 41 FUNCTIONAL AREA: WORKFORCE RECRUITMENT AND SELECTION KEY PLANS 1, Develop and administerentry-level firefighter outreach and selectionprocess. 2. Develop outreach network using Intemet technology for recruitment. PROGRESS 1. This key plan was completed. 2. This key plan was completed. Major Activity: Employee Selection IMPACT MEASURES 1996-97 ACTUALS 4. cent or bettera on customerratingsatisfactionlr4 rdaAchieve satisfaction of 80 pe_ /survey. (new) 1997-98 SiX 1997-98 1997:98 MONTH ESTIMATED ADOPTED ACTUALS ACTUALS 80%80% 4. This survey will be complete in Spring, 1998. FUNCTIONAL AREA: EMPLOYEE DEVELOPMENT/WORKLIFE KEY PLANS 1. Provide community college courses (for college credit) at the City Training Center. PROGRESS 1. Unable to provide this service to companies because it was not cost effective for Foothill College. Major Activity: Training Programs IMPACT MEASURES 4.Provide at least 250 spaces in cgmputer training classes. 1996-97 ACTUALS 600 ’ 1997-98 1997-98 ESTIMATED ADOPTED ACTUALS 250 1997r98 SIX MONTH ACTUALS 368 25O 4. Due to the NT transition, an additional 8 classes have been offered 42 Major Activity: Worklife Enhancement/Recognition 1996-97 IMPACT MEASURES ACTUALS 1997-98 SIX 1997-98 1997-98 MONTH ESTIMATED ADOPTED ACTUALS ACTUALS Provide classes that address worklife enhancement issues in 20 percent of the Training Center’s course offerings. 27%20%5%20% 1. The majority of Worklife Enhancement classes are scheduled for the Spring. FUNCTIONAL AREA: TRANSPORTATION DEMAND MANAGEMENT KEY PLANS 1. Decrease vehicle use among employees at City Hall by implementation of a Lunchtime Trip Reduction program and provision of public transit information through the use of Intemet. PROGRESS 1. Program continues with the actual figures being determined by May 1998. Intemet sites have been provided to employees through bookmarks that were distributed in July 1997. Major Activity: Commute Alternatives Programs 1996-97 IMPACT MEASURES,ACTUALS ¯1997-98 SIX 1997-98 1997-98 MONTH ESTIMATED ADOPTED ACTUAL ACTUALS Reduce Vehicle Employee Ratio (VER) by 4 percent during commute hours. Increase the number of registered transit users i 0 percent by June 1998. 5% 13% 4% 10% n]a 7.2% 4% 10% 1. Survey will be conducted in the months of April and May, 1998. 2. Due to new employees and heightened awareness,, the actual figures, are higher than expected 43 FUNCTIONAL AREA: RISK MANAGEMENT KEY PLANS 1. Develop and implement all new mandated regulations, including Family and Medical Leave Act, California Family Rights Act, Department of Transportation Alcohol/Drug Testing Fitness for Duty evaluations and CAL/OSHA Ergonomic Standards. 2. Act as liaison for risk management issues to the League of California Cities Legislative Assistant Director. 3. Develop an employee safety incentive program to be integrated into the employee recognition program. 4. Update insurance and worker’ s compensation program contracts to reflect changing trends in economics and industry standards. PROGRESS 1. The Family and Medical Leave Act policy and procedure, which includes the California Family Rights Act, has been drafted. The Department of Transpor- tation Alcohol/Drug Testing policy and procedure has been implemented, The Fitness for Duty policy and procedure will be implemented by June 1998. The CAL/OSHA Ergonomic program policy has been drafted and implementation will soon be complete. 2. Risk Manager contacted the League of California Cities Legislative Assistant Director and acted as a liaison for risk management issues. 3. The employee safety incentive program has been drafted and will be implemented by June 1998. 4. The insurance contracts were updated and the Request For Proposal process was completed. Major Activity: Injury/Illness Prevention IMPACT MEASURES 1. Assist departments in limiting thq number of employee injuries wher~ work time is lost to 40 injuries per year.[ 1997-98 SiX 1997-98 1996-97 1997-98 MONTH ESTIMATED ACTUALS ADOPTED ACTUALS ACTUALS 32 40 11 40 1. Due to increased awareness and hazard control the number of employee injuries is 45% below the 6 month target of 20 injuries. 44 FUNCTIONAL AREA: PUBLIC INVOLVEMENT, EDUCATION, ASSISTANCE KEYPLANS 1. Initiate a Zoning Ordinance update according to the Comprehensive. Plan Implementati6n Priorities adopted by the City Council. PROGRESS 1. Pending Council Comprehensive Plan. approval on the Major Activity: Education, Information, and Assistance IMPACT MEASURES 1996-97 ACTUALS 1997-98 ADOPTED 1997-98 SIX MONTH ACTUALS Update 2 public handouts per year in a user friendly format to incorporate submittal requirements and standard conditions of approval for all City Departments. 7 0 1997-98 ESTIMATED ACTUALS 2 2. Unable to met this impact measure due to unplanned vacancies. Major Activity: Board, Committee, Commission Support IMPACT MEASURES 1996-97 ACTUALS 1997-98 ADOPTED 1997-98 SIX MONTH ACTUALS Implement 50 percent of the recommendations for operational improvements identified at the Board and Commission annual retreats within one year. 50%n/a 1997-98 ESTIMATED ACTUALS 50% 1. The Architectural Review Board held a retreat in May 1997, just prior to the end of the year, so this measure will continue to be tracked in 1997-98. 45 FUNCTIONAL AREA: LIAISON, COORDINATOR AND TECHNICAL ADVICE KEY PLANS 1. Coordinate with the Public Works Department to implement the Downtown Urban Design Improvements capital project. 2. Continue to participate in the Silicon Valley uniform building code interpretation committee. PROGRESS 1. This project has been passed to Public Works; final contract negotiations are occurring and construction is expected tO begin in Summer 1998. 2. Staff has continued to participate in the Silicon Valley Uniform Building Code interpretation committee.- Major Activity: Local and Interdepartmental Activities 1996-97 IMPACT MEASURES ACTUALS 1. Convert 75 percent of all proposals foq 67% creek flood protection from concret~ solutions to more natural solutions. | 1997-98 SIX 1997-98 1997-98 MONTH ESTIMATED ADOPTED ACTUALS ACTUALS 75%0%100% 1. No proposals were submitted FUNCTIONAL AREA: DEVELOPMENT REVIEW KEY PLANS ¯ 1. Implement oversight of the conditions of approval, public infrastructure improvements and mitigation monitoring plan for the Sand Hill Road Corridor projects if approved by Council. PROGRESS 1. The Sand Hill Road Corridor projects were approved by the electorate in November 1997; staff oversight of the conditions of approval and mitigation monitoring has not begun. 46 Major Activity: Application Review and Processing IMPACT MEASURES 2.~Receive 100 percent of applicablq departmental comments within 10 day~ of a project’s submittal date. | 1997-98 SIX 1997-98 1996-97 1997-98 MONTH ESTIMATED ACTUALS ADOPTED ACTUALS ACTUALS 68%100%50%75% 2. This measure is out of the control of Planning Department staff due to competing deadlines for other departments and divisions, and the increased number of projects needing review. FUNCTIONAL AREA: CONSTRUCTION REVIEW/PROJECT MONITOR KEY PLANS 1. Implement the regional Standardized Permits application form developed by the Peninsula Chapter of the International Conference of Building Officials. PROGRESS 1. City is waiting for the finalized approved form. Staff anticipates implementing the new form in the next few months. Major Activity: Plan Review IMPACT MEASURES 1. Process 95 percent of express plan checks within 10 working days. Process 75 percent of non-express residential plans first checked within thirty calendar days. 1997-98 SIX 1997-98 1996-97 1997-98 MONTH ESTIMATED ACTUALS ADOPTED ACTUALS ACTUALS 97% 64% 95% 75% 74% 47% 85% 60% 1. & 2. lncrease in building permit activities and staffvacancyprevented division from achieving this impact measure. 47 FUNCTIONAL AREA: ADVANCE PLANNING KEY PLANS 1. Conduct and prepare Coordinated Area Plan. a SOFA/PAMF PROGRESS 1. Study is underway with a mid-process report to Council scheduled for March 1998, with completion in October 1998. 2. Utilizing a State grant and a Joint Agency process, develop the Palo Alto/Stanford Intermodal Interface Area Plan and develop phased construction drawings for the public improvements within the area. 2. )k draft work program for the consultants was prepared in December and will be finalized in February. Major Activity: Policy And Ordinance Development IMPACT MEASURES 1997-98 ACTUALS 1997-98 SIX 1997-98 1997-98 MONTH ESTIMATED ADOPTED ACTUALS ACTUALS Update the Work Program for Council adoption and respond to Council.withir the specified time limits established b) the work program 80 percent of th~ time. 78%80%0%100% t. The Work Program will be updated during the Spring for Council review and approval during the budget adoption proc.ess. FUNCTIONAL AREA: TRANSPORTATION A,ND PARKING MANAGEMENT KEY PLANS 1. Complete construction of the Embarcadero bridge and bike path project.. 