HomeMy WebLinkAbout2020-10-19 City Council Agendas (8)City of Palo Alto (ID # 11095)
City Council Staff Report
Report Type: Informational Report Meeting Date: 10/19/2020
City of Palo Alto Page 1
Summary Title: CIP Projects Update
Title: Semiannual Update on the Status of Capital Improvement Program
Projects
From: City Manager
Lead Department: Public Works
Recommendation
This report is provided for information only and requires no Council action.
Executive Summary
The City Council and Palo Alto community can be proud of the City’s capital improvement
program (CIP). The CIP represents major investments into infrastructure functionality and
sustainability, funded largely through the 2014 Council Infrastructure Plan, as well as utility
rates and various other sources totaling $729 million through 192 projects over the next five
years. Over the past five years, the City has completed 65 individual community-serving
projects totaling nearly $177 million of improvements.
The CIP also represents a major effort for much of the City workforce. The following table
summarizes the status of all projects for the six-month period of January to June 2020.
CITY OF
PALO
ALTO
City of Palo Alto Page 2
Project Type
Active Projects Construction
Phase
(excludes
Recurring)
Completed One-Time Recurring
Buildings & Facilities 28 10 6 4
Parks & Open Space 15 9 - -
Streets & Sidewalks 3 6 - -
Traffic & Transportation 10 5 2 -
Airport 3 - 1 -
Electric Fund 28 10 7 3
Fiber Optics Fund 1 2 - -
Gas Fund 2 4 1 -
Storm Drain 4 1 1 -
Water Fund 7 7 1 2
Wastewater Collection Fund 3 4 1 1
Wastewater Treatment Fund 6 1 1 -
Totals 110 59 21 10
Background
This report provides Council with an update on the status of capital improvement program (CIP)
projects. Prior to 2016, year-end and mid-year financial reports included very simplistic status
updates on CIP projects. In contrast, this semiannual report provides more detailed and useful
information for Council regarding general fund and enterprise fund projects that appear on
Council agendas and will be visible throughout the community.
Discussion
Project Update Organization
The City has a robust capital improvement program, and many individual projects are in
progress at any given time. In the five-year CIP Fiscal Year 2020-2024, there are 218 projects
(capital, enterprise and internal fund projects) totaling $751 million in funding. The attached
CIP project tables are intended to provide Council a quick overview of each project, including
budgetary information, the anticipated completion date, a brief description of the project
scope, the status of the project, and upcoming activities including Council actions. Also included
in the report, is a list of all completed projects since the introduction of the Infrastructure
Management System.
During the Fiscal Year 2021 budget process, several CIP projects were either defunded or saw
significant funding reductions as the City worked to address the projected revenue shortfalls
associated with the shelter-in-place orders instituted in response to COVID-19. Projects that
City of Palo Alto Page 3
were subject to funding reductions in the Fiscal Year 2021-2025 CIP will be called out
throughout this CMR with an asterisk * tag. Detailed information on the changes to these
projects can be found in Attachment A, Exhibit 2 of CMR#11376.
Major/Significant Projects Summary
The 2014 Council Infrastructure Plan is a major focus of staff’s capital improvement program
efforts. The following table details the Total Project Budget and Total Actual Expenses through
the second half of Fiscal Year 2020 for the Infrastructure Plan projects.
Significant milestones have been achieved on the Infrastructure Plan projects since December
2019, even though construction delays occurred due to the COVID-19 pandemic. The concrete
structural shell has been completed on the California Avenue Garage, the Highway 101
Pedestrian/Bicycle Bridge project started driving concrete piles and grading work, and phases 1
and 2 of the Charleston/Arastradero Corridor Project are complete. Current Infrastructure Plan
project schedules can be found at http://www.infrastructure.cityofpaloalto.org/
City of Palo Alto Page 4
Council
Infrastructure
Plan Projects
CIP
Number Update Total Project
Budget
Total Actual
Expenses**
New Public Safety
Building PE-15001
Plans were submitted for building permit in
December 2019. Review is nearly complete
and planning to bid in fall 2020.
$118,007,012 $9,189,964
Bicycle and
Pedestrian
Transportation
Implementation
Plan*
PL-04010
Project on hold pending recent project
evaluation and review of future project
scoping.
$16,616,736 $9,114,859
New Downtown
Parking Garage* PE-15007
Certified EIR and approved land use actions.
Project on hold pending review of
downtown parking supply options.
