HomeMy WebLinkAbout2023-02-15 Rail Summary MinutesRAIL COMMITTEE
SUMMARY MINUTES
Page 1 of 13
Special Meeting
February 15, 2023
The Rail Committee of the City of Palo Alto met on this date in the Community Meeting Room
and by virtual teleconference at 1:00 P.M.
Present In Person: Burt, Kou, Lauing
Present Remotely: None
Absent: Veenker
Call to Order
Chair Burt stated that Council Member Veenker was not able to attend the meeting and Mayor
Kou was filling in. He stated the focus of the meeting would be the 2022 to 2023 Work Plan.
Public Comment
1. Bob Lian of 101 Alma Street discussed the loud honking and horn blasting at the train
crossing several times per hour from early morning until midnight. He felt it was an
unhealthy and disturbing environment to live in and the continuous honking affected
the health and wellbeing of residents. He stated there were enough safety measures in
place to know a train was coming and felt creating a healthier environment for residents
was just as critical.
2. Penny Ellson asked Staff to explain how the project timelines for grade separation
planning and the Bicycle and Pedestrian Transportation Plan update would be aligned to
enable the BPTP to inform the grade separation process.
3. Laura Granka appreciated the Quiet Zone Study being done. She stated it would be
challenging to get a pedestrian underpass in the vicinity of Kellogg or Churchill with the
partial underpass option and underscored the importance of that intersection for
pedestrians and cyclists, for both the neighborhood community and the high school.
She requested creating success criteria in a time-bound manner to come to a decision
sooner rather than later on that crossing.
Verbal Update on Interagency Activities
A. Caltrain – There was no one present from Caltrain.
SUMMARY MINUTES
Page 2 of 13
(Sp.) Rail Committee Meeting
Summary Minutes: 2/15/2023
B. VTA - There was no one present from VTA.
C. City Staff
Chief Transportation Official Philip Kamhi described a grant submitted for the Transit and
Intercity Rail Capital Program with CalSTA on February 10, a funding request for final design and
right-of-way acquisition phase at the Meadow, Charleston, and Churchill crossings. Caltrain and
City Staff met on site at the San Francisquito Creek Bridge project to review impacts of the
recent storm on the embankments and bridge conditions. Staff followed up with Caltrain to
reiterate the interest in alternative plans for rehabilitation and strengthening of the bridge and
a cost-benefit analysis to determine the best path. Caltrain was still reviewing that request.
Regarding the Caltrain Corridor Study, Caltrain has had meetings with different stakeholders
groups, the City/County Staff Coordination Group (CSCG), and LMPG. The consultant, Kimley-
Horn, shared the project objectives and timeline and is reviewing case studies of similar
projects in the area. The Embarcadero Road bike improvement, previously a large CIP project,
has been re-scoped into a much smaller project, looking at the Emerson Avenue to Alma Street
portion of Embarcadero Road. BKF Engineers, the consultant that had previously prepared the
plans to nearly 100%, was now on board to review the plans. Staff was working with Menlo
Park and the consultant for the Quiet Zone Study at Palo Alto Avenue. An outreach meeting
was scheduled for March 23 at 6 p.m. at the Arrillaga Family Recreation Center Oak Room, 701
Laurel Street in Menlo Park.
Chair Burt was glad things were proceeding on the Embarcadero bike and ped section between
Alma and Emerson. He asked if there was an opportunity for input on prospective designs or
feedback on the tentative design developed by the consultant. He questioned the design role
of the consultant versus construction implementation.
Chief Transportation Official Kamhi stated the project was at essentially 100% design, past the
point of getting comments on prospective designs.
Senior Engineer Ripon Bhatia stated the project was being reviewed to make sure the proposed
improvements were in line with current standards and requirements and to make any revisions
or changes. The project has been finalized for a long time, and the community outreach will be
to familiarize and refresh people's minds, especially those in the fronting affected by that
project. Staff welcomed input and feedback, but it was hoped these would be in a project-
ready format.
Chair Burt recalled changes made in 2016 from the southeast to northwest side of
Embarcadero. He requested that the details be shared with the Committee as he had not seen
them previously.
Chief Transportation Official Kamhi responded that Staff would be happy to bring that to the
Committee.
