HomeMy WebLinkAboutStaff Report 5251 City of Palo Alto (ID # 5251) Finance Committee Staff Report Report Type: Action Items Meeting Date: 12/2/2014 City of Palo Alto Page 1 Summary Title: FY 2014 Year -End CIP Project Status Report Title: Fiscal Year 2014 Year -End Capital Improvement Program Project Status Report From: City Manager Lead Department: Administrative Services RECOMMENDATION Staff recommends that the Finance Committee review and accept the information on the City’s Capital Improvement Program contained in this report. BACKGROUND This report provides information on the status of the City’s Capital Improvement Program (CIP) projects as of the end of Fiscal Year (FY) 2014. The attached chart and matrices (Attachments A through D and Exhibit 1) list all CIP projects and their current status, and include any comments indicating a change in the scope or timing of the projects. The report is intended to update Council on the progress of all CIP projects that were open at the beginning of FY 2014, and on those that were added or completed during the fiscal year. The report also provides an update on the General Fund infrastructure strategy. DISCUSSION The following information provides detail for General Fund projects: o Chart depicting General Fund Capital Improvement Program Expenditures Summarized by Project Category for Fiscal Years 2010-2014 (Attachment A) o Supporting detail for General Fund Capital Improvement Program Expenditures by Project Category for Fiscal Years 2010-2014 (Exhibit 1) o Actual and planned General Fund Transfers to the Infrastructure Reserve for Fiscal Years 2010-2019 (Attachment B) The following information provides detail for all funds: o Fiscal Year 2014 Year-End Capital Improvement Program Project Status (Attachment C) o Continuous Capital Project Expenditures for Fiscal Years 2010-2014 (Attachment D) City of Palo Alto Page 2 In Attachments C and D, projects are listed by department for the General Fund and by fund for Enterprise and Internal Service Funds. CIP projects are further categorized into minor projects (projects that can be completed within a one-year period) and multi-year projects (projects that have multi-year budgets and/or complex implementation schedules with identifiable phases). In Attachment C, the city departments have submitted information on their projects and commented on any issues that might cause a change in the scope or timing of the projects. The project status portion of the matrix ident ifies the phase of the project at fiscal year-end, and illustrates how much progress was made. Three distinct phases are utilized, as follows: Phase Activities Pre-Design  Preparation of a feasibility study  Development of a master plan  Definition of a project scope  Preparation of an Environmental Impact Report Design  Hiring a design consultant  Completion of project design  Soliciting bids or proposals Construction  Acquisition of major equipment  Installation  Implementation of a project Attachment C includes information on the total budget of the project from inception, available budget as of the beginning of the fiscal year, fiscal year expenditures, fiscal year contingencies, fiscal year encumbrances, remaining balance in the project budget as of June 30, 2014, and the budget percent complete for the project. Attachment D lists all “continuous” projects. These projects, such as water meter replacement, have no definitive beginning or end dates and receive ongoing funding to reflect continuing replacement cycles or commitments. Continuous projects are listed by responsible department and fund and include five years of actual expenditures through June 30, 2014. Attachments C and D together represent all open CIP projects. RESOURCE IMPACT Following is a summary of the General Fund CIP budget through June 30, 2014. Total Adjusted Budget for FY 2014 $105,937,578 Less: Total Expenditures for FY 2014 (32,100,927) City of Palo Alto Page 3 Less: Total Encumbrances as of June 30, 2014 (27,767,838) Remaining balance of the budget carried over to FY 2015 $ 46,068,813 Continuing projects PG-13003 Golf Course Reconfiguration, PL-11002 California Avenue Transit Hub Corridor, and PE-12017 City Hall 1st Floor Renovations comprise a significant portion of the carry over amount. Actual expenditures for the past five fiscal years and budgeted expenditures for Fiscal Years 2015 to 2019 as projected in the Fiscal Year 2015 Adopted Capital Budget are depicted in the following chart: $16,342 $21,140 $26,655 $22,439 $25,184 $32,101 $30,068 $32,235 $30,601 $21,278 $0 $5,000 $10,000 $15,000 $20,000 $25,000 $30,000 $35,000 FY 2019 FY 2018 FY 2017 FY 2016 FY 2015 FY 2014 FY 2013 FY 2012 FY 2011 FY 2010 General Fund Capital Improvement Program Expenditures Fiscal Years 2010 -2014 Actual Fiscal Years 2015 -2019 Projected ($ in thousands) Projects that were completed but still had remaining appropriations as of FY 2014 were closed at the beginning of FY 2015 and the balances will be returned to the Infrastructure Reserve. Actual Capital Expenditures Projected Capital Expenditures City of Palo Alto Page 4 These projects are included in the year-end CMR ID #4962 “Close Budget and Approve CAFR for FY 2014” since Council approval is necessary to close them out. Below we have highlighted various General and Enterprise Funds projects: General Fund: PE-09006 Mitchell Park Library and Community Center Construction of the Mitchell Park Library & Community Center (MPL & CC) is complete and Certificate of Occupancy status was achieved. With a combined area of 56,000 square feet, this facility will offer a valuable space for the community to use a wide variety of library and community center services (such as a computer training room and a game room) in an outstanding environmentally friendly facility. Currently, library staff is busy moving into the new space and a grand opening date is set for December 6, 2014. PE-11000 Main (Rinconada) Library New Construction and Improvements The Main Library project is nearing completion of a major renovation and expansion, and is on schedule and within budget. The project incorporates upgrades to the historic building’s structural, electrical and mechanical systems while preserving the integrity of architect Edwards Durrell Stone’s iconic design. The renovation includes new additions to the existing building in order to accommodate a new program room for the library, group study rooms and new public restrooms. The project will be LED Certified and is the final library renovation approved by Bond Measure N in November 2008. FY 2014 accomplishments include installation of the new Program Room and completion of the new connectivity improvements between the Art Center and Main Library. Mechanical systems and electrical switchgear were completed in the basement and the general contractor also continued restoring the building interior finishes and replacing lighting in this historic structure. A Temporary Certificate of Occupancy was obtained in September 2014. During construction the facility underwent a renaming process and, with Council approval, will be known as Rinconada Library. PE-06007 Park Restroom Project A new restroom was installed and opened at Briones Park in south Palo Alto in October 2013. This project incorporated public art including a stamped concrete walkway and a mural on one of the outside walls. PE-10002 Ventura Community Center Open Space Renovation Projec t The Ventura Community Center Open Space area was renovated to provide a new accessible tot-lot playground, upgrades to the existing children’s playground equipment, resurfacing of the basketball courts, a new irrigation system, and new shade trees to coo l the asphalt recreation area. City of Palo Alto Page 5 PE-12012 Eleanor Pardee Park Renovation Project The renovation of Eleanor Pardee Park included the replacement of the asphalt walkway with a new wider concrete walkway, a new fully accessible tot-lot playground with swings, a new irrigation system for the entire park, and new site amenities such as benches, tables, bike racks and trash/recycle receptacles. The renovation project also reduced the amount of irrigated turf in the park, replacing turf areas with native plants for an estimated water savings of 85,000 gallons a year. PE-86070 Street Maintenance Program Beginning in 2011, the annual funding for streets was increased from $1.8 million to $3.8 million, and the FY 2014 five year budget plan increased the annual funding to $5.1 million. With this additional funding, the City has increased its average pavement condition index score (PCI) from 72 to 78, and is working toward a goal of reaching a City -wide average score of 85 by 2019. An additional $1 million was added to the streets program at the end of FY 2013, to address aging Portland Cement Concrete (PCC) streets. This project was completed in March 2014 and successfully repaired over 100,000 square feet of PCC streets. During FY 2014 over 35 lane miles (approximately 8% of the city) was resurfaced, including 10 blocks of Forest Avenue. PO-89003 Sidewalk Repairs Program Beginning in FY 2013 the funding for this project more than doubled with an additional $1 million per year allowing the project to accelerate progre ss for repairs in the City’s 23 Sidewalk Replacement Districts. The current 30-year cycle traversing the City (District by District) started in 1986 and the additional funding puts the City on track to meet the completion schedule. The additional $1 million added to the project in FY 2013 was used for a School Route Sidewalk Project to ensure that heavily used sidewalks surrounding Palo Alto schools are safe for student walking and bicycling. Safe Routes to School Program maps identified sidewalk routes that were evaluated and repaired within a one-half mile radius of each school. The School Route Sidewalk Project was completed in April 2014. Enterprise Funds:  Electric o Completed the $0.9 million Foothills Electric System Rebuild project to replace underground electric reaching the end of its useful life in the Foothills Park and Alexis Drive areas. o Completed the $0.5 million Site Security project (Phase III) involving the installation of cameras and sensors at Park, Quarry, Hansen Way, and Hanover Substations. o Completed the $1.0 million 4/12kV conversion of the distribution system in the Wilkie Way/Charleston Road area. o Completed the $2.0 million El Camino Real distribution system rebuild project that replaced electric facilities reaching the end of their useful life on El Camino Real from Arastradero Road to the Palo Alto/Mountain View city limit. City of Palo Alto Page 6 o Completed the $3.0 million project to replace the overhead conductor of the 60kV transmission line between Quarry and Park Blvd Substations. This increased ampacity, relieving possible overloads during emergency situations. o Completed the upgrade of relays and installation of line breakers at Adobe Creek Substation, installation of line switches at Hanover Substation, and upgrade of LTC controllers at Park Blvd Substation. o Completed over 280 customer service projects with a total cost of $2.8 million and revenue of $2.4 million. o The $2.2 million LED Streetlight Retrofit project (Phase III) is 95 percent complete. This work involves replacing 2,300 high pressure sodiu m light fixtures with LED light fixtures. o The $0.9 million project to upgrade the SCADA system is 95 percent complete. This is an upgrade of SCADA System hardware and software. The SCADA system is used for real time monitoring and alarming of electric, gas, and water systems.  Gas o $12.1 million contract for replacement of 68,811 linear feet of gas main pipe and 1,412 services with PE pipe is 95 percent complete. o Replacement of the regulating equipment of Gas Station 3 is complete. This completes the replacement of all four gas stations in the City of Palo Alto.  