2.Complete the Bicycle Plan, including new City Bicycle Routes map. PROGRESS 1. Project has been delayed indefinitely, pending resolution of issues related to the use of the railroad right, of-way. 2. Project delayed until 1998/99 pending additional TDA grant funding to supplement existing grant funding. 48 KEY PLANS 3. Complete planning and design study for a community-based local bus shuttle system. PROGRESS 3. Project has been delayed until December 1998 due to unexpected staff vacancy. 4. Initiate final design and formation of an assessment district for the new downtown parking structure(s). 4. This project has been transferred to the Public Works Department. 5. Conduct feasibility study for a residential arterial traffic calming program for Embarcadero Road. 5. Draft scope of work has been prepared and consultant selection is anticipated to be completed by June 1998. Major Activity: Traffic Signals Management IMPACT MEASURES 1997-98 SIX 1997-98 1996-97 1997-98 MONTH ESTIMATED ACTUALS ADOPTED ACTUALS ACTUALS Review traffic signal timings at 10 locations annually. Modify/install traffic signals within 1 year of funding approval. 10 1 year 8O Traffic Signal Timing Study, which will be complete this year. 2. There were no major traffic signal, modifications/installations scheduled this year. Major Activity: Traffic Engineering The timing of the majority of city operated traffic signals will be reviewed in the context of the Prepare annual report to identify high_ accident ioca~ions anc~ recommendations for improvements. ] 1997-98 SIX 1997-98 1996-97 1997-98 MONTH ESTIMATED ACTUALS ADOPTED ACTUALS ACTUALS Annual Annual IMPACT MEASURES 2.0 2. Report will be prepared in second half of the 1997-98fiscal year. Annual 49 Major Activity: Parking Management IMPACT MEASURES Conduct review of 5 locations (e.g. blockfaces, parking lots, etc.) In Downtown and California Avenue business districts annually to attempt to gain additional parking spaces. 1997-98 SIX 1996-97 1997-98 MONTH ACTUALS ADOPTED ACTUALS 0 1997-98 ESTIMATED ACTUALS 5 2. Review will be prepared in second half of the 1997-98 fiscal year. Major Activity: Bicycle Programs IMPACT MEASURES 1. Percent occupancy rate for City bik~ locker rentals. (60 lockers)/ 1997-98 SIX 1996-97 MONTH ACTUALS ACTUALS 51% 1997-98 ADOPTED 75%45% 1997-98 ESTIMATED ACTUALS 65% 1. A number of high demand bike lockers at California Avenue train station are damaged When " lockers are replaced, occupancy rate should increase. FUNCTIONAL AREA: NEIGHBORHOOD SERVICES AND PROGRAMS KEY PLANS 1. Develop policies and guidelines for a Neighborhood (Local and Collector Street) Traffic Calming Program for Council adoption. PROGRESS 1. Currently being developed for Council review and approval in Summer 1998. 2. Implement recommended improvements from the Citywide School Commute Safety Study. 2. Project is scheduled for Council review in April. 50 KEY PLANS 3. Investigate the towing of vehicles from private property. inoperable PROGRESS 3. Staff has obtained copies of San Jose’s ordinance dealing with the vehicle towing from private property for review and discussion in consultation with City Attorney’s office. Major Activity: School Safety Activities IMPACT MEASURES 1996-97 ACTUALS 1997-98 SIX 1997-98 1997-98 MONTH ESTIMATED ADOPTED ACTUALS ACTUALS Percentage of all adult crossing guard evaluations completed within 30 days ol receipt of request from the City/School Traffic Safety Committee. (Average 3 per year) 100%90%rl,/a 90% 1. No request were received during the first half of the year. Major Activity: Traffic and Planning Studies IMPACT MEASURES 1996-97 ACTUALS 1997-98 SIX 1997-98 1997-98 MONTH ESTIMATED ADOPTED ACTUALS ACTUALS Complete 90 percent of Council approved and’funded phases ot neighborhood traffic studies.(new) Review and analyze all road buml: request consistent with the approved Council guidelines and prepare ~ annual status report to the Council on the Road Bump Program. 0 0 90% Annual 0 0 Annual 1. No studies have been approved and funded this fiscal year. 2. To date four road bump request have been received of which three are complete and one is pending. Annual report will be prepared during second half of the fiscal year. 51 FUNCTIONAL AREA: AFFORDABLE HOUSING AND CDBG KEY PLANS 1. Monitor construction and funding requirements for the Alma Street SRO project. PROGRESS 1. Construction will be completed and. the project will accept tenants on February 17, 1998. Major Activity: Affordable Housing Development IMPACT MEASURES 1996-97 ACTUALS 1997-98 SIX 1997-98 1997-98 MONTH ESTIMATED ADOPTED’ACTUALS ACTUALS Increase the number of permanentl) affordable, low ix~come rental housing unity by an average annual increase ot 25 units over a five year period (1995- 2000). 0 25 0 131 1. No units will be counted until Alma Place SRO development opens for occupancy in second half of fiscal year 1997-1998. FUNCTIONAL AREA: INFORMATION MANAGEMENT KEY PLANS 1..Implement request system. an automated inspection 2. Develop GIS counter applications public use of automated cartography products and City orthophotos. PROGRESS 1. The project is on hold pending the outcome of the Permit Tracking System. 2. GIS team is ~ieveloping test program in Public Works; program expected to be available in Planning in Fall 1998. 52 Major Activity: Records and Map Management ¯ IMPACT MEASURES 1996-97 1997-98 ACTUALS ADOPTED !1.Percentage of zoning maps updatec~50% within 30 days of Council adoption rezoning.! 1997-98 SIX 1997-98 MONTH ESTIMATED ACTUALS ACTUALS 100%0 100% 1. Vacant staff positions prevented this impact measure from occurring. Major Activity: Data Collection & Reporting IMPACT MEASURES 1996-97 1997-98 ACTUALS ADOPTED 1997-98 SIX 1997-98 MONTH ESTIMATED ACTUALS ACTUALS 2. Maintain and update land use 100%100% projections, census, downtown monitoring data and submit annual monitoring reports on time. 3. Maintain a protected tree inventory n/a 100% system which numbers, tags, maps and photo documents 100 percent of all ,trees accepted or identified as having "protected" status within 30 days of being discovered (Oak trees) or designated (othbr species) by City Council. (New) _ 20%100% 0%100% 2. Vacant staff positions prevented this impact measure from occurring. 3. There were no ’~teritage "tree candidate trees submitted to the City by the public during the first six months~of the year. 53 FUNCTIONAL AREA: REQUESTS FOR SERVICE KEY PLANS 1. Evaluate the trial program of utilizing Community Service Officers in the field to assist in the implementation of the Downtown Health and Safety Program. PROGRESS 1. Program evaluation completed. Community Service Officers were assigned various duties in the field which allowed Police Officers to dedicate their time to the downtown area. 2. In order to minimize liability and reduce loss, prepare for and initiate the use of less lethal weapons in tactical situation~. Major Activity: Critical Incident Resolution IMPACT MEASURES 1996-97 ACTUALS 2. SWAT officers have been trained and less lethal weapons have been successfully used in the field. Designated Rifle Officers will be trained in the third quarter. 1997-98 SIX 1997-98 1997-98 MONTH ESTIMATED ADOPTED ACTUALS ACTUALS After the initial police response, respond with specially trained units tc the scene of a critical incident withir 1.5 hours after request. (Estimate thre~ incidents a year) .6 1.5 .6 1,5 1. Midyear actuals were based on four incidents for the first six months. Incidents were preplanned and personnel assigned to the specialty units were notified in advance of the incident. FUNCTIONAL AREA: COMMUNICATIONS SERVICES KEY PLANS 1. Achieve cost savings through the implementation of an automated radio equipment inventory tracking system for identification of parts usage, ordering patterns and repair histories. PROGRESS 1. Evaluated available off-the-shelf software programs for cost effectiveness and functionality. None appear to meet needs at a reasonable price. Development of an in-house automated inventory control system will continue. Implementation will occur in the fourth quarter of 1997-98. 54 KEY PLANS 2. Make recommendations and secure approval of a Computer Aided Dispatch (CAD) system. PROGRESS 2. Request For Proposal’ process was successful resulting in a vendor being selected. Negotiations of agreement and a request for Council approval targeted for late 1997-98. Major Activity: Police Dispatching Services IMPACT MEASURES 3.Maintain a ratio of sustained complaints call for service of less than 1 to 10,000.[ (Estimated 32,000 calls for service) 1996-97 ACTUALS 1996-97 SIX 1997-98 1997-98 MONTH ESTIMATED ADOPTED ACTUALS ACTUALS 0 3. No complaints based on 14,509 police calls for service. Major Activity: Fire Dispatching Services IMPACT MEASURES 1996-97 ACTUALS 1997-98 SIX 1997-98 1997-97 MONTH ESTIMATED ADOPTED ACTUALS " ACTUALS 2. Maintain a ratio of sustained complaints call for service at less than 1 to 10,000.