HomeMy WebLinkAbout2008-02-06 Utilities Advisory Commission Summary Minutes
Utilities Advisory Commission Minutes Approved on: March 5, 2008 Page 1 of 5
FINAL
UTILITIES ADVISORY COMMISSION
MINUTES OF FEBRUARY 6, 2008
CALL TO ORDER
Chairman Rosenbaum called to order at 7:05 P.M. the scheduled meeting of the Utilities Advisory
Commission.
Present: Commissioners Marilyn Keller, John Melton, Dick Rosenbaum, and Council Liaison Yiaway Yeh
Absent: Commissioner George Bechtel
ORAL COMMUNICATIONS
NONE
APPROVAL OF THE MINUTES
The minutes from the January 9, 2008, were unanimously approved.
AGENDA REVIEW
REPORT FROM COMMISSION MEETINGS/EVENTS
Vice Chair Dawes gave a detailed report on the NCPA Strategic Planning workshop that he attended with
Chair Rosenbaum and staff members. Vice Chair Dawes particularly noted the increased focus on
greenhouse gas emissions and emphasis on greenhouse gas reductions activities. Chair Rosenbaum shared
the question he raised at the meeting to CPUC Commissioner John Bohn regarding investor owned utilities’
achievement of the 20% mandated renewable portfolio supply standard. He noted his surprise at
Commissioner Bohn’s answer indicated the likely achievement by the IOUs of the RPS standard.
UTILITIES DIRECTOR REPORT
Utilities Director Valerie Fong gave the following updates:
Compact Florescent Light Bulbs
An update was provided to the Commission in response to a question raised by Commissioner Bechtel at the
previous Commission meeting: rebates on approximately 16,000 CFLs were provided to Palo Alto customers
in 2007 with an estimated savings of 1,600 MWh/year for an average bulb life of five years installed in
relatively high usage sockets. The annual saving of 1,600 MWh is equivalent to 0.16% of City’s annual load.
Hydro Conditions
As of 1/29 the Sierra snowpack is at 111% of average. Reservoirs are below average (Trinity 81% of average,
Shasta 69%, Folsom 53%, New Melones 107%). All reservoirs have space to fill. Releases are minimized
resulting in very little Western Base Resource in January and February. Median precipitation for the rest of the
year would result in less than average generation through winter 2009.
Utilities Advisory Commission Minutes Approved on: March 5, 2008 Page 2 of 5
COTP Transmission Asset Lay-off
City is exploring the option of laying-off City’s share of COTP transmission to other members who may place a
greater value on the asset. A successful lay-off of the COTP asset at cost will lower the level of stranded cost
reserve requirement. Staff expects to bring a recommendation on the topic to the UAC in the coming months.
Seattle City Light Energy Exchange Contract
City is also making progress in assigning City’s share of NCPA’s Seattle City Light Exchange Agreement to the
City of Santa Clara. The exchange agreement provides energy during the late spring and summer months to
Palo Alto, and the obligation to return the energy during the fall/winter months. This exchange arrangement is
no longer a good fit to the City’s energy portfolio that tends to be flush during the spring/early summer months
and short in energy during the fall/winter months.
Western GeoPower Incorporated
NCPA is negotiating a 20 year Power Purchase Agreement with Western GeoPower Incorporated for
qualifying renewable energy output from a new 25-33 MW Geysers area geothermal plant. Palo Alto staff
finds the output attractive as a resource to help meet the 33% renewable portfolio goal and is pursuing Council
approval of participation in a third Phase NCPA agreement to allocate between 10% and 20% of the output to
Palo Alto. The output is priced at $98/MWh with zero escalation and is attractive compared to other
renewables after considering capacity benefits. The cost would fit within the Council’s goal of acquiring 33%
renewables at a cost premium that would not drive retail rates up by more than 0.5 cents/kWh. To meet
negotiation time tables staff is seeking Council approval on February 19th.
Upcoming Meetings: Staff is scheduled to provide an informational overview on Utilities Enterprise Funds to
the Finance Committee in a study session on February 20th. The presentation will be a combined Utilities and
Public Works presentation.
UNFINISHED BUSINESS
NONE
NEW BUSINESS
ITEM 1: INFORMATION ITEM: Options to Manage the Calaveras Reserve:
Shiva Swaminathan, Sr. Resource Planner, discussed the relative merits of the 6 options identified to manage
the Calaveras Reserve on a going forward basis beginning with a recap of the Commission discussion at the
December meeting, where staff’s initial estimates showed that the reserve was potentially over funded by
approximately $20 million.