Water o $8.6 million contract for construction of the El Camino reservoir, pump station and well is complete. o $4.8 million contract for rebuilding the Mayfield Pump Station is complete. o $2.0 million contract for construction of the seismic retrofit of Mayfield reservoir is complete. o $2.6 million contract for rehabilitation of the five existing wells is 100 percent complete.  Wastewater o $4.0 million contract for the replacement of 30,960 linear feet of wastewater main pipe and 553 sewer laterals with PE pipe is complete. o $4.3 million contract to perform closed circuit TV scans of sanitary sewer laterals for the presence of gas crossbores is 70 percent complete. GENERAL FUND INFRASTRUCTURE UPDATE Infrastructure strategy and funding continues to be a top priority for the City Council. The Infrastructure Blue Ribbon Commission (IBRC) was created in October 2010 to identify and prioritize the City’s infrastructure needs and to determine funding source s and financing mechanisms to address the City’s backlog and future needs. The IBRC issued its final report, Palo Alto’s Infrastructure: Catching Up, Keeping Up, and Moving Ahe ad, in December 2011. The IBRC analyzed the City’ Infrastructure needs, and found that “keep -up” needs were City of Palo Alto Page 7 underfunded by over $2 million per year, a backlog of “catch -up” needs existed due to the chronic underfunding of infrastructure maintenance, and another $211 million was required for “new and replacement” needs, including a replacement of the public safety building, replacement of two fire stations, and various other transportation, parks and facility needs, including those funded through enterprise funds. As recommended by IBRC, the annual capital transfer from the General Fund was increased by $2.2 million starting in FY 2013. Further, an Infrastructure Committee comprised of four Council members was formed in February 2013 to refine and furth er evaluate infrastructure projects and financing mechanisms, with input from public opinion surveys. The Infrastructure Committee has refined the project list, reconciled it with the Five -Year Capital Improvement Plan (CIP Plan), and identified committed funding. In June 2014, City Council approved the Committee’s prioritized project list and a funding plan that includes dedicated Transient Occupancy Tax (TOT) revenues from new hotels, an increase in TOT from 12 percent to 14 percent (approved by the voters in November 2014), parking in-lieu fees, park impact fees, and funds from the Stanford University Medical Center development agreement. Additional sources include the Infrastructure Reserve and General Fund operating budget surpluses. Over the past three years, the General Fund has contributed $20.5 million of surplus funds to the Infrastructure Reserve, including $4.0 million in Fiscal Year 2014 In conclusion, the City Council has aggressively worked to improve the City’s infrastructure and continues to reiterate its commitment to addressing those needs, as demonstrated by the approval of the Infrastructure Plan in June 2014. FY 2016 CAPITAL BUDGET REAPPROPRIATION PROCESS In October 2014 the City Council approved an ordinance change regarding the reappropriation process for Capital projects. Prior to the change, capital project appropriations were automatically carried forward from one fiscal year to the next unless there were no dollars expended for two years. If no expenditures occurred within a two year period, reappropriations for Capital projects required City Council approval. With the Municipal Code change regarding the capital project reappropriation process, starting with FY 2016, all capital budget reappropriations require City Council approval. Also, the annual Capital budget only included projects for which dollars were added for the next fiscal year. Starting with FY 2016, the annual Capital budget will have a project detail page for all projects. Attachments:  Attachment A: GF CIP Expenditures By Project Category FY2010-2014 (XLSX)  Exhibit 1: Support for GF CIP Project Expenditures FY2010 -2014 (XLSX)  Attachment B: GF Transfers To IR FY2010-2019 (XLS)  Attachment C: FY14 YE Cap Improvement Project Status (PDF) City of Palo Alto Page 8  Attachment D: Continuous Capital Projects Expenditures FY2010-2014 (XLS) Attachment A Buildings & Facilities Streets & Sidewalks Parks & Open Space Land & Land Improvements Other FY 2010 9,312 5,855 3,460 2,353 298 FY 2011 20,250 7,422 1,731 98 1,100 FY 2012 23,868 6,977 1,113 17 259 FY 2013 14,040 12,748 1,480 460 1,340 FY 2014 17,935 10,546 2,898 80 642 0 2,000 4,000 6,000 8,000 10,000 12,000 14,000 16,000 18,000 20,000 22,000 24,000 26,000 General Fund Capital Improvement Program Expenditures Summarized by Project Category for Five Years: Fiscal Years 2010-2014 ($ in thousands) Page 1 of 1 11/25/2014 Exhibit 1 FY 2010 FY 2011 FY 2012 FY 2013 FY 2014 Project Project Project Expenditures Expenditures Expenditures Expenditures Expenditures Number Title Category AC-09001 Children's Theatre Replacement and Expansion Buildings and Facilities 5,019$ 4,581$ AC-09002 Community Theatre Sound System Replacement Buildings and Facilities 6,844 86,389 CC-09001 Dimmer Replacement and Lighting System Buildings and Facilities 995 7,611 4,609 11,266 149,191 CC-10000 Replacement of Cubberley Gym B Bleachers Buildings and Facilities 6,739 29,495 CC-11000 Cubberley Gym Activity Room Buildings and Facilities 58,041 FD-08001 Fire Station #6 Improvements Buildings and Facilities 8,061 48,110 271 PE-04012 Mitchell Park Library & Community Center Improvements Buildings and Facilities 123 PE-04014 Animal Shelter Expansion & Renovation Buildings and Facilities 61,539 General Fund Capital Improvement Program Expenditures by Project Category for Fiscal Years 2010-2014 Page 1 of 18 11/25/2014 Exhibit 1 FY 2010 FY 2011 FY 2012 FY 2013 FY 2014 Project Project Project Expenditures Expenditures Expenditures Expenditures Expenditures Number Title Category General Fund Capital Improvement Program Expenditures by Project Category for Fiscal Years 2010-2014 PE-05010 College Terrace Library Improvements Buildings and Facilities 1,545,763 846,020 7,344 4,600 PE-06001 San Antonio Bridge Structural Repairs & Maintenance Buildings and Facilities 494 82,782 PE-08005 Municipal Service Center Resurfacing Buildings and Facilities 326,898 PE-09003 City Facility Parking Lot Maintenance Buildings and Facilities 51,098 30,634 12,446 PE-09005 Downtown Library Improvements Buildings and Facilities 562,707 3,133,576 714,043 31,093 580 PE-09006 Mitchell Park Library & Community Center (New Construction) Buildings and Facilities 3,278,486 10,381,000 14,213,182 8,691,974 4,150,743 PE-09010 Library & Community Center Temporary Facilities Buildings and Facilities 518,623 110,020 2,205 412 PE-10002 Ventura Community Center and Park Buildings and Facilities 13,283 21,130 287,503 140,475 Page 2 of 18 11/25/2014 Exhibit 1 FY 2010 FY 2011 FY 2012 FY 2013 FY 2014 Project Project Project Expenditures Expenditures Expenditures Expenditures Expenditures Number Title Category General Fund Capital Improvement Program Expenditures by Project Category for Fiscal Years 2010-2014 PE-11000 Main Library New Construction and Improvements Buildings and Facilities 792,913 1,139,804 741,837 11,548,567 PE-11012 Temporary Main Library Buildings and Facilities 96,435 429,616 29,997 PE-12017 City Hall 1st Floor Buildings and Facilities 63,537 91,491 377,655 PE-14015 Lucie Stern Mechanical/Elecrical Upgrades Buildings and Facilities 219,686 PE-14018 Baylands Interpretive Center Improvements & Boardwalk Repair Buildings and Facilities 28,738 PE-98020 Public Safety Building Buildings and Facilities 175,289 30,910 14,943 7,252 17,143 PE-95030 Downtown Parking Structure Buildings and Facilities 469 PF-00006 Roofing Replacement Buildings and Facilities 251,344 104,617 319,495 246,068 119,682 Page 3 of 18 11/25/2014 Exhibit 1 FY 2010 FY 2011 FY 2012 FY 2013 FY 2014 Project Project Project Expenditures Expenditures Expenditures Expenditures Expenditures Number Title Category General Fund Capital Improvement Program Expenditures by Project Category for Fiscal Years 2010-2014 PF-01002 Civic Center Infrastructure Improvements Buildings and Facilities 1,344,006 3,803,962 1,950,609 423,121 344,298 PF-01003 Building Systems Improvements Buildings and Facilities 36,098 74,876 59,798 34,320 150,878 PF-01004 Fire Station Improvements Buildings and Facilities 237,018 394 PF-02022 Facility Interior Finishes Buildings and Facilities 11,076 23,874 234,085 70,609 390,667 PF-04000 Security System Improvements Buildings and Facilities 3,581 PF-04010 Cubberley Mechanical & Electrical Upgrades Buildings and Facilities 9,369 PF-05002 Municipal Service Center Renovation Buildings and Facilities 3,530 12,176 PF-05003 Foothills Park Interpretive Center Improvements Buildings and Facilities 1,290 12,897 141,633 7,869 36,063 Page 4 of 18 11/25/2014 Exhibit 1 FY 2010 FY 2011 FY 2012 FY 2013 FY 2014 Project Project Project Expenditures Expenditures Expenditures Expenditures Expenditures Number Title Category General Fund Capital Improvement Program Expenditures by Project Category for Fiscal Years 2010-2014 PF-06004 Cubberley Restroom Renovation Buildings and Facilities 27,422 3,129 11,849 86 PF-07000 Art Center Electrical & Mechanical Upgrades Buildings and Facilities 234,143 543,877 4,628,983 2,418,160 5,223 PF-07001 ADA Compliance - Cubberley Community Center Buildings and Facilities 205,388 PF-07003 Children's Theatre Fire/Life Safety Upgrade Buildings and Facilities 7,592 6,150 131 PF-07011 Roth Building Maintenance Buildings and Facilities 3,729 1,205 PF-08000 Art Center Kiln Hood Replacement Buildings and Facilities 14,570 PF-09000 Children's Theatre Improvements Buildings and Facilities 30,199 52,172 PF-09002 Lucie Stern Community Center and Theatre Exterior Paint Buildings and Facilities 4,510 90,816 Page 5 of 18 11/25/2014 Exhibit 1 FY 2010 FY 2011 FY 2012 FY 2013 FY 2014 Project Project Project Expenditures Expenditures Expenditures Expenditures Expenditures Number Title Category General Fund Capital Improvement Program Expenditures by Project Category for Fiscal Years 2010-2014 PF-10000 Civic Center Chiller Drive Replacement Buildings and Facilities 72,380 PF-10001 Rinconada Pool Plaster Buildings and Facilities 117,756 PF-10002 Lot "J" Cowper/Webster Structural Repairs Buildings and Facilities 23,682 15,260 32,672 448,804 PF-14000 Cubberley Roof Replacements Buildings and Facilities 1,489 PF-14002 Fire Station 1 Improvements Buildings and Facilities 820 PF-14003 University Avenue Parking District Parking Improvements Buildings and Facilities 51,117 PF-93009 ADA Compliance Buildings and Facilities 235,410 9,994 167,537 10,019 16,024 Total Buildings and Facilities 9,311,891$ 20,250,843$ 23,867,878$ 14,040,559$ 17,934,710$ Page 6 of 18 11/25/2014 Exhibit 1 FY 2010 FY 2011 FY 2012 FY 2013 FY 2014 Project Project Project Expenditures Expenditures Expenditures Expenditures Expenditures Number Title Category General Fund Capital Improvement Program Expenditures by Project Category for Fiscal Years 2010-2014 AC-86017 Art in Public Places Land and Land Improvements 17,256$ 77,956$ 17,171$ 59,526$ 80,497$ AS-08000 Acquisition of Los Altos Treatment Plant Land and Land Improvements 2,252,250 400,000 AS-09000 City of Palo Alto Municipal Airport Transition Project Land and Land Improvements 67,775 4,050 PE-09004 Los Altos Treatment Plant Master Plan Study Land and Land Improvements 15,468 16,278 Total Land and Land Improvements 2,352,749$ 98,284$ 17,171$ 459,526$ 80,497$ FD-09001 Fire Apparatus Equipment Replacement Miscellaneous 261,283$ FD-12000 