SUMMARY MINUTES
Page 3 of 13
(Sp.) Rail Committee Meeting
Summary Minutes: 2/15/2023
Chair Burt discussed that Caltrain had proposed to charge the City their full cost for design
review and project management. VTA has been interested in their role since, through Measure
B, they are the primary funding source. Caltrain has not historically had staff with this capacity
and expertise, but Palo Alto and other cities have not been happy with the MOU understanding.
An ad hoc committee was created for VTA with Mountain View, Sunnyvale, and Palo Alto
around grade separation issues, but Caltrain has no funding to do this themselves. He asked if
Staff was familiar with the earmark Congresswoman Eshoo had set aside for this purpose and
the specifics on how it could be used to meet these needs.
City Manager Ed Shikada recalled sending a letter of support at the time that earmark was
requested. He believed the grant recipient was VTA and that a conversation should be held
with them as to how to leverage that.
Chair Burt mentioned the LPMG meeting coming up, with Council Member Lauing as the
representative. Caltrain has a technical team on the grade separation and have engaged with
Kimley-Horn who have developed an extensive engagement and outreach plan. He was
encouraged by the design, how they are proceeding, and the capabilities and vision of those
staff members. Caltrain, like most transit agencies, is facing a fiscal cliff with ridership down
and the revenue from fare box recovery having tanked. Palo Alto had the second highest
boardings in the system prior to the pandemic and the highest in the pandemic period. Caltrain
passes were a condition of approval of the the Hospital Development Agreement in 2011.
Stanford expanded beyond that to include all employees. The TMA focused on providing VTA
or Caltrain passes to small, lower-income-paying service businesses downtown whose
employees needed the help. That then expanded to include lower-income riders. The City
provided passes for the City Hall area employees. With remote work and companies pushing
employees to have greater number of days at the office, these passes may be a real
inducement to come back to work, especially with the new downtown subway connection in
San Francisco and the new electrification with faster, more modern trains. He suggested Palo
Alto describe this as a model to offer to Caltrain to try to propagate it up and down the corridor
to drive ridership.
Nadia Naik believed some of the bike improvements on Embarcadero were related to money
for improvements due to Stanford going over their numbers. It was approved by Council and
has now come back after being dropped during COVID budget cuts. The previous argument for
limiting the improvements to only the bicycle part along Embarcadero was because the Council
had not yet decided on Churchill improvements. Now that the preferred alternative has been
decided for a partial underpass at Churchill, she asked if the Council needs to look at the
improvements at Embarcadero that were already approved by the previous Council in 2016.
Chief Transportation Official Kamhi stated there were multiple reasons the El Camino portion
was dropped and that Staff was currently trying to tackle a small portion fitting within the BPTP
implementation, without the need to seek an additional CIP.
No action taken; updates provided
SUMMARY MINUTES
Page 4 of 13
(Sp.) Rail Committee Meeting
Summary Minutes: 2/15/2023
Action Items
1. Rail Committee to Review and Provide Direction for the Development of the 2023 Rail
Committee Work Plan.
Chief Transportation Official Philip Kamhi reviewed the update on the Work Plan approved by
City Council on August 8, 2022, to provide context for the planned work items. He listed and
discussed the items and expected time frames at a high level: to review and approve the
conceptual plan refinements based on the discussions of 2 study sessions in 2022; results of the
geotechnical studies; to receive the peer review of cost estimates for the trench alternative and
discuss implications of the alternatives; to review the Caltrain Service Agreement for possible
recommendations to City Council; to receive Caltrain's update on the San Francisquito Creek
Bridge rehab and replacement; ongoing staff updates on funding and legislative information
and opportunities; to receive the Caltrain Corridor Crossings Strategy (CCS); Bicycle and
Pedestrian Transportation Plan and considerations for the new east and west bike-ped
crossings for possible recommendations to City Council; to review and provide feedback on the
improvements for the implementation of quiet zones at California Avenue; Rail Committee
recommendation to City Council for the implementation of quiet zones; Rail Committee to
provide a recommendation to City Council for narrowing or selection of alternatives for grade
separation.
Chair Burt added that the Work Plan gives much greater detail on the focus area, Rail
Committee activities, time frame, and a progress report, which gives a greater understanding of
what was summarized.
Nadia Naik mentioned the importance of the pending report of the El Palo Alto Tree. She
questioned how the BPTP bike crossings item lines up with outreach that may be needed for
these things, particularly Seale.
