HomeMy WebLinkAboutStaff Report 10363
City of Palo Alto (ID # 10363)
Policy and Services Committee Staff Report
Report Type: Action Items Meeting Date: 6/11/2019
City of Palo Alto Page 1
Summary Title: Status Updates of Audit Recommendations for Utilities
Department
Title: Staff Recommends the Policy and Services Committee Recommend the
City Council Accept the Status Updates on Recommendations from Audits of;
1) Water Meter Billing Accuracy, 2) Electric Substructure Contract Oversight,
and 3) the Cross Bore Inspection Contract
From: City Manager
Lead Department: Utilities
Recommendation
Staff recommends that the Policy and Services Committee recommend that the City Council
accept the status updates of the audits of Water Meter Billing Accuracy, Electric Substructure
Contract Oversight, and the Cross Bore Inspection Contract.
Background
The City Auditor’s Office previously issued audits of Water Meter Billing Accuracy, Electric
Substructure Contract Oversight, and the Cross Bore Inspection Contract.
Status updates are provided in Attachments A, B and C. All of the recommendations in the
Contract Oversight and Cross Bore Inspection audits are complete. Three items remain open in
the Water Meter Billing Accuracy audit; with one item pending for completion by Utilities
Department staff, and two items pending completion by Purchasing Department staff.
The open recommendations include a comprehensive utility field meter survey and updates to
the Purchasing Manual and Policies and Procedures. The field verification includes conducting
an inspection survey of approximately 75,000 electric, gas and water meters to validate meter
condition, size, and location. The survey is expected to begin in May 2019 and will be
completed within one year. The Administrative Services Department is in the process of
revising the Purchasing Manual and Policies and Procedures. Recommended revisions should
be completed by end of calendar year 2019.
Attachments:
• Attachment A - Accuracy of Water Meter Billing
City of Palo Alto Page 2
• Attachment B - Contract Oversight-Trenching
• Attachment C - Cross Bore Inspection Contract
STATUS OF AUDIT RECOMMENDATIONS
ACCURACY OF UTILITY WATER METER BILLING AUDIT – ISSUED 8/16/17
PAGE 1
The City Manager has agreed to take the following actions in response to the audit recommendations in this report. The City Manager will report progress on
implementation six months after the Council accepts the audit report, and every six months thereafter until all recommendations have been implemented.
Recommendation
Responsible
Department(s) Original Response and Target Date
Current Status
(Complete, In
Progress, or Not
Started) Implementation Update and Expected Completion Date
Finding 1: CPAU has not adequately prevented, detected, nor corrected water meter billing errors.
We recommend that CPAU:
1.1. Review and correct the meter
record errors identified for
meter sizes larger than 2
inches.
Utilities Concurrence: Agree
Target Date: December 2018
Action Plan: In preparation for the new
CIS Utility billing system and potential
advanced meter deployment, staff will
consider an in-house or contract service
audit of the three metered services
(electric, gas, water). Staff will also review
and update as needed roles and
responsibilities for key staff involved in
ensuring meter accuracy, including
procurement, inventory, testing,
installation, and billing records
management.
In progress June 2019 Management Update:
In preparation of new metering and billing systems and in
response to the audit, staff is retaining a consult to perform
a comprehensive utility field meter survey. The field
verification includes conducting an inspection survey of
approximately 75,000 electric, gas and water meters to
validate and ensure accurate meter data.
The contract was approved by Council in April 2019. The
project is scheduled to start in May 2019 and will be
completed within one year.
Expected Completion Date: May 2020
June 2018 Management Update:
Staff will be issuing an RFP for contract services to conduct a
field audit of 74,000 meters. One of the requirements is
verification of service connection size for 2” or greater
water meters.
Expected Completion Date: June 2019
1.2. Explore options for addressing
equity when making changes
to customer meter size rates
and establish a policy and
process for determining,
documenting, and notifying
customers of changes to their
Utilities Concurrence: Agree
Target Date: July 2018
Action Plan: The audit’s questioning of
utility practices regarding changes to
meter sizes is based on a unique situation
that occurred 22 years ago and does not
Completed
(pending
Council’s
approval of the
FY 2020 water
rates)
June 2019 Management Update:
Staff retained a consultant to update the water cost of
service study in late 2018. Based on the study results, and to
ensure uniform administration and equitable cost
allocation, staff proposes to charge all residential customers
with 5/8”, 3/4”, and 1” meters, which include fire flow, a
STATUS OF AUDIT RECOMMENDATIONS
ACCURACY OF UTILITY WATER METER BILLING AUDIT – ISSUED 8/16/17
PAGE 2
Recommendation
Responsible
Department(s) Original Response and Target Date
Current Status
(Complete, In
Progress, or Not
Started) Implementation Update and Expected Completion Date
meter size and, if appropriate,
the rate change associated
with the new meter size.
reflect current policy or process. The
situation arising out of Southgate was a
unique case and staff does not agree that
this or other meter replacement practices
raise equity issues.