ALS EKG Monitor Replacement Miscellaneous 517,914 92,966$ Page 7 of 18 11/25/2014 Exhibit 1 FY 2010 FY 2011 FY 2012 FY 2013 FY 2014 Project Project Project Expenditures Expenditures Expenditures Expenditures Expenditures Number Title Category General Fund Capital Improvement Program Expenditures by Project Category for Fiscal Years 2010-2014 LB-11000 Furniture & Technology for Measure N Project Miscellaneous 28,124 178,774 531,457 449,827 PE-12002 Tree Wells - University Avenue Irrigation Miscellaneous 28,743 152,993 37,553 PE-12004 Municipal Services Center Facilities Study Miscellaneous 220 PE-12009 Alma Guardrail Miscellaneous 5,888 34,353 397 PD-08000 Crime Scene Evidence Collection Vehicle Miscellaneous 174,201 6,039 PF-12004 Citywide Backflow Preventer Installations Miscellaneous 95,643 PO-10002 Downtown Tree Grates Miscellaneous 29,879 8,136 PO-12002 LATP Site Development Preparation & Security Miscellaneous 8,636 7,668 61,147 Total Miscellaneous 291,162$ 210,461$ 228,300$ 1,340,028$ 641,890$ Page 8 of 18 11/25/2014 Exhibit 1 FY 2010 FY 2011 FY 2012 FY 2013 FY 2014 Project Project Project Expenditures Expenditures Expenditures Expenditures Expenditures Number Title Category General Fund Capital Improvement Program Expenditures by Project Category for Fiscal Years 2010-2014 FD-05000 Sixteen (16) ALS Monitors Non-Infrastructure Management Plan 434$ PD-07000 Mobile Command Vehicle Non-Infrastructure Management Plan 695,337 PE-05001 Photovoltaic Design and Installations Non-Infrastructure Management Plan 6,448 PE-07011 Library Service Model Analysis Non-Infrastructure Management Plan PL-05002 Charleston/Arastradero Corridor Plan Non-Infrastructure Management Plan 193,613 26,988$ PL-06002 Comprehensive Parking Signage Plan Non-Infrastructure Management Plan 4,248 Total Non-Infrastructure Management Plan 6,448$ 889,384$ 31,236$ -$ -$ Page 9 of 18 11/25/2014 Exhibit 1 FY 2010 FY 2011 FY 2012 FY 2013 FY 2014 Project Project Project Expenditures Expenditures Expenditures Expenditures Expenditures Number Title Category General Fund Capital Improvement Program Expenditures by Project Category for Fiscal Years 2010-2014 AC-10000 Junior Museum & Zoo New Bobcat Habitat Parks and Open Space 101,790$ 23,210$ AC-12001 Junior Museum & Zoo Perimeter Fence and Footpath Parks and Open Space 31,101 OS-00001 Open Space Trails and Amenities Parks and Open Space 97,766 47,473 162,466 125,150 93,274$ OS-00002 Open Space Lakes & Ponds Maintenance Parks and Open Space 63,263 54,097 24,615 15,000 35,000 OS-07000 Foothills Park Road Improvements Parks and Open Space 150,000 OS-09001 Off-Road Pathway Resurfacing and Repair Parks and Open Space 24,719 4,130 13,248 52,060 OS-09002 Baylands Emergency Access Levee Repair Parks and Open Space 54,098 Page 10 of 18 11/25/2014 Exhibit 1 FY 2010 FY 2011 FY 2012 FY 2013 FY 2014 Project Project Project Expenditures Expenditures Expenditures Expenditures Expenditures Number Title Category General Fund Capital Improvement Program Expenditures by Project Category for Fiscal Years 2010-2014 PE-00110 College Terrace Park Improvements Parks and Open Space 522 PE-06005 University Avenue Gateway Landscaping Improvements Parks and Open Space 6,709 1,479 429 486 PE-06007 Park Restroom Installation Parks and Open Space 100,096 224,048 98,119 147,865 132,515 PE-07005 California Avenue Improvements Parks and Open Space 465,324 53,810 PE-07007 Cubberley Turf Renovation Parks and Open Space 969,963 PE-08001 Rinconade Park Improvements Parks and Open Space 2,591 PE-08004 Lytton Plaza Renovation Parks and Open Space 725,733 2,545 11,793 11,570 3,542 PE-09002 Greer Park Phase IV Parks and Open Space 515,091 925,076 142,030 8,078 Page 11 of 18 11/25/2014 Exhibit 1 FY 2010 FY 2011 FY 2012 FY 2013 FY 2014 Project Project Project Expenditures Expenditures Expenditures Expenditures Expenditures Number Title Category General Fund Capital Improvement Program Expenditures by Project Category for Fiscal Years 2010-2014 PE-12003 Rinconada Park Master Plan & Design Parks and Open Space 121,690 118,299 36,125 PE-12012 Eleanor Pardee Park Improvements Parks and Open Space 21,827 26,641 657,659 PE-12013 Magical Bridge Playground Parks and Open Space 129,237 92,606 134,795 PE-13003 Parks Master Plan Parks and Open Space 29,193 120,719 PE-13005 City Hall/King Plaza Landscape Parks and Open Space 1,337 72,956 PE-13007 El Camino Park Dog Park Parks and Open Space 977 2,117 PE-13008 Bowden Park Improvements Parks and Open Space 36,961 PE-13010 Greer Park Renovations Parks and Open Space 1,896 58,589 Page 12 of 18 11/25/2014 Exhibit 1 FY 2010 FY 2011 FY 2012 FY 2013 FY 2014 Project Project Project Expenditures Expenditures Expenditures Expenditures Expenditures Number Title Category General Fund Capital Improvement Program Expenditures by Project Category for Fiscal Years 2010-2014 PE-13016 El Camino Park Expanded Parking Lot and New Restroom Parks and Open Space 8,886 33,976 PE-13020 Byxbee Park Trails Parks and Open Space 21,374 4,625 PE-14010 LATP Site Development Preparation & Security Improvements Parks and Open Space 9,764 PF-12001 Parks and PWD Trees Work Space Improvements Parks and Open Space 836 7,515 371,406 PG-06001 Tennis and Basketball Court Resurfacing Parks and Open Space 100,159 77,512 53,635 506 PG-06003 Benches, Signage, Fencing, Walkways, and Perimeter Landscaping Parks and Open Space 73,480 118,366 105,225 168,788 242,964 PG-09002 Park and Open Space Emergency Repairs Parks and Open Space 50,883 147,651 52,875 42,793 100,044 PG-09003 Park Maintenance Shop Remodel Parks and Open Space 2,858 55,414 2,244 3,760 Page 13 of 18 11/25/2014 Exhibit 1 FY 2010 FY 2011 FY 2012 FY 2013 FY 2014 Project Project Project Expenditures Expenditures Expenditures Expenditures Expenditures Number Title Category General Fund Capital Improvement Program Expenditures by Project Category for Fiscal Years 2010-2014 PG-11000 Hopkins Park Improvements Parks and Open Space 4,100 8,400 PG-11001 Cogswell Plaza Improvements Parks and Open Space 11,123 134,635 PG-11002 Monroe Park Improvements Parks and Open Space 3,200 794 PG-11003 Scott Park Improvements Parks and Open Space 618 PG-12002 Golf Course Tree Maintenance Parks and Open Space 21,014 3,597 PG-13002 El Camino Park Playing Fields and Amenities Parks and Open Space 314,994 PG-98001 School Site Irrigation Parks and Open Space 161,399 PG-13003 Golf Reconfiguring Parks and Open Space 406,950 367,478 Page 14 of 18 11/25/2014 Exhibit 1 FY 2010 FY 2011 FY 2012 FY 2013 FY 2014 Project Project Project Expenditures Expenditures Expenditures Expenditures Expenditures Number Title Category General Fund Capital Improvement Program Expenditures by Project Category for Fiscal Years 2010-2014 Total Parks and Open Space 3,459,755$ 1,730,681$ 1,113,288$ 1,480,052$ 2,897,563$ PE-00104 San Antonio Road Median Improvements Streets and Sidewalks 239,404$ 142,556$ 676,384$ 314,834$ 58,823$ PE-06006 Alma Street Landscape Improvements Streets and Sidewalks 26,371 PE-10006 Bridge Rail, Abutment, and Deck Repair Streets and Sidewalks 167,062 PE-11011 Highway 101 Pedestrian / Bicycle Overcrossing Streets and Sidewalks 36,385 194,020 115,011 263,479 270,055 PE-12011 Newell Road Bridge / San Francisquito Creek Bridge Replacement Streets and Sidewalks 55,715 328,933 163,774 PE-13011 Charleston/Arastradero Corridor Project Streets and Sidewalks 32,880 106,656 Page 15 of 18 11/25/2014 Exhibit 1 FY 2010 FY 2011 FY 2012 FY 2013 FY 2014 Project Project Project Expenditures Expenditures Expenditures Expenditures Expenditures Number Title Category General Fund Capital Improvement Program Expenditures by Project Category for Fiscal Years 2010-2014 PE-13022 University Avenue Pedestrian/Bicycle Underpass Rehabilitation Streets and Sidewalks 178,901 PE-86070 Street Improvements (Street Improvement Fund) Streets and Sidewalks 3,658,566 5,110,791 3,170,679 7,097,782 5,072,597 PL-00026 Safe Routes to School Streets and Sidewalks 30,000 20,750 87,321 294,601 439,395 PL-04010 Bicycle Transportation Plan Implementation Project Streets and Sidewalks 30,000 80,862 103,599 57,921 135,827 PL-05003 College Terrace Traffic Calming Streets and Sidewalks 545 PL-05030 Traffic Signal Upgrades Streets and Sidewalks 279,590 183,141 244,272 385,302 290,944 PL-07002 El Camino Real/ Stanford Intersection Streets and Sidewalks 4,790 247,112 341,683 963,546 PL-11001 Dinah SummerHill Pedestrian/Bicycle Path Streets and Sidewalks 188,187 2,845 6,853 Page 16 of 18 11/25/2014 Exhibit 1 FY 2010 FY 2011 FY 2012 FY 2013 FY 2014 Project Project Project Expenditures Expenditures Expenditures Expenditures Expenditures Number Title Category General Fund Capital Improvement Program Expenditures by Project Category for Fiscal Years 2010-2014 PL-11002 California Avenue Transit Hub Corridor Streets and Sidewalks 16,361 81,210 573,960 PL-11003 Palo Alto Traffic Signal Central System Streets and Sidewalks 35,528 PL-11004 Alma Street Traffic Signal Improvements Streets and Sidewalks 645 PL-12000 Transportation and Parking Improvements Streets and Sidewalks 91,002 292,854 579,002 PL-14000 El Camino Real and Churchill Avenue Intersection Improvements Streets and Sidewalks 8,225 PL-98013 School Commute Safety Improvements (SIF) Streets and Sidewalks 6,170 PO-05054 Street Light Improvements Streets and Sidewalks 40,430 159,070 61,844 69,707 74,636 PO-11000 Sign Reflectivity Upgrade Streets and Sidewalks 20,792 136,380 2,029 Page 17 of 18 11/25/2014 Exhibit 1 FY 2010 FY 2011 FY 2012 FY 2013 FY 2014 Project Project Project Expenditures Expenditures Expenditures Expenditures Expenditures Number Title Category General Fund Capital Improvement Program Expenditures by Project Category for Fiscal Years 2010-2014 PO-11001 Thermoplastic Lane Marking and Striping Streets and Sidewalks 29,639 127,958 74,614 82,332 PO-12000 Wilkie Way Bridge Deck Replacement Streets and Sidewalks 37,944 PO-12001 Curb and Gutter Repairs Streets and Sidewalks 1,851 287,582 368,699 PO-12003 Foothills Fire Management Streets and Sidewalks 19,884 113,723 PO-89003 Sidewalk Improvements Streets and Sidewalks 1,341,916 1,211,917 1,673,715 1,864,954 2,160,793 Total Streets and Sidewalks 5,855,059$ 7,421,556$ 6,977,019$ 12,748,209$ 10,546,267$ Grand Total 21,277,064$ 30,601,209$ 32,234,892$ 30,068,374$ 32,100,927$ Page 18 of 18 11/25/2014 Attachment B Budgeted Transfer to Infrastructure Surplus Transfer to Infrastructure Return to General Fund Net Amount Fiscal Year (000's)(000's)(000's)(000's) 2010 9,900 0 3,243 6,657 2011 9,857 0 9,857 2012 11,044 7,600 a 18,644 2013 13,357 8,900 b 22,257 2014 13,235 4,000 c 17,235 2015 13,659 0 13,659 2016 14,000 0 14,000 2017 14,351 0 14,351 2018 14,709 0 14,709 2019 15,077 0 15,077 Total 129,189$ 20,500$ 3,243$ 146,446$ Notes:a. One-time transfer of $7.6 million to reduce GF BSR to 18.5 percent target level b. One-time transfer of $8.9 million to reduce GF BSR to 19.0 percent target level c. One-time transfer of $4.0 million to reduce GF BSR to 20.5 percent target level Sources:FY 2010 through 2014 are actual amounts FY 2015 through 2019 based on FY 2015 Adopted Capital Budget 6,657 9,857 18,644 22,257 17,235 13,659 14,000 14,351 14,709 15,077 5,000 7,000 9,000 11,000 13,000 15,000 17,000 19,000 21,000 23,000 25,000 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 $000 Fiscal Year General Fund Transfers to Infrastructure Reserve for Fiscal Years 2010-2019 (000's) Page 1 of 1 11/25/2014 Attachment C Total Budget FY 2014 FY 2014 FY 2014 FY 2014 FY 2014 Estimated Project Project Project From Available Expenditures Labor Contingencies Encumbrances Remaining Percent Project Completion Number Title Category Inception Budget Adjustments Balance Complete Status Date Comments AC-09001 Children's Theatre Replacement and Expansion Buildings and Facilities $107,600 $102,581 $4,581 $0 $0 $98,000 $0 100% Construction Dec 14 Construction began in May 2014 for installation of a theatrical audio system, inclusive of an assisted listening system. AC-09002 Community Theater Sound System Replacement Buildings and Facilities $200,000 $193,156 $86,389 $0 $0 $86,107 $20,660 90% Construction Oct 14 Construction began in May 2014 for installation of a theatrical audio system, inclusive of an assisted listening system. CC-09001 Dimmer Replacement and Lighting System Buildings and Facilities $180,651 $160,780 $135,671 $13,085 $435 $11,565 $24 100% Complete OS-09002 Baylands Emergency Access Levee Repair Parks and Open Space $175,000 $120,902 $0 $0 $0 $0 $120,902 31% Design Sep 14 Design and EIR complete. Project now independent of JPA and will no longer be paired with JPA flood control project. PG-09003 Park Maintenance Shop Remodel Parks and Open Space $159,096 $94,419 $0 $0 $0 $0 $94,419 41% Complete PG-11000 Hopkins Park Improvements Parks and Open Space $95,000 $90,900 $8,400 $0 $0 $0 $82,500 13% Design Jan 15 Design complete and going out to bid scheduled for Oct 2014. PG-11002 Monroe Park Improvements Parks and Open Space $250,000 $246,800 $794 $0 $0 $9,300 $236,706 5% Design Feb 15 Landscape architect hired for planning and development of scope of contract. Scheduled to go out to bid Nov 2014. PG-11003 Scott Park Improvements Parks and Open Space $100,000 $100,000 $618 $0 $0 $0 $99,382 1% Design Jan 15 Design complete (paid under PG-06003). Going out to bid scheduled for Nov 2014. PG-12001 Stanford / Palo Alto Playing Field Netting Parks and Open Space $50,000 $50,000 $0 $0 $0 $0 $50,000 0% Design TBD Project to be done concurrently with project PG-13001 Stanford Palo Alto Soccer Turf Replacement PG-12002 Golf Course Tree Maintenance Parks and Open Space $43,597 $43,597 $3,597 $0 $0 $0 $40,000 N/A Ongoing TBD Funds for this CIP are not expended due to golf course renovations. Funds for this CIP will be moved into Golf's Operating budget. PG-12004 Sarah Wallis Park Improvements Parks and Open Space $65,000 $65,000 $0 $0 $0 $28,358 $36,642 44% Pre-Design TBD Staff in initial planning and development of scope of contract. PG-12005 Relocate Power Poles for Soccer Field Parks and Open Space $0 $0 $0 $0 $0 $0 $0 0% Design TBD Project cancelled. OS-00001 Open Space Trails & Amenities Parks and Open Space $2,266,209 $346,914 $51,934 $41,340 $0 $168,808 $84,832 N/A Ongoing TBD Various trail improvements at Arastradero, Foothills Park, and Baylands in year 3 of 3. OS-00002 Open Space Lakes & Ponds Maintenance Parks and Open Space $442,183 $49,920 $35,000 $0 $0 $0 $14,920 N/A Ongoing TBD In year 3 of 3 year contract for maintenance of Boronda Lake with new bids anticipated in Oct 2014. MULTI-YEAR PROJECTS FY 2014 YEAR-END CAPITAL IMPROVEMENT PROGRAM PROJECTS STATUS GENERAL FUND COMMUNITY SERVICES DEPARTMENT MINOR PROJECTS Page 1 of 26 Budget Attachment C Total Budget FY 2014 FY 2014 FY 2014 FY 2014 FY 2014 Estimated Project Project Project From Available Expenditures Labor Contingencies Encumbrances Remaining Percent Project Completion Number Title Category Inception Budget Adjustments Balance Complete Status Date Comments FY 2014 YEAR-END CAPITAL IMPROVEMENT PROGRAM PROJECTS STATUS GENERAL FUND COMMUNITY SERVICES DEPARTMENT OS-09001 Off-Road Pathway Resurfacing and Repair Parks and Open Space $326,357 $313,109 $52,060 $0 $0 $1,250 $259,799 N/A Ongoing TBD Work is now done in-house by Public Works Engineering or combined with their paving contracts. PG-06001 Tennis & Basketball Court Resurfacing Parks and Open Space $741,443 $250,112 $0 $0 $0 $0 $250,112 N/A Ongoing TBD Staff in planning for new bids in Feb 2015. Schedule to be reworked to increase number of courts and scope to reconstruct courts, not just resurfacing due to additional funding. PG-06003 Benches, Signage, Fencing, Walkways, and Perimeter Landscaping Parks and Open Space $828,643 $303,055 $187,384 $38,967 $16,613 $58,227 $1,864 N/A Ongoing TBD Recent projects completed: Site Amenities: King Plaza site furniture trash receptacles and site furniture, Lucie Stern trash receptacle fabrication, Lucie Stern Brick Pathway design. Signage: Signage at Palo Alto Baylands and Duck Pond. PG-09002 Park and Open Space Emergency Repairs Parks and Open Space $417,761 $125,369 $100,044 $0 $0 $9,236 $16,089 N/A Ongoing TBD Recent projects completed: Playground equipment replacement at Cameron, Wery and Rinconada Parks, Mitchell Park tennis court repairs, Mitchell Park rope climber repairs, Baylands sailing station dock repairs. PG-13001 Stanford / Palo Alto Soccer Turf Replacement Parks and Open Space $725,000 $725,000 $0 $0 $0 $0 $725,000 0% Pre-Design Apr 15 Staff in initial planning and development of scope of contract. PG-13002 El Camino Park Playing Fields and Amenities Parks and Open Space $3,538,700 $3,538,700 $211,580 $103,414 $0 $0 $3,223,706 9% Design Nov 15 Project will be combined with parking lot and restroom projects for this park. Completion of park is expected Nov 2015. PG-13003 Golf Reconfiguring Parks and Open Space $11,258,312 $10,851,361 $158,047 $121,901 $87,530 $10,982 $10,472,901 7% Construction Sep 16 Design complete. Start of construction delayed pending resolution of permitting issues with SF Creek JPA Flood Protection Project. Page 2 of 26 Budget Attachment C Total Budget FY 2014 FY 2014 FY 2014 FY 2014 FY 2014 Estimated Project Project Project From Available Expenditures Labor Contingencies Encumbrances Remaining Percent Project Completion Number Title Category Inception Budget Adjustments Balance Complete Status Date Comments FD-14002 Fire Ringdown System Replacement Buildings and Facilities $157,500 $157,500 $0 $0 $0 $0 $157,500 0% Pre-Design Dec 15 FD-12000 ALS EKG Monitor Replacement Miscellaneous $610,884 $92,970 $92,966 $0 $0 $0 $4 100% Complete The project will be closed. FD-13000 Long Range CCTV Cameras Miscellaneous $65,000 $65,000 $0 $0 $0 $0 $65,000 N/A Ongoing TBD The Fire Department is currently evaluating several Thermal Imaging Cameras. FY 2014 YEAR-END CAPITAL IMPROVEMENT PROGRAM PROJECTS STATUS GENERAL FUND FIRE DEPARTMENT MULTI-YEAR PROJECTS MINOR PROJECTS Page 3 of 26 Budget Attachment C Budget FY 2014 FY 2014 Estimated Project Project Project From Available FY 2014 Labor FY 2014 FY 2014 Remaining Percent Project Completion Number Title Category Inception Budget Expenditures Adjustments Contingencies Encumbrances Balance Complete Status Date Comments PD-14000 Internal Alarm System Replacement Buildings and Facilities $78,000 $78,000 $0 $0 $0 $0 $78,000 0% Pre-Design Oct 15 Totals $78,000 $0 $0 $0 $0 $78,000 FY 2014 YEAR-END CAPITAL IMPROVEMENT PROGRAM PROJECTS STATUS GENERAL FUND POLICE DEPARTMENT MINOR PROJECTS Page 4 of 26 Budget Attachment C Total Budget FY 2014 FY 2014 FY 2014 FY 2014 FY 2014 Estimated Project Project Project From Available Expenditures Labor Contingencies Encumbrances Remaining Percent Project Completion Number Title Category Inception Budget Adjustments Balance Complete Status Date Comments LB-11000 Furniture & Technology for Library Measure N Project Miscellaneous $2,471,000 $1,732,645 $449,287 $0 $540 $341,555 $941,263 62% Construction Feb 15 Project activity is being coordinated with the construction schedule of the Mitchell Park Library & Community Center and Main Library Measure N building renovations. FY 2014 YEAR-END CAPITAL IMPROVEMENT PROGRAM PROJECTS STATUS GENERAL FUND LIBRARY SERVICES DEPARTMENT MULTI-YEAR PROJECTS Page 5 of 26 Budget Attachment C Total Budget FY 2014 FY 2014 FY 2014 FY 2014 FY 2014 Estimated Project Project Project From Available Expenditures Labor Contingencies Encumbrances Remaining Percent Project Completion Number Title Category Inception Budget Adjustments Balance Complete Status Date Comments PL-11001 Dinah SummerHill Pedestrian Bicycle Path Streets and Sidewalks $309,101 $122,906 $0 $6,853 $0 $0 $116,053 62% Construction Jul 15 Design is complete. Project will be reviewed bt PTC in Dec 2014, followed by ARB and City Council in Spring 2015. PL-14000 El Camino Real and Churchill Avenue Intersection Impovements Streets and Sidewalks $283,651 $283,651 $8,225 $0 $0 $266,775 $8,651 97% Design Dec 15 Design began in Spring 2014 and is currently underway. PL-00026 Local and Neighborhood Collector Street Traffic Calming Program (SIF) ("Safe Routes To Schools") Streets and Sidewalks $1,427,541 $618,779 $384,041 $55,354 $0 $178,569 $815 N/A Ongoing TBD This ongoing CIP implements traffic calming improvements along Residential Arterial Streets and funds the development of Safe Routes to School Programs and Projects at schools. PL-04010 Bicycle and Pedestrian Transportation Plan Implementation Project Streets and Sidewalks $1,541,149 $1,260,284 $114,512 $0 $21,315 $885,257 $239,200 N/A Ongoing TBD This ongoing CIP implements project recommendations from the City's Bike/Ped Transportation Plan. PL-11002 California Avenue Transit Hub Corridor Streets and Sidewalks $6,873,206 $6,775,943 $564,311 $9,649 $0 $1,615,111 $4,586,872 33% Construction Mar 15 Construction is underway. Outreach and coordination with merchants continues as contractor completes each block. PL-11003 Palo Alto Traffic Signal Central System Streets and Sidewalks $400,000 $364,472 $0 $0 $0 $0 $364,472 9% Design Jun 15 In May 2014 an RFQ was released for the upgrading of traffic signal technologies and cabinetry. In Nov 2014 staff expects to ask for Council authorization to approve a contract for implementation. PL-12000 Transportation and Parking Improvements Streets and Sidewalks $1,266,556 $973,701 $577,445 $1,557 $0 $394,074 $625 N/A Ongoing N/A Requests for Proposals for online permit sales and parking access controls and guidance systems to be released in Oct 2014. Residential parking program and additional transportation projects are in the studying and planning stages. PL-14001 Matadero Creek Trail Streets and Sidewalks $383,651 $383,651 $0 $0 $0 $369,446 $14,205 96% Design Jun 17 Project design began in Spring 2014. FY 2014 YEAR-END CAPITAL IMPROVEMENT PROGRAM PROJECTS STATUS GENERAL FUND PLANNING AND COMMUNITY ENVIRONMENT DEPARTMENT MINOR PROJECTS MULTI-YEAR PROJECTS Page 6 of 26 Budget Attachment C Total Budget FY 2014 FY 2014 FY 2014 FY 2014 FY 2014 Estimated Project Project Project From Available Expenditures Labor Contingencies Encumbrances Remaining Percent Project Completion Number Title Category Inception Budget Adjustments Balance Complete Status Date Comments PE-08004 Lytton Plaza Renovation Parks and Open Space $777,668 $5,042 $3,542 $0 $0 $0 $1,500 100% Complete Project to be closed. PE-11011 Highway 101 Pedestrian/Bicycle Overcrossing Streets and Sidewalks $2,205,232 $1,707,983 $92,275 $177,780 $0 $14,113 $1,423,815 35%Pre-Design Nov 15 The feasibility study was completed in Nov 2011. Preliminary Engineering and Environmental assessment is in progress. Staff is working with Caltrans on various environmental studies as part of the Grant funding requirement. Council directed staff to implement a design competition for the project. PE-12002 Tree Wells - University Avenue Irrigation Miscellaneous $194,845 $41,852 $21,460 $10,970 $5,123 $0 $4,299 100% Complete Project to be closed. PE-12003 Rinconada Park Long Range Plan & Design Parks and Open Space $225,893 $49,352 $10,833 $25,292 $0 $7,000 $6,227 97% Design Aug 15 Project is in environmental review phase to be completed for council approval in Aug 2015. PE-12004 Municipal Services Center Facilities Study Miscellaneous $249,780 $249,780 $0 $0 $0 $0 $249,780 0% Pre-Design TBD Scope of services for specialized consultant support has been drafted, but project on hold given other project priorities and uncertainty regarding potential future use of the Los Altos Treatment Plant site. PE-12009 Alma Guardrail