[ (Estimated 6,000 calls for service) 2. No complaints based on 3,383 fire calls for service. FUNCTIONAL AREA: INVESTIGATION AND DISPOSITION KEY PLANS 1. Develop and initiate formalized interagency cooperation and enhance regional policing among detective divisions of adjacent agencies. 55 PROGRESS 1. Menlo Park, East Palo Alto, Stanford and Mountain View have agreed to participate along with Palo Alto. As a result investigators from two agencies are working together on a string on bank robberies. KEY PLANS _. 2. Explore the feasibility of initiating an in-house polygraph and voice analyzer program, to be utilized in criminal investigations and/or pre- employment screening. PROGRESS 2. Feasibility study is complete. Information available on the utilizations of voice analyzers is limited and the technology is currently under rapid change. Use of the polygraph as a part of the hiring process for sworn personnel will begin during the next hiring process. Use of polygraph for criminal investigations, when appropriate, will continue. Major Activity: Investigations IMPACT MEASURES 1996-97 ACTUALS 1997-98 SIX 1997-98 1997-98 MONTH ESTIMATED ADOPTED ACTUALS ACTUALS Clear/close 65 percent of cases assigned by the supervisor to the investigator. (Estimate 260 cases per year) Return less than 5 percent of cases to patrol officers for follow-up due to deficiencies and/or incompleteness in the initial investigation. (Estimate 9,000 criminal cases per year) 78% 3% 65% 5% 109% 1% 85% 5% 1. Higher than normal clearance rate due in part to the arrest of an individual who admitted to eighteen burglaries. 2. There were 4,423 criminal cases reported for the first six months. Lower than anticipated return rate is due in part to lack of documentation during the transition to a new Court Liaison as well as an organizational emphasis on enhanced supervisory review. 56 FUNCTIONAL AREA: TRAFFIC SERVICES KEY PLANS 1. Participate in efforts to work with State legislation to change the eighty-five percentile rule of using radar on city streets to enforce speed limits. PROGRESS 1. Contacted other cities that have’ attempted to have legislation changed. Also have contacted League of California Cities. Council will be provided with an update during the third quarter. 2. Continue with the "Community Traffic Officer" Program. 2. Officers are assigned to Barron Park, University Avenue/Downtown, Midtown, Ventura, Embarcadero and Alma. There were 3,401 speeding citations issued at midyear. Major Activity: Traffic Enforcement IMPACT. MEASURES 1.Reduce injury accidents by 3 percent.I (Estimated 420 injury accidents) 1997-98 SIX 1996-97 1997-98 MONTH ACTUALS ADOPTED ACTUALS 6%3%1% 1997-98 ESTIMATED ACTUAL - 1. There were 211 injury accidents reported for the first six months. Although reduced only l% from the same period last year, injury accidents are running 8% lower than in 1995-96. FUNCTIONAL AREA: PROACTIVE POLICING SERVICES KEYPLANS PROGRESS - 1. Participate in public relations and educational efforts with the community through the production of a cable access Police news format show. 1. Participated in a half hour news format and in an one hour education format productions. Completed public service announcement of red light safety, to be aired during the. third quarter. 2.With the assistance from Community Services Department, evaluate the first year of the Positive Alternatives for Youth (PAY) program. 2. Evaluation criteria established with evaluation occurring after completion of a full year. 57 KEY PLANS 3. Formalize the problem solving model of Community Policing in targeted neighborhoods. PROGRESS 3. Presented the framework of Community Policing and problem solving to 150 block captains. Participated in neighborhood problem solving effort in Barton Park neighborhood. 4.In an effort to create greater police presence in the south end of town, increase the use of the Ventura substation. 4. In partnership with PAY and the YMCA, participated in the opening of the Teen Center at Ventura. Substation has been used by neighborhood groups, job placement, mentoring, and tutoring for youth. Use of the substation has increased 400%. 5. Study the feasibility of development of an "Adopt a Neighborhood Association" program. 5. Initiated discussion about pursuing imple- mentation of the "We’re Connected" program in place of the Adopt a Neighborhood Association program. "We’re Connected" is aimed at increasing direct participation by the neighborhoods and the business community in joint problem solving. Major Activity: Crime Suppression IMPACT MEASURES ¯ 1996-97 ACTUALS 1997-98 SIX 1997-98 1997-98 MONTH ESTIMATED ADOPTED ACTUALS ACTUALS Ensure Palo Alto’s violent crime rate remains within the lowest 7 percent ot all California cities between 50,000 and 100,000 population. (Based on approximately 80 cities) 6.5%7%6.5%7% 1. Palo Alto currently ranks fiflh out of the 77 California cities. Violent crime in Palo Alto has decreased-8% for the same six month period one year ago. 58 Major Activity: Youth Services IMPACT MEASURES 2.Ensure identified police officers visi~ each adopted school once a week.I (Based on 13 schools) | 1997-98 SIX 1997-98 1996-97 1997-98 MONTH ESTIMATED ACTUALS ADOPTED ACTUALS ACTUALS .5 .3 .25 2. Higher than normal vacancy rate of sworn officers, the concentration on an enhanced Avoid the 13 campaign and the implementation of the Downtown Health and Safety program has limited the number of visits to schools. Major Activity: Community Policing and Education IMPACT MEASURES 1.Notify affected businesses an~ residences of identified violent crim trends within 24 hours after[ /identification of trend. 1997-96 SIX 1997-98 1996-97 1997-98,MONTH ESTIMATED ACTUALS ADOPTED.ACTUALS ACTUALS n/a 24hrs lOhrs 1. Actuals based on only one identified violent crime trend 24hrs FUNCTIONAL AREA: POLICE PERSONNEL SERVICES KEY PLANS 1. Change the focus of the Health Resource Coordinator program from a reactive crisis resolution mode to a proactive employee orientation aimed at employee needs assessments related to career goals and enhancement. PROGRESS 1. Career Path Program has been implemented and is currently a part of the quarterly evaluation process for line level officers. 59 KEY PLANS 2. Maintain the quality of police officer applicants through the implementation of the newly designed recruitment incentive program. 3. Design and implement a basic .training program for newly assigned investigators to include those subjects not generally covered in the approved Police Officers Standard Training (POST) specialty courses. PROGRESS 2. Production has begun on the new recruiting video. This will be completed in the last half of the fiscal year. 3. POST has recently developed .a comprehensive basic detective class designed for new dectectives without previous investigative experience. Will continue to pursue alternative training programs for the more advanced investigator. Major Activity: Personnel Records Management IMPACT MEASURES 1996-97 ACTUALS Im(estigate and notify 80 percent ot complainants of outcome within 313 days. (Estimate 50 complaints per year) Ensure 100 percent compliance with the Police Officers Standards Training audit frr police ’personnel records management. 73% 100% 1997-98 SIX 1997-98 1997-98 MONTH EXTIMATED ADOPTED ACTUALS ACTUALS 80% 100% 18% n]a 55% 100% 1. Figures based on eleven complaints due during the first six months. Measures have been taken to improve complaint investigation process and notification rate. In almost all cases, complainants were notified on the progress of the investigation. 2. POST has yet to audit the PAPD personnel training records. This audit is unannounced, but we expect it to occur in the third or fourth quarter. Major Activity: Hiring and Retention IMPACT MEASURES 1.Maintain a vacancy rate of no more than 4 percent for sworn personnel. o Ensure 80 percent of newly hired police officers successfully complete the basic police academy and field training program. Maintain a vacancy rate of no more thai 4 percent for non-sworn personnel. 1997-98 SIX 1997-98 1996-97 1997-98 MONTH ESTIMATED ACTUALS ADOPTED ACTUALS ACTUALS 9.6% 84% 3.7% 4% 80% 4% 7% 57% 6% 7% 80% 4% 3. employees in Communications. Major Activity: Mandatory Training Due to the lack of interested, qualified applicants, vacancies are taking much longer to f!ll. Figures based on seven newly hired police officers. Three officers did not complete the program. Higher than estimated vacancy rate can be attributed to the retirement and resignation of three IMPACT MEASURES 2.Provide training on 100 percent on nev~ legislation and re’gulations to all officers~ ~2~eh.in three months of the effectiv 1 1997-98 SIX 1997-98 1996-97 1997-98 MONTH ESTIMATED ACTUALS ADOPTED ACTUALS ACTUALS 100%100%n/a 2. All training on new legislation that became effective January 1, was conducted in January. 1996-97 1997-98 ACTUALS ADOPTED Major Activity: Non-Mandatory Training 69% [ 100% 10o% IMPACT MEASURES 1.Provide diversity training each year ttall Police Department personnel. 