With regard to differential rates for
different meter sizes, staff is currently
reviewing policy options for addressing
this issue going forward, and will develop
options such as consolidating the fixed
rate for 5/8” and 1” meters for
consideration by the City Council.
uniform monthly service fee. The cost to the City of
providing service to these different residential meter sizes is
similar. Offering graduated meter sizes (up to 1”) is still
recommended in some cases, where there is inadequate fire
flow or low system pressure. Pending Council’s approval,
the change of monthly water meter service charges for
residential 5/8”, 3/4” and 1” meters will be effective July 1,
2019.
June 2018 Management Update:
Due to staffing changes, the Utilities Department was not
able to engage with a consultant to begin the water cost of
service study in FY 2018. Staff expects to issue an RFP in the
first half of FY 2019. Options to consolidate the fixed rates
for 5/8” and 1” meters will be considered. The study results
and staff recommendation will be brought forth for Council
review when completed.
Expected Completion Date: April 2019
Finding 2: CPAU has installed 1,178 water eMeters throughout the City’ however, there are no testing standards, and the accuracy, performance, and reliability of these
meters are uncertain.
We recommend that CPAU:
2.1. Develop a policy and
procedure to transparently
report significant, systemic,
infrastructure changes to
Council and update any CPAU
Rules and Regulations that
may be outdated to current
practice or affected by policy
changes.
Utilities Concurrence: Agree
Target Date: Immediately
Action Plan: Major infrastructure
changes are presented to Council for
approval. However, standards are
technical documents that provide the
general conditions and specifications for
the construction of the Water Gas and
Wastewater System. Updates to
Completed June 2019 Management Update:
These are the current control processes in place to
transparently report changes:
1.) Purchasing Policies and Procedures. Originating
department: Purchasing. Process status: Existing.
The purpose of this manual is to provide City
departments with a practical step‐by‐step guide
through the various stages of the purchasing
process. It also provides a means of assuring
STATUS OF AUDIT RECOMMENDATIONS
ACCURACY OF UTILITY WATER METER BILLING AUDIT – ISSUED 8/16/17
PAGE 3
Recommendation
Responsible
Department(s) Original Response and Target Date
Current Status
(Complete, In
Progress, or Not
Started) Implementation Update and Expected Completion Date
standards are subject to multiple levels of
professional review including
engineering, procurement and legal.
Updated standards will be communicated
to Council as informational when
substantive.
uniformity in the City’s purchasing practices. The
City of Palo Alto Municipal Code (Section 2.30 ‐
Contracting and Purchasing Procedures) serves as
the basis for the information in this manual.
a. Sole Source Standardization Process. When a
City department requires a specific products or
services over $10,000 that can only be
furnished by a certain provider or that should
be otherwise exempted from the competitive
solicitation process (ref. PAMC 2.30.360), the
requestor must complete an Exemption From
Competitive Solicitation Request Form
(Purchasing Manual Appendix E).
b. Contracts for professional services over
$85,000 per year and/or with terms greater
than three years require the approval of the
City Council. Chapter 14 of the Purchasing
Guide provides information regarding the
preparation of a City Manager’s Report (CMR)
to request Council contract approval.
2) Rules and Regulations. Originating
department: Utilities. Process Status: Existing.
Rules and regulations are updated as needed
to reflect new business practices and
provisions. These changes are reviewed by the
City Attorney’s Office and are brought forth to
Council for approval. Staff is currently working
with the City Attorney’s Office on updating 16
of the Rules and Regulations, for Council’s
approval later in 2019.
3) Meter and Specification Update Approval
Process. Originating department: Utilities.
Process Status: New. This process ensures that
STATUS OF AUDIT RECOMMENDATIONS
ACCURACY OF UTILITY WATER METER BILLING AUDIT – ISSUED 8/16/17
PAGE 4
Recommendation
Responsible
Department(s) Original Response and Target Date
Current Status
(Complete, In
Progress, or Not
Started) Implementation Update and Expected Completion Date
additions and deletions of meters in the
Warehouse and distribution system are
reviewed and approved by key staff and
management.
