HomeMy WebLinkAboutRESO 9417RESOLUTION NO. 9417
RESOLUTION OF THE COUNCIL OFTHE CITY OF PALO ALTO
MAKING FINDINGS OF FACT AND ADOPTING A MITIGATION MONITORING AND REPORTING
PROGRAM IN ACCORDANCE WITH THE CALIFORNIA ENVIRONMENTAL QUALITY ACT IN THE
CONTEXT OF APPROVAL OF THE CONSTRUCTION FUNDING AGREEMENT FOR THE SAN
FRANCISQUITO CREEK FLOOD PROTECTION PROJECT: SAN FRANCISCO BAY TO HIGHWAY 101
A. The San Francisquito Creek Joint Powers Authority (the uJPA") has prepared
plans for flood protection improvements along the lower section of San Francisquito Creek,
known as the San Francisquito Creek Flood Protection Project: San Francisco Bay to Highway
101 (the ((Project").
B. The JPA, as the Lead Agency under the California Environmental Quality Act
(uCEQA"), certified the Final Environmental Impact Report for the San Francisquito Creek Flood
Reduction, Ecosystem Restoration, and Recreation Project: San Francisco Bay to Highway 101
(the uEIR") in October 2012.
C. The JPA approved an Addendum to update information in the EIR in regard to
the longfin smelt in March 2013.
D. The City of Palo Alto (the ((City"), as one of several parties to the Construction
Funding Agreement (the ((Agreement"), is considering approval of the Agreement, because it
specifies the financial contributions that must be made by the JPA and some of its member
agencies (not including the City) in order to implement the Project.
E. The City, as a Responsible Agency under CEQA, must make certain findings prior
to making or granting any approval in support of the Project, for example, by approving the
Agreement.
F. The Council ofthe City of Palo Alto (((Council") has previously reviewed and
considered the information contained in the EIR and has received comments in regard to the
Project in a duly noticed public hearing on November 13, 2012.
The Council of the City of Palo Alto does hereby RESOLVE, as follows:
SECTION 1. The Final EIR has been completed in compliance with CEQA and is
adequate for purpose ofthe Council's consideration ofthe Project.
SECTION 2. The Final EIR reflects the independent judgment and analysis of the City.
140521sdi00710401A
SECTION 3. Changes have been incorporated into the Project which avoid and/or
substantially lessen several of the significant environmental effects identified in the Final EIR.
SECTION 4. Specific economic, social, and technological considerations make
infeasible mitigation for certain significant environmental effects of the Project. The Findings of
Fact, attached at Exhibit A, include a statement of overriding considerations that support
approval of the Project.
SECTION 5. The Findings of Fact are supported by substantial evidence in the record.
SECTION 6. The Mitigation, Monitoring, and Reporting Program (the "MMRP"t
attached as Appendix F in the Final EIR, and incorporated herein by this reference, is adopted.
The implementation ofthe MMRP is required as a condition of approval ofthe Project.
SECTION 7. Consistent with the California Public Resources Code, the documents
which constitute the record of proceedings for approval of this Project are located at the Office
of the City Clerk, 250 Hamilton Avenue, Palo Alto, California.
INTRODUCED AND PASSED: June 2, 2014
AYES: BERMAN, BURT, HOLMAN, KLEIN, KNISS, PRICE, SCHARFF, SCHMID, SHEPHERD
NOES:
ABSENT:
ABSTENTIONS:
ATIEST:
~ rl. ~ Y1i<._u 17
CityCierk r Mayor ~~--
APPROVED AS TO FORM: ~~
Senior Assistant City Attorney
Exhibit A
Resolution of the Council of the City of Palo Alto
Making Findings of Fact and Statement of Overriding Considerations for the San
Francisquito Creek Project Final EIR
FINDINGS OF FACT AND STATEMENT OF OVERRIDING CONSIDERATIONS BY THE
COUNCIL OF THE CITY OF PALO ALTO REGARDING THE FINAL ENVIRONMENTAL
IMPACT REPORT FOR THE SAN FRANCISQUITO CREEK FLOOD REDUCTION
ECOSYSTEM RESTORATION. AND RECREATION PROJECT-SAN FRANCISCO BAY TO
HIGHWAY 101
This document presents Findings of Fact (the "Findings") and a Statement of Overriding
Considerations (the "Statement") by the City of Palo Alto (the "City") regarding the Final
Environmental Impact Report (the "EIR") for the San Francisquito Creek Flood Reduction
Project, East Bayshore Road to San Francisco Bay (the "Project"), for which the City is acting as
a responsible agency under the California Environmental Quality Act ("CEQA"). The Findings
and the Statement presented herein were prepared in compliance with CEQA and the State's
CEQA Guidelines. Substantial evidence supporting all findings made herein is contained in the
EIR and/or the record of proceedings.
If a proposed project would have significant adverse effects on the environment, CEQA requires
a responsible agency to prepare findings describing how those effects would be reduced or
avoided. Under California Public Resources Code Section 21081(a), several findings are
possible. They include:
(1) Changes or alterations have been required in, or incorporated into, the project which
mitigate or avoid the significant effects on the environment.
(2) Those changes or alterations are within the responsibility and jurisdiction of another
public agency and have been, or can and should be, adopted by that other agency.
(3) Specific economic, legal, social, technological, or other considerations, including
considerations for the provision of employment opportunities for highly trained
workers, make infeasible the mitigation measures or alternatives identified in the
environmental impact report.
For any significant effects that cannot be avoided or reduced to a less-than-significant level, the
responsible agency must describe the reasons why mitigation or adoption of an alternative
approach is infeasible (California Public Resources Code ·Section 21081(a)(3)). Adoption of a
project that would have significant adverse effects on the environment requires that the lead
agency identify the project benefits that are evaluated as outweighing its significant effects on
the environment (Public Resources Code Section 21081(b)).
I. BACKGROUND
The Project proposes flood reduction facilities along an approximately 1.5-mile stretch of San
Francisquito Creek (the "Creek") from East Bayshore Road to the San Francisco Bay. Flooding
from the Creek is a common occurrence. A major flood event occurred as a result of record
creek flows in February 1998, when the Creek overtopped its banks in several areas, affecting
approximately 1 ,700 residential, commercial, and public structures and causing more than $28
San Francisquito Creek Flood Protection Project
Findings
Page 1 of28
million in property damages. The maximum instantaneous peak flow recorded during the
February 1998 event was 7,200 cubic feet per second ("cfs") The U.S. Army Corps of Engineers
estimates that the 1998 flood was a 45-year flood event. A 100-year flood event1 is anticipated
to result in flows of 9,400 cfs at the mouth of the Creek. These flows would exceed the existing
capacity of the Creek (San Francisquito Creek Joint Powers Authority 2009). The Project would
increase conveyance capacity of floodwaters from runoff and tides from the bay to protect
residents and property from flood events along the lower section of the Creek.
A. The City's role in the Project
The San Francisquito Creek Joint Powers Authority ("JPA") was formed in 1999 following the
flood of 1998, is a regional government agency whose members include the Cities of Palo Alto,
Menlo Park, and East Palo Alto; the San Mateo County Flood Control District, and the Santa
Clara Valley Water District. The JPA plans and implements flood management, ecosystem
restoration and recreational enhancements throughout the San Francisquito Creek watershed
and floodplain. The City plans to approve the Construction Funding Agreement that specifies
the financial contributions from the JPA and its member agencies needed to allow the
construction of the Project.
B. The City's Role as a Responsible Agency under CEQA.
The JPA, as the lead agency for the Project under CEQA, certified the Final EIR for the Project
in October 2012. In March 2013, the JPA prepared an Addendum to the Final EIR to evaluate
environmental effects associated with longfin smelt. When the JPA certified the EIR, it also
adopted a Mitigation Monitoring and Reporting Program (the "MMRP") and adopted a statement
of overriding considerations regarding the impacts that cannot be mitigated to less than
significant levels.
The City is a responsible agency for the Project under CEQA as it approved planning
entitlements, authorizing the Project, and will approve easem.ents allowing the Project to be
constructed on City-owned property. As a responsible agency, the City is required to consider
the environmental review document prepared by the lead agency and make findings regarding
the environmental effects of those parts of the Project that the City decides to carry out, fund or
approve.
C. The City's Review and Consideration of the Final EIR and Addendum
The Final EIR for the Project consists of the Draft EIR (July 2012), the Final EIR (October 2012),
and the Addendum (March 2013). These components are collectively referred to as the EIR in
the findings.
Prior to taking action on the Project, the Council of the City of Palo Alto fully reviewed and
considered the information contained in the record of proceedings. In accordance with PRC §
21167.6(e), the record of proceedings for the City's decision on the Project includes the
following documents:
1 The 1 00-year flood is more accurately referred to as the 1 percent annual exceedance probability flood because it is
a flood that has a 1 percent chance of being equaled or exceeded in any single year. A 1 00-year flood has
approximately a 63.4 percent chance of occurring in any 1 00-year period, not a 100 percent chance of occurring, but
conversely could theoretically occur in consecutive years.
San Francisquito Creek Flood Protection Project
Findings
Page 2 of28
• Notice of Preparation, September 15, 201 0;
• Draft EIR (July 2012) and all appendices thereto;
• Final EIR (October 2012) and all appendices thereto;
• Addendum to the EIR (March 2013);
• All written comments received in response to, or in connection with, environmental
documents prepared for the Project, including responses to the Notice of Preparation,
• Documents cited or referenced in the Draft EIR and Final EIR;
• All findings adopted by the JPA and the City for the Project;
• All reports, studies, memoranda, maps, staff reports, or other planning documents
relating to the Project prepared by the JPA or consultants to the JPA with respect to the
City's compliance with CEQA and with respect to the City's action on the Project;
• Any recordings of public meetings, public workshops and public hearings held by the
City in connection with the Project; and
• Any other materials required for the record of proceedings by Public Resources Code
Section 21167.6, subdivision (e).