$6,583,930 $1,440,311
New California
Avenue Area
Parking Garage
PE-18000
Construction is nearly complete with all
concrete floors poured and site work
underway. Project completion is expected in
October 2020.
$50,119,976 $37,889,567
Charleston
Arastradero
Corridor Project
PE-13011 Phase 1 & 2 improvements are complete.
Phase 3 to start construction in fall 2020. $19,554,473 $11,701,371
Fire Station 3
Replacement PE-15003 Completed $10,080,258 $9,189,964
Highway 101
Pedestrian/Bicycle
Overpass Project
PE-11011
Construction is underway with all piles
poured along East Bayshore Road. Work
continues on the supports and creek bridge
on the West Bayshore side. Project
completion is expected in Summer 2021.
$22,889,453 $7,182,628
Fire Station 4
Replacement PE-18004
A request for proposals was released in July
and a contract for design services will be
brought to Council for approval in Fall 2020.
$10,200,000 $17,781
Byxbee Park
Completion* PE-18006 On hold pending completion of Baylands
Comprehensive Conservation Plan. $3,240,043 $368,192
Downtown
Parking Guidance
System
PL-15002
A design build proposal will be released in
the fall and a contract will be brought to
Council in early 2021.
$2,857,335 $138,611
**Expenses as of June 30, 2020
Key considerations for the information presented in the project update tables include:
•Project status information is current as of June 2020
•The individual project tables align with the Capital Improvement Fund categories in the
FY 2020-2024 capital budget: Buildings and Facilities, Parks and Open Space, Streets
and Sidewalks, and Traffic and Transportation. Enterprise Fund projects follow the order
of their respective Fund in the capital budget
•Additional project information is available in the FY 2020-2024 capital budget
•Cubberley Property Infrastructure Fund projects are included in the Buildings and
Facilities table
City of Palo Alto Page 5
•Each project table is divided into a section for one-time projects and a section for
recurring projects that have ongoing annual funding
•Budgetary figures include staff oversight costs for projects to which staff costs have
been allocated
Completed Projects
Projects completed in the second half of Fiscal Year 2020, since the last update through
December 2019, from January 2020 to June 2020 include the following:
Capital Improvement Fund (general fund):
•Fire Station 3 Replacement (PE-15003)
•Cardiac Monitor Replacement (FD-20000)
•Parking Lot J Elevator Modernization (PF-18000)
•Self-Contained Breathing Apparatus Replacement (FD-18000)
Enterprise Funds:
•Rebuild Electrical Underground District 19 (EL-11008)
•Water Main Replacement – Project 27 (WS-13001)
•VA Hospital Customer Load Requirements (EL-17003)
•Wastewater Collection System Rehabilitation / Augmentation Project 28 (WC-15001)
•Water Reservoir Coating Improvements (WS-08001)
•Utility Site Security Improvements (EL-04012)
These completed projects do not include the significant amount of annual work completed
under ongoing recurring projects, such as streets and sidewalks repairs, parking lot
maintenance, roofing replacements, and regular maintenance of Utilities assets.
City of Palo Alto Page 6
Cardiac Monitor Replacement (FD-20000)
Fire Station # 3
City of Palo Alto Page 7
Projects Under Construction
Projects that are currently under construction include the following:
Capital Improvement Fund (general fund):
•Animal Shelter Renovation (PE-19002)
•Fire Station 1 Improvements (PF-14002)
•Fire Ringdown System Replacement (FD-14002)
•High and Bryant Street Garages Waterproofing and Repairs (PE-18002)
•Highway 101 Pedestrian/Bicycle Overpass Project (PE-11011)
•JMZ Renovation (AC-18001)
•New California Avenue Area Parking Garage (PE-18000)
•Municipal Service Center lighting, Mechanical, and Electrical Improvements (PF-16006)
Enterprise Funds:
•Airport Apron Reconstruction (AP-16000)
•Gas ABS/Tenite Replacement Project (GS-18000)
•HCB Pilot Wire Relay Replacement (EL-17005)
•Loma Verde Avenue Trunk Line Improvements (SD-19000)
•Mayfield Reservoir Subgrade and Venting Repair (WS-19000)
•Rebuild Electrical Underground District 24 (EL-10006)
•Reconfigure Quarry Feeders (EL-14005)
•Electrical Underground District 46 – Charleston, El Camino Real (EL-12001)
•Electrical Underground District 47 – Middlefield, Homer, Webster, Addison (EL-11010)
•Substation Physical Security (EL-16003)
•Substation 60kV Breaker Replacement (EL-17002)
•Wastewater Collection System Rehabilitation / Augmentation Project29 (WC-16001)
•Plant Master Plan (WQ-10001)
As described above for completed projects, the list of projects under construction does not
include work currently being conducted under recurring CIP projects.