1997-98 sIX 1997-98 MONTH ESTIMATED ACTUALS ACTUALS 61 1. Anticipate completing training in third and fourth quarter. Major Activity: Volunteer Program IMPACT MEASURES 2.Increase the number of active polic~ volunteers by 5 percent. (Estimate 5(~ active police volunteers) 1997-98 SIX 1997-98 " 1996-97 ,1997-98 MONTH ESTIMATED ACTUALS ADOPTED ACTUALS ACTUALS 17%5%10%5% 2. Higher than anticipated increase is due to interest generated through the Citizen’s Academy and revitalization in the recruitment and utilization of volunteers in numerous programs within the Police Department. FUNCTIONAL AREA: ANIMAL SERVICES KEY PLANS 1. Determine the feasibility and potential of entering into longer term agreements with Los Altos, Los Altos Hills, and Mountain View for animal control services. PROGRESS 1. Developed methodology for cost recovery and three year contract proposals with outside agencies. Successfully negotiated three year contracts with the three cities. 2. Ensure a smooth transition process to the new City veterinarian. 2. Transition tothe new City veterinarian is complete. Spay and neuter surgeries achieved 129% of mid year’s goals. Major Activity: Pet Recovery/Adoption Services 1996-97 IMPACT MEASURES ACTUALS 1997-98 SIX 1997-98 1997-98 MONTH ESTIMATED ADOPTED ACTUALS ACTUALS Maintain the number of cats reunited with their owner at 10 percent or more. (new) 10%19%10% 3. Higher than anticipated percentage due to a lack of historical information in setting the original goal and the shelter’S reputation with the residents. It is anticipated that the percentage will decline 62 as "cat season "begins in the Spring. The national average for reuniting cats with their owners is three percent. Major Activity: Animal Care IMPACT MEASURES 1997-98 SIX 1997-98 1996-97 1997-98 MONTH ESTIMATED ACTUALS ADOPTED ACTUALS ACTUALS Provide a shelter hygiene program to keep disease outbreak at the shelter at less than 5 percent of the total animals handled. (Estimate 2,300 animals handled per year) .7%5%.4%1% 2. Lower than anticipated rate is due &part to a lack of statistical experience in setting the original goal and staff’s commitment to separate and isolate animals, especially if any sign of illness is detected. FUNCTIONAL AREA: PARKING SERVICES KEY PLANS 1. Per Council direction, complete, a feasibility study regarding a residential parking permit program. 2. Assist City Attorney in the drafting of an ordinance regulating tow companies. 3. Design and implement a one month amnesty (i.e. no towing, but all fines due) program for vehicle with excessive parking tickets. PROGRESS ’ 1. Conducted numerous meetings with Downtown North Neighborhood Association, and the University South Neighborhood Group. Two model programs have been discussed. Surveys will be sent out to North and South residents during the third quarter to obtain additional feedback on the models. 2. Will meet with the City Attorney to schedule drafting of the ordinance. Anticipate completion of the draft ordinance in the fourth quarter. 3. Designed and implemented a One month amnesty program for a month. Mailed 56 letters to the registered owners. Eleven responded with payments totaling $4,068 in excessive parking citations. 63 Major Activity: Parking Enforcement IMPACT MEASURES Ensure a 50 percent compliance rate fo~ newly identified habitual offender: within 90 days. Resolve overnight parking issues withir 5 wbrking days of receipt of the compliant. 1997-98 SIX 1997-98 1996-97 1997-98 MONTH ESTIMATED ACTUALS ADOPTED ACTUALS ACTUALS 75% 3.3 50%90% 7.8 70% 2. Higher than anticipated rate is due in part to the one month amnesty program. 3. Higher than anticipated rate is due to one over night parking complaint which was misplaced and notaddressed for two weeks. FUNCTIONAL AREA: SPECIAL EVENTS KEY PLANS 1. Investigate the feasibility of renegotiating the Stanford reimbursement agreement for special events. PROGRESS 1. The plan is to schedule a meeting with Stanford University officials in the third quarter to discuss reimbursement for traffic control related to Stanford Stadium events. Major Activity: CiW Sponsored Events IMPACT MEASURES 1 .Maintain an attendee/calls-for-service of les~ than .5 percent at City sponsored events.I / (Estimate 20 events and 120,000 attendee~ per year) / 1997-98 SIX 1997-98 1996-97 1997-98 MONTH ESTIMATED ACTUALS ADOPTED ACTUALS ACTUALS .02%.5%0%.25% 1. Attendee/calls for service ratio is less than anticipated due in part to the coordinated planning efforts of the participating departments. To date approximately 36,000 attendees partieipated in four City sponsored events requiring police planning and assistance. 64 Major Activity: Non-City Sponsored Events 1996-97 IMPACT MEASURE ACTUALS 1..01%Maintain an attendee/calls-for-service o~ less than .5 percent at special events.] (Estimate 20 events and 16,00(~ attendees per year) " ] 1997-98 SIX 1997-98 1997-98 MONTH ESTIMATED ADOPTED ACTUALS ACTUALS .5%.01%.25% 1. Attendee/calls for service ratio is less than anticipated due in part to the coordinated planning efforts of the participating departments. Approximately 138,000 attendees participated in seven non-City sponsored events requiring police planning and assistance. Major Activity: Stanford Sponsored Events IMPACT MEASURE 1.Maintain an attendee/calls-for-service o~ less than .5 percent at Stanford. University special events. (Estimate 8I events and 300,000 attendees per year)] 1997-98 SIX 1997-98 1996-97 1997-98 MONTH ESTIMATED ACTUALS ADOPTED ACTUALS ACTUALS .01% ’.5%0%.25% 1. Attendee/calls for service ratio is less than anticipated due in part to the oordinated planning efforts of the participating departments. Approximately 300,000 attendees participated in six Stanford University sponsored events requiring Palo Alto Police Department planning and coordination. FUNCTIONAL AREA: POLICE INFORMATION MANAGEMENT ’ KEY PLANS 1. Pursue recommendations pertaining to a Computer Aided Dispatch System. PROGRESS 1. Received Council approval to distribute revised Request For Proposal which produced three proposals. Completed evaluations and two vendors retumed for product demonstrations and oral interviews. A vendor was selected. Negotiations of agreement and’ Council approval targeted for third quarter. 65 KEY PLANS 2. Begin the replacement process for the Police Recor.ds Management system. PROGRESS 2. Completed needs analysis of affected work groups. Reviewed Request For Proposal’ s from other agencies. Downloaded and evaluated programs found on Internet. Began draft of police department environment, needs, expectations, and technical requirements. 66 FUNCTIONAL AREA: STREETS KEY PLANS 1. Award a contract to resurface streets in the University Avenue Business District. 2. Survey the use frequency of all publicly owned bike lockers, and provide recommendations for an improved maintenance program. PROGRESS 1. The 1998 Resurfacing Project is scheduled to be bid in 2nd half of the fiscal year. 2. All bike locker location.s have been surveyed to determine which areas will be replaced this fiscal year. 3. Award a contract and oversee the construction 0fimprovements to the Page Mill Road and Foothill Expressway intersection. 3. The Page Mill Road and Foothill Expressway Intersection is scheduled to be bid in the 2nd half of the fiscal year. 4. Review and update a condition survey of the street system. Major Activity: Street Computer Mapping 4. The review and update of the condition survey is scheduled to be bid in 2nd half of the fischl year. IMPACT MEASURES 1. Every two years survey the condition o~ streets within the City and update th~ Pavement Maintenance Managemenq System (PMMS) data base. |. 1997-98 SIX 1997-98 1996-97 1997-98 MONTH ESTIMATED ACTUALS ADOPTED ACTUALS ACTUALS 0%95%0%95% 1. Survey is scheduled for second half of fiscal year. Major Activity: In-House Maintenance IMPACT MEASURES 2. Remo_ve all graffiti from reportec~ locations in the City. (Approximatel3~ 1,000 locations reported) | 1996-97 ACTUALS n/a 1997-98 SIX 1997-98 1997-98 MONTH ~ ESTIMATED ADOPTED ACTUALS ACTUALS 100%76%83 % 2. Private property and other agency calls make up 24 percent of all calls. 67 Major Activity: Street - CIP Support IMPACT MEASURES 1. Design and bid contracts to resurface 8 miles of streets per year to maintain an average 20 year maintenance cycle.(new) 2.Bid all projects in the year they are budgeted for construction. (Revised) 1997-98 SIX 1996-97 1997-98 MONTH ACTUALS ADOPTED ACTUALS .rga 8 miles 0 100%100% 1. & 2. Projects are scheduled to be bid in second half offiscal year. FUNCTIONAL AREA: SIDEWALKS 1997-98 ESTIMATED ACTUALS 8 miles 100% KEY PLANS 1. Maintain the existing backlog of"hot spot" sidewalk replacement by no mbre that six months. PROGRESS 1. Backlog has been maintained at six months. Major Activity: Sidewalks Cip Support IMPACT MEASURES 1.Reconstruct or repair 76,000 square fee1of sidewalks annually. (Revised) 1997-98 1996-97 1997-98 ESTIMATED ACTUALS ADOPTED ACTUALS 80,000 76,000 1997-98 SIX MONTH ACTUALS , 7,500 75,000 1. Due to inclement weather, only 10% of project completed Expect full completion by the end of the fiscal year. 68 FUNCTIONAL AREA: TREES KEY PLANS PROGRESS 1. Implement the remaining Tree Task Force recommendations for the Public Works Department by reducing the trimming cycle to seven years and adding the Office Specialist position. 