The Council designates the City Clerk of the City of Palo Alto, 250 Hamilton Avenue, Palo Alto,
CA 94301, as the custodian of documents and record of proceedings on which the decision was
based.
D. Project Objectives
Protection from the 1 00-year flood (1 percent flood protection) is the currently accepted standard
for flood protection works, and the Project is being designed specifically to meet a goal of
providing 1 percent flood protection for residents and businesses along the San Francisquito
Creek corridor. The specific objectives include the following:
• Protect properties and infrastructure between . East Bayshore Road and the San
Francisco Bay from Creek flows resulting from 1 00-year fluvial flood flows occurring at
the same time as a 100-year tide that includes projected sea level rise through 2067.
• Accommodate future flood protection measures that might be constructed upstream of
the Project.
• Enhance habitat along the Project reach, particularly habitat for threatened and
endangered species.
• Enhance recreational uses.
• Minimize operational and maintenance requirements.
£:, Project Description
The Project proposes to increase the Creek's capacity from San Francisco Bay to East
Bayshore Road by:
• Excavating sediment deposits within the channel to maximize conveyance.
• Rebuilding levees and relocating a portion of the southern levee to widen the channel to
reduce the influence of tides and increase channel capacity.
• Constructing floodwalls in the upper reach to increase capacity and maintain consistency
with the California Department of Transportation's (Caltrans) enlargement of the U.S.
1 01/East Bayshore Road Bridge over the Creek.
San Francisquito Creek Flood Protection Project
Findings
Page 3 of28
Major Project elements include:
• An overflow terrace at marsh elevation adjacent to the Baylands Preserve.
• Levee setback and improvements to widen the channel and increase levee height and
stability between East Palo Alto and the Palo Alto Golf Course.
• Floodwalls in the upper reach downstream of East Bayshore Road.
• Extension of Friendship Bridge via a boardwalk across new marshland within the
widened channel.
The majority of the Project's elements would occur on properties in Palo Alto and East Palo Alto
and are owned by the City within the Santa Clara Valley Water District's (the "District") or City of
East Palo Alto rights-of-way.
E Seeping and Draft EIR Circulation
The JPA submitted the Notice of Preparation ("NOP") for the Project to the State Clearinghouse
on September 15, 2010. Two public scoping meetings were held in September 2010. To reach
as many community members as possible, the first meeting (midday Wednesday, September
29, 2010) was held at the East Palo Alto Senior Center in East Palo Alto, and the second
meeting (Thursday evening, September 30, 201 0) was held at the International School of the
Peninsula in Palo Alto. Both meetings were publicized through direct mailings to approximately
11 ,000 affected and interested households, offices, and agencies.
The JPA circulated the Draft EIR for a 45-day public and agency review period, beginning on
July 30, 2012 and concluding on September 13, 2012. The Draft EIR and Notice of Completion
were transmitted to the State Clearinghouse on July 30, 2012. Bound hard copies of the Draft
EIR were placed on reserve at several public venues, including the East Palo Alto Public
Library, Palo Alto Public Library, and the JPA's offices in Menlo Park. The Draft EIR was also
niade available in electronic format online, via the JPA's website. Notice of the Draft EIR's
availability was e-mailed to interested parties, including adjacent residents and other community
members who had requested Project notification. Two public hearings to solicit comments on
the Draft EIR were held at 6 p.m. on August 15 and August 29, 2012 at East Palo Alto City Hall
(2415 University Avenue) in the East Palo Alto City Council Chambers.
G. Final EIR
Based on comments received on the Draft EIR, changes were made to the document and a
response was provided for each comment. The Final EIR consists of the following materials:
copies of all comments on the Draft EIR received by the JPA; the JPA's responses to those
comments; and the complete text of the EIR, including revisions made in response to comments
received. The Final EIR and all associated materials in the administrative record are
incorporated herein by this reference. The JPA certified the Final EIR on October 25, 2012.
!i Addendum to the EIR
Based on comments received from the California Department of Fish and Wildlife ("CDFW')
about longfin smelt, an Addendum to the EIR was prepared. The Addendum determined that
the Project, as proposed, including seasonal restrictions to in-channel work to avoid impacts to
steelhead, would not have a significant impact on longfin smelt. The Addendum to the EIR is
San Francisquito Creek Flood Protection Project
Findings
Page 4 of28
incorporated herein by this reference. The JPA considered and approved the Addendum on
March 18, 2013.
II. SIGNIFICANT IMPACTS WHICH CAN BE MITIGATED TO A LESS THAN
SIGNIFICANT LEVEL
The EIR identified a number of potentially significant environmental impacts that, absent the
adoption of mitigation measures, could occur with the implementation of the Project. The
Proposed Project was considered to have potentially significant impacts on odors, biological
resources, paleontological resources, greenhouse gas emissions, hazardous materials and
public health, flood hazards, noise and vibrations, and traffic.
The Council finds that, in response to each significant effect identified in the EIR and listed in
this section, all feasible changes or alterations have been required in, or incorporated into, the
Project which avoid or substantially lessen these environmental effects. With implementation of
the proposed mitigation measures described in the EIR and briefly summarized below, the
proposed Project is determined to have less-than-significant impacts on these resources except
for impacts on, air quality and recreational facilities, discussed in Section Ill, below.
The findings regarding the level of impacts and their mitigation are not intended to state all of
the substantial evidence in the EIR, or elsewhere in the record, that supports the conclusions
stated in these findings. In addition, the mitigation measures are described in an abbreviated
fashion; the EIR should be consulted for a complete description of the requirements of these
measures.
A CREATION OF OBJECTIONABLE ODORS
Impact
Project construction activities could generate odors associated with diesel exhaust, paving
activities, and other construction-related sources. Odors would be temporary and localized but
could still result in disturbance, potentially rising to the level of a significant impact, for all Project
elements, especially where construction takes place in close proximity to residences.
Mitigation
Odor impacts would be reduced to less-than-significant levels through Mitigation Measure
AQ2.1-Implement Tailpipe Emission Reduction for Project Construction, which requires all
construction contractors to implement the exhaust Basic Construction Mitigation Measures and
Additional Construction Mitigation Measures recommended by the Bay Area Air Quality
Management District ("BAAQMD") to control exhaust emissions; Mitigation MeasL(re AQ2.2-
Fieet Modernization for Onroad Material Delivery and Haul Trucks during Construction, which
requires that all on-road heavy-duty diesel trucks with a gross vehicle weight rating of 19,500
pounds or greater used at the Project site will comply with U.S. Environmental Protection
Agency (EPA) 2007 on-road emission standards for particulate matter less than 10 microns in
diameter (PM10) and oxides of nitrogen (NOx); Mitigation Measure AQ2.3-Modemization for
Directional Drilling Equipment during Construction, which requires that the contractor's
equipment used for directional drilling meet EPA Tier 2 or higher emissions standards, in
addition to being outfitted with the best available control technology ("BACT") devices certified
San Francisquito Creek Flood Protection Project
Findings
Page 5 of28
by the California Air Resources Board (GARB) that achieve emissions reductions no less than
what coul~ be achieved by a Level 2 or Level 3 diesel emissions control strategy for a similarly
sized engine as defined by GARB regulations; and Mitigation Measure NV1.3-Designate
Construction Noise and Air Quality Disturbance Coordinator to Address Resident Concerns,
which designates a representative to act as construction noise and air quality disturbance
coordinator, responsible for resolving construction noise and air quality concerns.
Finding
Changes or alterations have been required in, or incorporated into, the Project which mitigate or
avoid the significant effects on the environment. The Council finds that Mitigation Measures
AQ2.1, AQ2.2, AQ2.3, and NV1.3 are feasible and will adopt them as described in the Final
EIR. These measures will be incorporated into the Project construction documents (plans and
specifications) to ensure their implementation. With these measures in place, impacts related to
creation of objectionable odors during construction would be less than significant.
B. Biological Resources
81 -Disturbance or Loss of Special-Status Plant Populations
Impact
For all Project elements, construction activities could damage or remove individuals of the
following special-status species with potential to occur in the Project area: Alkali milkvetch, San
Joaquin spearscale, Congdon's tarplant, Point Reyes bird's-beak, Hairless popcornflower,
Slender-leaved pondweed, California seablite, and/or Saline clover. However, it is unlikely that
the Project would have any impact on Slender-leaved pondweed, if it is determined to be
present. Substantial loss of individuals of any of these species as a result of construction
disturbance (earthwork, staging activities, foot traffic, vehicle traffic, or other activity) or
destruction of suitable habitat adjacent to an existing population could result in a significant
impact on the species.
Mitigation
To ensure that significant impacts on special-status plants during Project construction are
avoided if possible, and are compensated if they cannot be avoided, the following measures will
be implemented: Mitigation Measure 8101.1-Conduct Botanical Surveys, Mitigation Measure
8101.2-Confine Construction Disturbance and Protect Special-Status Plants during
Construction, and Mitigation Measure 8101.3-Compensate for Loss of Special-Status Plants.
Mitigation Measure 8101.1 requires a qualified botanist to survey suitable habitat in the Project
area for special-status plants during the appropriate blooming periods for each species, in
accordance with the California Native Plant Society (CNPS) Botanical Survey Guidelines
(California Native Plant Society 2001). Mitigation Measure 8101.2 would be implemented if it is
determined that individuals of identified special-status plant species are present and could be
affected by construction traffic or activities. It requires that construction disturbance be confined
to the minimum area necessary to complete the work and requires avoidance of adjacent
habitat. If deemed necessary by a qualified botanist, a species-appropriate buffer area
determined in consultation with agency (California Department of Fish and Wildlife [CDFW] and
U.S. Fish and Wildlife Service [USFWS]) staff will be established to protect the special status
plants from encroachment and damage during construction by installing temporary construction
fencing. Mitigation Measure 8101.3 would be implemented if any individuals of listed special-
San Francisquito Creek Flood Protection Project
Findings
Page 6 of28
status plants are present and cannot be effectively avoided through implementation of Mitigation
Measure 8101.2. This measure requires that a compensation plan be developed and
implemented so that there is no net loss of special-status plants.