City of Palo Alto Page 8
Below are some photos of projects under construction:
Highway 101 Pedestrian/Bicycle Overpass Project (PE-11011)
City of Palo Alto Page 9
New California Avenue Area Parking Garage (PE-18000)
City of Palo Alto Page 10
Animal Shelter Renovation (PE-19002)
City of Palo Alto Page 11
JMZ renovation
Capital Improvements of Note Implemented by Others
El Camino Real:
El Camino Real (State Highway 82) is maintained by Caltrans. Pavement Condition Index scores
for El Camino Real are significantly lower than the average for Palo Alto streets. Staff has been
communicating with Caltrans about the upcoming plans to repave El Camino Real from the
Mountain View to Menlo Park borders. Currently, this work is planned for 2022.
Caltrain Electrification:
Construction continues on Caltrain Electrification in Palo Alto. More than 75% of the poles
needed for the project have been installed. These poles will hold the electric overhead lines
that will power the new electric trains. About 25% of the wiring has been completed in the City.
Crews will continue to install the remaining poles and wires over the next few months.
Construction also is continuing at the Paralleling Station near Page Mill Road in Palo Alto. The
facility is expected to be complete in Spring 2021.
Resource Impact
Funding for the projects discussed in this report is provided in the FY2020 Capital Budget and
5-Year Plan.
Stakeholder Engagement
Stakeholder engagement is conducted separately for each project.
Attachments:
•Attachment A: CIP Updates and List of Completed Projects
JUNE 2020
Semiannual Update on the Status of Capital Improvement Program Projects
Capital Improvement Fund CIP Projects
Buildings and Facilities Projects
Parks and Open Space Projects
Streets and Sidewalks Projects
Traffic and Transportation Projects
Enterprise Fund CIP Projects
Airport Projects
Electric Projects
Fiber Optics Projects
Gas Projects
Storm Drain Projects
Wastewater Collection Projects
Wastewater Treatment Projects
Water Projects
List of Completed Projects
ATTACHMENT A
Blank page
Buildings and Facilities Projects Status as of June 2020
*‐ Projects that were subject to funding reductions in the Fiscal Year 2021‐2025 CIP
Buildings and Facilities Projects – Page 1 of 10
One‐Time Projects
Automated
External
Defibrillator
Replacement
(FD‐21000)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$0 $200,000 Fire Design Summer 2021
Project Status: This project replaces the entire complement of Automated External Defibrillators (AEDs)
throughout City facilities and emergency response vehicles, which currently totals 93 AEDs.
Animal Shelter
Renovation
(PE‐19002)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$270,962 $3,929,979 Public Works Construction Summer 2021
Project Status: This project installs interim facility improvements to the Animal Shelter that accompany the
agreement for operation of the shelter by Pets in Need approved by City Council in November 2018. The medical
area upgrades and the modular office building are complete. The new kennel addition is currently in design and
construction is anticipated to start in fall 2020.
Cardiac Monitor
Replacement
(FD‐20000)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$0 $850,000 Fire Completed Spring 2020
Project Status: This project replaced the entire complement of twenty cardiac monitors in the Fire Department.
Along with other tools needed for patient assessment and airway verification, cardiac monitors assess cardiac
activity in patients and provide defibrillation and pacing. The Department has purchased and deployed the new
monitors.
City Facilities
Assessment and
Record Plan
Management
System
(PE‐20002)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$0 $314,000 Public Works Design Fall 2020
Project Status: The Kitchell Report in 2008 summarized the last City‐wide facility condition assessment. A new
facility condition assessment is warranted per the City’s APWA reaccreditation requirements. It is also an ideal
opportunity to develop a new electronic system for managing the record plans of all City facilities. Currently, older
record plans are managed through a Microsoft Access Database. Some record plans are still only available as
hardcopy sheets. The project will include scanning older hardcopy sets and compiling all records into a new
indexed system that will be easily accessible to all City staff.