4) Utilities Engineering Electric and WGW
Construction Standards. Originating
department: Utilities. Process Status: New.
This process periodically reviews and compares
current construction standards with the
industry. The standards also specifies meter
types (i.e. Badger disc meter). Recommended
changes by staff will be brought forward to
Council for consent.
June 2018 Management Update:
The Utilities Department will inform Council when technical
standards are substantive. Since August 2017, the
department has not updated the technical standards for
electric, gas or water.
American Water Works Association (AWWA) has drafted
new standards for electromagnetic and ultrasonic type
water meters. The public comment period on the proposed
new standards closed on April 29, 2018. Final publication of
the standard may take several months. Staff will notify
Council if Utilities adopts the new electromagnetic and
ultrasonic water meter standards.
Staff will review and update existing policies and procedures
if applicable.
Expected Completion Date: June 2019
2.2. Seek direction and approval
from Council before
proceeding further with the
Utilities Concurrence: Agree
Target Date: Ongoing
Completed June 2019 Management Update:
The American Water Works Association (AWWA) standards
for electromagnetic and ultrasonic water meters were
STATUS OF AUDIT RECOMMENDATIONS
ACCURACY OF UTILITY WATER METER BILLING AUDIT – ISSUED 8/16/17
PAGE 5
Recommendation
Responsible
Department(s) Original Response and Target Date
Current Status
(Complete, In
Progress, or Not
Started) Implementation Update and Expected Completion Date
future installation of eMeters
or any electronic meters.
Action Plan: Procurement and installation
of e-meters will remain suspended until
adoption of an AWWA standard for
testing and the availability of
independent test resources (either in-
house or contracted). It is expected that
a final standard for testing of E-meters
will be available at the end of 2017. The
new standards are not expected to
change the accuracy requirements from
those expected of the positive
displacement meter with the exception
that there will likely be an extended
range of accuracy for low flows. It should
be noted the E-Meters is a specific
product line, and mechanical meters may
also have electronic components.
published in October 2018. After staff’s review and meeting
with other water agencies and consultants, staff has
decided not to install new ultrasonic water meters until the
technology matures. At this time, Utilities will not be
adopting the new electromagnetic and ultrasonic water
meter standards. Utilities will notify Council in the future
when Utilities adopt the new AWWA electromagnetic and
ultrasonic water meter standards.
June 2018 Management Update:
American Water Works Association (AWWA) has drafted
new standards for electromagnetic and ultrasonic type
water meters. The public comment period on the proposed
new standards closed on April 29, 2018. Final publication of
the standard may take several months. Staff will notify
Council if Utilities adopts the new electromagnetic and
ultrasonic water meter standards or seeks to install
additional eMeters. Expected Completion Date:
Expected Completion Date: June 2019
2.3. Determine if the 1,178
installed eMeters should be
uninstalled and replaced with
the original displacement
meter and if billing
adjustments are required.
Utilities Concurrence: Agree
Target Date: July 2018
Action Plan: All customers with e-meters
installed will be immediately notified of
this audit, and that additional information
will be provided as available. For eMeter
testing, staff will send a sampling of
eMeters to independent testing
companies to determine if they are
performing per manufacturer
specification, and based on these results
will determine next steps. In addition,
Completed June 2019 Management Update:
The American Water Works Association (AWWA) standards
for electromagnetic and ultrasonic water meters were
published in October 2018. After staff’s review and meeting
with other water agencies and consultants, staff has
decided not to install new ultrasonic water meters until the
technology matures. Palo Alto will continue to meet with
other water agencies to monitor their electromagnetic and
ultrasonic water meter pilot projects.
Staff hired a contractor to test a sampling of eMeters. The
contractor tested the eMeters under four different
STATUS OF AUDIT RECOMMENDATIONS
ACCURACY OF UTILITY WATER METER BILLING AUDIT – ISSUED 8/16/17
PAGE 6
Recommendation
Responsible
Department(s) Original Response and Target Date
Current Status
(Complete, In
Progress, or Not
Started) Implementation Update and Expected Completion Date
the Water Meter Shop has staffing
challenges and does not currently have
the resources required to undertake this
replacement project. At this time, staff
will continue to monitor the meter reads
for irregularities of both the installed
positive displacement and eMeters as
part of the billing exception process.
Staff is also developing a customer plan
for addressing any accuracy concerns
with the e-meters already installed.
scenarios. Overall, the testing results measured correctly
within the manufacturer’s specifications. Based on
manufacturer’s test results, third party sampled testing and
monthly meter reading of eMeters, staff believes these
meters are functioning properly and does not recommend
replacing them until their end of life.
