HomeMy WebLinkAboutRESO 7940follows:
RESOLUTION NO. 7940
RESOLUTION OF THE COUNCIL OF THE CITY OF PALO ALTO
CERTIFYING THE ADEQUACY OF THE LATP SITE
DEVELOPMENT PROJECT ENVIRONMENTAL IMPACT REPORT
(STATE CLEARING HOUSE NO. 97032039) PURSUANT TO
THE CALIFORNIA ENVIRONMENTAL QUALITY ACT
The Council of the City of Palo Alto does RESOLVE as
SECTION 1. Background. The City Council of the City of
Palo Alto ("City Council") finds, determines, and declares as
follows:
A. The Los Altos Treatment Plant ("LATP") site is at the
end of North San Antonio Road, northeast of Highway 101. The site,
slightly more than 13 acres in area, was used by the City of Los
Altos as a waste water treatment plant until 1972. In 1984 the
City of Palo Alto ("City") purchased a half interest in the
property from the City of Los Altos. The two cities entered into
a lease for the property under which the City of Palo Alto managed
the property. In 1991, the City of Palo Alto Public Works
Department began studying future uses of the property.
B. In August of 1996 the City circulated a Notice of
Preparation of an Environmental Impact Report ( "EIR") on
development of the LATP site. The proposed project ("the Original
Project") included a refuse collection contractor facility, a
permanent household hazardous waste facility, and a construction
storage/staging yard for the City of Palo Alto Utility Department
field operations and contractors. The Draft EIR, dated August
1997, was circulated for public review in November and December of
1997. The public comment period was extended into January of 1998
to allow for additional public comment. The Planning Commission
held a public hearing on the Draft EIR on January 14, 1998.
C. The Planning Commission recommended certification of
the EIR when revised to respond to comments raised at its hearings.
The responses to comments made at the hearing and previous to it
are contained in that part of the Final EIR titled "Responses to
Comments-Final Environmental Impact Report, LATP Site Development
Project" dated September 1999.
D. After consideration of the Planning Commission
comments and recommendations, the Department of Public Works
revised its proposed project. The "Revised Project" is based on
the "Reduced Project Alternative" (Draft EIR Section 5.5). This
alternative eliminates the utility storage yard from the original
project. This permits preservation or restoration of 3.4 acres of
wetlands, while new development is limited to 3.8 acres.
1
000222 cl 0090423
E. The City as the lead agency for the Project has caused
to be prepared a Final Environmental Impact Report ("Final EIR").
Pursuant to State CEQA Guidelines section 15132, the Final EIR
consists of the following documents: "Draft Environmental Impact
Report-LATP Site Development Project" dated August 1997, "Responses
to Comments/Final Environmental Impact Report LATP Site Development
Project" dated September 1999," and "LATP Site Developments Project
Conceptual Mitigation and Monitoring Plan dated August 25, 1999",
and planning and other City records, minutes, and files
constituting the record of proceedings. The Final EIR was prepared
pursuant to the California Environmental Quality Act, Public
Resources Code section 21000, et seq. ("CEQA"), and the State CEQA
Guidelines, California Code of Regulations, Title 14, section
15000, et seq. The Final EIR is on file in the office of the
Director of Planning and Community Environment and, along with the
planning and other City records, minutes and files constituting the
record of proceedings, is incorporated herein by this reference.
F. The City Council, in conjunction with this resolution,
is also approving a reporting and monitoring program pursuant to
Public Resources Code section 21081.6, which program is designed to
ensure compliance with mitigation measures imposed to lessen the
significant effects identified in the Final EIR, and described in
detail in Exhibit A which is attached hereto and incorporated
herein by this reference.
SECTION 2. Certification. The City Council certifies that
the Final EIR has been completed in compliance with the California
Environmental Quality Act. The Final EIR was presented to the City
Council and the City Council has reviewed and considered the
information contained in the Final EIR. The City Council hereby
finds that the Final EIR reflects the independent judgment of the
City as lead agency.