Buildings and Facilities Projects Status as of June 2020
*‐ Projects that were subject to funding reductions in the Fiscal Year 2021‐2025 CIP
Buildings and Facilities Projects – Page 2 of 10
City Hall Space
Planning
(PE‐19000)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$0 $81,932 Public Works Pre‐Design Fall 2024
Project Status: This project involves space planning to determine future workgroup space needs and programming
for the City Hall office building. The project will include preliminary design of the space following the initial
feasibility phase.
Civic Center
Electrical
Upgrade & EV
Charger
Installation
(PE‐17010)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$87,860 $991,578 Public Works Design Spring 2021
Project Status: This project replaces the aging Civic Center electrical switchgear and motor control centers. A
request for proposals for a design contract is currently underway to hire an engineering consultant. Another part
of the project is to install 13 dual head level 2 chargers in City parking garages. Design for the EV chargers
installation is complete. Five new dual head EV chargers will be installed in the Civic Center garage. Two new dual
head EV chargers will be installed in the Bryant Street garage. Six new dual head EV chargers will be installed at
the Webster Street garage. Building permits have been approved and the project is out to bid. Construction
should start in October 2020 and conclude around December 2020.
Civic Center Fire
Life Safety
Upgrades
(PE‐18016)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$16,624 $627,017 Public Works Design Spring 2021
Project Status: This project will assess, update, and replace the Civic Center fire alarm system. The fire life safety
system is approaching the end of its useful life. The fire alarm panels and associated equipment need an upgrade
to meet current code requirements. Procurement documents are currently awaiting to be advertised for
competitive solicitation.
Civic Center
Waterproofing
Study and Repairs
(PE‐15020)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$54,493 $742,555 Public Works Design Fall 2020
Project Status: This project includes a condition assessment of the Civic Center plaza deck structural system. In
late 2016, RDH Building Science, Inc. was hired to investigate the problem. The results indicated that the
expansion joint on the plaza can be repaired. The scope expanded to include replacing the waterproof coatings on
the inside of the plaza perimeter planter boxes. The design contract is being amended and construction is
estimated to begin in fall 2020.
Buildings and Facilities Projects Status as of June 2020
*‐ Projects that were subject to funding reductions in the Fiscal Year 2021‐2025 CIP
Buildings and Facilities Projects – Page 3 of 10
Cubberley
Community
Center Master
Plan
(CB‐16001)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$505,301 $926,792 Community Services Design Summer 2020
Project Status: This project supports the development of a Master Plan for future use of the Cubberley Community
Center site by the City and Palo Alto Unified School District. A draft Cubberley Concept Plan was completed in
November 2019 and was distributed to the community for input. CEQA analysis of the concept plan began and is
expected to be completed in 2020.
Cubberley
Building
Management
Systems
(CB‐19001)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$0 $ 360,807 Public Works Design Fall 2020
Project Status: This project replaces the Building Management System (BMS) controls for the Pavilion, Theater,
Wing I, and Gyms A and B boiler rooms at the Cubberley Community Center. The project will include the
installation of control points for each building along with controllers, valve and damper actuators. A contractor
has been selected for this project and the contract goes to Council in August for approval. Construction will start in
September and conclude in December 2020.
Fire Ringdown
System
Replacement
(FD‐14002)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$244,144 $353,300 Fire Construction Summer 2020
Project Status: This project will replace the current ring down system that provides an audible alert of calls for
service in the fire stations. A vendor was selected through a cooperative purchasing agreement. Installation has
been ongoing since 2018 and the installation for Fire Station 3 has been completed. Final ringdown protocols are
being tested and adjusted.
Fire Station 1
Improvements
(PF‐14002)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$73,510 $187,064 Public Works Construction Summer 2020
Project Status: Construction is 85% complete with only painting, skylight replacement, and outdoor concrete pad
work remaining.
Fire Station 3
Replacement
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$9,189,964 $10,080,258 Public Works Completed Winter 2020
Buildings and Facilities Projects Status as of June 2020
*‐ Projects that were subject to funding reductions in the Fiscal Year 2021‐2025 CIP
Buildings and Facilities Projects – Page 4 of 10
(PE‐15003) Project Status: This project replaced the existing Fire Station at Embarcadero Road and Newell Road with a new
structure that meets essential services standards and current program needs. Construction on the new Fire
Station began in January 2018 and was completed in March 2020. The building is still awaiting LEED certification
by the US Green Building Council.
