Utilities Advisory Commission
Staff Report
From: Dean Batchelor, Director Utilities
Lead Department: Utilities
Meeting Date: January 3, 2024
Staff Report: 2306-1685
TITLE
Discussion and Update on Utilities Department Five-Year Capital Improvement Program Progress
and Projections
RECOMMENDATION
Staff recommends the Utilities Advisory Commission receive the update on the five-year capital
improvement program, shown in the attached tables.
BACKGROUND
Utilities Engineering oversees and implements the capital improvements program (CIP) for the
Utilities Department. The attached tables summarize implementation of the electric, gas, water,
and wastewater CIP projects over the past five years (i.e., fiscal year 2019 to present), including
their originally planned construction year, actual construction year, proposed budget, and
contract amount. The attached tables also show the currently planned CIPs, including fiber optic
construction, for the next five years (i.e., present to fiscal year 2028).
ANALYSIS
Water-Gas-Wastewater (WGW) CIP projects have generally been implemented within the
planned timeframe and allocated budget amounts. The exceptions are projects that were
delayed in fiscal year 2019 due to the Upgrade Downtown (UGDT) project, which was a large,
multi-departmental CIP project that included water, gas, electric, fiber, traffic signal, sidewalk
curb ramps, and sidewalk widening in the downtown area.
The Electric Utility has been impacted by staff vacancies, material shortages post-COVID, an
unexpected substation transformer replacement project, and a shift in priorities to supporting
Grid Modernization. These factors have led to the delay of some planned work which is being
incorporated into upgrades need for the Grid Modernization Project.
Staff will be available during the Utilities Advisory Commission meeting to answer any questions
regarding the summary tables and the implementation and status of individual projects.
Item No. 3. Page 2 of 2
2
5
8
0
FISCAL/RESOURCE IMPACT
This is an informational report and there is no fiscal or resource impact.
STAKEHOLDER ENGAGEMENT
None
ENVIRONMENTAL REVIEW
None required.
ALTERNATIVE ACTIONS
None
ATTACHMENTS
Attachment A: WGW CIP Project Summary
Attachment B: Electric CIP Project Summary
AUTHOR/TITLE:
Dean Batchelor, Director of Utilities
Staff, Tomm Marshall, Assistant Director of Utilities Electric
Staff, Matt Zucca, Assistant Director of Utilities WGW
Table 1
Capital Improvement Program Project Status Summary for Fiscal Years 2019 to 2028 (as of November 2023)
Water, Gas, and Wastewater Engineering
FY'19
Notes: All three FY'19 CIP projects were postponed due to the Upgrade Downtown (UGDT) project. UGDT was a $16.4M, multi-departmental CIP project which included water, gas, electric, fiber, traffic signal, sidewalk curb ramps, and
sidewalk widening. WGW Engineering team managed the project during the design, solicitation, and construction phases. The project received zero bids after going through a formal solicitation process, therefore extra time and efforts
were spent to negotiate a contract with a contractor who had the capacity and resources to perform the work. It was also time-consuming to coordinate with various City departments and the contractor on a regular basis, provide extensive
outreach to the property owners in the Downtown District and the public, manage high-volume construction related paperwork and tasks, etc. At that time, WGW Engineering was short-staffed and all available staff was reassigned to assist
with this high-profile and multifaceted project. Unfortunately, the regular CIP projects were impacted. As a result, WMR 27 and GMR 23 were postponed and SSR 28 scope was reduced by about 50% (from 20,000 LF to about 9,000 LF) and
construction was delayed a year.
Project Original Const Year Actual Const Year Proposed Budget*Contract Amount**Construction Period Status/Comments
WMR 27 FY'19 Postponed due to Upgrade Downtown Project.
GMR 23 FY'19 Postponed due to Upgrade Downtown Project.
SSR 28A FY'19 FY'19 $250,000 $236,401 8/14/18 - 9/26/18 Sewer main replacement at Junior Museum and Zoo (JMZ) was prioritized.
