HomeMy WebLinkAboutStaff Report 9849
City of Palo Alto (ID # 9849)
Finance Committee Staff Report
Report Type: Action Items Meeting Date: 12/4/2018
City of Palo Alto Page 1
Summary Title: Council Chambers A/V Phased Design Option
Title: Discussion and Recommendation to the City Council to Approve the
Chambers Audio Visual Phased Design Upgrade Approach
From: City Manager
Lead Department: IT Department
Recommended Motion
Staff recommends that Finance Committee:
1. Recommend to Council that the Council Chambers Audio Visual project be
approved to proceed using a multi-year phased approach, with anticipated
funding needs as follows:
a. Funding for Phase 1 and 2 in FY2020 of $1,000,000
b. Funding for Phase 3 in FY2021 of $750,000
2. Recommend to Council that the Council direct staff to proceed with the
development of the bridging documents with consultant The Shalleck
Collaborative, Inc. (Shalleck) for the Phase 1 and 2 design/build solicitation.
Executive Summary
On March 26, 2018, staff recommended to Council the Shalleck Design Option 2 with an
estimated cost of $2,040,000 (CMR 8997).
Council approved a motion to:
1. Refer this item to the Finance Committee with direction to evaluate options
between Design Option 1 and Design Option 2; and
2. Direct Staff to continue to value engineer the Project, continue to identify options
to reduce the overall cost, and identify items that can be completed
incrementally.
In response to this direction, staff reevaluated the scope of the project and removed
$290,000 of elements that were determined to be non-essential. Staff prioritized the
remaining features from the original Design Option 2, then separated them into three
potential phases considering priority and the efficiency of completing related scope
components together.
City of Palo Alto Page 2
Shalleck produced a cost estimation report and executive summary for a phased project
approach. Staff's recommendation is to combine Phases 1 and 2 for Year One, to be
followed by Phase 3 in the following year. This recommendation is consistent with
Council's motion.
If Finance Committee and Council approve staff’s recommendations, Shalleck will
develop bridging documents that will further define the scope and additional
information necessary to complete the design for the project and a design/build
Request for Proposal (RFP) for Phases 1 and 2 of the Council Chambers upgrade will be
issued.
Background
Consultant
Shalleck was hired to assist the City to design and implement upgrades to the Council
Chambers’ audio visual, broadcasting, and voting systems as well as integrate
peripheral sites that also have broadcast capability (e.g. Rinconada Library). After
receiving three responses to the Request for Proposals, staff determined Shalleck was
the most qualified firm, and the city entered into a professional services agreement with
them. Council approved staff’s recommendation to do so on 8/21/2017 – CMR ID
#8254.
Design
Shalleck produced three preliminary design options which staff reviewed to determine
the best fit for the City's needs and costs - CMR ID #8997. Staff recommended Design
Option 2.
Council directed staff to reduce the project’s cost and to explore an incremental
(phased) approach.
Phased Design Approach
Shalleck produced a prioritized 4-phase project approach to include the most essential
design items in Phase 1, then Phases 2 and 3 respectively. Items included in Phase 4
were determined to be optional and non-essential items.
Staff recommends combining Phases 1 and 2 the first year, followed by Phase 3 in the
second year.
Phase 1: $250,000
• Replace dais (Councilmember) screens/monitors, request to speak, and voting
system for functionality and reliability, as the system is no longer repairable
• Enable audience use of wireless assistive listening devices
• Install a height-adjustable lectern (public speaker) replacement for ADA
compliance and with speaker timer display
City of Palo Alto Page 3
Phase 2: $750,000
• Upgrade the broadcast system, with modern digital cameras, switcher,
captioning and supporting infrastructure
• Enable closed captioning capabilities
• Install new electrical system to accommodate upgraded audio visual (AV) devices
• Rebuild new control booth with HVAC
Phase 3: $750,000
• Upgrade the base audio system with speakers, wireless microphones, and
supporting infrastructure
• Install a dual screen & projector system, to display required 3 simultaneous
sources
• Install broadcast lighting system to optimize viewing and recording environment
• Install AV Control System for upgraded equipment
• Install skylight glare reduction film and motorized shades
• Demolition and infill of existing rear projection glass wall
Phase 4: $350,000 (Not recommended at this time).
• KZSU Radio desk system
• Audio Video links via network to (3) libraries & Media Center
• Glare reduction film at windows
• Motorized blackout shades
Discussion
Current Condition of Council Chambers Equipment and Facility
The current audio/visual (AV) and broadcast equipment in the Council Chambers have
exceeded their serviceable life and have been out of warranty since 2013. The outdated
analog hardware has no backup or redundant capabilities, and could lead to electrical
outages. A system failure would cease video streaming to the public, halt recording of
meeting content, and disrupt the general function of the Council meetings, Council
Standing Committee meetings, board and commission meetings, and meetings held by
outside agencies that use the equipment to record their meetings.