SECTION 3. All Significant Impacts Can Be Mitigated to a
Less Than Significant Level. The City Council finds that all
significant impacts can be mitigated to a less than significant
level. Mitigation is required for construction noise, construction
impacts on air quality, soils, and biological resources (wetlands).
Compliance with the proposed mitigation measures in the Final EIR
would reduce these impacts to less than significant levels.
SECTION 4. No Basis for Recirculation. The Council finds
that (a) no new impacts result from modifying the Original Project
and replacing it with the Revised Project, and (b) there is no
substantial evidence to support a conclusion that significant new
information has been added to the Final EIR so as to warrant
recirculation of the EIR pursuant to Public Resources Code Section
2
000222 cl 0090423
21092.1 and CEQA Guidelines Section 15088.5. This finding is based
upon all the information presented in the Final EIR and record of
proceedings to date.
INTRODUCED AND PASSED: March 6, 2000
AYES: BEECHAM, BURCH, EAKINS, FAZZINO, KLEINBERG, KNISS, LYTLE, MOSSAR,
OJAKIAN
NOES:
ABSENT:
ABSTENTIONS:
APPROVED AS TO FORM:
de-~~
irector · g and
Community Environment
3
000222 cl 0090423
TABLE 1-1
Summary of Impact and Mitigation Findings
Impact
3.1 Land Use
3.1.1: Elimination of Current Land Use
Designation. The project would require
conversion of 7.2 acres of land from a "Public
Park" designation to "Major Institution/Special
Facilities".
3.1.2: Consistency with LAFCO Issues.
The project would be consistent with
annexation/reorganization requirements of
LAFCO.
3.2 Geology, Soils, and
. Seismicity
3.2.1 : Settlement. Existing fill materials are
not compacted which could result in
differential settlement of facility foundations
due to compression or densification.
3.2.2: Seismic Shaking. Major earthquakes
could cause damage to the proposed
facilities.
3.3.3: Liquefaction. Fill materials in two
former sedimentation basins in Area B could
liquefy during a moderate earthquake event.
3.2.4: Fault Rupture: No active faults are
located beneath the site and the likelihood of
surface rupture or fault creep is remote.
S = Significant Impact
LS = Less than Significant Impact
SU = Significant Unavoidable Impact
SFO\sF0\971 070002.DOC
Significance
without
Mitigation
LS
LS
s
LS
s
LS
Mitigation
None required.
None required.
· Non-engineered fill material beneath building and facility
foundations will be replaced with appropriate engineered
fill material to the native ground surface. All fill will be
placed 4 to 6 weeks prior to construction of structures to
avoid differential settlement.
None required. All structures will be engineered,
designed, and constructed in accordance with current
local, state, and Uniform Building Code seismic code
requirements and engineering standards.
Existing fill within the sedimentation basins will be
removed and replaced with engineered fill.
None required.
w
Mitigation
Responsibility
City of Palo Alto
Public Works
Department and
construction
contractor
City of Palo Alto
Public Works
Department and
construction
contractor.
CHAPTER 1. SUMMARY
Significance
with
Mitigation
LS
LS
1-4
m >< I
OJ
...;
)>
TABLE 1·1
Summary of Impact and Mitigation Findings
Impact
3.3 Water Quality
3.3.1: Groundwater Quantity. Stormwater
runoff would be directed into the storm
drainage system, thereby reducing the
amount of recharge to the groundwater.
3.3.2: Drainage Patterns and Runoff. The
increase in impervious area (5.3 acres) would
decrease infiltration rates and increase the
rate and quantity of surface runoff.
3.3.3: Exposure to Flood Hazards. The
increase in impervious area and the
proposed increase in elevation of the site
could increase flooding in areas near the site.
3.3.4: Surface Water Quality. Construction
activities and materials associated with the
project could increase the runoff of sediment
and contaminants into drainage systems and
impact water quality.