Finding
Changes or alterations have been required in, or incorporated into, the Project which mitigate or
avoid the significant effects on the environment. The Council finds that Mitigation Measures
8101.1, 8101.2, and 8101.3 are feasible and will adopt them as described in the Final EIR.
These measures will be incorporated into the Project construction documents (plans and
specifications) and a Mitigation Monitoring Plan to ensure their implementation. With these
measures in place, impacts related to disturbance or loss of special-status plant populations
during construction would be less than significant.
82 -Disturbance. Injury. or Mortality of Western Pond Turtles
Impact
In the Project area, levee lowering on the right bank, levee raising on the right bank, levee
raising on the left bank and levee relocation, construction of the access road on the left bank,
and modification to Friendship Bridge have the potential to disturb upland habitat adjacent to the
freshwater pond in the Project area and could result in the loss of western pond turtle individuals
or nests; this potential for disturbance and loss would represent a significant impact.
Mitigation
Impacts to western pond turtles would be reduced to less than significant by implementing
Mitigation Measure 8102.1-Develop and Implement Worker Awareness Training, Mitigation
Measure 8102.2-lmplement Survey and Avoidance Measures to Decrease Disturbance to
Western Pond Turtles, and (if necessary) Mitigation Measure 8102.3-Dai/y Surveys and
Monitoring of Construction Activities to Decrease Disturbance to Western Pond Turtles.
Mitigation Measure 8102. 1 requires that prior to construction, Worker Awareness Training be
conducted to inform construction workers of their responsibilities regarding sensitive
environmental resources. Mitigation Measure 8102.2 requires that prior to the start of
construction activities at Project element sites that could support western pond turtle, a qualified
biologist is retained to conduct preconstruction surveys for western pond turtles. If
preconstruction surveys identify active nests, the biologist will establish no-disturbance buffer
zones in consultation with CDFW. If western pond turtles are found during the pre-construction
survey, then Mitigation Measure 8102.3 will be implemented, which requires that a qualified
biologist be retained to conduct daily surveys for western pond turtles in all suitable habitats in
the vicinity of work sites that will be active within the 3 days prior to the onset of site preparation
and construction activities with the potential to disturb turtles or their habitat. If a turtle is found
during the daily survey, construction in the vicinity of the .turtle will not commence until the turtle
is removed from the Project area to be relocated to suitable habitat outside of the Project limits
per CDFW protocols and permits.
Finding
Changes or alterations have been required in, or incorporated into, the Project which mitigate or
avoid the significant effects on the environment. The Council finds that Mitigation Measures
8102.1, 8102.2, and 8102.3 are feasible and will adopt them as described in the Final EIR.
These measures will be incorporated into the Project construction documents (plans and
specifications) and a Mitigation Monitoring Plan to ensure their implementation. With these
San Francisquito Creek Flood Protection Project
Findings
Page 7 of28
measures in place, impacts related to disturbance, injury, or mortality of western pond turtles
during construction would be less than significant.
B3 -Disturbance of Nesting Migratory Birds and Raptors (Excluding Burrowing Owl)
Impact
For all Project elements, heavy equipment and human activity during construction would
increase noise in the vicinity of the work area, potentially resulting in disturbance of birds
nesting and foraging in the area. If occupied nests are present on or adjacent to the construction
area, construction activities could result in the abandonment of nests, the death of nestlings,
and the destruction of eggs in active nests. Migratory birds, raptors, and their nests are
protected under the Migratory Bird Treaty Act and the California Fish and Game Code.
Disturbance of nesting migratory birds or raptors thus represents a significant impact.
Mitigation
Implementation of Mitigation Measure BI02.1-Develop and Implement Worker Awareness
Training described above, and Mitigation Measure BI03. 1-Estab/ish Buffer Zones for Nesting
Raptors and Migratory Birds (Excluding Burrowing Owl) would reduce the potential for impacts
on nesting raptors and migratory birds to less than significant.
Mitigation Measure Bl03. 1 requires that prior to the start of construction activities that begin
during the migratory bird nesting period (between January 15 and August 31 of any year}, a
qualified wildlife biologist be retained to conduct a survey for nesting raptors and migratory birds
that could nest along the Project corridor; and with the exception of raptor nests, inactive bird
nests may be removed. If an active nest is discovered during these surveys, the qualified wildlife
biologist will establish a no-disturbance buffer zone around the nest tree or nest in consultation
with CDFW, and construction will be stopped if necessary.
Finding
Changes or alterations have been required in, or incorporated into, the Project which mitigate or
avoid the significant effects on the environment. The Council finds that Mitigation Measures
8102.1 and 8103.1 are feasible and will adopt them as described in the Final EIR. These
measures will be incorporated into the Project construction documents (plans and
specifications) and a Mitigation Monitoring Plan to ensure their implementation. With these
measures in place, impacts related to disturbance of nesting migratory birds and raptors
(excluding burrowing owl) during construction would be less than significant.
B4 -Disturbance of Western Burrowing Owls and Habitat
Impact
Project elements with potential to affect this species include levee lowering on the right bank,
levee raising on the left bank and levee relocation, construction of the floodwall on the left bank,
construction of the downstream access road on the right bank, and construction of the upstream
access road on the right bank. Construction activities within these Project element sites during
the nesting period could result in direct injury or mortality, as well as disturbance impacts related
to elevated noise and human presence. Impacts could be significant.
San Francisquito Creek Flood Protection Project
Findings
Page 8 of28
Mitigation
Implementation of Mitigation Measure BI02.1-Develop and Implement Worker Awareness
Training described above (western burrowing owl awareness will be included in the
preconstruction worker awareness training required for all construction personnel) and
Mitigation Measure BI04.1-Implement Survey and Avoidance Measures for Western
Burrowing Owls Prior to Construction Activities would reduce this impact to less than significant.
Mitigation Measure BI04.1 requires that, prior to any construction activity, a qualified wildlife
biologist be retained to conduct seasonally appropriate preconstruction surveys for burrowing
owls. If any western burrowing owls are found within 250 feet of the construction footprint,
during the survey or at any time during the construction process, CDFW will be notified and
work will proceed under CDFW direction. Any necessary buffers will be established in
consultation with CDFW.
Finding
Changes or alterations have been required in, or incorporated into, the Project which mitigate or
avoid the significant effects on the environment. The Council finds that Mitigation Measures
8102.1 and 8104.1 are feasible and will adopt them as described in the Final EIR. These
measures will. be incorporated into the Project construction documents (plans and
specifications) and a Mitigation Monitoring Plan to ensure their implementation. With these
measures in place, impacts related to disturbance of western burrowing owls and their habitat
during construction would be less than significant.
85-Disturbance of California Clapper Rail and California Black Rail and Habitat
Impact
Clapper rail and black rail are considered to have a high potential to be present in suitable
habitat within and adjacent to the Project area. Disturbance of species and habitat could result
from construction activities associated with the following Project elements: levee lowering on
right bank, levee raising on right bank, construction of the floodwall on right bank, levee raising
on left bank and levee relocation, construction of the floodwall on left bank, modification of
Friendship Bridge, and all marshland restoration Project elements. In addition, maintenance of
Project facilities identified as being in or near suitable habitat would have some potential to
disturb California clapper rail and California black rail. Thus, construction and maintenance
impacts could be significant.
Mitigation
Implementation of Mitigation Measure BI02.1-Develop and Implement Worker Awareness
Training described above (California clapper rail and California black rail awareness will be
included in the preconstruction worker awareness training required for all construction
personnel), Mitigation Measure BI05.1-Implement Survey and Avoidance Measures for
California Clapper Rail and California Black Rail Prior to Construction Activities, and Mitigation
Measure BI05.2-Produce and Implement Habitat Monitoring Plan for Habitat within the Faber
Tract Prior to Construction Activities would reduce disturbance on California clapper rail and
California black rail to less than significant.
Mitigation Measure BI05. 1 states that work activities within 50 feet of California clapper rail
habitat will not occur within 2 hours before or after extreme high tides (6.5 feet or above) when
the marshplain is inundated. In addition, seasonally appropriate surveys will be conducted by a
permitted biologist. During breeding season, if necessary, Project activities occurring within 500
San Francisquito Creek Flood Protection Project
Findings
Page 9 of28
feet of active nests will be postponed until after young have fledged. Outside breeding season, if
necessary, no-disturbance buffer will be established, and no work will occur within the buffer
until the biologist verifies that California clapper rail or California black rail individuals have left
the area. If individuals are routinely observed in the work area, a species avoidance plan will be
developed in coordination with USFWS and CDFW. Mitigation Measure 8105.2 states that a
habitat monitoring plan will be developed and implemented for existing (i.e., pre-Project) habitat
within the Faber Tract that will document baseline conditions prior to Project implementation.
Plan approval by USFWS and CDFW will be necessary before implementation of activities ·
recommended by the plan.
Finding
Changes or alterations have been required in, or incorporated into, the Project which mitigate or
avoid the significant effects on the environment. The Council finds that Mitigation Measures
8102.1, 8105.1, and 8105.2 are feasible and will adopt them as described in the Final EIR.
These measures will be incorporated into the Project construction documents (plans and
specifications) to ensure their implementation. With these measures in place, impacts related to
disturbance of California clapper rail and California black rail and habitat during construction and
operation and maintenance would be less than significant.
86 -Disturbance of Salt Marsh Harvest Mouse and Salt Marsh Wandering Shrew and
Habitat
Impact
Construction activities could disturb salt marsh harvest mouse and salt marsh wandering shrew
and habitat for the following Project elements: levee lowering on right bank, levee raising on
right bank, construction of the floodwall on right bank, levee raising on left bank and levee
relocation, construction of the floodwall on left bank, modification to Friendship Bridge, and all
marshplain restoration Project elements. In addition, increasing in periodicity of fluvial inputs
associated with the levee lowering on right bank could potentially result in habitat changes
detrimental to salt marsh harvest mouse and salt marsh wandering shrew.