Outside agencies that routinely use the chambers and the audio/video equipment for
their meetings include; Congresswoman Eshoo (several times per year), SC County
Supervisor Simitian, Santa Clara County Planning Department, San Francisquito Creek
Joint Powers Board, North County Joint Recycled Water Board, Canopy, Palo Alto
Neighborhoods (PAN), Rotary Regional Speech Contest, administrative hearings such as
Edgewood Plaza citation hearings.
City of Palo Alto Page 4
Figure 1 – The existing equipment’s cables and wiring are cumbersome and difficult to
work with.
City Clerk staff reported to IT Service Desk on 11/14/18 that one of the projectors is
unable to maintain its resolution and display size. This remains an open request due to
the outdated nature of the equipment.
Council meeting recordings made in Council Chambers are low-quality, standard-
definition media that provide poor viewing quality for the public audience. In contrast,
HD recordings of meetings held at remote sites, using modern equipment, are far
superior in quality.
Figure 2 – Example of current recording capability of existing Council Chambers system,
resulting in low-quality standard-definition recordings with poor viewing quality.
City of Palo Alto Page 5
Figure 3 – Example of HD-quality recording of a meeting held at City’s Mitchell Park
venue, recorded using modern equipment.
On several occasions, City Clerk, IT staff, and/or contract support staff have had to
troubleshoot faulty audio/video equipment during Council meetings.
Figure 4 – Legacy wiring underneath the dais is a fire hazard to meeting members.
The large overhead Council Chambers display is low-quality standard definition, limited
to two simultaneous sources, mismatched in size, and the overall display quality is
greatly affected by variable lighting conditions due to time of day and season.
Information on the screens can be difficult to read unless a large font is used, which
limits how much information can be displayed at one time. Additionally, due to the
City of Palo Alto Page 6
current screen’s position and seating arrangement, audience seated to the right facing
towards the dais have a father viewing distance.
Figure 5 – Example no.1 of display with overhead glare from daylight.
Figure 6 – Example no. 2 of display with overhead glare due to daylight.
City of Palo Alto Page 7
The room where the projector equipment is located poses operational challenges due to
the slope of the floor.
Figure 7 – Rear-Projector Room
Figure 8 – Example of mismatched size displays, and the limitation to only two sources.
At the dais, the voting system is obsolete. There are no replacement parts for the
electrical components and electrical service providers are unable to service the system.
Similarly, the public speaking timer is outdated and in need of modernization.
City of Palo Alto Page 8
ADA Compliance
Technology and facilities Americans with Disabilities Act (ADA) compliance were
considered in the planning for this project. Based on Shalleck's report and
recommendation, the Building Official and Public Works Engineering determined a
number of accessibility improvements will be included in the project, while additional
improvements will be included in a planned future project coinciding with the Police
Department’s move to the planned Public Safety Building. These ADA implementation
items are included as essential items across all three design options.
Timeline
Milestones Completed
Date Description Notes
8/23/17 Project Kickoff
10/11/17 Completed all site visits including Mid-Peninsula Media Center
11/1/17 Three Design Options Delivered to Staff
2/21/18 Staff selection of Design Option 2 as recommendation to
Council
3/26/18 City Council Action - Resolution
Tentative Milestones
Date Description Notes
December 4, 2018 Recommendation to Finance
Committee
February 2019 Council Consideration of
Finance Committee
Recommendation
March - April 2019 Shalleck Design Process Phase 1 and 2
May - June 2019 RFP Procurement Process
August 2019 Council Approval of
Design/Build Contract
City of Palo Alto Page 9
September - December
2019
Contractor Design Process
February - July 2020 Phases 1 and 2 Construction
Period
TBD Phase 3
Resource Impact
Funding for the Council Chambers project is available in the Technology Fund and in the
Americans With Disabilities Act (ADA) Compliance capital project (PF-93003). The FY
2019-2023 Five Year Capital Improvement Plan has on average $147,000 allocated
annually to this project except for FY 2019 which has $608,000 appropriated. Finance
Committee and Council’s direction would be incorporated in the development of the
FY2020 Capital Budget and 5-year Plan. Preliminary project estimates are below; staff
recommends Phase 1 and 2 be completed in FY 2020.
Funding Source Phase 1 Phase 2 Phase 3 Est. Project
Total*
Technology Fund $200,000 $700,000 $650,000 $1,550,000
ADA Compliance Project** $50,000 $50,000 $100,000 $200,000
$250,000 $750,000 $750,000 $1,750,000
* Includes an assumption of 5% soft costs for items such as permit and inspection fees.
** Timing between Phases 1 & 2 contributions are estimates; in total Phases 1 and 2 are anticipated to
reach $100,000.
Policy Implications
This recommendation does not represent any change to existing City policies.
Environmental Review
This project is categorically exempt from California Environmental Quality Act (CEQA)
under Sections 15301 and 15302 of the CEQA guidelines as an alteration to an existing
facility and no further environmental review is necessary.