3.3.5: Groundwater Quality. Infiltration of
stormwater runoff that has contacted
pollutants from industrial activities on the site
could impact groundwater quality.
3.3.6: Surface Water Quantity: Filling of
wetlands would impact the amount of surface
water in water bodies on the site.
S = Significant Impact
LS = Less than Significant Impact
SU = Significant Unavoidable Impact
SFO\sF0\971070002.DOC
Significance
without
Mitigation Mitigation
LS None required.
LS
LS
LS
LS
s
None required. Drainage systems would be installed as
part of the project.
None required.
None required. Water quality protection features are part
of the project design.
None required. Water qua)ity protection features are part
of the project design.
See wetlands mitigation under Section 3.6, Biological
Resources.
Mitigation
Responsibility
CHAPTER 1. SUMMARY
Significance
with.
Mitigation
1-5
TABLE 1·1
Summary of Impact and Mitigation Rndings
Impact
3.4 Air Quality
3.3.1: Temporary Air Emissions During
Construction. Temporary emissions of d1,1st,
fuel combustion equipment exhaust, and
vehicle exhaust could impact the public near
the project area.
3.4.2: Potential Generation of Asbestos-
Bearing .Materials During Demoliti.on. If
existing buildings contain asbestos,
demoiition could release asbestos emissions.
S = Significant Impact
LS = Less than Significant Impact
SU = Significant Unavoidable Impact
SFO\sF0\971 070002.DOC
Significance
without
Mitigation
s
s
Mitigation
The following measures recommended by BAAQMD will
be implemented:
Water all active construction areas at least twice daily.
Cover all trucks hauling soil, sand, and other loose
materials or require all trucks to maintain at least 2 feet of
freeboard.
Pave, apply water 3 times daily, or apply non-toxic soil
stabilizers on all unpaved access roads, parking areas,
and staging areas at construction sites.
Sweep daily (preferably with water sweepers) all paved
access roads, parking areas, and staging areas at
construction sites.
Sweep streets daily (preferably with water sweepers) if
visible soil material is carried onto adjacent public streets.
Hydroseed or apply non-toxic soil stabilizers to inactive
construction areas (previously graded areas inactive for
ten days or more).
Enclose, cover, water twice daily or apply non-toxic soil
binders to exposed stockpiles (dirt, sand, etc.).
Limit traffic speeds on unpaved roads to 5 mph.
Install sandbags or other erosion control measures to
prevent silt runoff to public roadways.
Replant vegetation in disturbed areas as quickly as
possible.
The following measures, extracted from BAAQMD
Regulation 11, Rule 2 would be implemented:
Consult with BAAQMD's Enforcement Division prior to
commencing demolition.
Provide an onsite representative who is familiar with the
provisions cif BAAQMD Regulation 11, Rule 2 to be
present during .all stripping and removal of Regulated
Asbestos-Containing Material (RACM).
Mitigation
Responsibility
Construction
contractor.
City of Palo Alto
~ Public Works
and demolition
contractor
CHAPTER 1. SUMMARY
Significance
with
Mitigation
LS
LS
1·6
TABLE·1-1
Summary of Impact and Mitigation Findings
Impact·
3.4.3: Air Emissions from Project
Operations. Emissions could result from
vehicle trips, diesel and propane fuel storage
and dispensing, paint spray booth operations,
parts cleaning, and household hazardous
waste handling.
3.4.4: Odors. Project operation could result
in odors from vehicle exhaust, truck washing,
S = Significant Impact
LS = Less than Significant Impact
SU = Significant Unavoidable Impact
SFO\sF0\971 070002.DOC
Significance
without
Mitigation
LS
LS
Mitigation
Provide a written plan or NOI to demolish a stationary
structure, as directed by the air pollution control officer.
Remove RACM prior to other demolition or other
operations.