Mitigation
Implementation of Mitigation Measure 8102.1-Develop and Implement Worker Awareness
Training described above (salt marsh harvest mouse and salt marsh wandering shrew
awareness will be included in the preconstruction worker awareness training required for all
construction personnel), Mitigation Measure 8105.2-Produce and Implement Habitat
Monitoring Plan for Habitat within the Faber Tract Prior to Construction Activities (which is
described above), and Mitigation Measure 8106.1-lmplement Survey and Avoidance
Measures for Salt Marsh Harvest Mouse and Salt Marsh Wandering Shrew Prior to Construction
would reduce these impacts to less than significant.
Mitigation Measure 8106.1 requires that construction and maintenance work, including site
preparation, be avoided to the extent possible within suitable habitat for these species during
their breeding seasons (February 1 to November 30). As work during the species' breeding
seasons will be necessary, a species avoidance plan will be developed and implemented in
consultation with USFWS and CDFW. In addition, vegetation clearing will be monitored by a
permitted biologist, and appropriate measures will be taken if individuals are observed.
San Francisquito Creek Flood Protection Project
Findings
Page 10 of 28
Finding
Changes or alterations have been required in, or incorporated into, the Project which mitigate or
avoid the significant effects on the environment. The Council finds that Mitigation Measures
8102.1, 8105.2, and 8106.1 are feasible and will adopt them as described in the Final EIR.
These measures will be incorporated into the Project construction documents (plans and
specifications) to ensure their implementation. With these measures in place, impacts related to
disturbance of salt marsh harvest mouse and salt marsh wandering shrew and habitat during
construction and operation would be less than significant.
87 -Disturbance of California Least Tern and Western Snowy Plover and Habitat
Impact
Levee lowering on the right bank has potential to disturb California least tern and western snowy
plover. Construction activities serving this Project element would occur near suitable habitat for
these species and could disturb nesting or foraging individuals that could be present.
Disturbance of nesting or foraging California least tern and western snowy plover would be a
significant impact. In addition, because California least tern and western snowy plover have
potential to occur in habitat in the Faber Tract, flooding from San Francisquito Creek associated
with levee lowering on right bank and subsequent habitat alteration could affect these species
as well. This habitat alteration could be significant.
Mitigation ·
Implementation of Mitigation Measures 8102.1-Develop and Implement Worker Awareness
Training described above (California least tern and western snowy plover awareness will be
included in the preconstruction worker awareness training required for all construction
personnel), Mitigation Measure 8107.1-lmplement Survey and Avoidance Measures for
California Least Tern and Western Snowy Plover Prior to Construction Activities, and Mitigation
Measure 8105.2-Produce and Implement Habitat Monitoring Plan for Habitat within the Faber
Tract Prior to Construction Activities, described above, would reduce this impact to less than
significant.
Mitigation Measure 8107.1 requires that construction work, including site preparation, will be
avoided to the extent possible within 500 feet of suitable habitat for these species during their
breeding seasons. In addition, prior to the initiation of work within 500 feet of suitable habitat
(regardless of the time of year), a permitted biologist will be retained to conduct surveys of
appropriate habitat for California least tern and western snowy plover and their nests, and
Project activities will be postponed or appropriate buffers will be established, if necessary. If
individuals are routinely observed in or within 500 feet of the work area or do not leave the work
area, a species avoidance plan will be developed in coordination with USFWS and CDFW.
Finding
Changes or alterations have been required in, or incorporated into, the Project which mitigate or
avoid the significant effects on the environment. The Council finds that Mitigation Measures
8102.1, 8105.2, and 8107.1 are feasible and will adopt them as described in the Final EIR.
These measures will be incorporated into the Project construction documents (plans and
specifications) to ensure their implementation. With these measures in place, impacts related to
disturbance of California least tern and western snowy plover and habitat during construction
and operation would be less than significant.
San Francisquito Creek Flood Protection Project
Findings
Page 11 of28
88 -Disturbance of California Red-Legged Frog and San Francisco Garter Snake and
Habitat
Impact
The following Project elements have potential to disturb California red-legged frog and San
Francisco garter snake: levee lowering on right bank; levee raising on right bank; and levee
raising on left bank and levee relocation. Construction activities for these Project elements
would occur near suitable habitat for California red-legged frog and San Francisco garter snake
and could disturb individuals that might be present in the uplands and in the ponds. Such an
effect could constitute a significant impact.
Mitigation
Implementation of Mitigation Measures 8102.1-Develop and Implement Worker Awareness
Training described above (California red-legged frog and San Francisco garter snake
awareness will be included in the preconstruction worker awareness training required for all
construction personnel) and Mitigation Measure 8108.1-lmplement Survey and Avoidance
Measures for California Red-Legged Frog and San Francisco Garter Snake Prior to
Construction Activities would reduce this impact to less than significant.
Mitigation Measure 8108. 1 requires that a permitted biologist be retained to conduct a survey of
the freshwater ponds and surrounding upland habitat prior to initiation of construction activities
in accordance with applicable protocols, and buffer areas and/or a species avoidance plan will
be developed in coordination with USFWS and CDFW if needed. ·
Finding
Changes or alterations have been required in, or incorporated into, the Project which mitigate or
avoid the significant effects on the environment. The Council finds that Mitigation Measures
8102.1 and 8108.1 are feasible and will adopt them as described in the Final EIR. These
measures will be incorporated into the Project construction documents (plans and
specifications) and a Mitigation Monitor Plan to ensure their implementation. With these
measures in place, impacts related to disturbance of California red-legged frog and San
Francisco garter snake and habitat during construction would be less than significant.
89 -Disturbance of Steelhead Trout and Suitable Habitat
Impact
Construction activities for all Project elements would occur near suitable habitat for steelhead
trout and could disturb individuals that could be present in San Francisquito Creek. Such an
effect would be considered a significant impact.
Mitigation
Implementation of Mitigation Measures 8102.1-Develop and Implement Worker Awareness
Training (steelhead trout and habitat awareness will be included in the preconstruction worker
awareness training required for all construction personnel) and Mitigation Measure 8109.1-
lmplement Avoidance Measures for Steelhead Trout Prior to Construction Activities would
reduce this impact to less than significant.
Mitigation Measure 8109. 1 requires that no in-channel construction activities will occur during
the steelhead migration period, to reduce the likelihood· that steelhead are present during
construction activities, and a qualified fisheries biologist, approved by the National Marine
San Francisquito Creek Flood Protection Project
Findings
Page 12 of 28
Fisheries Service (NMFS), will survey the construction area 1 to 2 days before the Project
begins. If no surface water is present in the immediate construction area, fish will not be
relocated. If water is present, additional procedures will be implemented to capture and relocate
fish as described in the Final EIR.
Finding
Changes or alterations have been required in, or incorporated into, the Project which mitigate or
avoid the significant effects on the environment. The Council finds that Mitigation Measures
8102.1 and 8109.1 are feasible and will adopt them as described in the Final EIR. These
measures will be incorporated into the Project construction documents (plans and
specifications) and a Mitigation Monitoring Plan to ensure their implementation. With these
measures in place, impacts related to disturbance of steelhead trout and suitable habitat during
construction would be less than significant.
810-Disturbance or Loss of Riparian Habitat
Impact
The only Project element that would affect riparian habitat is channel widening and marshplain
creation and restoration in the upper reach of San Francisquito Creek in the Project area.
Extensive trimming, pruning, or removal of riparian habitat could represent a significant impact.
Mitigation
Implementation of Mitigation Measures 8102.1-Develop and Implement Worker Awareness
Training (described above), Mitigation Measure 81011.1-ldentify and Protect Riparian
Habitats, and Mitigation Measure 81011.2-Restore Riparian Habitat would reduce impacts to
less than significant by replacing any riparian areas permanently impacted.
Mitigation Measure 81011.1 requires that a qualified biologist or ecologist be retained to survey
arid demarcate riparian habitat on or adjacent to the proposed areas of construction in the upper
reach of San Francisquito Creek. Riparian areas not slated to accommodate Project
construction will be protected from encroachment and damage during construction by installing
temporary construction fencing to create a no-activity exclusion zone in accordance with
International Society of Arboriculture tree protection zone recommendations and any additional
requirements of the resource agencies with jurisdiction. Mitigation Measure 81011.2 requires
that permanently affected riparian habitat be restored at a mitigation-to-impact ratio of 2:1, and
temporarily affected habitat restored at a minimum impact-to-mitigation ratio of 1:1 to ensure no
net loss of riparian habitat in the affected stream reach. A Mitigation Monitoring Plan will be
developed in the context of the federal and state permitting processes under the Clean Water
Act and California Fish and Game Code, and will include success criteria as specified by the
permitting agencies.
Finding
Changes or alterations have been required in, or incorporated into, the Project which mitigate or
avoid the significant effects on the environment. The Council finds that Mitigation Measures
8102.1, 81011.1, and 81011.2 are feasible and will adopt them as described in the Final EIR.
These measures will be incorporated into the Project construction documents (plans and
specifications) and a Mitigation Monitoring Plan to ensure their implementation. With these
measures in place, impacts related to disturbance of or loss of riparian habitat during
construction and operation would be less than significant.
San Francisquito Creek Flood Protection Project
Findings
Page 13 of 28
811 -Disturbance or Loss of State-or Federally Protected Wetlands
Impact
Levee and floodwall construction activities would temporarily and permanently affect diked
marsh and tidal salt marsh habitat. Additionally, marshplain creation and restoration activities
would temporarily affect tidal salt marsh habitat.
Mitigation
Implementation of Mitigation Measures 8102.1-Develop and Implement Worker Awareness
Training, which is described above, and Mitigation Measure 81012.1-Avoid and Protect
Jurisdictional Wetlands during Construction would minimize impacts on wetlands not within the
grading footprint, including the low-flow channel, to less than significant.