SSR 28B FY'19 FY'20 $3,965,600 $1,930,066 8/21/19 - 6/15/20 Project scope was reduced and construction was delayed due to short-staffing.
FY'20
Notes: As indicated in the FY'20 Financial Plans, UTL Engineering started implementing the every-other-year construction for large main replacement projects. This schedule is more realistic to reflect the required duration for design,
solicitation practice, Staff Report/Council approval process, contract setup, and pre-construction preparation. This staggered schedule (water and wastewater constructing every even year and gas construction every odd year) also eases
scheduling difficulties for inspection coverage due to shared inspection staff across water, wastewater, gas, and large development services projects. The previous impacted projects were shifted to FY'20 (WMR 27) and FY'21 (GMR 23)
accordingly.
Project Original Const Year Actual Const Year Proposed Budget*Contract Amount**Construction Period Status/Comments
WMR 27 FY'20 FY'20 $6,500,000 $4,146,435 10/21/19 - 7/2/20 On target
SSR 29 FY'20 FY'20 $4,508,339 $2,040,841 2/3/20 - 11/6/20 On target with about 50% reduced scope.
FY'21
Project Original Const Year Actual Const Year Proposed Budget*Contract Amount**Construction Period Status/Comments
GMR 23 FY'21 FY'21 $7,620,000 $6,417,876 3/8/21 - 7/29/22 On target
Corte Madera Reservoir Rebuilt FY'21 FY'21 $7,000,000 $5,545,000 2/2/21 - 4/1/22 On target
FY'22
Project Original Const Year Actual Const Year Proposed Budget*Contract Amount**Construction Period Status/Comments
WMR 28 FY'22 FY'22 $8,500,000 $7,819,336 4/18/22 - 6/5/23 Completed
SSR 30 FY'22 FY'22 $4,130,000 $3,444,302 3/28/22 - 2/24/23 Completed
FY'23
Project Original Const Year Actual Const Year Proposed Budget*Contract Amount**Construction Period Status/Comments
GMR 24A FY'23 FY'23 $1,500,000 $1,411,059 1/1/23 - 3/31/23 On target
GMR 24B FY'23 FY'24 $8,500,000 TBD 1/30/24 - 5/31/25 Delayed due to grant application's late response.
FY'24
Project Original Const Year Actual Const Year Proposed Budget*Contract Amount**Construction Period Status/Comments
WMR 29 FY'24 FY'24 $8,500,000 $6,956,400 11/27/23 - 5/6/24 On target
Park Reservoir Upgrade FY'24 FY'25 $7,000,000 TBD TBD Delayed due to non-responsive proposals when seeking consultants to design the tanks.
SSR 31 FY'24 FY'24 $7,300,000 $7,707,055 7/31/23 - 5/6/24 Const cost for work on El Camino Real came in higher than estimated, used reseve $
FY'25
Project Original Const Year Actual Const Year Proposed Budget*Contract Amount**Construction Period Status/Comments
GMR 25 FY'25 TBD $10,000,000 TBD TBD Expected to be on target
FY'26
Project Original Const Year Actual Const Year Proposed Budget*Contract Amount**Construction Period Status/Comments
WMR 30 FY'26 TBD $8,500,000 TBD TBD Expected to be on target
Dahl Reservoir Upgrade FY'26 TBD $7,000,000 TBD TBD May be delayed since Park Reservoir Upgrade project is delayed.
SSR 32 FY'26 TBD $11,000,000 TBD TBD Expected to be on target
FY'27
Project Original Const Year Actual Const Year Proposed Budget*Contract Amount**Construction Period Status/Comments
GMR 26 FY'27 TBD $10,000,000 TBD TBD Expected to be on target
FY'28
Project Original Const Year Actual Const Year Proposed Budget*Contract Amount**Construction Period Status/Comments
Page 1 of 2
WMR 31 FY'28 TBD $8,500,000 TBD TBD Expected to be on target
SSR 33 FY'28 TBD $11,000,000 TBD TBD Expected to be on target
Legend:
WMR = Water Main Replacement
GMR = Gas Main Replacement
SSR = Sanitary Sewer Replacement
Notes:
*The proposed budget included construction contract, 10% contingency, staff time for design & construction management, street cut fee, soil compaction testing, and all other associated costs.