Fire Station 4
Improvements
(PE‐18004)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$17,781 $10,200,000 Public Works Pre‐design Fall 2023
Project Status: This project provides funding to replace Fire Station #4 at the corner of Middlefield Road and East
Meadow Drive. The replacement facility will be based on the prior Replacement Study and Needs Assessment
prepared in 2005. The project will go out with a request for proposals for design in summer 2020.
High and Bryant
Street Garages
Waterproofing
and Repairs
(PE‐18002)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$31,728 $352,729 Public Works Construction Summer 2020
Project Status: This project includes a study for analysis and repairs to the water proofing system in the High Street
and Bryant Street parking garages. Water proofing repairs have been completed in the High Street parking garage.
Repairs are 75% complete in the Bryant Street garage as additional repairs are needed in the subterranean
stairwells and a few remaining areas of the subterranean levels of the garage.
Internal Alarm
System
Replacement
(PD‐14000)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$50,759 $77,569 Police Design Fall 2020
Project Status: This project will replace the citywide Internal Alarm System. The City Hall alarms migrated to the
new system in FY 2019. There are on‐going discussions about adding additional sites and a CAD interface.
JMZ Renovation
(AC‐18001)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$1,041,302 $4,587,152 Community Services Construction Winter 2021
Project Status: This project will fund the relocation of the Junior Museum and Zoo to and from the Cubberley
auditorium building for two years. The renovation of the Cubberley auditorium was completed in June 2018. The
Junior Museum and Zoo moved into the Auditorium in June 2018 and opened to the public in July. Additionally,
the project paid permit fees and other costs ($306K in April 2019) for the new JMZ rebuild project in accordance
with the Council‐approved agreement between the Friends of the JMZ and the City. Construction of the new
Buildings and Facilities Projects Status as of June 2020
*‐ Projects that were subject to funding reductions in the Fiscal Year 2021‐2025 CIP
Buildings and Facilities Projects – Page 5 of 10
Junior Museum and Zoo commenced in June 2018 and is now 85% complete. Several animal exhibits have been
completed, several are in fabrication while the remainder are in final design. All exhibits are scheduled for final
installation in July 2020. Relocating staff, collections and equipment to the rebuilt facility is on a staggered
schedule of acquiring new animals, fabricating exhibits, and restoring temporary facilities to be completed by
December 2020. The public opening of the new JMZ is scheduled for March 2021.
Municipal Service
Center Lighting,
Mechanical, and
Electrical
Improvements
(PF‐16006)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$931,209 $7,218,763 Public Works Design Winter 2021
Project Status: This project replaces original mechanical, electrical, and lighting systems installed in 1966. It also
includes design and construction for office renovations for the Zero Waste group. Bids for the site‐wide
mechanical and electrical upgrades exceeded the available budget. Additional funding was added for FY 2020. A
contract amendment with the design consultant is currently in negotiation to better prepare the facility for
electrification in the future. Once the amendment is executed, the consultant will modify the design and it will be
issued for bids again in FY 2021.
Municipal Service
Center A, B, & C
Roof
Replacement
(PF‐17000)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$0 $2,146,289 Public Works Design Winter 2021
Project Status: This project installs a fluid, reinforced waterproofing application over the existing roof. The existing
asphalt and gravel roof has reached the end of its useful life and needs to be rehabilitated. If the existing roof is
allowed to deteriorate beyond a certain point, the fluid applied system cannot be used and a full replacement of
the roofing system would be required. The application will meet current cool roofing codes to optimize energy
efficiency. Project dates have been adjusted to coordinate with the Municipal Service Center Lighting, Mechanical,
and Electrical Improvements project (PF‐16006). Roof replacement will be done before the installation of new
rooftop equipment due to the condition of the roofs.
New California
Avenue Area
Parking Garage
(PE‐18000)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$37,889,567 $50,119,976 Public Works Construction Fall 2020
Project Status: This project will provide a new California Avenue Area Parking Garage, part of the 2014 Council
Infrastructure Plan and is being coordinated with the new Public Safety Building Project. The Public Safety Building
will be placed on Lot C‐6 while the new garage will be placed on Lot C‐7. Construction on the garage began in
Buildings and Facilities Projects Status as of June 2020
* ‐ Projects that were subject to funding reductions in the Fiscal Year 2021‐2025 CIP
Buildings and Facilities Projects – Page 6 of 10
January 2019 and has proceeded on schedule. Project completion is expected in late September 2020.