Commissioner Dawes reiterated his belief that staff needs to continue to look at opportunities to invest surplus
cash on long term capital projects such as local cogeneration. Staff assured the Commissioner that it is being
looked at closely. Commissioner Rosenbaum complemented staff for analyzing the option he identified at the
December meeting, to utilize surplus cash create a new reserve to manage hydro risk, and urged staff to look
at the option closely. Commissioners Melton and Dawes asked for the impact of laying-off City’s share of the
California-Oregon Transmission project (COTP). Staff responded that the COTP lay-off would result in
additional surplus in reserve.
ITEM 2: DISCUSSION ITEM: Cost Trends & Drivers for Utilities’ Five-Year Financial Forecasts
ITEM 3: DISCUSSION ITEM: Annual Risk Assessment of Rate Stabilization Reserves
Utilities Advisory Commission Minutes Approved on: March 5, 2008 Page 3 of 5
ITEM 4: DISCUSSION ITEM: Discussion of Five-Year Financial Projections
Items 2, 3 and 4 were discussed all together. Jane Ratchye, Assistant Director for Resource Management,
presented the Five-Year Financial Projections for the Electric, Gas, Water and Wastewater Funds. Ratchye
stated that the objective of the meeting was to provide information to the Commission and to obtain feedback
on utilities cost and revenue projections and resulting reserve levels. Staff did not make any recommendations
but presented one scenario each for the gas, water and wastewater fund, and three scenarios for the electric
funds for discussion purposes. Ratchye stated that the feedback from the Commission would inform staff as it
develops recommendations on rates for UAC action at the March meeting.
Gas fund scenario requires a 7.1 percent rate increase in FY 2008-09, a reduction from the 9.1 percent
increase in prior years’ budget, followed by no rate increases for the next five years given current projection of
costs. Ending reserve level for Supply RSR would be at the Risk Assessed Value for FY 2008-09 reserves.
Ending reserve level for Distribution RSR is projected to be slightly below the Risk Assessed Value for FY
2008-09, but this situation is eliminated by FY 2009-10.
Commissioner Keller questioned the certainty of the forecasts and why the proposals did not show ranges.
Ratchye explained that that these were expectations in the long term, not the risk around the long term. Fong
explained that the risk for the upcoming year was not that great as a large portion of the gas portfolio has been
purchased. Commissioner Dawes showed concern that we were above PG&E’s expected bill projections,
despite the laddering strategy used for purchasing gas. Fong explained that this was partially an issue of
economies of scale, the length of contracts and hedges they are allowed to purchase vs. Palo Alto, as well as
storage capacity that PG&E has access to. Ratchye clarified that we cannot project what PG&E’s rates will be
for the upcoming fiscal year, as they change prices based on the spot market. Commissioner Dawes
questioned whether the main replacement projects were coming to a close at the end of FY12-13, as the
Capital Improvement Project (CIP) costs are decreasing. Staff promised to provide an update.
Water fund scenario requires an 8.0 percent rate increase in FY 2008-09, followed by rate increases in the 8 –
10 percent every year for the next five years in anticipation of the water rate increases by SFPUC. The water
fund is also expected to utilize bond proceeds to finance its Reservoir and Wells replacement CIP. Ending
reserve level for Water RSR is above the Risk Assessed Value, as well as the Minimum Guidelines
established by the Council for FY 2008-09 reserves, as well as for the next five years.
Commissioner Melton sought clarification that the rates were being set to cover the cost of debt service, not
the capital costs. Staff confirmed this. Commissioner Dawes questioned the estimated cost of Reservoir
project and the required bond financing. Staff explained that this figure was still currently projected as $35
million.
Wastewater fund scenario requires no rate increase in FY 2008-09 or FY 2009-10. Based on current
projections, the wastewater fund will require rate increases starting in FY 2010-11 through FY 2012-13 in the
range of 6 – 10 percent. Ending reserve level for Wastewater RSR is above the Risk Assessed Value, as well
as the Minimum Guidelines established by the Council for FY 2008-09 reserves, and for the next five years.
Ratchye presented three scenarios for the electric fund. All scenarios end up with average system rate not to
exceed 13.5 c/kWh in the 2012-2013 time period. Scenario 1 meets either the short term risk or long term
reserve requirements in all years, Scenario 3 does not exceed 10 % rate increase in any given year and is the
same as what was presented during the prior budget process, and Scenario 2 is in the middle of these two.
Utilities Advisory Commission Minutes Approved on: March 5, 2008 Page 4 of 5
Rate increases required and ending reserve Electric Supply RSR balance for FY 08-09 were projected to be
as follows for each scenario:
Scenario 1: with a 19% rate increase: $33.8 M
Scenario 2: with a 14% rate increase: $29.4 M
Scenario 3: with a 10% rate increase: $26.0 M
Commissioner Dawes sought clarification that these scenarios assumed average hydro years. Ratchye
confirmed that FY 08-09 had a slightly lower hydro generation level assumed, but average after that, although
there is obviously much uncertainty around these values.