Chief Transportation Official Kamhi stated the El Palo Alto Tree was tied to the San Francisquito
Creek Bridge issue. The BPTP project was expected to begin soon. Outreach was the first
portion of the project. There was also a request to get the PAUSD dot maps, which show where
students travel from in order to get to Paly. In the refinement process, there are versions of
crossing at Seale and at Kellogg as part of refinements for the underpass alternatives.
Chief Burt believed the Committee voted not to have any further work done on Kellogg.
Engineer Ripon Bhatia stated that it was mentioned in the study session that any concepts
prepared for Kellogg would be applicable to Seale because they have the same cross section,
width, etc. It would be used as a comparison to show the benefits.
SUMMARY MINUTES
Page 5 of 13
(Sp.) Rail Committee Meeting
Summary Minutes: 2/15/2023
Chair Burt wanted to ensure the public knew Kellogg was not actively being pursued.
Ms. Naik suggested obtaining the dot maps be flagged for the City/School Liaison Committee to
address.
Public Comment:
1. Penny Ellson felt the timelines did not align. Staff anticipates starting to integrate BPTP
information into the planning process in November, but according to the Work Plan, the
process does not get approved until October. She wanted more detail on what needs to
be prioritized in the BPTP process in order to inform the Rail Committee in a timely way.
She stated the South Palo Alto bicycle situation during and after construction will be
worse than what exists in North Palo Alto because there are no existing grade
separations. She was very concerned about kids commuting to school by bicycle from
South Palo Alto and the increase in car traffic if kids are not able to commute by bicycle.
2. Laura Granka inquired about the criteria by which the Quiet Zone Study would be
expanded beyond Palo Alto Avenue as quiet zones would be a significant improvement
to the community given that grade separation seems to be a long way off. She also
wanted to ensure that ongoing safety improvements for other intersections, notably the
sidewalk expansion at Churchill Avenue, were still on the table and wondered if there
was an opportunity to improve the design for pedestrians.
Chair Burt encouraged committee members to go through the list in depth as it would be
important to make sure the year's agenda was set to reflect the priorities and sequencing.
Council Member Lauing wanted the overall messaging to be clear that it would be another year
before the Rail Committee could make recommendations to Council and Council could act on it.
He asked Staff to itemize some of the dependencies affecting the timeline.
Chief Transportation Official Kamhi agreed but clarified that the Rail Committee could make a
decision that any one of the items on the list was the deciding factor. For example, if the trench
alternative cost estimate came back very high, the Rail Committee might decide to eliminate
the trench from consideration. He stated the challenge was in predicting when it could all
complete.
Council Member Lauing asked if, for example, a decision was made on the Churchill partial
bypass, it could be done in June before other recommendations at end of year.
Chief Transportation Official Kamhi responded that that was a great example because the
Council had already selected a preferred alternative for Churchill.
Mayor Kou asked if it was possible to determine approximate funding for some of the plans, for
example, a ballpark figure about what a trench or underpass would cost. She also asked about
Caltrain's committee to review the questions for the designs.
SUMMARY MINUTES
Page 6 of 13
(Sp.) Rail Committee Meeting
Summary Minutes: 2/15/2023
Chief Transportation Official Kamhi stated there were cost estimates for all the existing
alternatives and a matrix with a comparison of all the costs on the Connecting Palo Alto
website. He also stated Caltrain's Corridor Crossing Strategy was a study for the entire corridor
but could answer some of those questions.
Mayor Kou wanted people to understand that Caltrain would be coming back late with these
answers while Palo Alto was trying to move ahead. There was responsibility with Caltrain for
not providing some of the answers.
Chief Transportation Official Kamhi stated Kimley-Horn was leading the project and has a good
process set up to get the project going.
Council Member Lauing stated not all residents understand that and felt the messaging was
important.