Expected Completion Date:
June 2018 Management Update:
The Utilities department sent letters to the 1,178 residents
with installed eMeters. In response, 55 customers
requested their meters to be exchanged. A couple credit
adjustments were required for the eMeter exchanges. As of
June 2018, the City has 1,122 eMeters installed.
Status: Completed
Staff hired a contractor to test a sampling of eMeters. The
contractor tested the eMeters under four different
scenarios. Overall, the testing results measured correctly
within the manufacturer’s specifications and guidelines of
+/- 1.5%.
After AWWA publishes the final standards for
electromagnetic and ultrasonic type meters, staff will meet
with other water agencies to determine the pros and cons
of these meters. Staff will make a determination in 2019 on
whether to standardize displacement and/or ultrasonic type
meters.
Expected Completion Date: June 2019
STATUS OF AUDIT RECOMMENDATIONS
ACCURACY OF UTILITY WATER METER BILLING AUDIT – ISSUED 8/16/17
PAGE 7
Recommendation
Responsible
Department(s) Original Response and Target Date
Current Status
(Complete, In
Progress, or Not
Started) Implementation Update and Expected Completion Date
Finding 3: Purchase of water eMeters did not meet purchasing policy and eMeter expenditures were not monitored.
We recommend that ASD Purchasing Division:
3.1. ASD Purchasing to clarify its
purchasing policy and
procedures for new and
renewals of product
standardization.
ASD Concurrence: Agree
Target Date: December 2017
Action Plan: Staff will update the policy
and coordinate with stakeholders to
ensure the policy is clear and easy to
follow. Staff will then finalize the policy
and disseminate to departments.
In Progress June 2019 Management Update:
Revisions to the Purchasing Manual will be drafted and
reviewed by the CFO in July. Proposed changes will be
disseminated to the organization early fall 2019.
Expected Completion Date: Fall 2019
June 2018 Management Update:
This is in the queue for development to update Purchasing’s
Policy and Procedures. Purchasing has the “Solicitation Plan
Checklist” already and the nuances of the process are
currently being written. The current Exemption Form
addresses the “Standardization” process in the P&P. The
“How To” and step-by-step self-learning tool regarding
standardization are in development.
Expected Completion Date: Q4 of FY18
3.2. ASD Purchasing to retrain
appropriate ASD and CPAU
staff on Purchasing policies
and procedures, and
completion of required forms.
ASD Concurrence: Agree
Target Date: January 2018
Action Plan: In conjunction with 3.1 staff
will provide training.
In Progress June 2019 Management Update:
The targeted completion of item 3.1 is early fall 2019. We
expect to conduct ongoing training to ensure that the
Department is aware of Purchasing’s revised P&P’s
regarding standardization.
Expected Completion Date: Winter 2019
June 2018 Management Update:
Training is being done on an as needed basis. Purchasing will
STATUS OF AUDIT RECOMMENDATIONS
ACCURACY OF UTILITY WATER METER BILLING AUDIT – ISSUED 8/16/17
PAGE 8
Recommendation
Responsible
Department(s) Original Response and Target Date
Current Status
(Complete, In
Progress, or Not
Started) Implementation Update and Expected Completion Date
conduct formal training once item 3.1 is complete.
Expected Completion Date: Q2 of FY19
STATUS OF AUDIT RECOMMENDATIONS
CONTRACT OVERSIGHT: TRENCHING AND INSTALLATION OF ELECTRIC SUBSTRUCTURE – ISSUED 10/30/13
PAGE 1
The City Manager has agreed to take the following actions in response to the audit recommendations in this report. The City Manager will report
progress on implementation six months after the Council accepts the audit report, and every six months thereafter until all recommendations have been
implemented.
Recommendation
Responsible
Department Original Target Date and Response
Current
Status
Implementation Update and
Expected Completion Date
Finding 3: The Utilities Department did not enforce contract billing terms that were the basis for awarding the contract to Casey Construction, Inc.
5. The Utilities Department should
work with ASD to review existing
contract performance management
policies and develop procedures to
ensure staff appropriately
administers the City’s contracts.
Procedures should address the
following areas:
● Monitoring of contractor billings to
ensure accuracy and compliance with
contract terms.
● Ensuring contracts are
appropriately and timely modified, if
required.
Administrative
Services and
Utilities
Departments
3/31/14
Utilities staff is formalizing the
process by which contractor work is
requested, approved, inspected,
reviewed, and invoiced.