New Public Safety
Building
(PE‐15001)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$8,577,817 $ 118,007,012 Public Works Design Spring 2023
Project Status: This project will provide a new, modern Public Safety Building (PSB) that will meet essential services
standards and the current and future needs of the public safety departments. The PSB and new garage in the
California Avenue business district are now an integrated project and both are part of the 2014 Council
Infrastructure Plan. The PSB plans were submitted for building permit review in late December 2019. Project
bidding will take place in fall 2020 with construction beginning shortly after the new California Avenue garage
opens in late September 2020.
New Downtown
Parking Garage
(PE‐15007)*
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$1,440,311 $6,583,930 Public Works Design Spring 2024
Project Status: This project was intended to provide a new parking structure in the University Avenue commercial
area at existing Parking Lot D at the corner of Hamilton Avenue and Waverley Street. The project received ARB
approval in July 2018. In February 2019, the City Council certified the EIR by adopting the Resolution and
Mitigation Monitoring and Reporting Program. The Record of Land Use Action was approved for three (3) years
and the project is on hold until after the City returns to the Policy and Services Committee for further discussion on
the downtown parking management strategy. As part of the FY 2021 budget strategy, all Capital Improvement
Fund funding has been removed and only the downtown parking in‐lieu fee funding remains for this project.
Potential opportunities to use the remaining funding include public/private partnerships that may result in an
increase in public parking spaces.
Parking Lot J
Elevator
Modernization
(PF‐18000)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$413,998 $781,324 Public Works Completed Spring 2020
Project Status: This project modernized the existing elevators at parking Lot J. The project involved upgrading the
interior of the elevators, elevator control interface, call buttons, and meeting current ADA standards. Construction
started in April 2019. Project is complete except for the State final inspection on the second car. The State final
inspection is behind because of COVID, but the inspection should be done by the end of July 2020.
Buildings and Facilities Projects Status as of June 2020
* ‐ Projects that were subject to funding reductions in the Fiscal Year 2021‐2025 CIP
Buildings and Facilities Projects – Page 7 of 10
Performing Arts
Venues Seat
Replacement
(AC‐18000)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$0 $419,000 Community Services Design Summer 2021
Project Status: This project to replace the self‐rise mechanism in three venues for performing arts has been revised
to replace all the seats in the Community and Children’s Theatres. Staff will be seeking a consultant to advise on
ADA upgrade requirements that need to be completed with the seat replacement, in assessing the costs and
finalizing the scope of the project.
Police Video
Recording
Systems
Replacement
(PD‐20000)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$0 $300,000 Police Design Winter 2021
Project Status: This project replaces the Palo Alto Police Department video recording systems used to record
events in the field with in‐car cameras as well as body‐worn cameras (BWC). The in‐car camera technology was
introduced in 2013. In‐car systems are fixed in the vehicles and BWCs operate on rechargeable batteries for up to
8 hours, secured to the officer’s uniform. The in‐car video system is nearing the end of its service life and will need
to be replaced as they fail in FY 2021. The BWCs are under warranty for the current fiscal year after a one‐year
pilot program was implemented in FY 2019.
Self‐Contained
Breathing
Apparatus (SCBA)
Air Compressor
Replacement
(FD‐20001)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$0 $ 86,000 Fire Pre‐Design Summer 2021
Project Status: This project replaces the central air compressor that provides air for Self‐Contained Breathing
Apparatus (SCBA) tanks to ensure firefighter safety when entering environments with hazardous air quality. The
Department is researching potential vendors and collecting pricing.
Self‐Contained
Breathing
Apparatus
Replacement
(FD‐18000)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$730,140 $ 799,999 Fire Completed Spring 2020
Project Status: This project replaced Self Contained Breathing Apparatus equipment (SCBA) used by firefighters
when entering hazardous conditions when responding to fire and hazardous materials incidents. The SCBA
provides breathable air for firefighters when entering environments where the atmosphere is immediately
dangerous to life or health. The expected service life for SCBAs is 15 years. When this project was funded in FY
2018, 26 percent of the Palo Alto Fire Department (PAFD) SCBAs were past their useful life and 41 percent were
approaching the end of their useful life. Final coupling units and Bluetooth connectivity components were
Buildings and Facilities Projects Status as of June 2020
* ‐ Projects that were subject to funding reductions in the Fiscal Year 2021‐2025 CIP
Buildings and Facilities Projects – Page 8 of 10
purchased and the project is complete.