Chair Burt discussed further historical context of Caltrain approving design differences from the
limited existing technical design standards. With Palo Alto's corridor being narrow and built out
on either side, the grade crossings are more challenging than most of the rest of those in the
corridor, so Palo Alto needs to pursue a series of exceptions. Caltrain has acknowledged that
most of those exceptions will likely be built into new technical standards. He would like to look
at Staff composing a draft of explanation of this for the public. Regarding the item "Peer
review, cost estimates of trench alternatives and their implications," he stated the trench was
not a viable option for Churchill or Palo Alto Avenue, only for Meadow and Charleston. Caltrain
requires a passing track section of 3 to 4 miles from South Mountain View to the north edge of
Palo Alto. North Palo Alto is amongst the narrowest in the entire corridor, and Caltrain has
acknowledged it is not likely they will choose the area of Churchill and north of Oregon as part
of those 3 to 4 miles, though they have not officially ruled it out. Charleston and East Meadow
are likely areas Caltrain will need to reserve the possibility of a 4-track. The alternatives do not
have to be built for 4 tracks but cannot preclude a future 4-track. A 4-track trench was
infeasible from a fit standpoint and construction impact, and he suggested there may be no
point in further pursuing the trench alternative. He questioned how to proceed with
recommendations to Council.
There was further discussion about the requirement for 4 tracks.
Chief Transportation Official Kamhi stated if the Committee believed the trench was no longer
viable at any point, there was value in removing that from consideration as more time could be
focused on the alternatives with more merit or likelihood of success.
Chair Burt wanted to resolve the 4-track issue, especially as it relates to the trench option, as
soon as possible and then perhaps move forward on dropping that from the list.
Ms. Naik stated that because the viaduct was eliminated from the alternatives, PABAC was only
giving feedback on the remaining alternatives, trench, hybrid, and underpass. She felt it made
sense to discuss the viaduct, both for the bike community and because it takes much less
SUMMARY MINUTES
Page 7 of 13
(Sp.) Rail Committee Meeting
Summary Minutes: 2/15/2023
construction time. The first bullet on attachment A is "Review grade separation selection
criteria for any revisions." That criteria has not been looked at since 2017, and now would be a
good time to think about what is being optimized for because the cost estimates from the
consultants do not account for all the disruption.
Chair Burt asked if there was anything active in the process of additional work on the peer
review cost for the trench alternative. He questioned if the Committee should give guidance on
a recommendation to hold off on those expenses until there is an answer on the 4-track.
Chief Transportation Official Kamhi stated all that is being done is reviewing bids for that. The
vendor has not been selected, so that has not started. He stated the Council had directed Staff
on this but did not feel there was harm in holding on that.
Chair Burt stated it could be added to the early recommendations of the Committee to the
Council to do early this year.
Mayor Kou was concerned about outreach to South Palo Alto as there is a large number of
people who are quite vocal about a trench. It is not clear what the underpass is going to look
like, especially with the U-turn, the circle, and the potential of housing being taken away. This
will require quite a lot of communication and clarity for people in South Palo Alto.
Chair Burt wondered about Congresswoman Eshoo's earmark potentially covering the cost to
have Caltrain pursue this as exception without costing the City.
Ms. Naik stated part of the challenge was the only work done has been on 2-track alternatives,
not 4 tracks. She suggested letting it be known to Representative Eshoo's office that Palo Alto
is unable to use the money secured because of not getting an answer from Caltrain about the
location of the 4 tracks, which might help speed things up. If 4 tracks need to be allowed for,
this can be done as a design exception to the 2-track alternatives.
Chair Burt stated the decision-making should be based on criteria and felt there should be a
review of the criteria at the next meeting, as a starting point to reflect the current best
understandings.
Council Member Lauing and Mayor Kou agreed.
Chair Burt asked about inclusion of quiet zones in other locations than just Palo Alto Avenue as
it could be many years before the grade crossings are constructed.
Chief Transportation Official Kamhi stated Palo Alto Avenue would be used as an example to
apply to the other crossings.
Senior Engineer Bhatia added there was a plan to have an RFP by the end of the year to get a
consultant on board to do the 3 other crossings.
SUMMARY MINUTES
Page 8 of 13
(Sp.) Rail Committee Meeting
Summary Minutes: 2/15/2023
Chair Burt asked to have it reflected in the Work Plan that Palo Alto Avenue was the impetus
for the other crossings, to help people all of them are being looked at.
Mayor Kou about the status of the Palo Alto Avenue Quiet Zone.
Senior Engineer Bhatia stated the original study was in the outreach phase, seeking feedback
from the community on March 23. That information will be brought to the Rail Committee in
April, another opportunity for the public to provide input. The concept plan would be finalized
based on the Rail Committee's input and direction and then recommended to the City Council
for implementation, which starts with approval from CPUC and construction of the
improvements. Once the improvements are complete, installation of the quiet zone by FRA
would be requested.