Mitigation Measure 81012.1 requires that a qualified resource specialist (biologist, ecologist, or
soil scientist) clearly identify wetland areas outside of the direct impact footprint with temporary
orange construction fencing before site preparation and construction activities begin at each site
or will implement another suitable low-impact measure. Construction will not encroach upon
jurisdictional wetlands identified by the wetland specialist.
Finding
Changes or alterations have been required in, or incorporated into, the Project which mitigate or
avoid the significant effects on the environment. The Council finds that Mitigation Measures
8102.1 and 81012.1 are feasible and will adopt them as described in the Final EIR. These
measures will be incorporated into the Project construction documents (plans and
specifications) to ensure their implementation. With these measures in place, impacts related to
disturbance of or loss of state-or federally protected wetlands during construction would be less
than significant.
812 -Loss of, or Damage to. Protected Trees
Impact
Construction of all Project elements could damage and/or would remove protected tree species
outside of riparian habitat. Damage to protected trees affecting their chances of survival and/or
removal of any protected trees would be considered a significant impact. Note that removal of
trees in riparian habitat is addressed and compensated separately above.
Mitigation
Implementation of Mitigation Measure 81013.1-Transplant or Compensate for Loss of
Protected Landscape Trees, Consistent with Applicable Tree Protection Regulations and
Mitigation Measure 81013.2-Protect Remaining Trees from Construction Impacts would
reduce this impact to less than significant.
Mitigation Measure 81013.1 requires that protected landscape trees slated for removal be
transplanted or replaced as appropriate in accordance with a landscape plan. Mitigation
Measure 81013.2 provides that trees not designated for removal will be protected from damage
during construction by the installation of temporary fencing in a manner consistent with
International Society of Arboriculture tree protection zone recommendations.
San Francisquito Creek Flood Protection Project
Findings
Page 14 of 28
Finding
Changes or alterations have been required in, or incorporated into, the Project which mitigate or
avoid the significant effects on the environment. The Council finds that Mitigation Measures
81013.1 and 81013.2 are feasible and will adopt them as described in the Final EIR. These
measures will be incorporated into the Project construction documents (plans and
specifications) to ensure their implementation. With these measures in place, impacts related to
disturbance of, or damage to, protected trees during construction would be less than significant.
C. Damage to Significant Paleontological Resources
Impact
Project construction activities for all Project elements, such as excavations associated with
channel widening and floodwall placement, could affect sensitive, previously undisturbed
geologic units, potentially unearthing and damaging previously unknown paleontological
resources or unique geologic features. According to available geologic maps, such sensitive
native sediments may exist on both sides of the channel nearest the upstream portion of the
Project area. Any such disturbance could result in a significant impact on sensitive deposits
potentially containing paleontological resources. The remainder of the Project site is in areas
mapped as artificial fill and artificial levee deposits of varying depth. Should Project-related
excavation extend below artificial fill, the Project could result in a significant impact on sensitive
deposits underlying the artificial fill potentially containing paleontological resources.
Mitigation
Implementation of Mitigation Measure Paleo1.1-Conduct a Pre-Construction Paleontological
Resources Field Survey and Paleontological Resources Inventory and Evaluation; Mitigation
Measure Paleo1.2-Conduct Worker Awareness training for Paleontological Resources Prior to
Construction; and Mitigation Measure CR1.3-Stop Work Immediately if Buried Cultural
Resources are Discovered Inadvertently would reduce impacts on paleontological resources to
less than significant level.
Mitigation Measure Paleo1.1 requires that qualified personnel be retained to conduct a
paleontological resources field survey to determine whether significant resources exist, and
paleontological resources monitoring will be conducted if necessary. Mitigation Measure
Paleo1.2 requires that prior to the initiation of any site preparation and/or start of construction,
all construction workers receive training overseen by a qualified professional paleontologist, to
ensure that forepersons and field supervisors can recognize paleontological resources in the
event that any are discovered during construction. Mitigation Measure CR1.3 requires that if
paleontological resources are discovered during ground-disturbing activities, work will stop in
that area and within 100 feet of the find until a qualified paleontologist can assess the
significance of the find and, if necessary, develop appropriate treatment measures in
consultation with project sponsors as appropriate.
Finding
Changes or alterations have been required in, or incorporated into, the project which mitigate or
avoid the significant effects on the· environment. The Council finds that Mitigation Measures
Paleo1.1, Paleo1.2 and CR1.3 are feasible and will adopt them as described in the Final EIR.
These measures will be incorporated into the Project construction documents (plans and
specifications) to ensure their implementation. With these measures in place, impacts related to
significant paleontological resources during construction would be less than significant.
San Francisquito Creek Flood Protection Project
Findings
Page 15 of28
D. Generate greenhouse gas emissions. either directly or indirectly, that may have a
significant impact on the environment
Impact
Individual projects contribute to the cumulative effects of climate change by directly or indirectly
emitting greenhouse gases (GHGs) during construction phases. Project operation would not
generate any direct long-term, operational emissions, or contribute to indirect emissions. While
not established as a construction threshold, construction-related emissions from the Project are
slightly above the Bay Area Air Quality Management District's (BAAQMD) 1,100 metric ton
operational threshold.
Mitigation
BAAQMD's Air Quality Guidelines do not recommend a GHG em1ss1on threshold for
construction-related emissions. However, they do recommend implementation of best
management practices (BMPs) to help control and reduce GHG emissions. Implementation of
BAAQMD's BMPs is therefore required to reduce construction-related GHG emissions. Impact
GHG1 is considered less than significant with implementation of Mitigation Measure GHG1.1-
Implement BAAQMD Best Management Practices for Construction, which requires use of
alternative fueled vehicles, local building materials, and construction waste recycling.
Finding
Changes or alterations have been required in, or incorporated into, the project which mitigate or
avoid the significant effects on the environment. The Council finds that Mitigation Measure
GHG1.1 is feasible and will adopt it as described in the Final EIR. This measure will be
incorporated into the Project construction documents (plans and specifications) to ensure its
implementation. With this measure in place, impacts related to generation of greenhouse gas
emissions, either directly or indirectly, that may have a significant impact on the environment
during construction would be less than significant.
E. Hazardous Materials and Public Health
E1 -Creation of Hazard through Transport. Use. or Disposal of Hazardous Materials
Impact
Construction and maintenance of all Project elements would require the use of hazardous
substances such as vehicle fuels, lubricants, and solvents. Improper storage and handling,
including spills and releases, could result in exposure of the workers and the general public to
toxins and carcinogens, a significant impact. In addition, Periodic activities required to maintain
the new Project elements would require the use of vehicle fuels, lubricants, etc., and could also
require solvents, paints, paving media, and other substances and would be similar to existing
maintenance requirements. As for construction, improper storage and handling, including spills
and releases, could result in exposure of the workers and the general public to toxins and
carcinogens, a significant impact.
Mitigation
Implementation of Mitigation Measure HAZ1.1-Preparation and Implementation of a Spill
Prevention, Control, and Countermeasure Plan and Mitigation Measure and HAZ1.2-Require
Proper Storage and Handling of Potential Pollutants and Hazardous Materials would reduce this
impact to less than significant.
San Francisquito Creek Flood Protection Project
Findings
Page 16 of 28
Mitigation Measure HAZ1.1 requires that the contractor prepare and implement a Spill
Prevention, Control, and Countermeasure Plan before any construction activities begin; and
Measure HAZ1.2 requires that the storage and handling of potential pollutants and hazardous
materials be in accordance with all local, state and federal laws and other requirements.
Finding
Changes or alterations have been required in, or incorporated into, the project which mitigate or
avoid the significant effects on the environment. The Council finds that Mitigation Measures
HAZ1.1 and HAZ 1.2 are feasible and will adopt them as described in the Final EIR. These
measures will be incorporated into the Project construction documents (plans and
specifications) to ensure their implementation. With these measures in place, impacts related to
the transport, use or disposal of hazardous materials, either directly or indirectly, that may have
a significant impact on the environment during construction and maintenance, would be less
than significant.
E2 -Exposure of Workers or the Public to Existing Hazardous Materials Contamination
Impact
Due to current and historic uses of properties adjacent to the Project site, there is a possibility of
undocumented soil and/or groundwater contamination that, if disturbed, could impact the Project
site. This translates to some risk that construction workers or the public could be exposed to
hazardous substances through disturbance during Project construction, potentially constituting a
significant impact.
Mitigation
Any impacts would be reduced to a less-than-significant level by implementing Mitigation
Measure HAZ1.1-Preparation and Implementation of a Spill Prevention, Control, and
Countermeasure Plan, which is described above, and Mitigation Measure HAZ2.1-Stop Work
and Implement Hazardous Materials Investigations and Remediation in the Event that Unknown
Hazardous Materials Are Encountered would reduce this impact to less than significant.
Finding
Changes or alterations have been required in, or incorporated into, the project which mitigate or
avoid the significant effects on the environment. The Council finds that Mitigation Measures
HAZ1.1 and HAZ2.1 are feasible and will adopt them as described in the Final EIR. These
measures will be incorporated into the Project construction documents (plans and
specifications) to ensure their implementation. With these measures in place, impacts related to
exposure of workers or the public to existing hazardous materials contamination during
construction would be less than significant.
E3 -Generation of Hazardous Emissions/Use of Hazardous Materials within 0.25 Mile
of Schools
Impact
The upstream portion of the Project reach is located within 0.25 mile of the International School
of the Peninsula. Because construction would require the use of a variety of hazardous
substances, there would be some potential for exposure of students, school employees, and the
public to hazardous materials. The same would be true for ongoing maintenance activities. This
is a potentially significant impact for all Project elements.
San Francisquito Creek Flood Protection Project
Findings
Page 17 of28
Mitigation
This impact would be reduced to less than significant by implementing Mitigation Measure
HAZ1. 1-Preparation and Implementation of a Spill Prevention, Control, and Countermeasure
Plan, which is described above.