Miscellaneous $40,871 $629 $0 $397 $0 $0 $232 100% Complete Project to be closed. PE-12013 Magical Bridge Playground Parks and Open Space $3,454,665 $3,297,869 $66,575 $68,220 $0 $52,892 $3,110,182 10% Construction Jan 15 Construction of playground currently underway. PE-12017 City Hall First Floor Renovations Buildings and Facilities $4,087,633 $3,996,139 $235,306 $142,349 $0 $200,908 $3,417,576 16% Construction Feb 15 Contract awarded in Jun 2014. Chambers carpet and upholstery to be replaced during Council break in July. Other work to be phased through Feb 2015. PE-13003 Parks Master Plan Parks and Open Space $566,947 $537,754 $32,965 $87,754 $0 $343,700 $73,335 87% Design Sep 15 Master Plan Process underway. Expected Council approval of the plan in Sept 2015. PE-13008 Bowden Park Improvements Parks and Open Space $357,595 $357,595 $11,366 $25,595 $0 $33,062 $287,572 20% Design Jun 15 City Council Park Improvement Ordinance needs to occur and construction bidding of project is expected Feb/Mar 2015. PE-13010 Greer Park Renovations Parks and Open Space $318,562 $316,666 $27,288 $16,666 $14,635 $0 $258,077 19% Construction May 15 Pathway project to be completed by Nov 2015. Skatebowl renovation in design phase with expected construction in Spring 2015. PE-13012 Structural Assessment of City Bridges Streets and Sidewalks $185,394 $185,394 $0 $0 $0 $0 $185,394 0% Pre-Design Feb 15 Scope and inventory of bridges completed. RFP scheduled for Summer 2014. PE-13014 Streetlight Condition Assessment Streets and Sidewalks $220,078 $220,078 $0 $0 $0 $0 $220,078 0% Pre-Design Jun 15 Scope of work is being prepared and expect consultant to start work in Jan 2015. PE-13016 El Camino Park Expanded Parking Lot and New Restroom Parks and Open Space $1,002,860 $993,975 $0 $33,976 $0 $0 $959,999 4% Design Sep 15 Project is currently in the design building permit phase with the start of construction expected to be in early 2015. PE-13020 Byxbee Park Trails Parks and Open Space $360,607 $339,233 $0 $4,625 $0 $64,471 $270,137 25% Design Dec 14 RFP for design services is being released. This project is being jointly managed by PWD Environmental Services and CSD Open Space. PE-14010 LATP Site Development Preparation & Security Improvements Parks and Open Space $1,668,782 $1,668,782 $5,840 $3,924 $0 $171,927 $1,487,091 11% Pre-Design TBD Wetland regulatory issues stalled progress on the former treatment pond's remediation. All work on hold. PE-14015 Lucie Stern Mechanical/Electrical Upgrades Buildings and Facilities $2,808,133 $2,808,133 $151,553 $68,133 $0 $118,910 $2,469,537 12% Design Oct 15 Project submitted plans for building permit. PF-04000 Security System Improvements Buildings and Facilities $275,000 $59,768 $0 $0 $0 $0 $59,768 78% Construction Apr 15 Utilities Dept. constructing fiber optic infrastructure for security system. FY 2014 YEAR-END CAPITAL IMPROVEMENT PROGRAM PROJECTS STATUS GENERAL FUND PUBLIC WORKS DEPARTMENT MINOR PROJECTS Page 7 of 26 Budget Attachment C Total Budget FY 2014 FY 2014 FY 2014 FY 2014 FY 2014 Estimated Project Project Project From Available Expenditures Labor Contingencies Encumbrances Remaining Percent Project Completion Number Title Category Inception Budget Adjustments Balance Complete Status Date Comments FY 2014 YEAR-END CAPITAL IMPROVEMENT PROGRAM PROJECTS STATUS GENERAL FUND PUBLIC WORKS DEPARTMENT PF-06004 Cubberley Restroom Renovation Buildings and Facilities $41,678 $136 $0 $86 $0 $0 $50 100% Pre-Design Dec 14 Finalizing design. Due to workload constraints this project has been delayed. PF-11001 Council Chambers Carpet Replacement Buildings and Facilities $80,000 $80,000 $0 $0 $0 $0 $80,000 0% Construction Aug 14 This project scope has been included in the schedule for the City Hall First Floor Renovation project. Contract awarded Jun 2014. PF-07011 Roth Building Maintenance Buildings and Facilities $224,395 $58,576 $0 $0 $0 $0 $58,576 100% Complete Project to be closed. PF-12001 Parks and PWD Trees Work Space Improvements Parks and Open Space $420,773 $413,258 $331,226 $38,258 $1,922 $0 $41,852 100% Complete Project to be closed. PF-12004 Citywide Backflow Preventer Installations Miscellaneous $100,643 $5,000 $0 $0 $0 $0 $5,000 100% Complete Project to be closed. PF-14002 Fire Station 1 Improvements Buildings and Facilities $280,377 $280,377 $0 $820 $0 $0 $279,557 0% Design Jun 15 Design phase expected to be completed by Jun 2015. PO-12000 Wilkie Way Bridge Deck Replacement Streets and Sidewalks $51,509 $51,509 $32,784 $1,509 $3,651 $0 $13,565 100% Complete Construction complete Oct 2013. Keep the project open for 1 year during the warranty period. PO-12001 Curb and Gutter Repairs Streets and Sidewalks $824,578 $536,995 $264,655 $15,429 $88,615 $168,212 $84 100% Construction Jun 15 Ongoing. This is an annual project being done in conjunction with PO-89003. PO-12002 LATP Site Development Preparation & Security Miscellaneous $80,303 $64,000 $56,265 $4,882 $0 $0 $2,853 100% Complete Combined into PE-14010. PO-12003 Foothills Fire Management Streets and Sidewalks $200,000 $180,116 $113,723 $0 $0 $16,498 $49,895 N/A Ongoing Jun 17 Burn was completed and clearing to still take place. Fire taking the lead on organization. PE-00104 San Antonio Road Median Improvements Streets and Sidewalks $2,163,729 $58,823 $13,134 $0 $45,689 $0 $0 100% Complete Project is closed. PE-06007 Park Restroom Installation Parks and Open Space $531,666 $198,088 $101,693 $22,436 $8,386 $0 $65,573 100% Complete Project to be closed. PE-08001 Rinconada Park Improvements Parks and Open Space $189,233 $189,233 $0 $2,591 $0 $0 $186,642 1% Design Mar 16 The project is under design phase. Construction is expected to start Spring 2016. PE-09003 City Facility Parking Lot Maintenance Buildings and Facilities $678,902 $648,268 $12,446 $0 $0 $0 $635,822 N/A Ongoing Jun 15 This is an annual project. FY2014 projects have been completed. Funding will be used for repaving the Mitchell Park Library parking lot in Dec 2014. PE-09005 Downtown Library Improvements Buildings and Facilities $4,530,212 $45,631 $580 $0 $0 $45,051 $0 100% Complete PE-09006 Mitchell Park Library & Community Center (New Construction) Buildings and Facilities $49,704,775 $13,091,849 $3,107,026 $496,955 $546,762 $5,875,984 $3,065,122 94% Construction Nov 14 Construction began Sep 2010 and has experienced delays. The City terminated the original Contractor and the Sureties have brought on a replacement Contractor who is completing the project. PE-09010 Library & Community Center Temporary Facilities Buildings and Facilities $793,181 $135,261 $0 $0 $0 $23,861 $111,400 86% Construction Apr 15 After final invoices are received, project will remain open until warranty period is over. Demobilization when Mitchell Park Library has opened. PE-10002 Ventura Community Center and Park Buildings and Facilities $477,219 $174,684 $5 $0 $140,470 $0 $34,209 100% Complete Project to be closed. PE-11000 Main Library New Construction and Improvements Buildings and Facilities $23,362,045 $22,620,208 $11,111,602 $369,146 $67,819 $10,917,974 $153,667 99% Construction Dec 14 Construction started Jun 2013. New driveway between art center and Library to open in Jul 2014. Library expected to reopen in Dec 2014. MULTI-YEAR PROJECTS Page 8 of 26 Budget Attachment C Total Budget FY 2014 FY 2014 FY 2014 FY 2014 FY 2014 Estimated Project Project Project From Available Expenditures Labor Contingencies Encumbrances Remaining Percent Project Completion Number Title Category Inception Budget Adjustments Balance Complete Status Date Comments FY 2014 YEAR-END CAPITAL IMPROVEMENT PROGRAM PROJECTS STATUS GENERAL FUND PUBLIC WORKS DEPARTMENT PE-11012 Temporary Main Library Buildings and Facilities $665,218 $139,167 $29,997 $0 $0 $4,889 $104,281 84% Construction Dec 14 Conversion of Art Center auditorium opened May 2013. This project must stay open as restoration of the temporary main library will occur when the Main Library reopens, which is expected to be Dec 2014. Restoration will be coordinated with AC-14000 (Art Center Audio Visual Furnishings) PE-12011 Newell Road Bridge / San Francisquito Creek Bridge Replacement Streets and Sidewalks $812,750 $483,818 $133,438 $30,336 $0 $301,568 $18,476 98% Pre-Design Oct 15 Project planning process has been modified to include an EIR analysis. Alternatives analysis completed, narrowed to five project alternatives. Contract amendment for EIR delayed pending approval of additional Caltrans grant funding. PE-12012 Eleanor Pardee Park Improvements Parks and Open Space $755,439 $728,477 $602,223 $55,436 $0 $29,919 $40,899 95% Complete Construction completed in Spring 2014. PE-13005 City Hall/King Plaza Landscape Parks and Open Space $190,150 $188,813 $34,143 $38,813 $0 $19,213 $96,644 49% Design Jun 15 First two phases of project completed. Final phase to go out to bid Oct 2014 with construction starting Feb 2015. PE-13007 El Camino Park Dog Park Parks and Open Space $3,178 $2,221 $0 $2,117 $0 $0 $104 97% N/A N/A Environmental analysis determined this project not to be viable. PE-13011 Charleston/Arastradero Corridor Project Streets and Sidewalks $919,846 $886,967 $15,194 $91,462 $0 $724,589 $55,722 94% Design Sep 15 Conceptual design and environmental review is underway. PE-13017 El Camino Median Landscape Improvements Streets and Sidewalks $46,445 $46,445 $0 $0 $0 $0 $46,445 0% Design Dec 14 This project will be coordinated with the California Avenue project. PE-14018 Baylands Interpretive Center Improvements & Boardwalk Repair Buildings and Facilities $98,738 $98,738 $0 $28,738 $0 $0 $70,000 29% Pre-Design Nov 14 Due to the location in the Baylands, staff are working on environmental issues and impacts and need to coordinate with State of California Fish and Game. PE-98020 Police Building Project Buildings and Facilities $4,254,781 $50,610 $0 $17,143 $0 $0 $33,467 99% Design TBD Potential sites are under evaluation for a new Public Safety Building to be funded via the Jun 2014 Council Infrastructure Funding Plan. A new Public Safety Building project will be created. PF-01002 Civic Center Infrastructure Improvements Buildings and Facilities $16,077,749 $423,194 $307,732 $36,566 $0 $0 $78,896 100% Construction Infrastructure work complete. Remaining CIP balance used to augment CIP PE-12017. PF-05002 Municipal Service Center Renovation Buildings and Facilities $191,487 $0 $0 $0 $0 $0 $0 N/A N/A N/A Project on hold per City Manager. PF-05003 Foothills Park Interpretive Center Improvements Buildings and Facilities $369,004 $103,554 $17,217 $18,846 $0 $1,650 $65,841 82% Construction Jun 15 Bid packet back in Purchasing to get rebidded. Original informal bid came in much higher than expected, so resubmitting as formal bid. PF-07000 Art Center Electrical & Mechanical Upgrades Buildings and Facilities $7,780,362 $16,731 $2,347 $2,876 $0 $9,978 $1,530 100% Complete Project completed as of Jun/2013. However, project needs to be opened to pay for the storage of the two pianos until Main Library construction is completed and temporary main library is converted back to Auditorium. PF-09000 Children's Theater Improvements Buildings and Facilities $82,371 $52,172 $52,172 $0 $0 $0 $0 100% Complete Combined into PE-14015. Project is closed. PF-14000 Cubberley Roof Replacements Buildings and Facilities $455,420 $455,420 $0 $1,489 $0 $0 $453,931 N/A Ongoing Jun 19 Specs being written to complete Wings L & S before end of FY2014. PF-14003 University Avenue Parking District Parking Improvements Buildings and Facilities $340,900 $340,900 $51,117 $0 $0 $0 $289,783 N/A Ongoing Jun 19 FY2014 projects have been completed. PF-14004 California Avenue Parking District Parking Improvements Buildings and Facilities $186,400 $186,400 $0 $0 $0 $0 $186,400 N/A Ongoing Dec 15 Lot 7 will