Chief Transportation Officer Kamhi stated it would be in front of Council for recommendation
to implement August or September.
Mayor Kou asked if that outreach is being done by Menlo Park or Palo Alto.
Senior Engineer Bhatia stated the first community outreach meeting will be in collaboration
with Menlo Park but Palo Alto will be meeting virtually with different stakeholders with
opportunity for the Rail Committee, constituents, and stakeholders to provide feedback.
Chair Burt suggested contacting the leadership of the resident association at 101 Alma to do an
outreach. He also suggested that, because the quiet zone evaluation at Palo Alto Avenue will
potentially lead into Churchill, East Meadow, and Charleston, the outreach for the March
meeting in Menlo Park should include those interested in those other 3 grade crossings.
Chief Transportation Officer Kamhi stated 101 Alma would be included in outreach and there
would be a separate outreach once the process for the other crossings is started.
Chair Burt explained that the massive construction project for the vehicular grade crossings
would disrupt the ability of kids to go to and from school by bike; therefore, moving forward
with dedicated bike and ped crossings ahead of the vehicular ones has been considered. It was
also explained last year by multiple agencies that there is a lot of funding available for this type
of construction, and additional funding sources have been opening up at the federal and state
levels. It would be ideal to go forward in parallel with the new BPTP rather than waiting
another year or two to get the plan to begin the process, which would hold up the sequencing
of grade crossings and potentially make Palo Alto less eligible for funding. There are currently 4
grade crossings north of Oregon and none south of Oregon, and this was also a priority for the
community. A Work Plan priority to look at integrated safe systems for cars, bikes, and
pedestrians was referred by the Council. At-grade crossings are high on the list of risks to
safety, yet they are more complicated and expensive to solve. He encouraged the Committee
to look at the decision to pursue bike and ped grade separations in South Palo Alto sooner
rather than later.
SUMMARY MINUTES
Page 9 of 13
(Sp.) Rail Committee Meeting
Summary Minutes: 2/15/2023
Chief Transportation Official Kamhi stated that mitigations for bicycles and pedestrians, even on
a temporary basis, would be ensured during construction of any alternative selected for
Charleston, Meadow, and Churchill. One dependency for starting additional crossings is
figuring out whether the rail is going up or down, if it is a tunnel or overcrossing.
Chair Burt stated the crossing in the vicinity of Loma Verde would be outside either elevating or
depressing tracks. South of there, the way bike and peds were dealt with will be tied in with
the design for vehicular separation. There were concerns about whether that addresses the
needs. He thought separated could be completed on a more accelerated basis at Loma Verde
and conceivably at Seale, but he felt Seal was a lower priority.
Chief Transportation Official Kamhi stated the Council had directed to use the Bicycle and
Pedestrian Transportation Plan to look at the possibility for new east-west crossings. Public
engagement would be necessary even for Loma Verde. There is also a need to look at the
bicycle and pedestrian network as a whole. One of the first parts of work on the BPTP will be
community outreach.
Chair Burt stated the east-west need was looked into in 2015 with considerable work pursued
at that time. He listed several parallel paths east and west of Caltrain and stated the lack of
perpendicular routes had been well established as a significant gap in the bike system. The
exact path was another question.
City Manager Ed Shikada stated another issue was the lack of staff bandwidth to do the work
and whether to organize it as part of grade separation work or part of the BPTP work.
Chair Burt felt if the situation was a need to sequence and a rare set of opportunities for very
significant capital dollars but lack of internal capacity, it should be conveyed to the Council
what it would take to accomplish. The Council could then make a decision on whether or not to
do it. If it was something to be prioritized in the May budget, Staff needs that decision soon
enough to fold into the budget, at least as an alternative if not a recommendation.
Chief Transportation Official Kamhi agreed that resources were a major constraint but Staff was
planning to include a request in the budget for someone to work on this and would be in a good
position to apply for funding for additional crossings.
Chair Burt discussed the Measure B dollars and questioned if some of those funds were
potentially available for internal staffing purposes.
Chief Transportation Official Kamhi was not sure if that covered staff time and would look into
it. He added that additional staffing would not be for this alone but also for other projects that
resources are not currently available for.