Utilities will hire a Project Coordinator
to assist Engineering in administrating
contracts, verifying invoices, and
processing payments. Utilities will be
requesting for similar positions in
Operations and Customer Support
Services in the 2014 mid‐year budget.
Utilities will also develop a tracking
mechanism to monitor contractor
work, reconcile invoices, and verify
payments.
ASD will conduct a review of the
entire purchasing process citywide.
The departments will collaborate to
bring contract management training
to appropriate staff. This training will
be rolled out to all departments.
Completed June 2019 Management Update:
Utilities has participated in construction contract and
project management training, and will continue offering
training to staff regularly or as needed. Training topics
include pre-bid conferences, prevailing wage
requirements, change orders, stop notices, payments,
project closeout and recordkeeping. The procedures
and/or guidelines for these topics have been
documented and made available for staff to use.
The Senior Engineers and Project Coordinators are
responsible for project management and contract
administration of capital projects and construction
contracts. With the additional training, staff has been
performing the administrative contract duties to ensure
contractor billing accuracy, compliance with contract
terms, and timely processing of change orders.
May 2018 Management Update:
Utilities has completed contract administration training
and will seek additional training for purchasing, project
management and risk management on an as-needed
basis.
Utilities has established general project management
STATUS OF AUDIT RECOMMENDATIONS
CONTRACT OVERSIGHT: TRENCHING AND INSTALLATION OF ELECTRIC SUBSTRUCTURE – ISSUED 10/30/13
PAGE 2
Recommendation
Responsible
Department Original Target Date and Response
Current
Status
Implementation Update and
Expected Completion Date
guidelines including roles and responsibilities,
scheduling, change orders, negotiations, payments and
contract closing. Utilities will continue to work toward
uniform implementation of the guidelines and usage of
the forms.
The Project Coordinator position remains vacant as
Utilities redefines the contract administration and
project management responsibilities of the position to
better address department needs.
ASD has and continues to collaborate with the City
Attorney’s Office on further developing the IFB
Template on a regular basis. The latest revision is made
available and in use. This collaborative effort now
includes the new “Design-Build” templates. Contracts
are regularly being uploaded into Planet Bids Contracts
Management Module. On boarding department project
managers is forthcoming. Meanwhile ASD is also
considering contracts management in an Electronic
Document Management System (EDMS), as with ARC’s
“Infolink” platform, for public record management
functionalities, like contract management.
Expected Completion Date: December 2017:
December 2015 Management Update:
In February 2015, construction contract management
training was conducted in conjunction with PWD and
ASD. The training covered procurement, project
manager responsibilities, project scheduling, change
STATUS OF AUDIT RECOMMENDATIONS
CONTRACT OVERSIGHT: TRENCHING AND INSTALLATION OF ELECTRIC SUBSTRUCTURE – ISSUED 10/30/13
PAGE 3
Recommendation
Responsible
Department Original Target Date and Response
Current
Status
Implementation Update and
Expected Completion Date
order requests, claims, payments and project closure.
In October 2015, ASD provided citywide training on
compliance to the new prevailing wage requirements
for construction and improvement contracts. The
training identified the roles and responsibilities of
Purchasing and project managers and reporting
requirements to the Department of Industrial Relations.
The Utilities Project Coordinator position is currently
vacant in Engineering. Utilities is currently reassessing
the job classification for this role and evaluating the
need for a higher Project Manager classification. Staff
will recruit for the position in 2016. Until the position is
filled, the project managers will continue administering
the contracts with support from administrative staff on
invoice verification and payments. All contract, invoice
and supporting documentations are managed in a
central shared drive.
The Invitation for Bid (IFB) template is currently in the
process of being revised to simplify and coordinate
language between other sections of the contract; the
boilerplate language should be completed by the
second half of 2016.
The firm that ASD selected to implement an invoice
management system was unable to deliver on the
scope as planned in 2015. ASD will evaluate the
possibility of acquiring another invoice management
solution or consider waiting until the new ERP system is
implemented with built in invoice management.
Expected Completion Date: Q4 2016
June 2014 Management Update: Utilities has
STATUS OF AUDIT RECOMMENDATIONS
CONTRACT OVERSIGHT: TRENCHING AND INSTALLATION OF ELECTRIC SUBSTRUCTURE – ISSUED 10/30/13
PAGE 4
Recommendation
Responsible
Department Original Target Date and Response
Current
Status
Implementation Update and
Expected Completion Date
developed contract management guidelines and a
project charter for large construction projects and
professional services. These contracts and documents
are stored on a centralized SharePoint website.