be complete once California Avenue project is completed. PO-11000 Sign Reflectivity Upgrade Streets and Sidewalks $197,820 $61,440 $1,654 $375 $0 $25,000 $34,411 83% Design Jun 15 Sign assessment complete. Data is in GIS . Next step is addressing sign deficiencies and creating data maintenance enhancements to GIS. Page 9 of 26 Budget Attachment C Total Budget FY 2014 FY 2014 FY 2014 FY 2014 FY 2014 Estimated Project Project Project From Available Expenditures Labor Contingencies Encumbrances Remaining Percent Project Completion Number Title Category Inception Budget Adjustments Balance Complete Status Date Comments FY 2014 YEAR-END CAPITAL IMPROVEMENT PROGRAM PROJECTS STATUS GENERAL FUND PUBLIC WORKS DEPARTMENT PO-11001 Thermoplastic Lane Marking & Striping Streets and Sidewalks $275,000 $92,789 $82,332 $0 $0 $0 $10,457 N/A Ongoing Jun 17 Ongoing annual contract in conjunction with PE-86070 (Streets Maintenance Program Projects). Page 10 of 26 Budget Attachment C Total Budget FY 2014 Budget Estimated Project Project Project From Available FY 2014 Labor FY 2014 FY 2014 Remaining Percent Project Completion Number Title Category Inception Budget Expenditures Adjustments* Contingencies Encumbrances Balance Complete Status Date Comments VR-01001 MSC Fuel Storage Tank /Svc Island Replacement Minor $2,623,368 $67,603 $4,520 $0 $0 $1,001 $62,082 N/A Ongoing Dec 14 Equipment is currently being evaluated by the Fleet Manager, award of construction contract would occur before the end of the calendar year. VR-06801 Replace City-Wide Fuel Transaction and Inventory Management System Minor $310,831 $109,838 $883 $0 $0 $22,967 $85,988 N/A Ongoing Jun 15 Fuel Focus software upgrade taking place on October 24th and looking into upgrade of current fuel software at Fire Stations. VR-07001 Automated Motor Pool Reservation and Vehicle Key Management System Minor $127,875 $10,979 $0 $0 $0 $0 $10,979 N/A Complete CIP has been TECO'D and is ready to close. VR-11000 Vehicle Replacement Minor $1,585,767 $325,177 $0 $0 $0 $0 $325,177 N/A Complete CIP has been TECO'D and is ready to close. VR-12001 In-Ground Vehicle Lift Minor $450,000 $83,525 $0 $0 $0 $0 $83,525 N/A Complete CIP has been TECO'D and is ready to close. VR-13000 Vehicle Replacement Minor $4,424,664 $2,887,981 $1,413,300 $0 $0 $465,749 $1,008,932 N/A Ongoing Mar 15 Awaiting for delivery of four vehicles and still need to purchase one vehicle after scope has been verified. VR-14000 Vehicle Replacement Minor $3,000,000 $3,000,000 $1,217,538 $0 $0 $435,959 $1,346,503 N/A Ongoing Jun 15 Eight vehicles remaining to be purchased out of twenty. VR-14001 Emergency Repair and Minor $100,000 $100,000 $73,538 $0 $0 $6,046 $20,416 100% complete CIP has been TECO'D and is ready to close. VR-14002 MSC Fuel Station Demo Minor $240,000 $240,000 $23,656 $0 $0 $2 $216,342 10% Design Dec 15 Design is almost complete, bid will be solicited to begin work after winter rain ceases. VR-04010 Vehicle Maintenance Facility Upgrades Multi-Year $561,733 $262,860 $0 $0 $0 $24,292 $238,568 100% Complete CIP has been TECO'D and waiting for Purchasing to change commitment item to an open contract and then will be ready to close. VR-07002 Diesel Truck Engine Emissions Retrofits Multi-Year $846,488 $25,344 $0 $0 $0 $0 $25,344 N/A Ongoing June 15 Next set of Diesel Particulate Filters (DPF) will be added in FY 2015. Additional funding may be requested at midyear. VR-92006 Fuel Tank Storage/Upgrade Multi-Year $260,378 $9,664 $465 $0 $0 $0 $9,199 96% Design June 15 Additional hardware pieces may be needed after Fuel Focus upgrade is complete. FY 2014 YEAR END CAPITAL IMPROVEMENT PROGRAM PROJECTS STATUS MINOR PROJECTS MULTI-YEAR PROJECTS INTERNAL SERVICE FUND VEHICLE REPLACEMENT AND MAINTENANCE FUND PUBLIC WORKS DEPARTMENT Page 11 of 26 Attachment C FY 2014 YEAR-END CAPITAL IMPROVEMENT PROGRAM PROJECTS STATUS TECHNOLOGY FUND Total Budget FY 2014 Budget Project Project Project From Available FY 2014 Labor FY 2014 FY 2014 Remaining Percent Project Completion Number Title Category Inception Budget Expenditures Adjustments Contingencies Encumbrances Balance Complete Status Date Comments TE-01012 IT Disaster Recovery Plan Minor $578,626 $524,794 $58,485 $0 $0 $255,449 $210,860 64% Construction Dec-16 TE-08004 Fire Mobile Data Computer Minor $250,000 $61,083 $0 $0 $0 $1 $61,082 76% Construction Nov-14 A disaster recovery and business continuity assessment was completed in early 2014. The assessment will determine disaster recovery requirements to feed into an overall disaster recovery implementation plan and a determination of needed solutions. Projects included in this CIP are: ID 129, Firewall Replacement ID 132, DR BCP Assessment ID 52, Info Security Risk Assessment ID 19, File Services Cloud Migration (DR portion only for StorSimple) ID 185 Internet Redundancy Implementation Final phase of project is in progress to upgrade Fire Mobile Data Computers and add new Fire Mobile Data Computers to the fire engines for patient and permit reporting purposes. Instals started the week of 10/20/14. TE-09000 Public Safety Computer-Aided Dispatch Replacement Minor $1,400,000 $1,064,626 $145,645 $0 $0 $0 $918,981 34% Construction Dec-15 TE-11001 Library Computer System Software Minor $570,250 $499,925 $58,612 $0 $0 $21,151 $420,162 26% Complete Jun-15 TE-11002 Police Mobile In-Car Video System Replacement Minor $310,000 $305,412 $271,342 $0 $0 $31,546 $2,524 99% Complete Dec-14 The Computer Aided Dispatch (CAD) system went live on March 17, 2014 and has passed acceptance. It is in the process of implementing the Records Management System (RMS) with an estimated go-live in September of 2015. Project is currently in the planning phase and an RFP has been started for a software solution. Vendor demo and staff evaluation are completed. Contract negotiation is expected to start early November. Staff Report is prepared for December 15 Council Consent Calendar Completed the installation and now in the acceptance period. Passes acceptance; testing body worn cameras and MAV for motors TE-95016 Permit Information Tracking System Multi-Year $980,050 $176,648 $0 $0 $0 $0 $176,648 82% Construction Jun-15 Development Services is exploring permit streamlining efforts in FY15 that will include but are not limited to GIS, Accela Citizen Access, expanded mobile technology, and other automation toolsTE-07006 SAP Continuous Improvement Project Multi-Year $8,898,680 $95,694 $65,428 $0 $0 $1,949 $28,317 100% Complete This project will be closed. TE-99010 Acquisition of New Computers Multi-Year $437,350 $188,074 $0 $0 $0 $0 $188,074 100% Complete This project will be closed. TE-00010 Telephone System Replacement Multi-Year $2,646,587 $849,452 $244,207 $0 $0 $90,355 $514,890 81% Construction Jun-15 Phase 1 complete: Upgrade of high-speed network and implementation of new telephone system. Phase 2 includes e911 implementation which is complete. Removal of legacy network is part of phase 2. Included in Phase 2 are Fire Station Upgrades. TE-13001 Interactive Voice Response System Multi-Year $200,000 $200,000 $0 $0 $0 $0 $200,000 0% On hold Dec-14 On hold until November 2014 due to other priorities and assessments that will drive priorities/roadmap for Utilities. TE-13002 ESS/MSS Enhancements Multi-Year $150,000 $150,000 $0 $0 $0 $0 $150,000 100% Complete This project will be closed. TE-13003 SAP Refuse Billing Improvements Multi-Year $250,000 $250,000 $0 $0 $0 $0 $250,000 0% On hold Jun-15 Leaning towards eliminating this CIP given the likely direction to move to a new billing system to replace SAP. Will keep CIP on-hold until decisiom hasd been made. MULTI-YEAR PROJECTS TE-13004 Infrastructure Management System Multi-Year $300,000 $300,000 $48,808 $0 $41,425 $209,767 30% Construction Jul-15 This CIP has been split into two phases, an analysis of Enterprise Asset Management Systems (EAMS) to determine our requirements and solutions that will fit the City's needs, and the implementation of the chosen solution. The analysis phase was completed September 2014. Phase 2 will be implementation and will be started at the end of 2014. INTERNAL SERVICE FUND INFORMATION TECHNOLOGY DEPARTMENT MINOR PROJECTS MULTI-YEAR PROJECTS Page 12 of 26 Attachment C FY 2014 YEAR-END CAPITAL IMPROVEMENT PROGRAM PROJECTS STATUS TECHNOLOGY FUND Total Budget FY 2014 Budget Project Project Project From Available FY 2014 Labor FY 2014 FY 2014 Remaining Percent Project Completion Number Title Category Inception Budget Expenditures Adjustments Contingencies Encumbrances Balance Complete Status Date Comments INTERNAL SERVICE FUND INFORMATION TECHNOLOGY DEPARTMENT TE-14002 Library Virtual Branch Multi-Year $100,000 $100,000 $2,029 $0 $0 $13,100 $84,871 15% Pre-design Jun-15 Strategy for executing this project has concluded. It will be split into 2 phases: hiring a consultant for the analysis on requirements and solution options, and implementation of solutions(s) by a vendor. The first phase is targeted to begin in Mar 14. The consultant is working with staff to complete Phase I by January, 2015. TE-05000 Radio Infrastructure Replacement Multi-Year $2,565,980 $1,722,879 $405,020 $0 $0 $95,548 $1,222,311 52% Construction Dec-17 This CIP continues to fund ongoing maintenance of the City's existing radio system infrastructure and may fund a new effort to migrate to a planned new county-wide system. If the City participates in the regional radio system additional funding for this program will be required; estimated additional cost for CPA and Utilities is $3 million TE-06001 Library Radio Frequency Identification (RFID) Implementation Multi-Year $810,000 $564,828 $75,379 $0 $0 $16,382 $473,067 42% Construction Jun-15 Will activate when Mitchell Park Construction is completed and when the AMH (Automated Material Handling) system is in place. Then main library will be the next to use RFID which will be late Dec 14. TE-10001 Utility Customer Billing System Multi-Year $600,000 $516,088 $0 $0 $0 $4,500 $511,588 N/A Ongoing Dec-15 In the spring of 2015, a comprehensive third-party review of the Utilities Billing System is planned with the objective to amass the system’s business process requirements, identify key improvements, and determine the best approach to enhance. This includes reviewing the various “Meter-to- Cash” business processes, the “My Utilities Account” online customer portal, Utilities reporting tools, and the Customer Relationship Management (CRM) solution. TE-12001 Development Center Blueprint Multi-Year $1,738,001 $1,623,005 $344,431 $0 $0 $78,295 $1,200,279 31% Construction Dec-16 To date, the Accela V360 upgrade is complete and GIS Integration with Accela is near completion. Accela Inspection Apps has launched and Accela Citizen Access has started. Future projects include initiating a document management system and electronic plan check capabilities, as well as expanding other mobile technologies and automation tools. Page 13 of 26 Attachment C Total Budget FY 2014 Budget Estimated Project Project Project From Available FY 2014 FY 2014 FY 2014 Remaining Percent Project Completion Number Title Category Inception Budget Expenditures Contingencies Encumbrances Balance Complete Status Date Comments EL-04010 Foothills System Rebuild Minor $931,517 $110,587 $28,458 $0 $0 $82,129 100% Complete Project will be closed. EL-09004 W. Charleston/Wilkie Way to South City Limit 4/12 kV Conversion Minor $562,466 $135,000 $49,517 $0 $0 $85,483 100% Complete Construction is completed and project will be closed when all invoices have been confirmed paid. EL-10008 Advanced Metering Infrastructure System Minor $183,885 $74,597 $18,409 $0 $22,500 $33,688 82% Complete Implementation of recommendations from Smart Grid Feasibility Study are in progress and are funded by EL-11014. EL-11001 Torreya