Chair Burt proposed bringing a recommendation sooner rather than later on sequencing of bike
and ped crossings, with the prospect of the one in the vicinity of Loma Verde being the most
unconstrained and highest priority. The Churchill Avenue Enhanced Bikeways Project was
SUMMARY MINUTES
Page 10 of 13
(Sp.) Rail Committee Meeting
Summary Minutes: 2/15/2023
already moving forward, and even though that did not answer the question of the ultimate
grade separated crossing, it was a significant improvement already in the CIP. Loma Verde
stood out as the one where construction dollars could be tapped into and construction done
sooner rather than later, with real impacts on the community. It was not dependent on
another item on a critical path and had a well-established need in that approximate location.
Issues had been raised with Caltrain regarding the San Francisquito Creek Bridge replacement
and the degradation of the bridge. Regarding the item, "Updates on funding and legislative
information and opportunities for grade separations," he stated there was certain funding to
help with furthering the selection and preliminary design, the prerequisites to tap into the big
dollars. Breaking that down, the questions were the funding to proceed on the selection of
preferred alternative, the preliminary design, the construction dollar pursuit, and legislative
aspects. He asked Staff to speak about available dollars for proceeding on design alternatives
and then for preliminary design.
Chief Transportation Official Kamhi listed Measure B grade separation dollars, which VTA has
agreed can be used to pursue additional studies as part of the conceptual design phase in order
to help complete the selection, and the Measure B Local Streets and Roads dollars, which can
be used for congestion-relieving activities. This item was intended for any other funding
sources that may come into play, such as the Mega federal grant program, INFRA federal grant
program, TIRCP, Section 190 funds. Prioritizing and getting to a selected alternative for all
locations would make the City more competitive in applying for grants.
Chair Burt stated it was unlikely the City would get construction dollars to cover all 3 at once
and suggested getting to a preferred alternative and preliminary design on one of them.
Chief Transportation Official Kamhi believed Council had prioritized Meadow-Charleston, so
that was how Staff was applying currently.
Chair Burt added that narrowing the alternatives for Churchill was probably farther along but
the higher priority was Charleston-East Meadow.
Ms. Naik added that this plan does not include looking at alternatives for Palo Alto Avenue. The
City was pushing back on Caltrain that the replacement of the San Francisquito Creek Bridge
should be a rehabilitation, and she felt there was a chance Caltrain could decide it was a safety
issue with a need to replace the bridge. That would put options for Palo Alto Avenue in
jeopardy. She wanted to be sure this was part of the conversation for the ad hoc committee for
Stanford, as Stanford owns the station area.
Chair Burt wanted to add a placeholder to the list for lower-priority, lower-sequence projects
like the Creek Bridge replacement, Palo Alto Avenue, and the intermodal station. He stated the
intermodal station was outdated and had the highest boardings in the Caltrain system. It has
been recognized for decades as a critical part of county transportation and Caltrain. There was
a question of whether there were still Measure A dollars or other funding sources to be tapped
into. VTA has talked about helping with MTC, and more recently Caltrain had an action item on
SUMMARY MINUTES
Page 11 of 13
(Sp.) Rail Committee Meeting
Summary Minutes: 2/15/2023
negotiation guiding principles for the downtown intermodal station. That is racing forward
because it potentially has massive federal dollars in funding and huge political support. He
wanted to keep in mind that it was on the future list and that having preliminary involvement
with it may tee up funding that needs to be discussed with various agencies. It was not the
most immediate priority but was of high importance.
Chief Transportation Official Kamhi explained that the internal strategy was to get one of the
other locations into the next phase so Staff had the capacity to take on Palo Alto Avenue.
Chair Burt felt it was important to get it on the list for strategizing as opposed to staff
resources.
Ms. Naik added there was a team on the Caltrain side taking every opportunity to get
replacement money and the bridge qualified under the State of Good Repair. It may pop up
unexpectedly if Caltrain make an aggressive move because it is high on their list. She worried
that Caltrain could replace that bridge without Palo Alto having a say in it. She felt one thing
that allowed the City to have an impact on that was the El Palo Alto Tree.
Chief Transportation Official Philip Kamhi stated Staff has been working closely with the people
working on the El Palo Alto Tree report, and Caltrain is awaiting that. He agreed that Ms. Naik
was right about the State of Good Repair money and hoped that the word repair in the title of
the funding meant it did not have to be a replacement.
Council Member Lauing asked the legality Caltrain saying the tree was in the way.