Finding
Changes or alterations have been required in, or incorporated into, the project which mitigate or
avoid the significant effects on the environment. The Council finds that Mitigation Measure
HAZ1.1 is feasible and will adopt it as described in the Final EIR. This measure will be
incorporated into the Project construction documents (plans and specifications) to ensure its
implementation. With this measure in place, impacts related to generation of hazardous
emissions/use of hazardous materials within 0.25 Mile of schools during construction and·
maintenance would be less than significant.
E4 -Interference with Emergency Response or Evacuation Plan
Impact
For all Project elements, the presence of construction equipment and vehicles, worker activities,
and materials storage would have the potential to impede emergency access to the Project site
and/or interfere with emergency evacuation plans. This would also be true for maintenance
activities, although to a lesser degree because fewer pieces of equipment and vehicles would
typically be involved. This is a potentially significant impact.
Mitigation .
Implementation of Mitigation Measure TT1-Require a Site-Specific Traffic Control Plan, which
requires contractors to develop and implement a traffic control plan for each construction site
and would impose similar requirements for maintenance activities, would reduce this impact to
less than significant.
Finding
Changes or alterations have been required in, or incorporated into, the project which mitigate or
avoid the significant effects on the environment. The Council finds that Mitigation Measure TT1
is feasible and will adopt it as described in the Final EIR. This measure will be incorporated into
the Project construction documents (plans and specifications) to ensure its implementation. With
this measure in place, impacts related to interference with an emergency response or
evacuation plan during construction and maintenance would be less than significant.
E5 -Breeding or Harborage of Disease Vector Organisms
Impact
Construction of any of the Project elements has potential to create or expand the potential for
mosquito breeding in the Project area, which would be a significant impact.
Mitigation
Mitigation Measure HAZ8.1-Prevent Mosquito Breeding During Project Construction, which
requires that standing water that accumulates on the construction site be removed within four
days (96 hours) and that construction personnel properly dispose of unwanted or unused
artificial containers and tires, would reduce this impact to less than significant.
San Francisquito Creek Flood Protection Project
Findings
Page 18 of 28
Finding
Changes or alterations have been required in, or incorporated into, the project which mitigate or
avoid the significant effects on the environment. The Council finds that Mitigation Measure
HAZ8.1 is feasible and will adopt it as described in the Final EIR. This measure will be
incorporated into the Project construction documents (plans and specifications) to ensure its
implementation. With this measure in place, impacts related to breeding or harborage of disease
vector qrganisms during construction would be less than significant.
F -Effects on Flood Hazards
Impact
For all Project elements, water diversions associated with Project construction have the
potential to disrupt storm water flows within the Creek during significant storm events.
Temporary relocation of storm drains would occur during the dry season. This is a potentially
significant impact. In addition, the permanent alteration of storm drainage facilities as a result of
new Project facilities (i.e., levees) could affect conditions during flood events. This impact has
the potential to be significant if relocated storm drains are not designed to accommodate
preconstruction flood flows.
Mitigation
Mitigation Measure HWR1.1-Design of Temporary Relocation of Storm Drainage Facilities
during Construction states that temporary storm drainage design during construction will include
the necessary review and assessment of alternative routes and ancillary facilities to ensure that
they can safely accommodate the redirected flow to the same level of design and performance
(i.e., storm drain capacity) as that of the existing facilities until such time that the original
facilities are restored. Implementation of Mitigation Measure HWR1.1 reduces construction
impacts to less than significant.
Mitigation Measure HWR1.2-Design of Permanent Relocation of Storm Drainage Facilities
states that the permanent relocation of stormwater conveyance facilities would be designed so
as not to alter the original outlet locations and internal routes. The design will include the
necessary review and assessment of pipeline additions and ancillary facilities to ensure that
they can safely accommodate flood flows to the same level of design and performance (i.e.,
storm drain capacity) as that of the existing facilities. Implementation of Mitigation Measure
HWR1.2 reduces operational impacts to less than significant.
Finding
Changes or alterations have been required in, or incorporated into, the Project which mitigate or
avoid the significant effects on the environment. The Council finds that Mitigation Measures
HWR 1.1 and HWR 1.2 are feasible and will adopt them as described in the Final El R. These
measures will be incorporated into the Project construction documents (plans and
specifications) to ensure their implementation. With these measures in place, impacts related to
flood hazards during construction and operation would be less than significant.
San Francisquito Creek Flood Protection Project
Findings
Page 19 of 28
G -Noise and Vibration
G1 -Excessive Groundborne Vibration Levels
Impact
For all Project elements, pile driving associated with Pacific Gas and Electric (PG&E) tower
relocations is expected to exceed the thresholds at which vibration may become an annoyance
and/or damage plaster-walled residential structures for homes within 50 feet of the proposed
tower locations. In addition, vibration impacts may be significant ·tor the first row of homes
located within approximately 25 feet of the construction sites using heavy construction
equipment that is not high-impact equipment. ·
Mitigation
Mitigation Measure NV2. 1-Conduct Construction Vibration Monitoring and Implement Vibration
Control Approach(es) would reduce this impact to less than significant. It requires that during
periods of construction a qualified acoustical consultant or engineering firm to conduct vibration
monitoring at homes or occupied vibration-sensitive buildings to determine if the measured peak
particle velocity (PPV) is in excess of 0.2 inches/second. If the threshold is exceeded,
construction activity will cease and alternative methods of construction and excavation will be
considered. In addition, if permitted, a preconstruction survey will be conducted that documents
any existing cracks or structural damage at vibration-sensitive receptors by means of color
photography or video, and a designated complaint coordinator (Mitigation Measure NV1.3) will
be responsible for handling and responding to any complaints received during such periods of
construction.
Finding
Changes or alterations have been required in, or incorporated into, the Project which mitigate or
avoid the significant effects on the environment. The Council finds that Mitigation Measure
NV2.1 is feasible and will adopt it as described in the Final EIR. This measure will be
incorporated into the Project construction documents (plans and specifications) to ensure its
implementation. With this measure in place, impacts related to excessive groundborne vibration
levels during construction would be less than significant.
G2 -Substantial Temporary Increase in Ambient Noise
Impact
For all Project elements, construction activities could result in substantial short-term noise
increases at noise-sensitive land uses that could rise to the level of a significant impact.
Mitigation
Implementation of Mitigation Measure NV4.1-Provide Advance Notification of Construction
Schedule and 24-Hour Hotline to Residents, Mitigation Measure NV4.2-Implement Work Site
Noise Control Measures, Mitigation Measure NV4.3-Designate a Noise and Air Quality
Disturbance Coordinator to Address Resident Concerns, and Mitigation Measure NV4.4-Install
Temporary Noise Barriers would reduce this impact to less than significant.
Mitigation Measure NV4.1 requires that advance written notification of the proposed
construction activities be provided to all residences and other noise and air quality sensitive
uses within 750 feet of the construction site, including the name and contact information of the
San Francisquito Creek Flood Protection Project
Findings
Page 20 of28
person responsible for ensuring that reasonable measures are implemented to address the
problem. Mitigation Measure NV4.2 requires that all contractors adhere to specific noise control
measures. Mitigation Measure NV4.3 states that the JPA will designate a representative to act
as construction noise and air quality disturbance coordinator, responsible for resolving
construction noise and air quality concerns. Mitigation Measure NV4.4 requires that if a resident
or school employee submits a complaint about construction noise, and the contractor is unable
to reduce noise levels to below the significance threshold (exceeding 110 dBA at a distance of
25 feet) through other means, the contractor will install temporary noise barriers to reduce noise
levels below the applicable construction noise standard, and work will be suspended until
barriers are installed.
Finding
Changes or alterations have been required in, or incorporated into, the Project which mitigate or
avoid the significant effects on the environment. The Council finds that Mitigation Measures
NV4.1, NV4.2, NV4.3, and NV4.4 are feasible and will adopt them as described in the Final EIR.
These measures will be incorporated into the Project construction documents (plans and
specifications) to ensure their implementation. With these measures in place, impacts related to
substantial temporary increases in ambient noise during construction would be less than
significant.
H -Traffic and Transportation
H1 -Potential to Create Traffic Safety Hazards
Impact
For all Project elements, the presence of large, slow-moving construction-related vehicles and
equipment among the general-purpose traffic on roadways in the study area could result in
safety hazards, which would be a significant impact.
Mitigation
To address the potential for safety hazards related to construction traffic Mitigation Measure
TT1-Require a Site-Specific Traffic Control Plan, will be implemented which requires
contractors to develop and implement a traffic control plan for each construction site. This
measure would reduce this impact to less than significant.
Finding
Changes or alterations have been required in, or incorporated into, the Project which mitigate or
avoid the significant effects on the environment. The Council finds that Mitigation Measure TT1
is feasible and will adopt it as described in the Final EIR. This measure will be incorporated into
the Project construction documents (plans and specifications) to ensure its implementation. With
this measure in place, impacts related to potential to create traffic safety hazards during
construction would be less than significant.
H2 -Potential to Obstruct Emergency Access
Impact
At all Project work areas, construction would have the potential to affect emergency vehicle
access. Construction-related traffic .could also delay or obstruct the movement of emergency
vehicles on local area roadways. This would be a potentially significant impact.
San Francisquito Creek Flood Protection Project
Findings
Page 21 of28
Mitigation
Implementation of Mitigation Measure TT1-Require a Site-Specific Traffic Control Plan, which
is described above, would include provisions to ensure unrestricted access and passage for
emergency vehicles and would reduce this impact to less than significant.
Finding
Changes or alterations have been required in, or incorporated into, the Project which mitigate or
avoid the significant effects on the environment. The Council finds that Mitigation Measure TT1
is feasible and will adopt it as described in the Final EIR. This measure will be incorporated into
the Project construction documents (plans and specifications) to ensure its implementation. With
this measure in place, impacts related to potential to obstruct emergency access during
construction would be less than significant.