Court Rebuild Minor $103,301 $15,224 $8,029 $0 $0 $7,195 100% Complete Project will be closed. EL-11004 Hewlett Subdivision Rebuild Los Trancos Minor $697,050 $73,406 $12,772 $0 $0 $60,634 100% Complete Project will be closed. EL-11006 Rebuild UG District 18 Minor $554,298 $442,955 $0 $0 $0 $442,955 20% Design Mar 15 Design and estimate completed; will start bid process. EL-12002 Hanover 22 - Transformer Replacement Minor $1,200,450 $94,009 $87,329 $0 $0 $6,680 100% Complete Construction is completed and project will be closed when all invoices have been confirmed paid. EL-14004 Maybell 1 and 2 4/12 kV Conversion Minor $450,000 $450,000 $5,873 $0 $0 $444,127 1% Construction Jun 15 Design and estimate completed, awaiting crew availability to start construction. MULTI-YEAR PROJECTS EL-02010 SCADA System Upgrades Multi-Year $852,565 $179,498 $52,782 $0 $69,561 $57,155 93% Construction Dec 14 Software and hardware upgrades completed. Testing and commissioning in progress. ELECTRIC FUND FY 2014 YEAR-END CAPITAL IMPROVEMENT PROGRAM PROJECTS STATUS ENTERPRISE FUND UTILITIES DEPARTMENT MINOR PROJECTS Page 14 of 26 Attachment C Total Budget FY 2014 Budget Estimated Project Project Project From Available FY 2014 FY 2014 FY 2014 Remaining Percent Project Completion Number Title Category Inception Budget Expenditures Contingencies Encumbrances Balance Complete Status Date Comments ELECTRIC FUND FY 2014 YEAR-END CAPITAL IMPROVEMENT PROGRAM PROJECTS STATUS ENTERPRISE FUND UTILITIES DEPARTMENT EL-04012 Utility Site Security Improvements Multi-Year $1,125,373 $495,996 $440,722 $0 $26,806 $28,468 97% Design Ongoing Phase III completed. Starting design work for Phase IV. EL-05000 El Camino Underground Rebuild Multi-Year $2,000,994 $471,287 $188,774 $0 $0 $282,513 86% Complete Construction is completed and project will be closed when all invoices have been confirmed paid. EL-11008 Rebuild UG District 19 Multi-Year $161,286 $104,880 $3,407 $0 $0 $101,473 37% Design Aug 15 Design and estimate are complete. Crew shortages now require that we go out to bid for this project. Bid package is being prepared and will go out to bid by Jan 15. EL-06001 230 KV Electric Intertie Multi-Year $606,154 $162,523 $86,008 $0 $64,265 $12,250 98% Pre-design Ongoing Awaiting agreement to project from SLAC and Stanford. EL-06002 Underground District 45 Multi-Year $3,622,018 $144,856 $10,585 $0 $0 $134,271 96% Construction Dec 14 AT&T completed removal of poles on Cambridge and is now finishing up work on Everett. EL-08000 E. Charleston 4/12kV Conversion Multi-Year $768,125 $414,116 $530 $0 $244,437 $169,149 78% Construction Nov 14 Bid awarded, construction started. EL-09000 Middlefield Underground Rebuild Multi-Year $849,489 $220,823 $62,895 $0 $0 $157,928 81% Design Aug 15 Work is to be re-bid due to scope change. EL-09003 Rebuild UG District 17 (Downtown) Multi-Year $851,693 $84,429 $1,844 $0 $0 $82,585 100% Complete Project will be closed. MULTI-YEAR PROJECTS Page 15 of 26 Attachment C Total Budget FY 2014 Budget Estimated Project Project Project From Available FY 2014 FY 2014 FY 2014 Remaining Percent Project Completion Number Title Category Inception Budget Expenditures Contingencies Encumbrances Balance Complete Status Date Comments ELECTRIC FUND FY 2014 YEAR-END CAPITAL IMPROVEMENT PROGRAM PROJECTS STATUS ENTERPRISE FUND UTILITIES DEPARTMENT EL-10006 Rebuild UG District 24 Multi-Year $1,350,481 $926,881 $163,982 $0 $169,066 $593,833 56% Design Aug 15 Design and estimate are complete. Crew shortages now require that we go out to bid for this project. Bid package is being prepared and will go out to bid by Jan 15. EL-13006 Sand Hill/Quarry 12kV Tie Multi-Year $250,011 $249,891 $12,391 $0 $0 $237,500 5% Design TBD Waiting for response from legal Department regarding easement for equipment. EL-13007 Underground distribution System Security Multi-Year $300,000 $300,000 $828 $0 $7,178 $291,995 3% Pre-design TBD Project assigned, currently researching options for securing vaults and boxes. EL-13008 Upgrade electric Estimating System Multi-Year $150,000 $150,000 $1,350 $0 $0 $148,650 1% Design TBD Out for bid for construction standards that will be a key component of estimating software. EL-14005 Reconfigure Quarry Feeders Multi-Year $50,000 $50,000 $49 $0 $0 $49,951 0% Design Jun 15 Evaluating alternatives and field conditions to develop the design that best addresses the problems identified. New relays are required at Quarry to facilitate this work. EL-10009 Street Light System Conversion Project Multi-Year $2,279,558 $958,383 $409,507 $0 $449,761 $99,115 96% Construction Nov 14 Construction of Phase III in progress. EL-11003 Rebuild UG District 15 Multi-Year $481,079 $469,210 $12,783 $0 $0 $456,427 5% Design TBD Design work started. EL-11007 Rebuild Greenhouse Condo Area Multi-Year $508,843 $347,384 $13,794 $0 $172,278 $161,312 68% Construction Nov 14 Bid awarded, construction started. EL-11010 UG District 47 - Middlefield, Homer Avenue, Webster Street and Addison Avenue Multi-Year $1,855,574 $1,794,260 $100,453 $0 $2 $1,693,805 9% Design Dec 15 Electric sub-structure design complete, waiting for comments from AT&T and Comcast. MULTI-YEAR PROJECTS Page 16 of 26 Attachment C Total Budget FY 2014 Budget Estimated Project Project Project From Available FY 2014 FY 2014 FY 2014 Remaining Percent Project Completion Number Title Category Inception Budget Expenditures Contingencies Encumbrances Balance Complete Status Date Comments ELECTRIC FUND FY 2014 YEAR-END CAPITAL IMPROVEMENT PROGRAM PROJECTS STATUS ENTERPRISE FUND UTILITIES DEPARTMENT EL-11014 Smart Grid Technology Installation Multi-Year $1,102,846 $872,345 $105,259 $23,800 $137,559 $605,727 45% Design Jan 17 Two pilot projects are in place and in the evaluation stage. EL-11015 Reconductor 60kV Overhead Transmission System with ACCR conductor Multi-Year $3,002,412 $1,098,300 $997,321 $33,889 $0 $67,090 100% Complete Construction is completed and project will be closed. EL-12000 Rebuild UG District 12 Multi-Year $530,781 $461,185 $27,806 $0 $233,385 $199,994 62% Construction Nov 14 Bid awarded, construction started. EL-12001 UG District 46 - Charleston/El Camino Real Multi-Year $153,954 $99,883 $11,537 $0 $0 $88,346 43% Pre-design Jun 16 Procedural steps in progress. Affected customers have been notified and moving forward with establishment of Utility Underground District. EL-13004 Hansen Way/Hanover 12kV Ties Multi-Year $0 $0 $0 $0 $0 $0 0% Cancelled Project cancelled as design alternatives are being developed and considered. Page 17 of 26 Attachment CFY 2014 YEAR-END CAPITAL IMPROVEMENT PROGRAM PROJECTS STATUS Total Budget FY 2014 Budget Estimated Project Project Project From Available FY 2014 FY 2014 FY 2014 Remaining Percent Project Completion Number Title Category Inception Budget Expenditures Contingencies Encumbrances Balance Complete Status Date Comments GS-08000 Gas Station 2 Rebuild Minor $207,007 $10,023 $0 $0 $0 $10,023 100% Complete Project will be close. GS-09000 Gas Station 1 Rebuild Minor $201,000 $6,631 $0 $0 $0 $6,631 100% Complete Project will be close. GS-10000 Gas Station 3 Rebuild Minor $207,007 $8,489 $0 $0 $0 $8,489 96% Design Nov 14 Station is activated. A concrete walk need to be installed around the gas receiving equipment and permanent fencing. GS-11001 Gas Station 4 Rebuild Minor $337,000 $16,897 $0 $0 $0 $16,897 100% Complete Project will be close. GS-13003 Cooperatively-owned Back- up Generators Minor $0 $0 $0 $0 $0 $0 Closed GS-14004 Gas Distribution System Model Minor $150,000 $150,000 $1,392 $0 $55,700 $92,908 38% Pre-design Jul 15 Consultant has been selected and contract was sent to Consultant for signature in Sep 14. The gas model shall be created within 6 months from the date of the agreement and consultant will provide model/soft- ware maintenance for 3 years following creation of the model. ENTERPRISE FUND UTILITIES DEPARTMENT MINOR PROJECTS GAS FUND Page 18 of 26 Attachment CFY 2014 YEAR-END CAPITAL IMPROVEMENT PROGRAM PROJECTS STATUS Total Budget FY 2014 Budget Estimated Project Project Project From Available FY 2014 FY 2014 FY 2014 Remaining Percent Project Completion Number Title Category Inception Budget Expenditures Contingencies Encumbrances Balance Complete Status Date Comments ENTERPRISE FUND UTILITIES DEPARTMENT GAS FUND GS-01019 Global Positioning System Multi-Year $381,062 $82,448 $2,142 $0 $2,810 $77,496 80% Construction Jun 15 Integrating field data into mapping system, defining additional equipment needs. GS-08011 GMR - Project 18 Multi-Year $5,900,883 $466,693 $433,624 $22,538 $0 $10,531 100% Complete Project will be closed. GS-09002 GMR - Project 19 Multi-Year $5,787,828 $4,519,005 $2,089,893 $80,863 $2,051,126 $297,123 95% Construction Feb 15 Combined GMR 19B-21. Construction started Mar 13 GS-10001 GMR - Project 20 Multi-Year $6,616,749 $6,519,841 $1,525,786 $238,475 $4,608,445 $147,135 98% Construction Feb 15 Combined GMR 19B-21. Construction started Mar 13. GS-11000 GMR - Project 21 Multi-Year $6,667,478 $5,878,721 $3,563,876 $0 $2,189,310 $125,535 98% Construction Feb 15 Combined GMR 19B-21. Construction started on Mar 13. GS-11002 Gas System Improvements Multi-Year $726,549 $438,081 $171,311 $0 $231,926 $34,844 N/A Ongoing TBD This project addresses ongoing capital system improvements. GS-12001 GMR - Project 22 Multi-Year $94 $0 $0 $0 $0 $0 100% Design Jun 15 Design funds are delayed until FY 2016. Construction to begin 2016. GS-13002 General Shop Equipment/Tools Multi-Year $50,000 $50,000 $1,938 $0 $6,020 $42,042 N/A Ongoing TBD This project is for replacement of equipment and tools for Operations. MULTI-YEAR PROJECTS Page 19 of 26 Attachment C Total Budget FY 2014 Budget Estimated Project Project Project From Available FY 2014 FY 2014 FY 2014 Remaining Percent Project Completion Number Title Category Inception Budget Expenditures Contingencies Encumbrances Balance Complete Status Date Comments WS-09000 Seismic Water Tank Valve Minor $4,443,000 $4,414,174 $129,754 $0 $2,367,781 $1,916,639 57% Construction Nov 17 Boronda reservoir construction will commence Nov 14 and be completed by Jun 15. Steel tanks and three (3) turnouts in design phase and construction to begin Spring 15 and completed by Fall 17. WS-13003 GPS Equipment Upgrade Minor $200,000 $200,000 $0 $0 $0 $200,000 0% Pre-Design Jun 15 Working with Asset Management on group development. WS-13004 Asset Management Mobile Deployment Minor $100,000 $100,000 $1,529 $0 $0 $98,471 2% Pre-Design Jun 15 Working with Asset Management group on identifying needs and development of a deployment plan. WS-13006 Water Meter Shop Renovations Minor $315,000 $287,148 $215,002 $15,253 $20,148 $36,745 95% Design Nov 14 Funding Operations efforts and providing ongoing support. WATER FUND FY 2014 YEAR-END CAPITAL IMPROVEMENT PROGRAM PROJECTS STATUS ENTERPRISE FUND UTILITIES DEPARTMENT MINOR PROJECTS Page 20 of 26 Attachment C Total Budget FY 2014 Budget Estimated Project Project Project From Available FY 2014 FY 2014 FY 2014 Remaining Percent Project Completion Number Title Category Inception Budget Expenditures Contingencies Encumbrances Balance Complete Status Date Comments WATER FUND FY 2014 YEAR-END CAPITAL IMPROVEMENT PROGRAM PROJECTS STATUS ENTERPRISE FUND UTILITIES DEPARTMENT WS-07000 Water Regulation Station Improvements Multi-Year $544,001 $400,936 $30,112 $0 $369,933 $891 100% Design Nov 17 Mayfield seismic retrofit completed. Boronda reservoir construction will commence Nov 14 and be completed by Jun 15. Steel tanks and turnout rehabilitation construction to begin Spring 15 and completed by Fall 17. WS-07001 Water Recycling Facilities Multi-Year $901,126 $394,519 $6,098 $0 $192,338 $196,083 78% Pre-Design Jun 16 Preparing Environmental Impact Report (EIR). Study to be completed