1. Implemented the reduced trimming cycle and an Office Assistant position was added and the position filled. Major Activity: In-House Park Tree Maintenance IMPACT MEASURES 1996-97 ACTUALS 11. Annually trim, prune, raise, and remov~4% deadwood from ten percent of Cit3J street trees. (Approximately 35,00(~ trees) 1997-98 SIX 1997-98 1997-98 MONTH ESTIMATED ADOPTED ACTUALS ACTUALS 10%6%10% 1. Scope of work currently being prepared Expect completion by May 1998. FUNCTIONAL AREA: STRUCTURES AND GROUNDS KEY PLANS 1. Complete modules 2 & 3 and initiate Module 4 of the Infrastructure Management Study. 2. Replace roof on the Mitchell Park Library, Mitchell Park Community Center ~and Fire Station 5. PROGRESS 1. Modules 2 and 3 of the Infrastructure Management Study have been completed. Module 4 will be started this fiscal year. 2. Design for the Mitchell Park Library and Community Center Re-Roof is nearly completed. Station 5 design has started and both will be put out to bid in April with construction scheduled for late June 1998. 69 KEY PLANS 3. Complete Phase II of the facility rekeying project. 4. Complete Main Library and Mitchell Park Library lighting improvements. 5. Complete construction phase of the Civic Center Chiller Replacement Project. 6. Coordinate with Open Space and Sciences on the 7-acre restoration of Harbor Point to marsh. PROGRESS 3. This project has been delayed due to staff scheduling. Both phase I and II will be completed as a design/build project in 98/99. 4. Design is nearly complete and the project is scheduled to go out to bid for the construction phase the first week of March 1998. 5. The construction phase of the Chiller Replacement project began in December and will be complete by February 1998. 6. The marsh at Harbor Point has ’been completed. 7. Implement a newspaper rack improvement project in the University Avenue Business District, contingent on Council approval. 7. The plan is being reviewed by the City Attorney. 8. Start construction of the Golf Course Master Plan project. 8. The Golf Course Improvements will commence in the spring of 1998. Major Activity: Contract Maintenance Projects IMPACT MEASURES 1997-98 SIX 1997-98 1996-97 1997-98 MONTH ESTIMATED ACTUALS ADOPTED ACTUALS ACTUALS /3.Percentage of maintenance service call~97% completed within three weeks oil request./ 100%29%100% 3. Staff time is weighted heavily on design in the first half of the year and construction in the second half. 70 Major Activity: Structures/Grounds CIP Support IMPACT MEASURES 1.Bid 70 percent of projects in the yeaq they are budgeted for construction. | 1996-97 1997-98 ACTUALS ADOPTED 1. Projects are scheduled to be bid in the second half of the fiscal year. FUNCTIONAL AREA: PRIVATE DEVELOPMENT 1997-98 SIX 1997-98 MONTH ESTIMATED ACTUALS ACTUALS 0% I 70% KEY PLANS 1. Provide timely review of Palo Alto Medical Clinic and Stanford West construction documents, if approved by Council, and coordinate activities with the Planning Department. " 2. Through training, expand the expertise of the One Stop Counter staff in water quality issues in accordance with the Permit Streamlining recommendations. 3. Participate with Planning Department in updating standardized traffic control plans for development projects in accordance with the Permit Streamlining recommendations. PROGRESS 1. Palo Alto Medical Clinic (building interiors) permits issued in December 1997. " Stanford West (Corridor) coordinating permit meeting are scheduled for January. Workshops are schedule for spring of 1998. 2. Training in process and will continue through the end of the fiscal year. 3. Updating of the standardized traffic control plans are scheduled for the 2nd half of the fiscal year. 71 FUNCTIONAL AREA: GENERAL SERVICES KEY PLANS 1. Upgrade traffic signals and install a new signal on Middlefield Road at Midtown in 1997-98. PROGRESS 1. Midtown Project was delayed. indefinitely Major Activity: Street Lights Operations/Maintenance IMPACT MEASURES 1996-97’ ACTUALS 1997-1998 ADOPTED 1997-1998SIX MONTH ACTUALS 1. No more then 6 street lights (of 6000) will remain non-operational in a 24 hour period. 6 1997-98 ESTIMATED ACTUALS 6 I. Above expectations, due to preventative replacement program. Major Activity: Traffic Signals Operations/Maintenance IMPACT MEASURES 1996-97 ACTUALS 1997-1998 ADOPTED 1997-1998 SIX MONTH ACTUALS 1. Respond to all t~affic signal system problems within 1 hour. 33.Smin lhr 37min 1. Above expectations. 1997-98 ESTIMATED ACTUALS 72 Major Activity: Communications Operations/Maintenance 1996-97 1997-1998 IMPACT MEASURES ~ACTUALS ADOPTED 1997-1998 SIX MONTH ACTUALS 1. Restore service to all system users within 4 hours of an unscheduled system failure. 1.25hrs 4hrs 0 1997-98 ESTIMATED ACTUALS 4hrs 1. No failures reported Major Activity: Communications - CIP IMPACT MEASURES 1996-97 ACTUALS 1997-1998 ADOPTED 1997-1998 SIX MONTH ACTUALS 1. Limit communication system outages to less than a system-wide average of 1 hour per customer per year. lhr 0 1997-98 ESTIMATED ACTUALS lhr 1. No outages reported FUNCTIONAL AREA: RESOURCE MANAGEMENT KEY PLANS 1. Coordinate and lead implementation 0fthe action plan to position the electric utility for open competition on January 1, 1998. 2. Coordinate the implementation of guidelines for protecting confidentiality of utility, supplier and customer information. PROGRESS 1. Completed action plan and procedures to offer customer open access. Implementation began on schedule. 2. Continue to work with the City Attorney to establish Confidentiality Guidelines to protect business and customer information. 73 3. Develop a strategic public relations/ communications plan to help position the Utility as the resource provider of choice in a competitive market. 4. Develop plans to address the need for a diverse portfolio of supply resources to meet increasing competitive pressures. 5. Develop methodology to benchmark Palo Alto’s cost of providing supply resources and demand-side management program services against potential competitors. 3. Completed November 1997. 4. In the process of reviewing existing procedures to make recommendations for future changes. Plan is scheduled for completion by end of the fiscal year. 5. Marketing plans for key accounts (approximately 15) have been completed. Marketing plans for the small commercial and residential customers are in progress with expected completion by June 1998. 6. Develop custom tailored marketing plans for each.cust~omer market segment. 6. Staff has been trained to do the benchmarking. However, due to the heavy work load associated with deregulation the actual creation .or development of the methodology to benchmark to outside marketers or suppliers has been delayed. Major Activity: Competitive Assessment 1996-97 IMPACT MEASURES ACTUALS 1.Forecast customer electric usage within I 2.5% 5% of actual consumption.I ¯ 1997-1998 SIX 1997-98 1997-1998 MONTH ESTIMATED ADOPTED ACTUALS ACTUALS 1. Slight fluctuation primarily as a resultof weather variations, expected year end target to remain the same. 74 Major Activity: Demand-Side Management Programs IMPACT MEASURES 1997-1998 SIX 1997-98 1996-97 1997-1998 MONTH ESTIMATED ACTUALS ADOPTED ACTUALS ACTUALS Implement 90 percent of the Utilities’ programs identified and approved by Utilities Advisory Commission and Council. 90%90%70%90% 1. Implementing all high-priority large commercial and industrial programs. Completed design, implementation and evaluation criteria for future Public Benefits programs (AB1890). Major Activity: Market Programs IMPACT MEASURES 1.Coordinate production of packages of utility programs, services and supply resources for 100 percent of key customers who may seek resources for Utilities’ competitors. 1997-1998 SIX 1997-98 1996-97 1997-1998 MONTH ESTIMATED ACTUALS ADOPTED ACTUALS ACTUALS Implement 90 percent of the strategies identified in the annual Utility Marketing Services Communication Plan. 100% 100% 100% 90% 70% 65% 100% 90% 1. Provided significant customer education and assistance regarding deregulation and supply issues. Coordinated customized supply options, including long-term contracts. Significantly increased utility visibility among customers. 2. Working with other utility divisions to resolve customer reliability, billing, and outage management issues. Initiated the ’RESCUE"consulting service for customers with critical back-up generation needs. 