Adequately wet and keep wet all exposed RACM during
cutting, stripping, demolition, removal, and handling both
inside and outside the building or; use a local High
Efficiency Particulate Air (HEPA) exhaust, ventilation, and
collection system designed and operated to capture
RACM emissions. ·
Remove elements that contain RACM in units, sections,
leak-tight chutes, or containers.
Isolate the building, room, facility, or installation by
physical barrier from the outside air, to the extent
feasible, as determined by the air pollution control officer.
After wetting, and while still wet, seal all RACM in a leak-
tight container prior to removal of the isolated area and
deposit at an approved disposal site. All containers must
be properly labeled. Other methods include:. processing
RACM into nonfriable forms (when dry, cannot be
crumbled. pulverized, or reduced to powder by hand
pressure}, or converting RACM into asbestos-free
material.
None required
None required.
Mitigation
Responsibility
CHAPTER 1. SUMMARY
Significance
with
Mitigation
1-7
TABLE 1-1
Summary of Impact and Mitigation Findings
Impact
and the HHWF.
3.5 Traffic and Traffic Safety
3.5.1: Short-Term Future (1998) Plus
Project Conditions. The project would
increase traffic volumes by 4.3 percent at the
U.S. 101 northbound on-ramp, increase
volumes by less than 1 percent of capacity on
U.S. 101, increase peak-hour traffic volumes
by 1 0 vehicles, require queuing of vehicles
for the HHWF, and change circulation
. patterns at the site ...
3.5.2: Comprehensive Plan Update Year
2010 Plus Project Conditions. The project
would increase traffic volumes by 4.3 percent
at the U.S. 101 northbound on~ramp,
increase volumes by less than 1 percent of
capacity on U.S. 101, increase peak-hour
traffic volumes by 10 vehicles, require
queuing of vehicles for the HHWF, and
change circulation patterns at the site.
3.5.3: Pedestrian and Bicyclist Safety.
Development of three new driveways on the
west sid~ of North San Antonio Road could
result in traffic conflicts with pedestrians
and/or bicyclists and vehicles entering and
exiting the facilities.
3.6 Biological Resources
Long-term Impacts To Vegetation
3.6.1: Loss of. non-native grassland
vegetation. Approximately 3. 7 acres of non-
S = Significant Impact
LS = Less than Significant Impact
SU = Significant Unavoidable Impact
SFO\sF0\971 070002.DOC
Significance
without
Mitigation
LS
LS
LS
LS
Mitigation
None required.
· None required.
None required. Safety features such as a sidewalk and
stop ~igns at driveways are part of the project design.
None required.
Mitigation
Responsibility
CHAPTER 1. SUMMARY
Significance
with
Mitigation
1-8
TABLE 1-1
Summary of Impact and Mitigation Findings
Impact
native grassland (including non-native trees)
would be lost in Areas 8 and C.
Approximately 1.4 acres of non-native
grassland may be lost in Area A during
wetland mitigation activities.
3.6.2: Invasion of Non-Native Plant
Species'into Non-Native Grassland
Habitat. During construction, invasion of
exotic species (e.g., seeds transported via
truck tires) into non-native grassland habitat
adjacent to the project area could occur.
3.6.3: Loss of Seasonal Wetland
Vegetation. Approximately 0.2 acr~s of
seasonal wetland vegetation would be lost.
3.6.4: Loss of Brackish Water Wetland
Vegetation. A small area that supports
brackish water wetland vegetation in Area A
could be lost during wetland creation
activities.
Short-Term Impacts To Vegetation
3.6.5: Disturbance to Non-Native
Grassland Vegetation. Small strips of non-
native grassland habitat located onsite and
adjacent to the project area could be
temporarily disturbed during project
construction. Small areas of non-native
grassland adjacent to the location of wetland
mitigation activities could be temporarily
disturbed.
S = Significant Impact
LS =Less than Significant Impact
SU = Significant Unavoidable Impact
SFO\sF0\971 070002.DOC
Significance
without
Mitigation
LS
s
s
LS
Mitigation
None required.
Conceptual and final wetlands mitigation plans will be
. developed and implemented in coordination with re~ource
agencies.