Water, Gas,
Wastewater
Office Remodel
(PE‐19001)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$5,996 $754,437 Public Works Design Summer 2021
Project Status: This project incorporates renovations to the Utilities Water Gas Wastewater (WGW) office space at
the Municipal Service Center (MSC). The current space no longer meets the operational needs of the department.
This project will reconfigure the work area so it is more efficient for department operations and replace aging
furniture and finishes. The new space will include a small reception area, additional offices and cubicles for new
staff. Upgrades to lighting, fire life systems and enhancements to the WGW corridors will also be included with
this renovation. The project is currently in design, and construction is anticipated to start in spring 2021.
Recurring Projects
Americans With
Disabilities Act
Compliance
(PF‐93009)*
Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion
$227,637 $822,220 Public Works N/A Recurring
Project Status: This project provides accessibility upgrades to City facilities and equipment. It includes continued
funding for improvements such as path of travel, restrooms, drinking fountains, and counters. Work in FY 2020
includes Council adoption of the update to the citywide ADA Transition Plan that began in November 2015. On
December 17, 2018, Council approved an amendment to the consultant contract for public outreach to complete
the ADA Transition Plan update. The public outreach process for the updated plan was completed in June 2019
and survey responses were compiled and taken into consideration to the ADA Transition Plan Schedule. A final
report was submitted to the City by the consultants for review and finalization in September 2019. The updated
Transition Plan is expected to go to Council for acceptance in fall 2020.
Building Systems
Improvements
(PF‐01003)*
Prior Year Actuals Current Year Budget Implementing Department Project Phase
Construction
Project Completion
$26,223 $419,991 Public Works N/A Recurring
Project Status: This project provides electrical, mechanical, plumbing, structural, and security upgrades for City
Buildings and Facilities Projects Status as of June 2020
* ‐ Projects that were subject to funding reductions in the Fiscal Year 2021‐2025 CIP
Buildings and Facilities Projects – Page 9 of 10
facilities. The installation of a new air‐cooled chiller for SA‐5 at City Hall was completed. This CIP was partially
defunded because of COVID budget cuts. The LED lighting upgrades for Rinconada and Mitchell Park tennis courts
have been delayed until FY 2021 due to City staffing constraints. The design for tennis courts lighting upgrade has
been started. The new cooling tower media replacement originally scheduled for winter 2020 will be delayed until
FY 2022.
City Bridge
Improvements
(PE‐20001)
Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion
$0 $16,000 Public Works N/A Recurring
Project Status: This project includes bridge maintenance, repair, and an improvement program over the next five
years. This program will include on‐going inspections to report physical changes to the structures,
recommendations for work to be done, and additional information to meet functional and structural standards in
accordance with industry standards.
City Facility
Parking Lot
Maintenance
(PE‐09003)*
Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion
$27,831 $1,024,611 Public Works N/A Recurring
Project Status: This project maintains parking lots and walkways at City facilities. As part of the FY 2020 Street
Resurfacing Project the Lucie Stern Drive‐through parking lot and four small parking lots in Las Trampas Valley
along the road near Foothills Park Interpretive Center will be resurfaced in fall 2020.
Cubberley Roof
Replacements
(CB‐16002)
Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion
$282,779 $576,500 Public Works N/A Recurring
Project Status: This project replaces existing roofs at Cubberley Community Center. Cubberley Wings F and FH
roofs are scheduled to be completed in summer 2020.
Cubberley
Repairs
(CB‐17001)
Prior Years
Actuals
Current Year Budget Implementing Department Project Phase Project Completion
$84,889 $786,462 Public Works N/A Recurring
Project Status: This project is for general maintenance needs of the Cubberley campus. Several more concrete
walkway repairs were completed to address trip and fall concerns.
Buildings and Facilities Projects Status as of June 2020
* ‐ Projects that were subject to funding reductions in the Fiscal Year 2021‐2025 CIP
Buildings and Facilities Projects – Page 10 of 10
Facility Interior
Finishes
Replacement
(PF‐02022)*
Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion
$75,238 $1,175,656 Public Works N/A Recurring
Project Status: This project improves the interior finishes of City facilities, including flooring, walls, cabinets, paint,
lighting, ceiling tiles, soundproofing, and fixed office furniture, doors, windows, and associated fire/life safety,
mechanical, electrical and plumbing code compliance requirements. Design for the Office of Management and
Budget’s (OMB) furniture reconfiguration is complete, and installation was completed in April 2020. Conceptual
design for the Revenue Collections area is in process and includes new furniture, new casework, and painting of
the interior office space. The Children’s Library carpet replacement is scheduled to be completed in summer 2020.