75 FUNCTIONAL AREA: SUPPORT SERVICES AND RATES KEY PLANS 1. Implement operational changes and business process improvements identified by the Utilities Business Process Reengineedng Study. 2. Implement new rate structures and-pricing options to address retail wheeling under a restructured electric industry. 3. Expand automatic meter reading to accommodate customer requirements under retail wheeling. 4. Coordinate the design of application software for hsers of the Customer Information System (CIS) Project and provide for expanded capabilities which will become necessary under retail wheeling. PROGRESS 1. The majority of the remaining operational changes and improvements are dependent upon the availability of the new CIS (Customer Information System) currently being installed. 2. Completed. 3.. Automatic Meter Reading test sites are being selected with a view toward accomodating the most likely Direct Access customers in the first two phases. Installation will be completed this Fiscal Year. 4. In-house development of the CIS was halted, and a commercial CIS was purchased. It is currently being installed. 5. Introduce a Competition Transition Charge (CTC). 5. Electric rates have been unbundled into 4 components: Commodity, Transition Cost Recovery Charge, Distribution Charge, and the Public Benefit Charge. 76 Major Activity: Customer Services IMPACT MEASURES 1997-1998 SIX 1997-98 1996-97 1997-1998 MONTH ESTIMATED ACTUALS ADOPTED ACTUALS ACTUALS 1.Answer 74 percent Of all incoming calls before the call is placed on hold. Maintain an average time under 20 seconds for customer calls placed on hold. 75% 15 sees 74% <20 sees 98.2% 32 sees 98% 20 sees 1. Telephone system has been redesigned since goal was set. This variance results in part from performance improvement and in part from a change in statistical methods. 2. This figure represents only 1.8% of all calls received," 98.2% of calls are never placed on hold. Major Activity: Meter Reading IMPACT MEASURES’ 1997-1998 SIX 1997-98 1996-97 1997-1998 MONTH ESTIMATED ACTUALS ADOPTED ACTUALS ACTUALS Total meter reader .productivity, as measured by number of reads per Meter Reader per month, will exceed the national average by at least 15%. (revised) 15%15%27.4%25% 1. Variance is partly due to better-than-usual weather for the first half of the fiscal year. If performance continues above current goal target will be adjusted upward next year. FUNCTIONAL AREA: DISTRIBUTION SYSTEM KEY PLANS 1. Continue replacing deteriorated cable installed,on E1 Camino Real. 2. Improve system reliability and increase system capacity by designing and completing construction on a second transformer replacement at Hanover Substation. PROGRESS 1. Project has been delayed to 2002. Cable replacements in the Stanford Business Park and emergency pole replacements have been given priority. 2. Second transformer will not be purchased. ,An existing transformer will be " refurbished and used to replace the Hanover 21 transformer. 3. Continue the conversion of overhead facilities to underground by completing the construction work on District #37. (Embarcadero/Seale/ Middlefield) and completing the planning and design on District #38. 3. Substructure bid package is being prepared. Construction will occur in the Spring. Initial planning on District 38 is complete, and underground ordinance will go to Council in January. 4. Complete the system capacity increase at Alma #2 substation by replacing a transformer and constructing an architectural facade along Alma Street. 5. Replace old and unreliable 4 kV equipment by converting the College Park area and Maybell 1 and 2 circuits to 12 kV. 4. Transformer has been installed. Design competition for the wall will start in March. 5. Construction for College Park is 70% complete. Conversion of the Maybell 1 and 2 circuits have been delayed. Conversion in El Camino and Park Blvd area and the Loma Verde Louis Road area will be substituted. 78 Major Activity: Distribution Operations/Maintenance IMPACT MEASURES 1996-97 ACTUALS 1997-1998 ADOPTED 1997-1998 SIX 1997-98 MONTH ESTIMATED ACTUALS ACTUALS 1. Limit power outages to less than a system-wide average of 60 minutes per customer. 2. Begin field restoration and repairs for unscheduled outages within 1 hour. 3. Respond to customer inquiries or problems within 2 hours. 4. Limit average number of service interruptions to fewer than 2 per customer (new) 49.6min 31.6min 43min n/a <60min lhr 2hrs <2 <40min 28min 35min <1 <60min liar 2bxs <2 1. On target to meet goal 2. On target to meet goaL 3. Above expectations, on target. 4. Fewer interruptions than anticipated. Major Activity: Customer Design/Connection-CIP IMPACT MEASURES 1996-97 ACTUALS 1997-1998 ADOPTED 1997-1998 SIX 1997-98 MONTH ESTIMATED ACTUALS ACTUALS 1. Review plans for new service requests within 12 working days. 10 12 Exceeded expectations. 79 Major Activity: System Improvement - CIP IMPACT MEASURES 1996-97 ACTUALS 1997-1998 SIX 1997-98 1997-1998 MONTH ESTIMATED ADOPTED ACTUALS ACTUALS 3. Convert overhead facilities to underground at a capital expenditures rate of 2 percent of annual gross electric revenues. 3%2%.1%1.7% 3. Variance is due to project delay in previous year. Work done in 1996-97. Overall percentage is still at 2percent as established by the Public Utilities Commission. FUNCTIONAL AREA: COMMERCIAL TELECOMMUNICATION KEY PLANS 1. Evaluate additional fiber optic cable deployment opportunities that would support. the needs of network developers and service providers. PROGREss 1. Completed two extensions of the fiber backbone adding 0.6 new route-miles. Evaluating backbone design modification that would add an estimated 1.9 new route-miles. 2. Continue to negotiate fiber optic license agreements. 2. Signed agreement with WebTV Networks. Received advance engineering requests from five other parties. Advance engineering requests have now been received for new fiber connections to 28 different locations in. Palo Alto. 80 KEY PLANS 3. Coordinate and implement a marketing effort on behalf of all companies that have entered into fiber optic license agreements with th~ City. PROGRESS 3. Established set of web pages dedicated to marketing the fiber backbone. Prepared and distributed a package of marketing materials to several prospective customers. Full- scale marketing efforts targeted to begin in January 1998. Major Activity: Planning/Marketing/Contract Negotiations IMPACT MEASURES 1.Negotiate agreements for the lease of at least 15% of the fibers installed. Negotiate agreements that will recover at least 15% of construction cost annually. 1997-1998 SIX 1997-98 1996-97 1997-1998 MONTH ESTIMATED ACTUALS ADOPTED ACTUALS ACTUALS 0.3% 1.9% 15% 15% 2.5% 6.2% 6% 15% 1. lnitial projections anticipated bulk fiber licenses by telecommunications carriers seeking to reserve fiber at volume discounts. Demand for large reserve quantities of fiber has not yet materialized 2. The 6-month actual assumes no contract renewals beyond Fiscal Year 1997-1998 (i.e., worst case scenario). 81 FUNCTIONAL AREA: RESOURCE MANAGEMENT KEY PLANS 1. Coordinate the implementation of guidelines for protecting confidentiality of utility, supplier and customer information. PROGRESS 1. Continue to work with the City Attomey to establish Confidentiality Guidelines to protect business and customer information. 2. Develop custom tailored marketing plans for each customer market segment. 2. Marketing plans for key accounts (approximately 15) have been completed. Marketing plans for the small commercial and residential customers are in progress with expected completion by June 1998. 3. Develop a strategic public relations/ communications plan to help position the Utility as the resource provider of choice in a competitive market. 3. In progress. Completion planned for June 1998. 4. Develop methodology to benchmark Palo Alto’s cost of providing supply resources and services against potential competitors. 4. Staff has been trained to do the benchmarking. However, due to the heavy work load associated with deregulation the actual creation or development of the methodology to benchmark to outside marketers or suppliers has been delayed. Major Activity: SUPPLY RESOURCES IMPACT MEASURES 1. Procure natural gas commodity and transportation for a cost of at least 2%. less than what PG&E would charge Palo Alto to supply the same commodity. 1997-1998 SIX 1997-98 1996-97 1997-1998 MONTH ESTIMATED ACTUALS ADOPTED ACTUALS ACTUALS 13.5%<2%<39%<10% 1. Palo Alto obtained excess revenues from a temporary transportation agreement. Without this agreement the 6 month actual savings reduce to 17%. 82 Major Activity: Demand-Side Management Programs IMPACT MEASURES 1997-1998 SIX 1997-98 1996-97 1997-1998 MONTH ESTIMATED ACTUALS ADOPTED ACTUALS ACTUALS 1. Implement 90 percent of the Utilities’ annual resource goals approved by the Utilities Advisory Commission and Council. 