Conceptual and final wetlands mitigation plans will be
developed and implemented in coordination with resource
agencies. The mitigation plan will include mitigation for
the loss of brackish water wetland vegetation, as well as
criteria to gauge and document the recovery of the
brackish water wetland vegetation.
None required.
Mitigation
Responsibility
City of Palo Alto
Public Works
Department
City of Palo Alto
Public Works
Department
CHAPTER 1. SUMMARY
Significance
with
Mitigation.
LS
LS
1-9
TABLE 1-1
Summary of Impact and Mitigation Findings
Impact
3.6.6: Disturbance to Seasonal Wetland
Vegetation. Short-Term impacts that would
negatively affect the growth and/or survival of
remaining seasonal wetland vegetation could
occur during construction.
3.6.7 Disturbance to Brackish Water
Wetland Vegetation. Temporary impacts to
brackish water wetland vegetation could
occur during construction activities and
during wetland mitigation activities.
Long-term Impacts To Wildlife
3.6.8: Interference With Wildlife
Movements. Wildlife movements during
dispersal and wildlife movements within a
home range or territory would be altered.
3.6.9: Loss of Nesting Habitat for
Terrestrial Avian Species. Loss of
landscaping vegetation {i.e., trees and
shrubs) along the western boundary of the
site, which is used for nesting by terrestrial
avian species.
3.6.1 0: Noise and Lighting. Project-related
noise and increased lighting may discourage
the use of the remaining ponds by waterfowl
and shorebirds.
3.6.11: Loss of Habitat for Wetland
Species. The loss of Ponds 81, 82, 83, 86
and Ditches 1-3 would reduce the availability
of wetland and open water habitat for
numerous avian species; the number of
S = Significant Impact
LS = Less than Significant Impact
SU = Significant Unavoidable Impact
SFO\SF0\971 070002.DOC
Significance
without
Mitigation Mitigation
S Pond 84 and Pond 85 will be fenced off and denoted on
project plans as environmentally sensitive areas.
s
LS
LS
s
s
The slough area in Area A will be denoted on project
plans as environmentally sensitive areas. The mitigation
plans will include criteria to gauge and document the
recovery of brackish water wetland vegetation from
temporary disturbance.
None required.
None required.
Lights installed on the project site will be shielded and
directed away from the remaining ponds, A fence would
be erected to shield the wetland birds from the vehicle
and human activity on the project site.
Mitigation plans for creation of replacement wetlands will
be developed and implemented in coordination with
resource agencies. Mitigation could include creating a
combination of wetland types in the proposed location in
Mitigation
Responsibility
City of Palo Alto
Public Works
Department
City of Palo Alto
Public Works
Department
City of Palo Alto
Public Works
Department
City of Palo Alto
Public Works
Department
CHAPTER 1. SUMMARY
Significance
with
Mitigation
LS
LS
,·
LS
LS
1-10
TABLE 1·1
Summary of Impact and Mitigation Findings
Impact.
wetland species that use the site would be
reduced.
3.6.12: Contamination of Adjacent Wildlife
Habitats. If contamination from surface water
runoff were to occur to habitats adjacent to
the project area, the health or reproduction of
wildlife (or plant~} could be adversely
affected.
Short· Term Impacts To Wildlife
3.6 .• 13: Disturbance to Wildlife. Temporary
impacts to wildlife during project construction
or wetlands creation could include increased ·
noise and human activity associated with
earthwork.
Long-term Impacts To Wetland Resources
3.6.14: Loss of 1.4 Acres of Waters of the
U.S. (Including Wetlands). Approximately
1.2 acres of open water habitat and 0.2 acres
of seasonal wetlaRd habitat would be lost.
Ponds 81, 82, 83, 86 and Ditches 1 and 2
would be physically lost due to the
importation of fill; Ditch 3 would be
functionally lost.
3.6.15: Disturbance to Wetland Resources.