Ratchye presented a slide expanding the components of the electric purchase costs to show how costs are
projected to change. Commissioner Rosenbaum thanked staff for this slide, and asked why the debt service
was not included. Staff explained it was an accounting issue. Commissioner Dawes requested a cents-per-
kilowatt hour assumption placed on the bar chart, and staff agreed that was a good idea.
Ratchye then explained that since the risk-assessment value was $33.8 M for FY 08-09,
Scenario 1: with a 19% rate increase, had sufficient reserve balance at year end
Scenario 2: with a 14% rate increase, had a shortfall of $4.4 M to meet risk assessment value
Scenario 3: with a 10% rate increase, had a shortfall of $7.8 M to meet risk assessment value.
Staff expressed their feeling that Scenario 3 was adequate for FY 08-09, with no transfer of funds from the
Calaveras reserve, with the understanding that Staff may come back next year and request Calaveras funds in
FY 09-10 and/or 10-11, based on how supply reserve levels pan out in light of future cost uncertainties.
Commissioner Dawes asked how much money may be recaptured from the layoff of COTP. Ratchye and
Swaminathan stated that the figure might be around $20 million for all stranded costs (Calaveras, COTP, and
Seattle City-light). Staff asked for comments and questions on these scenarios.
Commissioner Keller asked if there were other issues, such as the message to customers, that there was such
variability in costs and asked if rate increases could serve to achieve further resource conservation. Fong
stated that there is always a balance between rate-shock vs. sending proper price signals. Staff’s inclination
was to mitigate rate shock and go for a lower electric increase, in light of increases in the other funds as well.
Commissioner Dawes agreed with the thinking of Staff, that cost uncertainties were large enough and reserves
were large enough to not go for a Scenario 1 increase. Scenario 3 was a possibility, but perhaps a 12 percent
increase would be a better compromise position.
Commissioner Melton stated that this backs up why he desired having a rate increase in February 2007 to
avoid a large increase in July. As Council has discussed and determined minimum and maximum reserve
guideline levels, a Scenario 1 increase was required to meet those policy objectives, as well as the short term
risk assessment values, even though it would be a large sticker shock for customers. Swaminathan explained
that those policies did not take into account excess funds in the Calaveras reserve, which was also at issue
here.
Commissioner Keller asked how high and low hydro scenarios would affect the reserve projections. Staff
showed Table 2 which showed those uncertainties.
Utilities Advisory Commission Minutes Approved on: March 5, 2008 Page 5 of 5
Commissioner Rosenbaum felt that Scenario 2 (14% increase) was the clearly the best scenario.
Commissioner Keller asked if the rate was high if that would get customers to conserve more, and how
customers would react. Fong stated that it might look like poor planning on the part of the Utilities, and with
reserves being so large, customers might balk.
Council liaison Yeh asked how a potential inflow of funds from Calaveras reserve would influence the RSR
reserve levels. Staff confirmed that it would present a one-time bump up in levels, but the trends would
persist. As a follow up question, would reserves below guideline levels in any particular fund influence our
bond ratings. Staff said that the total reserve balances would be looked at, and the debt ratios would still be
favorable.
Commissioner Melton stated that if there was a signal from Council that they were willing to use funds from the
Calaveras reserve, then the 14% scenario would make a lot of sense. The fact that the short term risk
assessment and the long term guidelines show the same values lends validity to the need for that level of
funds in the supply reserves. Fong asked whether, as an advisor to the Council, they could take the position
that being below the long term min level would be acceptable because there were other funds available, and
advise the Council to such an effect. Commissioner Melton agreed, if there were surplus funds, that he would
advise to move surplus funds from Calaveras to the supply reserve to get to the minimum level.
Commissioner Rosenbaum stated that, in the financial forecasts, there should be a footnote regarding lines 17
and 12 about the CVP loan advance funding.
Commissioner Keller stated that she was leaning toward the 14% rate increase scenario, provided the future
increase percentages were modifiable and flexible. Commissioner Melton stated that, save for certain
commercial customers, in general people don’t look at the five year planning horizon, only the upcoming year.
Commissioner Melton stated that three were in favor of the 14% scenario. Commissioner Rosenbaum asked if
there had been enough input on the rate scenarios, and staff confirmed that there had been.
The next scheduled meeting March 5, Keller not being able to attend.
Meeting adjourned at 8:50 P.M.
Respectfully submitted,
Marites Ward
City of Palo Alto Utilities