HomeMy WebLinkAboutStaff Report 13806City of Palo Alto (ID # 13806)
Utilities Advisory Commission Staff Report
City of Palo Alto Page 1
Meeting Date: 1/5/2022
Title: Discussion and Update on the Permit Processes for Various Energy
Technologies
From: Director of Utilities
Lead Department: Utilities
Recommendation
This item is for Utilities Advisory Commission (UAC) information and discussion; no action is
requested.
Background/Discussion
Palo Alto Utilities (PAU) and the Planning and Development Services department (PDS)
provided its last update to the UAC on September 1, 2021 on the City’s permitting and
inspection process related to electrification permits.
The prior UAC staff report1 provided information on improvements that have been
implemented or ongoing and additional work that was anticipated in the near future. This
report provides an update on specific initiatives that are currently underway and updated
permit performance data.
Automated Solar Permitting (Solar APP +)
City staff continues its conversations with representatives of the National Renewable Energy
Laboratory (NREL) with the goal to incorporate Solar APP+ in the City’s permitting process. Solar
App+ would streamline permit issuance for residential roof mounted solar photovoltaic (PV)
systems. Eventually, it is anticipated that battery storage systems will be added to the
permitting platform.
The City recently performed a simulated test of three PV projects; two were cleared for permit
and one project, appropriately, was rejected. Solar App+ reviews projects to basic code state
requirements. It does not incorporate local jurisdiction regulations or utility service provider
requirements. As a full service city, Palo Alto needs to consider the implications of
implementing Solar App+ and the effect it may have on the City’s utility infrastructure.
1 UAC Staff Report, dated September 1, 2021: https://www.cityofpaloalto.org/files/assets/public/agendas-
minutes-reports/agendas-minutes/utilities-advisory-commission/archived-agenda-and-minutes/agendas-and-
minutes-2021/09-01-2021-special/id-13530-item-1.pdf
Staff: Jonathan Lait
CITY OF
PALO
ALTO
City of Palo Alto Page 2
While staff continues to ready the permitting system to work with Solar App+, its
implementation is pending review of the City’s infrastructure capabilities to support larger PV
systems without plan review prior to permit issuance. Palo Alto Utilities will lead that analysis,
which may impact existing utility policies requiring City Council review or resource
considerations prior to implementation.
Revisions to Application, Plan Review and Inspection Checklists (all electrification permits)
Concurrent with efforts on Solar App+, staff continues to work on refinements to the City’s
electrification permit application, plan review and inspection checklists. A draft of the
residential checklists was sent to contractors working in Palo Alto and who have expressed an
interest in assisting the department with this effort. Staff received feedback and is updating the
checklists in response to comments received. Where staff has a different perspective than a
commenter, we will reach out and have a discussion to understand why there may be a
difference of opinion about a requirement or protocol. It is the department’s goal to have the
residential checklists uploaded and on the City’s website in February 2022.
Customer Service Feedback Survey
At the time of this report, staff was finalizing a short survey that will be used for all touchpoints
the Planning and Development department has with its customers. Two programs in particular
–our inspection program and development center – have program specific questions to illicit
feedback on staff’s customer service, professional, efficiency and technical knowledge. The
intent is to be able to provide customers an opportunity to provide immediate feedback by way
of links in our email signature line, with QR codes at these touchpoints and by text message to
contractors at job sites after an inspector’s visit. These survey’s will be anonymous allowing for
candid customer feedback. Staff will monitor and anticipates posting all results online. With the
survey language nearly complete, some online formatting and programming is required before
the survey can be published and available before the end of the year.
Electrification Permitting Performance
The following tables provide timeline information on different aspects of the permitting process
and generally reflect improved efficiency compared to the same period last year. As staff
continues to refine its online permit system and monitor daily performance reports, it is
anticipated some additional efficiencies can be achieved. Two metrics below (shaded) include
applicant time to respond to staff or are impacted by the quality of the initial application
submittal. As noted above, staff is working on checklists to help identify and facilitate a
smoother transition between submittal and approval.
City of Palo Alto Page 3
Timeline
This report provides an update on current initiatives and performance reporting. Staff will
continue to advance the efforts listed in this report and in the first quarter next year begin to
initiate improvements to the department’s webpage providing greater access to information
for homeowners and contractors regarding electrification permits. Later, staff will attempt to
prepare a contractor’s database of those companies that install solar panels in Palo Alto.
Resource Impact
The recommendation in this report does not have any significant fiscal or budgetary impacts.
Policy Implications
This report details specific action taking place to align the City’s permitting and inspection
programs with the City Council’s expressed goals to advance carbon reduction strategies. PDS
and other departments involved in the review process have dedicated staff resources aimed at
reducing the amount of time it takes to process applications and improve consistency in its
requirements and clarify expectations for inspecting installations in the field.
Stakeholder Engagement
Staff has scheduled regularly meetings with UAC to provide a status update on efforts that
improve the City’s electrification permitting and inspection processes. From time to time, either
on specific projects, or as partners to help review draft City documents, staff is engaging
contractors and other individuals interested in our electrification efforts. Internal coordination
among City departments, supported by the department heads from PDS, Fire and PAU are a key
component of this engagement strategy.
Environmental Review
Pre-Appllc.ltlon Aa:epta~ Pr •Appllc.ltlon Acceptance Pr •Appl" tlon Converted 10 Pre-Appllca11on Conv rted 10
Bulldlng Permit w/fn 7 Days Bulldlng P rmlt w/ln 7 Days
c, •orea end4or .,. to Accept r, .... 01 ond 001' IOA<cept (Catenc!Ar Oa,.. o Aa:<i>t ~ coho,, ...,., .,. to Accept Appl atlon
App!,c ,onM ,2020-oaooe, 20 Apcll ion 2021 -~ 2021) ,.. 2020 • Qaobef y ml • 0ctooef 2021)
ALL ElectrlflCllllon 1S 10 54% 65% Permits
Electrl cation Permit
w/ Solar PV 12 7 62% 79%
component
Pre-Applic.ltlon 1st Response Pr -Appl tlon ls Response Building Permit 1st Round of
Corrections to Appllc nt
IA ... I crfCa cndt< Oats 0 ht ,.-... •occait ,o..,. 01$1i>e-spon.,., (4 ~or lend r Oots to IJt 1te,po,nse
Pespon1e v 2020 • oaooer 11 -oa-II .•~yl021 • oaot>et 20211
ALL Eltttrlfic lion 3 3 19 11.S Permlts
Electri cation Permit
w/ Solar PV 3 3 17.S 12
component
City of Palo Alto Page 4
The UAC’s review of the information provided in this report does not meet the definition of a
project under Public Resources Code section 21065, so California Environmental Quality Act
review is not required.