95%90%60%90% 1. Key Accounts, Major Accounts, Small Commercial and Residential plans either updated or in progress. Major Activity: Market Programs - IMPACT MEASURES 2. Implement 90 strategies in the Marketing Services Plan. percent of the annual Utility Communication 1997-1998 SIX 1997-98 1996-97 1997-1998 MONTH ESTIMATED ACTUALS ADOPTED ACTUALS ACTUALS 100%90%45%100% 2. A significant communication effort will be made later in the fiscal year to prepare for the restructuring of the California gas industry allowing choice of suppliers. FUNCTIONAL AREA: SUPPORT SERVICES AND RATES KEY PLANS 1. Implement operational changes and business process improvements identified by the Utilities Business Process Reengineering Study. 2. Complete migration to a 21 working-day meter reading cycle. 1. The majority of the remaining operational changes and improvements are dependent upon the availability of the new CIS (Customer Information System) currently being installed. 2. Further migration is dependent on completion of CIS implementation. 83 KEY PLANS 3. Expand automatic meter reading where it is cost justified to increase customer satisfaction and achieve timely billing. 4. Coordinate the design of application software users of the Customer Information system (CIS). Project and provide for expanded billing capabilities. 3. Automatic Meter Reading test sites are being, selected with a view toward accomodating the most likely Direct Access customers in the first two phases of the Gas Restructuring Plan. Installation will be completed by the end of the fiscal year. 4. In-house development of the CIS was halted, and a commercial CISwas purchased. It is cu.rrently being installed. FUNCTIONAL AREA: DISTRIBUTION SYSTEM KEY PLANS PROGRESS 1. Design and construct mandated Department of Transportation and National Electrical Code safety improvements for Gas Station Number 1, located at Embarcadero Road and Geng Road. 1. The planning for the safety improvements at this gas station is on schedule. Improvements will be designed by June 1998. 2. Design and construct Phase 8 of the Gas Main Replacement Project which will replace mains on sections of the following streets: Waverly, Lytton, Welch, Pastuer, Winter-green, David, Elbridge, Murray, Richardson, Loma Verde, Flowers, Holly Oak, Ames, Cork Oak, Christine and Arastradero Road. These locations are subject to change based on system emergency and maintenance needs. 2. GMR.Phase 8 is in the design phase. The project will be out ,to bid in April 1998. Construction will start by June 1998. 84 FUNCTIONAL AREA: SOLID WASTE KEY PLANS 1. Continue to direct two-thirds ofPalo Alto’s solid waste stream to the Sunnyvale Materials and Recovery Transfer Station (SMART) to achieve a minimum 15 percent waste diversion goal. PROGRESS 1.As of December 1997, 55 percent of Palo Alto’s solid waste stream was sent to the SMART Station for a 12 percent waste diversion goal. Major Activity: Solid Waste Permit/Enforcement IMPACT MEASURES 2.Conduct two visual inspectionspe week of garbage truck contents illegal materials. 1996-97 ACTUALS 6 1997-98 SIX 1997-98 ’1997~98 MONTH ESTIMATED ADOPTED ACTUALS ACTUALS 6 6 2. Six inspections are being done to ensure clean loads. Major Activity: Landfill Operations IMPACT MEASURES. 1996-97 ACTUALS -- 1997-98 SIX 1997-98 1997-98 MONTH ESTIMATED ADOPTED ACTUALS ACTUALS Annually recover 24 tons of recyclable materials from the landfill disposal area. (Revised) 101 24 38 72 1. Currently an average of 6 tons of scrap metal per month is diverted from the working face. Increased recovery is achieved through use of heavy equipment.. 85 Major Activity: Hazardous Waste IMPACT MEASURES 2.Conduct .a minimum of 14 Saturda~ household hazardous waste collectior~ events annually. " [ 1997-98 SIX 1997-98 1996-97 1997-98 MONTH ESTIMATED ACTUALS ADOPTED ACTUALS ACTUALS 13 14 14 2. Recycling Program events consisted of garage sale, Chamber of Commerce Showcase, five home composting workshops and Business Recycling Link event. Major Activity: Composting IMPACT MEASURES 1997-98 SIX .1997-98 1996-97 1997-98 MONTH ESTIMATED ACTUALS ADOPTED ACTUALS ACTUALS o Sell a minimum of 5,000 tons of compost produced each fiscal year. Annually process 10,000 tons of green yard waste into compost. (Revised) n/a n/a 2,500 10,000 5,644 8,610 10,000 16,000 2. Ther~ is a new marketing contract for compost. 4. More efficient processing achieved through screening and turning material FUNCTIONAL AREA: COLLECTION, HAULING AND DISPOSAL KEY PLANS 1. Oversee completion of the EIR and design of the former Los Altos Treatment Plant site for the refuse, collection, hauling and disposal operations yard. PROGRESS 1. The draft EIR was approved by the Planning Commission on January 14, 1998. 86 Major Activity: Collection and Hauling Contract IMPACT MEASURES call back rate to .5 percent oftota~3.Limit collections, and respond within 2,~ hours. . ’ | 1996-97 ACTUALS .5% 1997-98 ADOPTED .5% 1997-98 SIX MONTH ACTUALS .1% 3. PASCO has been very responsive to customer requests. 1997-98 ESTIMATED ACTUALS .5% FUNCTIONAL AREA: STREET SWEEPING KEY PLANS 1. Redu6e illicit dumping of debris and leaves from pri,vate properties onto City streets and parking lots. PROGRESS 1. Supervisor attending code enforcement class to increase knowledge of codes and skills to enforce them. Completion date is January 1998. 87 FUNCTIONAL AREA: STORM DRAINAGE SYSTEM IMPROVEMENTS KEY PLANS 1. Implement construction of local storm drainage improvements in the Barron Park neighborhood. 2. Complete construction of a storm drain pipeline replacement/rehabilitation projects and initiate design of the next phase of the work. PROGRESS 1. Completed 20% of local storm drainage improvement project in Barron Park neighborhood. 2. Construction of storm drain pipeline replacement/rehabilitation project delayed until Spring 1998 due to workload constraints. FUNCTIONAL AREA: STORM DRAINAGE OPERATION/MAINTENANCE KEY PLANS 1. Implement the new Performance Standard and the associated expanded inspection and compliance program required by the new storm water discharge permit issued to Palo Alto. PROGRESS 1. The new Performance Standard and the associated expanded inspection and compliance program have been implemented and both are fully operational. 88 FUNCTIONAL AREA: SUPPORT SERVICES AND RATES KEY PLANS 1. Implement operational changes and business process improvements identified by the Utilities Business Process Reengineering Study. 2. Coordinate the design of application software for users of the Customers Information system (CIS) Project and provide for expanded billing capabilities. PROGRESS 1. The majority of the remaining operational changes and improvements are dependent upon the availability of the new CIS (Customer Information System) currently being installed. 2. As experience with the CIS increases, application software needs will be defined, but none are anticipated currently. FUNCTIONAL AREA: DISTRIBUTION SYSTEM KEYPLANS 1.. Complete construction of wastewater collection system rehabilitation projects in College Terrace, in easement from East Bayshore and Amarillo under Highway 101 to the Water Quality Control Plant near Embarcadero Way; and on Amarillo from Elmdale to East Bayshore Road. PROGRESS 1.College Terrace area collection system rehabilitation projects have been completed. Amarillo avenue to Embarcadero Way Relief Sewer Negative Declaration and alignment have been approved by Council. Final design is being completed by the project consultant. Project will be bid during the summer Of 1998. 2. Replade wastewater collection mains on Middlefield from Everett to Channing; Colorado from Huggins Place to Simpkins Court; in easement between Colorado and Amarillo south of Simpkins Court; and Amarillo from Elmdale Place to Tanland Drive. 2. Project is in the design phase and will be out to bid by May 1998. 89 FUNCTIONAL AREA: WASTEWATER TREATMENT KEY PLANS 1. Prepare construction plans and financial agreements for implementing long-term solids treatment and disposal facilities. PROGRESS 1. Financial agreements for implementing long-term solids treatment are scheduled for Council approval March 1998. 2. Install and program computerized process controllers for the dual media filters and the chlorination system. 2. Programable Logic Controllers installed on chlorination system. were 3. Complete Phase 2 of the 72- inch interceptor sewer rehabilitation and begin Phase 3, completion of the rehabilitation. project. 