**The listed construction contract amount excludes 10% contingency.
Table 1
Capital Improvement Program Project Status Summary for Fiscal Years 2019 to 2028 (as of November 2023)
Water, Gas, and Wastewater Engineering
Page 2 of 2
Table 1
Capital Improvement Program Project Status Summary for Fiscal Years 2019 to 2028 (as of November 2023)
Electric and Fiber Optic Engineering
FY'19
Project Original Const Year Actual Const Year Proposed Budget*Actual Construction Period Status/Comments
Utility Control Center Upgrades FY'18 FY'19 $522,017 $519,204 07/01/18 - 06/30/19 Project Completed
FY'20
Project Original Const Year Actual Const Year Proposed Budget*Actual Construction Period Status/Comments
Colorado 115/60 kV Transformer FY'19 FY'20 $3,377,671 $2,375,018 07/01/19 - 06/30/20 Work in progress
FY'21
Project Original Const Year Actual Const Year Proposed Budget*Actual Construction Period Status/Comments
Caltran Modification FY'18 FY'21 $2,471,000 $2,419,907 07/01/19 - 06/30/21 Project Completed
Colorado 115/60 kV Transformer FY'19 FY'21 $1,016,384 $232,954 07/01/19 - 06/30/21 Project Completed
FY'23
Project Original Const Year Actual Const Year Proposed Budget*Actual Construction Period Status/Comments
UG46 FY'19 FY'23 $4,018,052 $3,443,285 07/01/19 - 06/30/23 Project Completed
Capacitor Bank Installation FY'22 FY'23 $2,300,000 $2,265,166 07/01/22 - 06/30/23 Project Completed
Foothills Underground Program FY'21 Ongoing $12,000,000 $4,494,104 07/01/21- 06/30/26 On-going
AMI Project FY'16 Ongoing $11,552,898 $5,293,930 07/01/22-07/01/25 On-going
Substation Security Upgrades FY'16 On-going $5,000,000 $2,078,888 07/01/22-07/01/25 On-going
Substation Breaker Replacement FY'20 Ongoing $3,000,000 $1,138,886 07/01/20-07/01/25 On-going
FY'24
Project Original Const Year Actual Const Year Proposed Budget*Contract Amount**Construction Period Status/Comments
GridMod FY'24 TBD $10,000,000 TBD TBD Expected to be on target
FTTP FY'24 TBD $10,000,000 TBD TBD Expected to be on target
FY'25
Project Original Const Year Actual Const Year Proposed Budget*Contract Amount**Construction Period Status/Comments
GridMod FY'25 TBD $25,000,000 TBD TBD Expected to be on target
FTTP FY'25 TBD $10,000,000 TBD TBD Expected to be on target
FY'26
Project Original Const Year Actual Const Year Proposed Budget*Contract Amount**Construction Period Status/Comments
GridMod FY'26 TBD $25,000,000 TBD TBD Expected to be on target
FTTP FY'26 TBD $10,000,000 TBD TBD Expected to be on target
FY'27
Project Original Const Year Actual Const Year Proposed Budget*Contract Amount**Construction Period Status/Comments
GridMod FY'27 TBD $50,000,000 TBD TBD Expected to be on target
FTTP FY'27 TBD TBD TBD TBD Pending Council's direction
FY'28
Project Original Const Year Actual Const Year Proposed Budget*Contract Amount**Construction Period Status/Comments
GridMod FY'28 TBD $50,000,000 TBD TBD Expected to be on target
FTTP FY'28 TBD TBD TBD TBD Pending Council's direction
Page 1 of 1