Utilities Engineering hired a Project Coordinator in
March 2014 to assist with contract administration and
project management. The coordinator has developed a
contract database, coordinated project management
training, and formalized policies and procedures.
Utilities Operations reclassified a position in the FY
2015 to assist with contract and inventory
management.
Utilities is working with the City Attorney's Office to
strengthen the boilerplate language in the IFB and
professional service contract templates.
ASD hired a consultant to perform an independent
review of the entire purchasing process. The review
recommended a new purchasing system, increased
training, and additions to the Purchasing Manual
among other recommendations. Staff is in the process
of implementing the recommendations.
ASD has selected an online invoice management system
to improve the review, approval and tracking invoices
received by the City. This system will be implemented
in 2015 and will provide increased accountability and
visibility into the invoice review and payment process.
Expected Completion Date: 6/30/15
Finding 4: The Utilities Department did not appropriately manage its contract with Casey Construction, Inc. to ensure the City’s projects were completed in
accordance with plans and cost estimates.
6. The Utilities Department should
work with ASD to review existing
Administrative
Services and
Recommendation 5 & 6 are similar.
See response to recommendation 5.
Completed June 2019 Management Update:
Utilities has established and updated general project
STATUS OF AUDIT RECOMMENDATIONS
CONTRACT OVERSIGHT: TRENCHING AND INSTALLATION OF ELECTRIC SUBSTRUCTURE – ISSUED 10/30/13
PAGE 5
Recommendation
Responsible
Department Original Target Date and Response
Current
Status
Implementation Update and
Expected Completion Date
contract performance management
policies and develop procedures to
ensure staff appropriately
administers the City’s contracts.
Procedures should address the
following areas:
• Roles and responsibilities for the
contract administrator and any
additional training requirements
for staff.
• Monitoring of contractor
performance.
• Ensuring payments are made only
for services and materials included
in the contract scope.
• Ensuring there is an adequate
process and documentation to
show planned work has been
completed.
Utilities
Departments
management guidelines and construction
administration manual including roles and
responsibilities, scheduling, change orders,
negotiations, payments, project closeout and contract
closing. The procedures, guidelines, and/or forms for
these topics have been documented and made
available for staff to use.
May 2018 Management Update:
Utilities has established general project management
guidelines including roles and responsibilities,
scheduling, change orders, negotiations, payments and
contract closing. Utilities will continue to work toward
uniform implementation of the guidelines and usage of
the forms
A vendor evaluation form has been drafted but has not
been implemented. The purpose of the evaluation
form is to monitor the performance of the vendor and
identify any incidents that occurred during the project.
Utilities will work with ASD on implementing the form.
Expected Completion Date: December 2017
December 2015 Management Update:
Utilities is monitoring contractor performance through
routine inspections, weekly meetings and
communication. During inspections, staff reviews and
verifies the contractor’s performance by documenting
and signing off the work completed (i.e. number of
boxes installed, footage of pipe installed). In the weekly
STATUS OF AUDIT RECOMMENDATIONS
CONTRACT OVERSIGHT: TRENCHING AND INSTALLATION OF ELECTRIC SUBSTRUCTURE – ISSUED 10/30/13
PAGE 6
Recommendation
Responsible
Department Original Target Date and Response
Current
Status
Implementation Update and
Expected Completion Date
meetings, staff reviews the work schedule, scope of
work, claims and change orders with the contractor.
ASD has updated the City’s procurement training guide
including contract administration roles and
responsibilities, process workflow, best practices and
common pitfalls. ASD will continue to provide
procurement training annually and update the guide on
an as-needed basis (eg., to reflect changes to prevailing
wage laws).
http://cityconnect.staff.copa/civica/filebank/blobdload.
asp?BlobID=4255
ASD implemented PlanetBids as the City’s new
eProcurement solution. PlanetBids includes a contract
management module that provides a structure for
managing contracts. This module of PlanetBids will be
rolled out to departments beginning in 2
2016.
Expected Completion Date: Q2 2016
June 2014 Management Update: Roles, responsibilities,
and workflow for contract administration are
documented and saved on SharePoint.
Utilities Engineering completed a mandatory 3-day
project management course in July 2014.
ASD provided purchasing and contract administration
training to the Executive Team and City staff in 2013
and 2014. This training will continue in 2014 and 2015
as part of an ongoing purchasing training curriculum for
City staff.