During wetlands creation in Area A, a small
amount of brackish water wetland vegetation
niay be lost and the hydrologic regime of the
slough may be altered.
S = Significant Impact
LS = Less than Significant Impact
SU = Significant Unavoidable Impact
SFO\sF0\971 070002.DOC
Significance
without
Mitigation
LS
LS
s
s
Mitigation
Area A (see Figure 3.6-1 }.
/ None required. With incorporation of project features
(described in Section 3.3,Water Quality}, to protect water
quality, contamination would be prevented.
None required.
As part of the permitting process, conceptual and final
mitigation plans will be developed and implemented in
consultation with resource.agencies.
Conceptual and final wetlands mitigation plans will be
developed and implemented in coordination with resource
agencies. The wetlands mitigation plans will include
mitigation for the loss of brackish water wetland
vegetation and altered hydrological regime of the slough,
as well as criteria to gauge and document the recovery .of
the brackish water slough and associated wetlands. As
Mitigation
Responsibility
City of Palo Alto
Public Works
Department
City of Palo Alto
Public Works
Department
CHAPTER 1. SUMMARY .
Significance
with
Mitigation
LS
LS
1·11
TABLE 1·1
Summary of Impact and Mitigation Findings
Impact
Short· Term Impacts To Wetland
Resources
3.6.16: Disturbance to Wetland Resources.
The remaining ponds and the slough could
be disturbed by activities such as inadvertent
trampling and earthwork associated with
construction.
Long-term Impacts To Special Status
Species
3.6.17: Impacts to Special Status Plants.
No Special Status Plants were found on the
site.
3.6.18: Loss of Habitat for Special Status
Wildlife Species. A small reduction in
foraging habitat for special status birds would
occur.
Short-Term Impacts To Special Status
Species
3.6.19: Disturbance to Special Status
Wildlife Species. Temporary disturbance to
special status wildlife species observed in
Area A (American peregrine falcon and
saltmarsh common yellowthroat) could
include increased noise and other human
S = Significant Impact
LS = Less than Significant Impact
SU = Significant Unavoidable Impact
SFO\SF0\971070002.DOC
Significance
without
Mitigation
s
LS
LS
s
Mitigation
part of project plans, permanent security fencing would
be erected and native shrubs would be planted to prevent
long-term disturbance to remaining wetland areas onsite
due to operation of proposed facilities.
The remaining pond areas and slough onsite would be
fenced off and denoted on project plans as
environmentally sensitive areas. The northern border of
the project boundary would be inspected periodically by
the contractor. Workers would be informed that the ponds
in Area B and the slough in Area A are valuable
resources and that they should be avoided.
None required.
None required.
Any wetlands mitigation in Area A would be conducted
outside of the breeding season of the saltmarsh common
yellowthroat.
Mitigation
Responsibility
Construction
contractor
City of Palo Alto
PUblic Works
Department
CHAPT9J 1. SUMMARY
Significance
with
Mitigation
LS
LS
1-12
TABLE 1·1
Summary of Impact and Mitigation Findings
Impact·
activities associated with construction of the·
proposed project and during the potential
creation of wetlands in Area A. Wetlands
mitigation activities could disturb breeding
activities of the saltmarsh common
yellowthroat.
3.7 Hazards
3.7 .1: Public and Worker Exposure to
Hazardous Waste at the HHWF. Public and
worker exposure to hazardous waste could
occur in the event of illicit entry into the
HHWF, emergency situations such as an
explosion in the flammables bay; accidents
during transport of packaged wastes from the
facility, and accidents resulting from a major
earthquake.
3.7.2: Worker e)Cposure from Fueling
Station, Storage Tanks, and Paint Spray
Booth.
3.7.3: Acc.idental Releases from the HHWF
to the Environment. Accidental release of
contaminants to surface water and
groundwater could result from unauthorized
drop-off of waste during non-business hours
and from emergency situations.