in 2015. Construction to be completed (yet TBD) based on findings. WS-08001 Water Reservoir Coating Improvements Multi-Year $2,476,491 $2,235,134 $57,574 $0 $369,955 $1,807,605 27% Design Nov 17 Mayfield seismic retrofit completed. Boronda reservoir construction will commence Nov 14 and be completed by Jun 15. Steel tanks and turnout rehabilitation construction to begin Spring 15 and completed by Fall 17. WS-08002 Emergency Water Supply Project Multi-Year $36,463,630 $7,286,620 $1,368,644 $4,707,486 $1,210,154 $336 100% Complete El Camino reservoir, well, PS construction 99% complete. Mayfield Pump Station construction 100% complete. Wells rehabilitation construction 100% complete. WS-09001 WMR - Project 23 Multi-Year $3,136,843 $124,688 $3,070 $9,597 $0 $112,021 100% Complete Project will be closed. MULTI-YEAR PROJECTS Page 21 of 26 Attachment C Total Budget FY 2014 Budget Estimated Project Project Project From Available FY 2014 FY 2014 FY 2014 Remaining Percent Project Completion Number Title Category Inception Budget Expenditures Contingencies Encumbrances Balance Complete Status Date Comments WATER FUND FY 2014 YEAR-END CAPITAL IMPROVEMENT PROGRAM PROJECTS STATUS ENTERPRISE FUND UTILITIES DEPARTMENT WS-10001 WMR - Project 24 Multi-Year $3,259,205 $462,132 $250,385 $3,443 $0 $208,305 100% Complete Project will be closed. WS-11000 WMR - Project 25 Multi-Year $5,444,709 $5,433,284 $2,815 $0 $12,831 $5,417,638 0% Design Jan 15 Re-bidding Jan 15 project for 3rd time due to high bids received. Cut back scope to meet budget constraints. WS-11003 Water Distribution System Improvements Multi-Year $2,015,241 $1,856,113 $194,924 $0 $639,363 $1,021,826 N/A Ongoing Jun 15 This project addresses ongoing capital distribution system improvements. WS-11004 Water System Supply Improvements Multi-Year $711,995 $584,609 $426,987 $0 $51,456 $106,166 N/A Ongoing Jun 15 This project addresses ongoing capital supply system improvements. WS-12001 WMR - Project 26 Multi-Year $505,000 $505,000 $43,935 $0 $0 $461,065 9% Pre-Design Jun 15 Research basemaps to determine optimal alignment corridor. WS-13002 Fusion and General Equipment/Tools Multi-Year $50,000 $28,132 $0 $0 $6,020 $22,112 N/A Ongoing Dec 15 This project addresses the purchase of PE fusion equipment for Operations to perform their work. MULTI-YEAR PROJECTS Page 22 of 26 Attachment CFY 2014 YEAR-END CAPITAL IMPROVEMENT PROGRAM PROJECTS STATUS Total Budget FY 2014 Budget Estimated Project Project Project From Available FY 2014 FY 2014 FY 2014 Remaining Percent Project Completion Number Title Category Inception Budget Expenditures Contingencies Encumbrances Balance Complete Status Date Comments WC-11000 WC Reh/Aug. Prj 24 Multi-Year $3,119,809 $2,967,027 $454,592 $0 $2,801 $2,509,634 20% Design Jan 15 Design completed. Re-bidding Jan 15 for the 2nd time due to budget exceedence. WC-12001 WC Reh/Aug. Prj 25 Multi-Year $3,212,000 $3,158,502 $303,525 $0 $16,851 $2,838,126 12% Design Jan 15 Design completed. Re-bidding Jan 15 for the 2nd time due to budget exceedence. WC-13001 WC Rehab/Aug. Prj 26 Multi-Year $310,000 $310,000 $37,450 $0 $0 $272,550 12% Pre-design Jun 15 Awaiting additional resource availability to start the design of WC Reh/Aug Prj 26. WC-13002 Fusion and General Equipment/Tools Multi-Year $52,187 $28,132 $0 $0 $0 $28,132 N/A Ongoing Jun 15 This project addresses replacing PE fusion tools needed by WGWW Operations to perform their work. WC-15002 Wastewater System Improvements Multi-Year $416,403 $315,580 $33,878 $0 $79,886 $201,816 N/A Ongoing Jun 15 This project addresses on going capital system improvements. MULTI-YEAR PROJECTS ENTERPRISE FUND UTILITIES DEPARTMENT WASTEWATER COLLECTION FUND Page 23 of 26 Attachment C ENTERPRISE FUND REFUSE FUND PUBLIC WORKS DEPARTMENT Total Budget FY 2014 Budget Estimated Project Project Project From Available FY 2014 FY 2014 FY 2014 Remaining Percent Project Completion Number Title Category Inception Budget Expenditures Contingencies Encumbrances Balance Complete Status Date Comments RF-09004 LATP Site Development Preparation Minor $200,000 $0 $0 $0 $0 $0 100% Closed RF-10002 Flare Relocation Project Minor $867,734 $740,997 $698,646 $0 $318 $42,033 95% Complete Project completed in Feb 14. As-builts for the project were received. RF-07001 Relocation of Landfill Facilities Multi-Year $825,968 $206,192 $187,494 $0 $0 $18,698 98% Complete Project completed in Jan 14. RF-10003 Drying Beds, Material Storage and Transfer Area Multi-Year $69,669 $0 $0 $0 $0 $0 100% Closed RF-11001 Landfill Closure Multi-Year $4,718,404 $3,768,586 $789,925 $0 $2,190,739 $787,922 83% Construction Dec 15 Construction of the new cap - an evapotranspirative soil cap began in Jan 14. Approximately 50% of the site has been capped and another large section is expected to be capped by the end of dec 14. Final work on the landfill closure may occur sooner but is subject to availability of soil and weather conditions. FY 2014 YEAR-END CAPITAL IMPROVEMENT PROGRAM PROJECTS STATUS MINOR PROJECTS MULTI-YEAR PROJECTS Page 24 of 26 Attachment CFY 2014 YEAR-END CAPITAL IMPROVEMENT PROGRAM PROJECTS STATUS Total Budget FY 2014 Budget Estimated Project Project Project From Available FY 2014 FY 2014 FY 2014 Remaining Percent Project Completion Number Title Category Inception Budget Expenditures Contingencies Encumbrances Balance Complete Status Date Comments SD-06102 San Francisquito Creek Storm Water Pump Station Multi-Year $6,387,642 $36,246 $1,088 $0 $0 $35,158 99% Complete Jun 19 Required mitigation monitoring for 10 years (through FY 2019) is the only remaining task. SD-06104 Connect Clara Drive Storm Drains to Matadero Pump Station Multi-Year $953,480 $807,065 $736,558 $0 $0 $70,507 93% Complete Project was completed in Mar 14. SD-10101 Southgate Neighborhood Storm Drain Improvements Multi-Year $2,176,878 $1,966,110 $222,965 $0 $1,713,540 $29,605 99% Construction Nov 14 Construction contract awarded in Apr 14. Work will be substantially completed in Nov 14 following street resurfacing. SD-11101 Channing Avenue/Lincoln Avenue Storm Drain Improvements Multi-Year $7,442,779 $3,695,465 $378,494 $0 $7,214 $3,309,757 56% Design Apr 15 Phase I & Phase II are complete. Phase III design will be completed in Apr 15, construction to be completed by Dec 15. SD-13002 Matadero Creek Storm Water Pump Station & Trunk Lines Improvements Multi-Year $340,687 $340,387 $0 $0 $0 $340,387 0% Design Nov 15 RFP for design consultant to be issued Nov 14. Design will be completed by Nov 15. MULTI-YEAR PROJECTS STORM DRAINAGE FUND ENTERPRISE FUND PUBLIC WORKS DEPARTMENT Page 25 of 26 Attachment CFY 2014 YEAR-END CAPITAL IMPROVEMENT PROGRAM PROJECTS STATUS Total Budget FY 2014 Budget Estimated Project Project Project From Available FY 2014 FY 2014 FY 2014 Remaining Percent Project Completion Number Title Category Inception Budget Expenditures Contingencies Encumbrances Balance Complete Status Date Comments WQ-10001 Plant Master Plan Minor $1,594,697 $362,398 $215,963 $0 $79,992 $66,443 96% Construction Jun 19 Long Range facilities Plan Report 100% completed Oct 12; BAO for Biosolids Plan completed in Jan 13 for $421,678. Biosolids Facility Plan completed Sep 14. Biosolids Facility Plan 100% complete. WQ-04011 Facility Condition Assessment and Retrofit Multi-Year $3,994,613 $1,076,519 $2,196 $0 $0 $1,074,323 73% Design Jun 19 Ongoing retrofit projects. Facility Repair and Retrofit Project #2 construction completed. Facility Repair and Retrofit Project #3 contract to be awarded to Anderson Pacific Engineering. MINOR PROJECTS ENTERPRISE FUND PUBLIC WORKS DEPARTMENT WASTEWATER TREATMENT FUND MULTI-YEAR PROJECTS Page 26 of 26 Attachment D Project Category Department/Fund Project Title FY 2010 FY 2011 FY 2012 FY 2013 FY 2014 Community Services - General Fund : Land & Land Improvements AC-86017 Art in Public Places $17,256 $77,956 $17,171 $59,526 80,497 Planning & Community Environment - General Fund : Streets & Sidewalks PL-05030 Traffic Signal Upgrades 278,187 183,141 244,272 385,302 290,944 Public Works - General Fund : Streets & Sidewalks PE-86070 Street Improvements (Street Improvement Fund)3,323,063 4,710,791 3,170,679 7,097,782 5,072,597 Building & Facilities PF-00006 Roofing Replacement 227,495 104,617 319,495 246,068 119,682 Building & Facilities PF-01003 Building Systems Improvements 36,053 74,876 59,798 34,320 150,878 Building & Facilities PF-02022 Facility Interior Finishes 11,076 23,874 234,085 70,609 390,667 Building & Facilities PF-93009 ADA Compliance 216,133 9,994 167,537 10,019 16,024 Streets & Sidewalks PO-05054 Street lights Improvements 32,976 159,070 61,844 69,707 74,636 Streets & Sidewalks PO-89003 Sidewalk Improvements 952,503 1,611,917 1,673,715 1,864,954 2,160,793 Public Works - Storm Drainage Fund : SD-06101 Storm Drain System Replacement 81,878 488,793 242,488 745,927 98,479 Public Works - Wastewater Treatment Fund : WQ-80021 RWQCP Plant Equipment Replacement 403,293 66,916 589,965 1,840,887 2,449,616 WQ-80022 RWQCP System Flow Metering 0 28,468 0 0 9,770 Electric Fund : EL-02011 Electric Utility GIS 188,231 321,713 175,382 127,798 65,294 EL-06005 Fiber Optics Ring System Improvements 5,531 0 0 0 0 EL-06006 Fiber Optics Customer Design and Connection Services 17,203 0 0 0 0 EL-89028 Electric Customer Connections 1,702,232 1,882,242 2,522,815 2,802,451 2,922,100 EL-89031 Communications System Improvements 0 3,501 0 3,345 13,935 EL-89038 Substation Protection Improvements 133,185 129,086 200,418 188,049 158,683 EL-89044 Substation Facility Improvements 3,133 148,871 180,672 60,458 243,564 EL-98003 Electric Distribution System Reconstruction and Improvements 1,330,082 1,608,521 2,389,593 1,453,123 1,319,059 Fiber Optics Fund : FO-10000 Fiber Optic Customer Connections 68,373 88,061 125,913 291,425 360,428 FO-10001 Fiber Optic Network System Improvements 34,614 327,736 448,950 137,878 154,906 Five Years of Expenditures for Fiscal Years 2010-2014 Continuous Capital Projects Page 1 of 2 11/25/2014 Attachment D Project Category Department/Fund Project Title FY 2010 FY 2011 FY 2012 FY 2013 FY 2014 Five Years of Expenditures for Fiscal Years 2010-2014 Continuous Capital Projects Gas Fund : GS-02013 GS-03007 Directional Boring Equipment 0 162 20,160 0 289,195 GS-03002 GS-04003 GS-05002 Gas Main Replacements 87,706 86,159 54,157 0 0 GS-03008 Polyethylene Fusion Equipment Replacement 0 444 0 24,055 26,718 GS-03009 System Extensions-Unreimbursed 4,005 7,718 0 90,838 92,466 GS-06001 Gas Main Replacements, GMR-Project 16 89,180 127,056 0 0 0 GS-07002 Gas Main Replacements, GMR-Project 17 3,681,252 211,515 139,958 577 0 GS-80017 Gas System Extensions 347,412 471,001 605,635 932,035 904,684 GS-80019 Gas Meters and Regulators 313,598 294,191 325,988 25,652 2,178 Wastewater Collection Fund: WC-02002 WC-03003 WC-04002 Sewer System Rehabilitation and Augmentation, Project 15,16 and 17 27,141 122,870 57,715 0 0 WC-05003 WC-06003 WC-07004 Sewer System Rehabilitation and Augmentation, Project 18,19 and 20 1,761,725 94,468 188,511 241,489 56,751 WC-08012 WC-09001 WC-10002 Sewer System Rehabilitation and Augmentation, Project 21,22 and 23 543,313 1,928,374 1,023,537 2,139,395 2,236,935 WC-80020 Sewer System Extensions 251,152 224,066 270,793 445,570 279,411 WC-99013 Sewer Manhole Rehabilitation 168,722 378,841 357,343 555,382 516,840 Water Fund : WS-02014 Water-Gas Wastewater Utilities GIS Data 204,583 289,694 222,244 282,573 195,881 WS-06002 Water Main Replacements, Project 20 349 10,821 0 0 0 WS-07003 Water Main Replacements, Project 21 1,383,427 1,432,826 528 0 0 WS-80013 Water System Extensions 285,945 258,968 551,131 528,788 528,260 WS-80014 Service and Hydrant Replacements 43,538 44,232 151,928 359,994 67,570 WS-80015 Water Meters 2,298 0 34,000 4,183 346,743 Page 2 of 2 11/25/2014