Summary Title: Status Update of Audit Recommendations for Cross Bore
Inspection Contract Audit
Title: Staff Recommendation That the Policy and Services Committee
Recommend the City Council Accept the Status Update on the Cross Bore
Inspection Contract Audit
From: City Manager
Lead Department: Utilities
Recommendation
Staff recommends the Policy and Services Committee recommend that the City Council
accept the attached Status of Audit Recommendations for the Cross Bore Inspection
Contract Audit.
Background
The City Auditor’s Office previously issued an audit with objectives to determine
whether Hydromax USA, LLC, (Hydromax) met its contract requirements for inspecting
City
sewer pipelines to rule out cross bores and whether the City exercised appropriate
contract oversight. This will be the first update since the audit was presented to Council
on June 1, 2017. (https://www.cityofpaloalto.org/civicax/filebank/documents/60898)
Staff provided an update to the Utility Advisory Commission (UAC) on January 18, 2018.
(https://www.cityofpaloalto.org/civicax/filebank/documents/62828)
Based on lessons learned from the initial Hydromax investigation, staff recommends
that subsequent inspections be phased, with the highest risk laterals inspected first.
Staff intends to issue a request for proposal (RFP) for phase 2 of the Cross-Bore Safety
Program by end of calendar year 2018 which will address high risk laterals that were
not completed previously. The RFP will address the auditor’s recommendation to
prioritize a list of sewer pipelines to inspect and incorporate applicable industry
standard National Association of Sewer Service Companies (NASSCO) guidelines into the
contract specifications.
City of Palo Alto Page 2
Since the audit, two Operations staff members have been NASSCO certified for CCTV
video inspection. The certification enables the operators to identify defects in a pipeline
system with standardized codes and ratings. Staff has requested for additional budget
of $1,000,000 in FY 2019 to fund the first year of the phase 2 contract.
Attachments:
Cross Bore Inspection_June 2018 Final 5-31-18
STATUS OF AUDIT RECOMMENDATIONS
UTILITIES DEPARTMENT: CROSS BORE INSPECTION CONTRACT AUDIT ISSUED 6/1/17
6055040 PAGE 1
The City Manager has agreed to take the following actions in response to the audit recommendations in this report. The City Manager will report progress on
implementation six months after the Council accepts the audit report, and every six months thereafter until all recommendations have been implemented.
Recommendation Responsible
Department(s) Original Target Date and Response
Current
Status
Implementation Update and
Expected Completion Date
Finding: 1. Hydromax inspected 10,791 (60 percent) of 18,028 laterals and could not complete nearly half of its attempted inspections because of adverse
conditions in sewer lines.
1.1. Identify sewer pipelines that
Hydromax did not fully inspect or
attempt to inspect. Prioritize these
sewer pipelines for inspection under a
future contract(s). To the extent
possible, based on past experience,
predict potential inspection
challenges, such as poor pipeline
conditions, that may hinder future
inspections. Disclose these challenges
in future contract solicitations.
Utilities Concurrence: Agree
Target Date: Late 2018
Action Plan:
Staff will review a previously generated
prioritization list based on assessment of
risk for property classifications, review
inventory of parcels that do not have an
associated lateral, and develop a final
prioritization list and cost estimates
based on experience and data from the
original crossbore contract.
Implementation of next phase will
proceed based on available funding.
In Progress June 2018 Management Update:
Utilities Engineering performed a risk analysis of
the laterals staff identified as not completed
during the initial cross-bore project, to prioritize
future inspection and predict potential inspection
challenges. The prioritization was based on
criteria such as occupancy rates, installation of
safety devices, service material, age of service,
and distance from gas service. Phase 2 priority
categories include high occupancy properties, gas
services without excess flow valves, separation
distance between sanitary sewer lateral and gas
service, and polyethylene (PE) material.
Staff expects to issue the RFP for Phase 2 of the
crossbore safety inspection program, which will
include the risk analysis findings, in summer 2018.
Staff has requested for additional budget of
$1,000,000 in FY 2019 to fund the contract.
Expected Completion Date: Q2 of FY 2019
Finding: 2. City oversight and NASSCO contracting guidelines can help ensure accurate, complete, and cost effective future inspections.
2.1. Identify missing data in its laterals
database by comparing it with
independent databases such as
Hydromax inspection data. Update its
Utilities Concurrence: Agree
Target Date: Mid 2018
Action Plan:
In Progress June 2018 Management Update:
Staff is in the process of reconciling and updating
the lateral information in the GIS database, to
STATUS OF AUDIT RECOMMENDATIONS
UTILITIES DEPARTMENT: CROSS BORE INSPECTION CONTRACT AUDIT ISSUED 6/1/17
6055040 PAGE 2
Recommendation Responsible
Department(s) Original Target Date and Response
Current
Status
Implementation Update and
Expected Completion Date
laterals database to ensure it can
effectively serve to track inspection
progress.
Staff will utilize existing data to review
and update the City’s GIS to reflect
missing active City-owned laterals. This
will be done in conjunction with the
inventory of parcels referenced in
Finding 1.1.
identify missing laterals. The lateral database will
be updated prior to issuance of the RFP for Phase
2 of the project.
Common sewer laterals are shared by more than
one parcel, thus there is not a one to one ratio of
laterals to premises. Staff has started a
preliminary review of the various scenarios
related to parcels without sanitary sewer laterals
and has updated GIS with the two latest capital
improvement projects.
Staff is working on identifying a dedicated
resource to complete the reconciliation process
between City mapping data on GIS and Hydromax
findings.
Expected Completion Date: Q2 of FY 2019
2.2. Incorporate relevant and useful
provisions from NASSCO’s contract
template, such as linear foot pricing
and prior verification of inspector
certifications, in future sewer
inspection contracts. Consult with the
Administrative Services Department’s
purchasing staff and the City
Attorney’s Office to determine if City
can enforce NASSCO template
provisions that it plans to incorporate.
Utilities Concurrence: Agree
Target Date: Mid to Late 2018
Action Plan:
Staff will review the NASSCO contract
template and look for provisions to
incorporate in a future City contract, as
applicable.
In Progress June 2018 Management Update:
Utilities Engineering is in the process of reviewing
and adopting applicable National Association of
Sewer Service Companies (NASSCO) standards
which are appropriate for the City. These include
industry standards for the rehabilitation of
underground pipelines and continued acceptance
and growth of trenchless technologies.
Staff has started reviewing the NASSCO contract
templates and will incorporate applicable
NASSCO standards that can be applied to a future
contract.
STATUS OF AUDIT RECOMMENDATIONS
UTILITIES DEPARTMENT: CROSS BORE INSPECTION CONTRACT AUDIT ISSUED 6/1/17
6055040 PAGE 3
Recommendation Responsible
Department(s) Original Target Date and Response
Current
Status
Implementation Update and
Expected Completion Date
Expected Completion Date: Q2 of FY 2019
2.3. Identify gaps in staff expertise needed
to monitor and facilitate field
inspections and to review and track
inspection data. Develop a training
and certification plan for field staff
who should have the expertise to help
meet the City’s inspection goals and
objectives.
Utilities Concurrence: Agree
Target Date: Late 2018 to Start of
future contract
Action Plan:
Staff will continue to review staffing
gaps for office and field personnel. If
gaps are identified and are not resolved
by training, additional expertise will be
identified within the City or via contract.
In Progress June 2018 Management Update:
Currently two Operations Staff members are
NASSCO certified for CCTV inspection. Staff is
working on identifying a dedicated resource for
the GIS and database analysis experience.
Expected Completion Date: On-going