3.8 Noise
3.8.1: Increase rn Ambient Noise Levels at
Adjacent Commercial Office Buildings and
Open Space Areas. Noise from refuse
collection vehicle start up and_ vehicle
S = Significant Impact
LS = Less than Significant Impact
SU =Significant Unavoidable Impact
SFO\sF0\971 070002.DOC
Significance
without
Mitigation
LS
LS
LS
s·
Mitigation
None required. Implementation of safety features and
regulatory requirements as part of the project would
ensure protection of human health and the environment.
None required. Implementation of safety features and
regulatory requirements as part of the project would
ensure protection of human health and the environment.
None required. Implementation of safety features and
regulatory requirements as part of the project would
ensure protection of human health and the environment.
If workers in the adjacent office buildings are impacted by
increased noise levels, the City would implement one of
the following measures depending on the severity of the
impact: 1) Install soundproofing and noise reducing
Mitigation
Responsibility
City of Palo Alto
Public Works
Department and
CHAPTER 1. SUMMARY
Significance
with
Mitigation
LS
1-13
TABLE 1-1
Summary of Impact and Mitigation Findings
Impact
maintenance activities could increase the
highest instantaneous noise level inside
adjacent office buildings to 60 dBA. Noise
would exceed 50 dBA at the property line, an
increase of over 8 dBA above the local .
ambient noise level, which is considered a
violation of the City's Noise Ordinance.
3.8.2: Increased Noise Levels at Adjacent
Office Buildings During Construction.
Construction activities such as grading and
site paving could result in maximum noise
levels of up to 90 dBA outside of the closest
office buildings and 60 dBA inside the
buildings.
3.8.3: Increase in Noise Levels on San
Antonio Road Between the Site and the
101 Freeway. Refuse collection and
recycling trucks would create an increase in
noise levels during typical office hours by
more than 1 or 2 dBA, an undetectable
difference.
3.9 Aesthetics
3.9.1: Aesthetic Change of Physical Site.
The importation of fill to raise the refuse .
collection contractor portion of the site to 8
feet above MSL would cause the new
structures to be more visible than the existing
buildings.
3.9.2: Increased Light or Glare. New light
sources would be created on the site with
S = Significant Impact
LS = Less than Significant Impact
SU = Significant Unavoidable Impact
SFO\SF0\971 070002.DOC
Significance
without
Mitigation Mitigation
windows in the office building, 2) Construct a shed over
the parking spaces adjacent to the buildings to deflect
noise, 3) Negotiate agreements regarding the timing of
any particularly loud maintenance activity.
S All equipment used on the site will be adequately muffled
and maintained. The construction contractor will
designate a noise disturbance coordinator who would
notify workers in the adjacent office building on the west
side of the site about any particularly noisy activities,
allowing them to adjust their schedules accordingly.
LS
LS
LS
None required.
.None required. Design features implemented as part of
the project would ensure visual compatibility with the
surrounding environment.
None required.
Mitigation
Responsibility
PASCO.
Construction
contractor
CHAPTER 1. SUMMARY
Significance
with
Mitigation
LS
1-14
TABLE 1-1
Summary of Impact and Mitigation Findings
Impact
lighting at the refuse collection contractor
facility from 2:30 A.M. until dawn.
· 3.10 Recreation
3.1 0.1: Loss of Public Park Land Use
Designation. A land use designation change
would result in the loss of 7.2 acres of land
designated as "Public Park" in the
Comprehensive Plan.
3.10.2: Impacts to Recreation. Users of
adjacent parks could be impacted by traffic,
noise, and dust generated during
construction, and by traffic and noise during
project operations. See these sections of the
EIR for a discussion of impaCts.
S = Significant Impact
LS = Less than Significant Impact
SU = Significant Unavoidable Impact
SFO\SF0\971 070002.DOC
Significance·
without
Mitigation
LS
LS
None required.
None required.
Mitigation
Mitigation
Responsibility
CHAPTER 1. SUMMARY
Significance
with
Mitigation
1-15