Additional Contract administration training is planned
for November 2014 with Purchasing and City Attorney's
STATUS OF AUDIT RECOMMENDATIONS
CONTRACT OVERSIGHT: TRENCHING AND INSTALLATION OF ELECTRIC SUBSTRUCTURE – ISSUED 10/30/13
PAGE 7
Recommendation
Responsible
Department Original Target Date and Response
Current
Status
Implementation Update and
Expected Completion Date
Office.
See responses above related to vendor performance
review and new invoice management system.
Expected Completion Date: 6/30/15
STATUS OF AUDIT RECOMMENDATIONS
UTILITIES DEPARTMENT: CROSS BORE INSPECTION CONTRACT AUDIT ISSUED 6/1/17
PAGE 1
The City Manager has agreed to take the following actions in response to the audit recommendations in this report. The City Manager will report progress on
implementation six months after the Council accepts the audit report, and every six months thereafter until all recommendations have been implemented.
Recommendation Responsible
Department(s) Original Response and Target Date
Current Status
(Complete, In
Progress, or Not
Started)
Implementation Update and
Expected Completion Date
Finding: 1. Hydromax inspected 10,791 (60 percent) of 18,028 laterals and could not complete nearly half of its attempted inspections because of adverse
conditions in sewer lines.
1.1. Identify sewer pipelines that
Hydromax did not fully inspect or
attempt to inspect. Prioritize these
sewer pipelines for inspection under a
future contract(s). To the extent
possible, based on past experience,
predict potential inspection
challenges, such as poor pipeline
conditions, that may hinder future
inspections. Disclose these challenges
in future contract solicitations.
Utilities Concurrence: Agree
Target Date: Late 2018
Action Plan:
Staff will review a previously
generated prioritization list based on
assessment of risk for property
classifications, review inventory of
parcels that do not have an
associated lateral, and develop a
final prioritization list and cost
estimates based on experience and
data from the original crossbore
contract. Implementation of next
phase will proceed based on
available funding.
Completed June 2019 Management Update:
Staff has completed identification of
approximately 1,200 high risk laterals for Phase 2
of the crossbore verification project. The
prioritization was based on criteria such as
occupancy rates, installation of safety devices,
service material, age of service, and proximity of
natural gas service pipelines to sewer laterals.
The Crossbore Verification Invitation for Bid (IFB)
was issued on March 26, 2019. Staff has
evaluated the four bid responses. In the IFB, staff
provides cross bore inspection guidelines which
covers video quality and inspection procedures,
specialized industry equipment, and minimum
qualifications to improve the overall success rate
of verified clear sewer laterals. The contract for
Phase 2 of the crossbore verification project is
scheduled for Council approval on June 24, 2019.
June 2018 Management Update:
Utilities Engineering performed a risk analysis of
the laterals staff identified as not completed
during the initial cross-bore project, to prioritize
future inspection and predict potential inspection
challenges. The prioritization was based on
STATUS OF AUDIT RECOMMENDATIONS
UTILITIES DEPARTMENT: CROSS BORE INSPECTION CONTRACT AUDIT ISSUED 6/1/17
PAGE 2
Recommendation Responsible
Department(s) Original Response and Target Date
Current Status
(Complete, In
Progress, or Not
Started)
Implementation Update and
Expected Completion Date
criteria such as occupancy rates, installation of
safety devices, service material, age of service,
and distance from gas service. Phase 2 priority
categories include high occupancy properties, gas
services without excess flow valves, separation
distance between sanitary sewer lateral and gas
service, and polyethylene (PE) material.
Staff expects to issue the RFP for Phase 2 of the
crossbore safety inspection program, which will
include the risk analysis findings, in summer 2018.
Staff has requested for additional budget of
$1,000,000 in FY 2019 to fund the contract.
Expected Completion Date: Q2 of FY 2019
Finding: 2. City oversight and NASSCO contracting guidelines can help ensure accurate, complete, and cost effective future inspections.
2.1. Identify missing data in its laterals
database by comparing it with
independent databases such as
Hydromax inspection data. Update its
laterals database to ensure it can
effectively serve to track inspection
progress.
Utilities Concurrence: Agree
Target Date: Mid 2018
Action Plan:
Staff will utilize existing data to
review and update the City’s GIS to
reflect missing active City-owned
laterals. This will be done in
conjunction with the inventory of
parcels referenced in Finding 1.1.
Completed June 2019 Management Update:
Staff continues to improve the information and
accuracy of the Utility database using information
gathered during all construction projects, capital
improvement projects, sewer crossbore
inspections and daily operations. This
information is identified as a Map Update
Request and Engineering researches and updates
the GIS database regularly.