3. Inspection of 72-inch interceptor 90% complete. Expect completion by October 1999. Major Activity: WQCP System Improvement (CIP) IMPACT MEASURES I’l. Bid 80 percent of all projects in the yeaq they’are budgeted for construction. | 1997-98 1996-97 1997-98 ESTIMATED ACTUALS ADOPTED ACTUALS 75%8O% 1997-98SIX MONTH ACTUALS 25%80% 1. Projects delayed due to staff vacancy in Engineering. FUNCTIONAL AREA: WASTEWATER ENVIRONMENTAL COMPLIANCE KEY PLANS 1. Obtain a new, five year permit for discharge of treated wastewater to San Francisco Bay and insure that its terms and conditions are reasonable and achievable. Provide quarterly updates to Council. PROGRESS 1. In order to obtain the new discharge permit, a detailed technical application was prepared and submitted January 28, 1998. Discussion~ ~vith the permit issuing agency have commenced and are scheduled to be completed before the July 21, 1998 expiration date. 90 FUNCTIONAL AREA: RESOURCE MANAGEMENT KEY PLANS 1. Actively participate with the Bay Area Water Users Association and the San Francisco Public~ Utilities Commission (SFPUC) in the preparation of a Regional Water Supply Master Plan. (WSMP) PROGRESS 1. As active member of the WSMP . Steering Committee, provided direction throughout the scoping, Phase 1, of the project. 2. Develop custom-tailored marketing plans for each customer market segment. 2.Marketing plans for key accounts (approximately 15) have been completed. Marketing plans for the small commercial and residential customers are in progress with expected completion by June 1998. 3. Develop an extensive review of all water supply options including the Santa Clara Valley Water District supply, given the expected increase of SFPUC water supply costs and the potential for future SFPUC capital expenditt~re. 3. Delayed until fall of 1998 to accommodate the delayed schedule of SFPUC’s Phase 2 Water Supply Master Plan. 4. Develop a strategic public relations and communications plan to broaden public awareness ~of Utility involvement in the eorrmaunity. 4. In progress. Completion planned for June 1998. 5. Investigate Demand Side Management options, including altematives to base-year allotments, for future drought years. 5. Gathering information. Coordinating the City’s response to revisions to the Water Best Management Practices (BMP’s). 91 Major Activity: Market Programs IMPACT MEASURES 1. Within 5 Working day.s, complete design review of commercial landscape plans submitted for compliance with Palo Alto Landscape Water Efficiency Standards. 2. Implement 90 percent of the strategies included in the annual Utility Marketing Services Communication Plan. 1997-1998 SIX 1997-98 1996-97 1997-1998 MONTH ESTIMATED ACTUALS ADOPTED ACTUALS ACTUALS <5 90%75%<5 90% 1. Completed 31 commercial landscape plans with an average turnover of 3 days. ¯ 2. Providing end-use information using either mass-marketing (brochures, pamphlets and bill. stuffers) and individual contact (workshops, account services, drop-ins, telephone inquiries). Coordinating planned outages for Key and Major Accounts to minimize customer inconvenience. FUNCTIONAL AREA: SUPPORT SERVICES & RATES KEY PLANS 1.Coordinate the design of application software for users of the Customer Information System (CIS) Project and provide for expanded billing capabilities. PROGRESS 1. In-house development of the CIS was halted, and a commercial CIS was purchased. It is currently being installed. 2. Complete migration to a 21 working-day meter reading cycle. 2. Further migration is dependent on completion of CIS implementation. 92 KEY PLANS 3. Continue to implement operational _changes and business process improvements identified by the Utilities Business Process Reengineering Study. 4. Evaluate potential impact of Proposition 218 on current rate structure and develop appropriate rate structures to meet future revenue requirements. PROGRESS 3. The majority of the remaining operational changes and improvements are dependent upon the availability of the new CIS (Customer Information System) currently being installed. 4. Still being evaluated. Waiting for legal decision. FUNCTIONAL AREA: DISTRIBUTION SYSTEM KEY PLANS 1. Evaluate need for corrosive control measure on Park, Corte Madera and Dahl. Perform fence and pavement repairs on reservoir sites. 2. Complete the installation ofwater main replacements in Phase XII on sections of Crescent Drive, .Southwood, Edgewood, Newell, Dana King Lane, Kirby, Greenwood, Chaucer, Tevis, Fife, Wilson, Parkinson, Melville, Somerset, Regent, Kent, Hopkins and Pine. 3. Complete installation of corrosive control measures on Montebello Reservoir. Perform remaining fence and pavement repairs at all reservoir sites. PROGRESS 1. Project is in the design phase. A contract for the work will be awarded by Council during June 1998. 2. Project has been designed, bid and awarded by Council. Installation of the mains was started in January, 1998. 3. Warranty inspections have been made and the contractor is scheduling minor repairs with City staff. 93 Major Activity: Vehicle Replacement/Outfitting IMPACT MEASURES 1996-97 ACTUALS 1997-98 SIX 1997-98 1997-98 MONTH ESTIMATED ADOPTED ACTUALS ACTUALS Replace 95 percent of vehicles within six months of the budgeted replacement date for approved vehicles. 95%95%55%95% 2. Due to staff vacancies this impact measure will be achieved by March 1, 1998. FUNCTIONAL AREA: VEHICLE OPERATIONS/MAINTENANCE KEY PLANS 1. Link paperless shop work orders system to Department’ s preventive maintenance scheduling, pool care use and accident/damage reporting. 2. Modify shop personnel responsibilities to account for staff reductions through attrition (per organization review) due to position retirement estimated 7/1/97. PROGRESS 1. A semi-automated preventive maintenance scheduling and department notification system is now is place. 2. The Assistant Fleet Manager’s responsibilities have been shifted to more direct shop supervision and the Fleet Coordinator has been reassigned to full time administrative support for the maintenance activity. 94 Major ~Activity: Vehicles (_~perations, Monitoring IMPACT MEASURES 1996-97 ACTUALS 1997-98 ADOPTED 1997-98 SIX MONTH ACTUALS 1997-98 ESTIMATED ACTUALS Provide 95 percent of monthly billing statements to Administrative Service~ Department for previous month’s vehicle cost within five working days after the end of each month. 92%95%33%100% 2. Provide departments with quarterly 4 revised 4 n/a rda usage, accident and repair cost data reports which Summarize exceptions of either under-utilized or excessive use vehicles. (Revised) 1. Statements through October. 1997 were the responsibility of the prevtous Fleet Manager. Since October 1997, 100% of statements have been provided on time. 2. Not currently being done due to staff vacancy. Major Activity: Fuel Storage and Dispensing IMPACT MEASURES 2.Provide 4 percent annual fuel savingq from use of Compressed Natural Ga~ (CNG) in Vehicles from base year 1993-~ | 1996-97 ACTUALS 1% 1997-98 SIX 1997-98 1997-98 MONTH ESTIMATED ADOPTED ACTUALS ACTUALS 4%0%0% 2. This is extremely difficult to track using ggavings ~ This should be revised to report on CNG utilization rather than dgavings ~ ¯ 95 FUNCTIONAL AREA: PRINTING AND MAILING SERVICES KEY PLANS PROGRESS 1.Study the~ feasibility of producing four-color 1. Gathering data and reviewing suitable formats printing inthePrintShop, to report findings in order to support equipment and staffing requirements necessary to produce four-color printing. A report will be produced by the end of the fiscal year. 96 FUNCTIONAL AREA: COMPUTER EQUIPMENT REPLACEMENT KEY PLANS 1. Evaluate the benefits recommendation related to the purchase of personal computers. and make lease versus 2. Identify and analyze citywide personal computer needs and install computers for staff that do not currently have personal computer access. 3. Upgrade all existing 486 personal computers to Pentium models. 4. Purchase thirteen new servers for application processing, printing and file sharing. 5. Provide for the replacement and plan the configuration and installation of workstations and hardware for the Geographic Information System. 6. Finaliz~ detailed policies and procedures for administration. PROGRESS ’ 1. The lease versus buy analysis has postponed until fiscal year 1998-99. been 2. There were 13 personal computers added to the replacement fund for new employees or employees who now require personal computers to effectively perform their assignments. 3. The contract is in place to replace all 486/66Mhz processors or less. This amounts to approximately 225 personal computers. Replacements will begin in January 1998. 4. Ten of the City’s existing thirteen personal computer servers have been replaced or upgraded. The two servers-for the Police Department’s Computer Aided Dispatch function are in the planning stage. 5. The hardware has been received and is in the process of being installed. Implementation of the new hardware configuration is being planned for March 1998. 6. A draft of the new policies and procedures have been generated and are being reviewed. 97 Major Activity: Computer Relacement IMPACT MEASURES 1996-97 ¯ ACTUALS 1997-98 .ADOPTED 1997-98 SIX MONTH ACTUALS 1997-98 ESTIMATED ACTUALS Upgrade more than 25 percent of the City’s personal computer inventory annually. n/a 25%0 40% 2 Contract awarded in January 1998. Upgrades will occur in the second halfofthefiscal year. 98