H3 -Potential to Conflict with Alternative Transportation
Impact
Construction of all Project elements would require closure of existing pedestrian and bicycle
trails located on both sides of the Project portion of the Creek and Friendship Bridge. In
addition, the support transit and/or bikeways on the designated truck routes of the Project could
be interrupted by slow moving trucks. The impact on the alternative transportation would be
temporary but significant.
Mitigation
Implementation of Mitigation Measure TT1-Require a Site-Specific Traffic Control Plan, which
is described above, would include provisions for maintaining safe, efficient passage for transit,
bicyclists, and pedestrians and would reduce this impact to less than significant.
Finding
Changes or alterations have been required in, or incorporated into, the Project which mitigate or
avoid the significant effects on the environment. The Council finds that Mitigation Measure TT1
is feasible and will adopt it as described in the Final EIR. This measure will be incorporated into
the Project construction documents (plans and specifications) to ensure its implementation. With
this measure in place, impacts related to potential to conflict with alternative transportation
during construction would be less than significant.
Ill. SIGNIFICANT IMPACTS WHICH CANNOT BE FULLY MITIGATED
Even after the adoption of all feasible mitigation, the Project may cause or contribute to
potentially significant, unavoidable environmental effects on air quality and recreation. The
Council finds that the proposed Project will result in the following potentially significant and
unavoidable impacts, even with the implementation of all feasible mitigation:
Violation of an Air Quality Standard or Substantial Contribution to Existing or
Projected Air Quality Violation
Changes or alterations have been required in, or incorporated into, the Project which minimize
the significant effects on the environment to the greatest extent feasible, but the Council finds
San Francisquito Creek Flood Protection Project
Findings
Page 22 of28
that mitigation is unlikely to reduce NOx emissions to a less than significant level (i.e., mitigation
is unlikely to reduce NOx emissions below BAAQMD daily emission threshold of 54 pounds per
day), and that no alternate or additional mitigation that would provide such a reduction has been
identified as feasible. Consequently, the Council finds that a significant residual impact is likely
during construction of some of the Project elements.
The following mitigation measures, as described in the Final EIR, will be incorporated into the
Project construction documents (plans and specifications) to ensure their implementation:
Mitigation Measure AQ2.1-Implement Tailpipe Emission Reduction for Project Construction,
Mitigation Measure AQ2.2-Fieet Modernization for Onroad Material Delivery and Haul Trucks
during Construction, Mitigation Measure AQ2.3-Modernization for Directional Drilling
Equipment during Construction, Mitigation Measure NV1.1-Provide Advance Notification of
Construction Schedule and 24-Hour Hotline to Residents, and Mitigation Measure NV1.3-
Designate Construction Noise and Air Quality Disturbance Coordinator to Address Resident
Concerns. The proposed mitigation measures represent all feasible, cost-effective mitigation
measures to reduce exhaust emissions to be implemented by the construction contractor.
Although the maximum emissions would be generated only when construction activities from all
Project elements overlap and would likely to be short-term, the impact would still be significant
and unavoidable with mitigation incorporated.
With implementation of all feasible mitigation, Project construction would generate daily
emissions of NOx exceeding the BAAQMD threshold for various Project components during all
construction phases: Utility Relocation, Phase One, and Phase Two. During the Utility
Relocation phase, gas line work and directional drilling would result in daily NOx emissions of
65.71 lbs/day. During Phase One, construction of the new left bank levee and construction of
the right bank levee would result in daily NOx emissions of 110.45 and 94.63 lbs/day,
respectively. During Phase Two, Conservative Scenario 1----,overlap of gas line work, directional
drilling, and construction of new left bank levee (Utility Relocation and Phase One) would result
in daily NOx emissions of 176.16 lbs/day. In addition, a second scenario was evaluated for
Phase Two. Conservative Scenario 2-overlap of site prep, installation of right and left bank
floodwalls, and flatbed trailer truck trips (Phase Two) would result in daily NOx emissions of
68.45 lbs/day.
In summary, the Council will adopt mitigation (Measures AQ2.1, AQ2.2, AQ2.3, NV1.1, and
NV1.3) that comprise all of the approaches identified as feasible to reduce criteria pollutant
impacts associated with construction of various Project elements. However, even with these
measures in place, pollutant levels could intermittently be high enough to exceed BAAQMD
thresholds. Any such exceedance would constitute a significant residual impact, and is
considered unavoidable.
Exposure of Sensitive Receptors to Substantial Pollutant Concentrations .
Changes or alterations have been required in, or incorporated into, the Project which mitigate
the significant effects on the environment to the greatest extent feasible, but the Council finds
that mitigation is unlikely to reduce Toxic Air Contaminant ("TAC") emissions to a less-than-
significant level (i.e., mitigation is unlikely to reduce TAC emissions below BAAQMD daily
emission thresholds: annual PM2.5 concentration of 0.3 micrograms per cubic meter (1Jg/m3),
cumulative diesel particulate matter ("DPM") cancer risk of 100 per million, and cumulative
average annual PM2.5 concentration of 0.8 1Jg/m3), and that no alternate or additional mitigation
that would provide such a reduction has been identified as feasible. Consequently, the Council
finds that a significant residual impact· is likely during construction of some of the Project
elements.
San Francisquito Creek Flood Protection Project
Findings
Page 23 of28
The following mitigation measures, as described in the Final EIR, will be incorporated into the
Project construction documents (plans and specifications) to ensure their implementation:
Mitigation Measure AQ2.1-Implement Tailpipe Emission Reduction for Project Construction,
·Mitigation Measure AQ2.2-Fieet Modernization for Onroad Material Delivery and Haul Trucks
during Construction, Mitigation Measure AQ2,3-Modernization for Directional Drilling
Equipment during Construction, Mitigation Measure NV1.1-Provide Advance Notification of
Construction Schedule and 24-Hour Hotline to Residents, and Mitigation Measure NV1.3-
Designate Construction Noise and Air Quality Disturbance Coordinator 'to Address Resident
Concerns. The proposed mitigation measures represent all feasible, cost-effective mitigation
measures to reduce exhaust emissions to be implemented by the construction contractor.
With implementation of all feasible mitigation, Project construction would generate daily
emissions of PM2.5 and DPM exceeding the BAAQMD threshold for various Project elements
during all construction phases: Utility Relocation, Phase One, and Phase Two. During the Utility
Relocation phase, construction of Shoofly Towers (T1-4) and gas line work/directional drilling
would result in annual PM2.5 concentrations of 0.65 and 0.40 1Jg/m3, respectively. During Phase
One, site preparation would result in an annual PM2.5 concentration of 0.46 1Jg/m3; construction
of new left bank levee would result in an annual PM2.5 concentration of 0.52 1Jg/m3;
modifications to Friendship Bridge would result in an annual PM2.5 concentration of 0.35 1Jg/m3;
and channel widening and marsh plain terracing would result in an annual PM2.5 concentration
of 1.57 1Jg/m3, cumulative DPM cancer risk of 141.83/million, and cumulative average annual
PM2.5 concentration of 2.45 1Jg/m3. During Phase Two, site preparation would result in a
cumulative DPM cancer risk of 139.77/million and a cumulative average annual PM2.5
concentration of 1.13 1Jg/m3; installation of right and left bank floodwalls would result in an
annual PM2.5 concentration of 3.46 1Jg/m3, cumulative DPM cancer risk of 149.23/million, and a
cumulative average annual PM2.5 concentration of 4.35 1Jg/m3; construction of upstream access
road on right and left banks would result in a cumulative DPM cancer risk of 139.83/million and
a cumulative average annual PM2.5 concentration· of 1.18 1Jg/m3; Conservative Scenario 1-
overlap of gas line work, directional drilling and construction of new left bank levee (Utility
Relocation and Phase One) -would result in an annual PM2.5 concentration of 0.9 1Jg/m3, a
cumulative DPM cancer risk of 0.6/million, and a cumulative average annual PM2.5
concentration of 0.9 1Jg/m3; Conservative Scenario 2-overlap of site prep, installation of right
and left bank floodwalls, and Flatbed trailer truck trips (Phase Two) -would result in an annual
PM2.5 concentration of 3.7 1Jg/m3, a cumulative DPM cancer risk of 149.3/million, and a
cumulative average annual PM2.5 concentration of 4.6 1Jg/m3.
In summary, the Council will adopt mitigation (Measures AQ2.1, AQ2.2, AQ2.3, NV1.1, and
NV1.3) that comprise all of the approaches identified as feasible to reduce impacts associated
with TAC emissions during construction of various Project elements. However, even with these
measures in place, TAC levels could intermittently be high enough to exceed BAAQMD
thresholds. Any such exceedance would constitute a significant residual impact, and is
considered unavoidable.
Result in Reduced Availability of Existing Recreational Facilities or Uses
Changes or alterations have been required in, or incorporated into, the Project which mitigate
the significant effects on the environment. The Project would relocate the levee on the left bank
of San Francisquito Creek inland from its existing location, thereby widening the Creek and
cutting through a portion of the Golf Course. To accommodate the new levee footprint and
maintain playability of the course, holes 12 through 15 (which are adjacent to the Creek) and
certain holes among the remaining fourteen holes would need to be reconfigured on a timetable
San Francisquito Creek Flood Protection Project
Findings
Page 24 of28
to be determined by the City of Palo Alto. The total area of the Golf Course to be permanently
incorporated into the Project is 7.4 acres. The converted portion of the Golf Course would
remain dedicated parkland, but would be permanently converted from Golf Course use to open
space as part of the Project. However, it is feasible to reconfigure the Golf Course design in
order to maintain or improve the Golf Course's Professional Golfers' Association (PGA) rating
and its playability. Mitigation Measure REC-1-Compensate the City of Palo Alto for the
Conversion of 7.4 Acres of the Palo Alto Municipal Golf Course to Accommodate Project
Features requires the SFCJPA to provide monetary compensation to the City to compensate for
the costs of reconfiguring the Golf Course to maintain its PGA regulation status. Implementation
of the proposed mitigation measure REC-1 would reduce permanent impacts on the Golf
Course to a less-than-significant level.