June 2018 Management Update:
Staff is in the process of reconciling and updating
the lateral information in the GIS database, to
identify missing laterals. The lateral database will
be updated prior to issuance of the RFP for Phase
2 of the project.
STATUS OF AUDIT RECOMMENDATIONS
UTILITIES DEPARTMENT: CROSS BORE INSPECTION CONTRACT AUDIT ISSUED 6/1/17
PAGE 3
Recommendation Responsible
Department(s) Original Response and Target Date
Current Status
(Complete, In
Progress, or Not
Started)
Implementation Update and
Expected Completion Date
Common sewer laterals are shared by more than
one parcel, thus there is not a one to one ratio of
laterals to premises. Staff has started a
preliminary review of the various scenarios
related to parcels without sanitary sewer laterals
and has updated GIS with the two latest capital
improvement projects.
Staff is working on identifying a dedicated
resource to complete the reconciliation process
between City mapping data on GIS and Hydromax
findings.
Expected Completion Date: Q2 of FY 2019
2.2. Incorporate relevant and useful
provisions from NASSCO’s contract
template, such as linear foot pricing
and prior verification of inspector
certifications, in future sewer
inspection contracts. Consult with the
Administrative Services Department’s
purchasing staff and the City
Attorney’s Office to determine if City
can enforce NASSCO template
provisions that it plans to incorporate.
Utilities Concurrence: Agree
Target Date: Mid to Late 2018
Action Plan:
Staff will review the NASSCO
contract template and look for
provisions to incorporate in a future
City contract, as applicable.
Completed June 2019 Management Update:
In the Crossbore Verification IFB, staff requested
the City-owned sewer laterals be assessed per
NASSCO standards by a certified NASSCO Lateral
Assessment and Certification Program (LACP)
trained operator or technician. The Contractor
will identify and code pipe defects in
conformance with LACP within the portion of the
sewer lateral owned by the City. Reports from
this program will be used to prioritize laterals
with the highest deficiencies for replacement.
June 2018 Management Update:
Utilities Engineering is in the process of reviewing
and adopting applicable National Association of
Sewer Service Companies (NASSCO) standards
which are appropriate for the City. These include
industry standards for the rehabilitation of
STATUS OF AUDIT RECOMMENDATIONS
UTILITIES DEPARTMENT: CROSS BORE INSPECTION CONTRACT AUDIT ISSUED 6/1/17
PAGE 4
Recommendation Responsible
Department(s) Original Response and Target Date
Current Status
(Complete, In
Progress, or Not
Started)
Implementation Update and
Expected Completion Date
underground pipelines and continued acceptance
and growth of trenchless technologies.
Staff has started reviewing the NASSCO contract
templates and will incorporate applicable
NASSCO standards that can be applied to a future
contract.
Expected Completion Date: Q2 of FY 2019
STATUS OF AUDIT RECOMMENDATIONS
UTILITIES DEPARTMENT: CROSS BORE INSPECTION CONTRACT AUDIT ISSUED 6/1/17
PAGE 5
Recommendation Responsible
Department(s) Original Response and Target Date
Current Status
(Complete, In
Progress, or Not
Started)
Implementation Update and
Expected Completion Date
2.3. Identify gaps in staff expertise needed
to monitor and facilitate field
inspections and to review and track
inspection data. Develop a training
and certification plan for field staff
who should have the expertise to help
meet the City’s inspection goals and
objectives.
Utilities Concurrence: Agree
Target Date: Late 2018 to Start of
future contract
Action Plan:
Staff will continue to review staffing
gaps for office and field personnel. If
gaps are identified and are not
resolved by training, additional
expertise will be identified within
the City or via contract.
Completed June 2019 Management Update:
Several staff members from Engineering and
Operations have been NASSCO certified for CCTV
inspection. With the industry standard pipe
rating codes, staff will be able to prioritize sewer
mains more effectively for future replacement
projects.
Staff is also seeking knowledgeable natural gas
industry personnel to facilitate Project
Management and Inspection of gas projects.
The City will continue to provide ongoing training
and certification to employees across all utilities
with industry recognized standards organizations.
Staff will assign a dedicated City Inspector to the
crossbore verification project to field Inspect and
ensure all attempt have been made to
successfully clear sewer laterals of potential
crossbores.
June 2018 Management Update:
Currently two Operations Staff members are
NASSCO certified for CCTV inspection. Staff is
working on identifying a dedicated resource for
the GIS and database analysis experience.
Expected Completion Date: On-going