Chief Transportation Official Philip Kamhi thought that would be difficult because of the tree's
historic impacts.
Chair Burt wanted to ensure the tree had adequate designation and concluded his list of
questions and input on the plan.
Mayor Kou asked what kind of legislative information was expected. She asked if there was a
reason to do lobbying for funding during the National League of Cities.
Chief Transportation Official Kamhi stated that was added as a catchall in case something
becomes available.
City Manager Shikada clarified that lobbying was separate from the NLC.
Chair Burt stated there was a differentiation between legislative advocacy versus advocacy
through agencies that already have this unprecedented funding. He wanted to ensure the
agencies knew where Palo Alto was in the process and understood how high the grade
separations were on the safety hazard ranking. He added that the need to grade separate the
Caltrain corridor was a high priority because the state budget and surpluses in the last 2 years
have been driven by the economic engine served by the Caltrain line. The entire state budget
SUMMARY MINUTES
Page 12 of 13
(Sp.) Rail Committee Meeting
Summary Minutes: 2/15/2023
and a real impact on the U.S. economy resides in this corridor. He felt the argument to carry
forward at the state and federal level and regionally with MTC was that it is in their interest to
prioritize this. He asked if the Committee had answered the questions well enough to help
refine the year's agenda.
Mayor Kou questioned if jack boxing was still being looked into as she did not see that included.
Chair Burt explained that was within the construction method part of technical standards and
there were a couple of construction method elements that were not necessarily design
standards that intersect.
Chief Transportation Official Kamhi added that Caltrain committed to providing information
about alternative construction techniques.
Chair Burt stated it also fit into the service agreement, with questions on having Caltrain review
designs as one-offs versus under the Corridor Crossing Strategy. This was all related to getting a
refinement and constructing things with better designs, at lower cost, or at lower construction
impact to the community. There were several paths to take to get to that endpoint.
Ms. Naik stated it would be great to have a Caltrain presentation on jack box construction prior
to the Council deciding on a trench, viaduct, or hybrid.
Chair Burt asked about interest on Caltrain or VTA presenting at future meetings, as having
them present gets their attention and causes them to move more quickly on Palo Alto's
priorities.
Chief Transportation Official Kamhi responded that some of it ties into the standard agreement.
Caltrain had committed to talking about alternative construction methods, which they can do
outside of either the study or the service agreement.
Chair Burt suggested asking them to come to the March meeting or even asking them to a
series of meetings on different subtopics.
Council Member Lauing stated that of the 4 projects, Churchill was not the highest priority. He
felt that if the proposal with the partial underpass was found to work, Churchill should proceed
forward even though Meadow was a higher priority.
Chair Burt did not want to decide that at this point but felt there may be a crunch point when
that decision could be made.
Council Member Lauing agreed.
Ms. Naik clarified that there were technically 3 projects because Meadow and Charleston were
considered one project and had to be done together, which qualified for different funding than
a regular grade separation.
SUMMARY MINUTES
Page 13 of 13
(Sp.) Rail Committee Meeting
Summary Minutes: 2/15/2023
Chief Transportation Official Kamhi stated for the next meeting, Rail Committee was to review
selection criteria and Staff would try to get Caltrain to talk about alternative construction
techniques, specifically jack boxing. He asked the attorney if an action was needed for the list
of items.
Assistant City Attorney Tim Shimizu stated it was up to the Chair if he wanted to do a formal
motion about making changes but it did not sound like there was much question about the
topics.
Chair Burt felt Chief Transportation Official Kamhi and he could work together on the agenda
plan and then have an opportunity for the Committee to review it.
Ms. Naik described that XCAP's report has a section on suggestions for the updates to the
criteria. The report referenced the fact that there was conflicting criteria, and she suggested
looking at that for the staff report, discussing having several policy documents that seem to
contradict each other when thinking about priorities.
Chief Transportation Official Philip Kamhi added Staff would have a temporary hold on doing
the cost peer review on the trench alternative until it gets back to Council.
City Manager Shikada suggested reporting this out to the full Council at the next Council
meeting, if not more formally.
Chair Burt wanted to consider a discussion in March about the most immediate things to take
back to the Council for affirmation.
No action taken
Next Steps and Future Agendas
Next tentative meeting is March 15, 2023.
Adjournment: The meeting was adjourned at 3:39 P.M.