The Council finds that implementation of Mitigation Measure REC-1 is within the responsibility
and jurisdiction of the City and has been, or can and should be, adopted by the City. Since the
City does not have the ability to guarantee the implementation of this measure, a significant and
unavoidable impact on the Golf Course is assumed. The JPA is committed to providing funding
to compensate for the costs of reconfiguring the Golf Course as described in Mitigation Measure
REC-1.
In summary, the Council will adopt Mitigation Measure REC-1 that comprises all of the
approaches identified as feasible to reduce impacts associated with the permanent
incorporation of 7.4 acres of the Golf Course into the Project. However, because implementation
of the mitigation measure is outside the City's and the JPA's jurisdiction and fulfillment cannot
be guaranteed, a significant and unavoidable impact is assumed.
Contributions to Cumulative Air Quality Impacts
Impact and Project Contribution
The San Francisco Bay Area Air Basin is a nonattainment area for the federal 8-hour ozone
standard, the state 1-hour ozone standard, and the state PM10 and PM2.5 standards; this
represents a significant existing cumulative impact on air quality. Construction of the proposed
project would temporarily increase emissions of ozone precursors, such as NOx. BAAQMD has
established emissions thresholds which it believes a project's individual operational criteria
pollutant emissions would be cumulatively considerable. Therefore, it considers the project-level
criteria pollutant thresholds to address both project-level and cumulative impacts (Bay Area Air
Quality Management District 2011). The Project's construction emissions were estimated to
exceed BAAQMD daily emission threshold for NOx. Therefore, construction-related tailpipe
emissions are expected to constitute a considerable contribution to existing cumulative air
quality degradation, notwithstanding the mitigation incorporated into the Project as discussed
above.
Mitigation
Implementation of Mitigation Measures AQ2.1 through AQ2.3 and Mitigation Measures NV1.1
and NV1.3 discussed above would reduce NOx emissions, but BAAQMD's NOx thresholds
would still be exceeded. Therefore, the project's construction activities on cumulative air quality
impacts are expected to be significant and unavoidable.
Finding
Changes or alterations have been required in, or incorporated into, the Project which mitigate or
avoid the significant effects on the environment. The Council finds that Mitigation Measures
San Francisquito Creek Flood Protection Project
Findings
Page 25 of28
AQ2.1 through AQ2.3 and Mitigation Measures NV1.1 and NV1.3 are feasible and will adopt
these measures as described in the Final EIR. These measures will be incorporated into the
Project construction documents (plans and specifications) to ensure their implementation.
However, even with this measure in place, the Project is expected to have a cumulatively
considerable contribution to regional air quality degradation.
Except for the temporary air quality impacts from construction, and recreational impacts to the
Palo Alto Golf Course, the Council finds that the EIR identifies no significant environmental
effects of the proposed Project which cannot be mitigated to levels of insignificance and further
finds that all impacts will either be avoided or reduced to a level that is both insignificant and
acceptable. All mitigation measures which are included in the proposed Project and EIR
(whether or not they are expressly designated as mitigation measures), or which are referenced
in these Findings, or which are included in the Mitigation Monitoring and Reporting Program,
shall be deemed adopted as part of the Council's approval of the Project and certification of the
Final EIR to the extent they have been identified as measures to be undertaken by the City.
IV. ALTERNATIVES ANALYSIS
CEQA requires that an EIR describe a range of reasonable alternatives to a project, or to the
location of a project, which could reduce potential impacts while still attaining the basic
objectives of the project, and to evaluate the comparative merits of the alternatives. CEQA
Guidelines also require that the range of alternatives considered include a "No Project"
alternative. For comparative purposes, the objectives of the Proposed Project are set forth in
Section I. D of these findings, and impacts are analyzed in Sections II and Ill above. As set forth
below, the JPA considered various alternatives in selecting the Proposed Project.
The Council finds the following with regard to the alternatives analyzed in the EIR, as discussed
in more detail below.
• The EIR describes a reasonable range of alternatives to the Project as proposed.
• The Council has evaluated the comparative merits of the alternatives and rejected them
in favor of the proposed Project.
• There are no feasible alternatives within the City's powers that would substantially
lessen or avoid any significant effects from the Project.
The EIR analyzed two alternatives advanced from the preliminary alternatives analysis in
addition to the Project as proposed: Alternative 3 (Golf Course Bypass) and the No Project
Alternative.
Findings Regarding the Alternatives-Environmentally Superior Alternative
Alternative 3 (Golf Course Bypass) includes in-channel marshplain terraces, similar to the
Project and a large bypass channel extending across the center of the Golf Course. It does not
include levee setbacks in either the middle or upper reaches as set forth in the Project. The
differentiating feature of Alternative 3 is a large bypass channel extending from south to north
through the center of the Golf Course. This bypass reach would intersect the existing channel
just downstream of the Baylands Athletic Center and reconnect with the main channel near the
San Francisquito Creek Flood Protection Project
Findings
Page 26 of28
airport runway. During both normal daily flows and fluvial flood events, a portion of upstream
flows would be diverted through the bypass channel, therefore significantly reducing water
levels in the middle reach and conveying a large percentage of flows away from the residences
of East Palo Alto. Maintenance and operations of Alternative 3 would be identical to those of the
Project. Although Alternative 3 would accomplish Project goals and objectives and reduce
impacts on biological resources it would result in greater impacts to aesthetics, cultural
resources, land use, noise and vibration, recreation, and traffic. The Council finds that specific
economic, legal, social, or other considerations make this alternative infeasible. Specifically, the
Council finds this alternative infeasible and undesirable from a policy standpoint because it
would result worse environmental impacts when compared to the Project.
The No Project Alternative would avoid numerous significant impacts identified for the proposed
Project, but would not accomplish the Project's identified goal and objectives. The Council finds
that specific economic, legal, social, or other considerations make this alternative infeasible.
Specifically, the Council finds that this alternative is infeasible because it would not meet the
Project objectives.
V STATEMENT OF OVERRIDING CONSIDERATIONS
As described in the Background section, flooding from the Creek is a common occurrence and
the most recent major flood event in February 1998 affected approximately 1 ,700 residential,
commercial, and public structures and caused more than $28 million in property damages. The
maximum instantaneous peak flow recorded during the February 1998 event was 7,200 cfs. The
USACE estimates that the 1998 flood was a 45-year flood event. A 1 00-year flood event is
anticipated to result in flows of 9,400 cfs at the mouth of the Creek, and these flows would
exceed the existing capacity of the Creek (San Francisquito Creek Joint Powers Authority
2009). Protection from the 100-year flood (1-percent flood protection) is the currently accepted
standard for flood protection works, and the Project is being designed specifically to meet a goal
of providing 1 percent flood protection for residents and businesses along the San Francisquito
Creek corridor.
Construction of the Project would likely result in significant and unavoidable effects on air quality
associated with construction of various Project elements during all Project phases. The Council
finds that the construction-related air quality impacts are temporary and an unavoidable
byproduct of the need to use heavy equipment to complete the Project. The Project would also
result in significant and unavoidable effects related to reduced availability of existing
recreational facilities due to the permanent incorporation of 7.4 acres of the Golf Course into the
Project. The City has committed to all feasible mitigation to reduce this impacts, but the
implementation of the mitigation measure for recreation impacts is outside the City's and JPA's
jurisdiction and fulfillment cannot be guaranteed. No additional feasible mitigation is available.
The Council finds that specific economic, legal, social, technological, or other considerations
make infeasible any additional mitigation measures or Project alternatives identified in the Final
EIR, as detailed above in Section IV. All feasible mitigation measures have been incorporated
into the Project by way of adoption of the Mitigation Monitoring and Reporting Program, as
requirements of implementation of the Project.
San Francisquito Creek Flood Protection Project
Findings
Page 27 of 28
In making this Statement of Overriding Considerations in support of the findings of fact and the
Project, the Council has considered information contained in the Final EIR for the Project as well
as the public testimony and record of proceedings in which the Project was considered. The City
has balanced the Project's benefits against the unavoidable adverse impacts identified in the
Final EIR. This determination is made based upon the public benefits identified in the Finai.EIR
and record of proceedings as flowing from the Project.
The project provides long term solution to flood management
Key project objectives include improving public safety through flood risk management;
accommodating future flood protection measures upstream; enhancing habitat and recreational
opportunities in the project area; and minimizing maintenance needs of the Project. The
impacts of the Project are localized to the project vicinity, but the Project provides long term
regional benefits from implementation.
The Council finds that the benefits of the Project outweigh the unavoidable adverse
environmental effects
The Final EIR was prepared pursuant to the CEQA Guidelines. The Council has independently
determined that the Final EIR fully and adequately analyzes the impacts and mitigation
measures of the Project. The number of Project alternatives identified and considered in the EIR
meets the test of "reasonable" analysis and provides the Council with important information from
which to make an informed decision. Substantial evidence in the record from public meetings
and other sources demonstrates various benefits and considerations including economic, legal,
social, and technological which would be achieved from implementation of the Project.
In consideration of the existing flood risks along the Creek associated with lack of adequate
capacity in the Creek channel, and the analysis of the Project outcomes presented in the Final
EIR, the Council balanced the Project's benefits and considerations against the unavoidable
and irreversible environmental risks identified in the EIR and concluded that those impacts are
outweighed by the Project's benefits. Upon balancing the environmental risk and countervailing
Project's benefits, the Council has concluded that the benefits that will derive from
implementation of the Project outweigh those environmental risks many of which are temporary.
The remaining unavoidable and irreversible impacts of the Project are acceptable in light of
economic, legal, social, technological, and other considerations set forth herein because the
benefits of the Project outweigh any significant and unavoidable or irreversible environmental
impact of the Project.
San Francisquito Creek Flood Protection Project
Findings
Page 28 of 28