Roofing
Replacement
(PF‐00006)*
Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion
$770,934 $712,014 Public Works N/A Recurring
Project Status: This project replaces existing roofs at City facilities that have outlived their useful lifespans. The
roof replacement for the Ventura Community Center has been completed. The Animal Shelter roof recoating has
been delayed due to roof modifications required for the current remodel of the facility. The Baylands Athletic
Center Snack Shack and Restroom roof and Mitchell Park Tiny Tot Restroom roof are scheduled for replacement in
summer 2020.
Roth Building
Maintenance
(PF‐07011)
Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion
$1,420 $41,073 Public Works N/A Recurring
Project Status: This project is for window repairs, waterproofing of foundation walls, installation of electrical
service, and a new ventilation system at the Roth building. In addition, roofing repairs will be done on an as
needed basis until such time that the building is leased and occupied.
University
Avenue Parking
Improvements
(PF‐14003)
Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion
$48,116 $361,100 Public Works N/A Recurring
Project Status: This project maintains parking lots and parking structures within the University Avenue Downtown
Business Parking District. After Parking Lot C was completed in spring 2019, all University Avenue parking district
lots have been resurfaced and no additional work is needed at this time
Parks and Open Space Projects Status as of June 2020
* ‐ Projects that were subject to funding reductions in the Fiscal Year 2021‐2025 CIP
Parks and Open Space Projects – Page 1 of 6
One‐Time Projects
Pearson
Arastradero
Preserve
Parking Lot
Improvement
(OS‐18001)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$0 $188,000 Community Services Design Spring 2021
Project Status: This project provides funding to improve the Pearson Arastradero Preserve parking lot by improving the
base rock surfacing, adding drainage, widening the entrance for safety, and new fencing. The improvement will allow the
overflow parking area to be open year‐round, rather than only during the dry periods of the year.
Baylands
Comprehensive
Conservation
Plan (PG‐
17000)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$322,220 $431,029 Community Services Design Summer 2021
Project Status: This project develops a conservation plan examining native vegetation, wildlife habitat, and public access
for trails, recreation amenities, and interpretive messaging. Staff interviewed and selected a consultant, AECOM, to
create the plan. Staff and the consultant created an existing conditions report, formed a stakeholder and staff advisory
group, held three stakeholder meetings, and one community meeting, created draft chapters of the report, and have
developed conceptual plans for Byxbee Park including the former ITT property. An environmental impact study is in
process and upon completion the Baylands Comprehensive Conservation Plan will be presented to Council for formal
adoption.
Boulware Park
Improvements
(PE‐17005)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$100,462 $550,805 Public Works Pre‐Design Fall 2022
Project Status: This park renovation project was initially planned in FY 2018 but was postponed due to project priorities
and potential purchase of the adjacent AT&T lot located at 3350 Birch Street. In fall 2019, the lot was purchased by the
City. In response to the purchase, the City utilized the funding for the initial renovation project for preliminary design and
outreach for both the existing park and the newly purchased park land. Additional funding was requested as part of the
FY 2021 CIP process to implement park renovations for the existing Boulware Park and the new park land. In early 2020, a
Parks and Commission meeting and second community meeting were held to obtain input on project design. A third
online community meeting is planned for summer 2020. Staff is also assessing California Environmental Quality Act
(CEQA) needs.
Foothills Park,
Pearson
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$0 $486,096 Community Services Pre‐Design Winter 2024
Parks and Open Space Projects Status as of June 2020
* ‐ Projects that were subject to funding reductions in the Fiscal Year 2021‐2025 CIP
Parks and Open Space Projects – Page 2 of 6
Arastradero
Preserve and
Esther Clark
Park
Conservation
Plan
(PG‐17001)*
Project Status: This project creates a comprehensive conservation plan for Foothills Park, Pearson Arastradero Preserve,
and Esther Clark Park. The plan will provide guidance on wildlife and habitat management, public access and recreation,
trails, and interpretive messaging. The plan will provide insight on best management practices for wildlife, habitat,
vegetation, and recreation management. The plan will also provide priorities, which will help guide resources to the most
important projects. This project has been delayed to FY 2024 due to staffing and funding impacts.
Cameron Park
Improvements
(PG‐14002)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$0 $237,000 Community Services Pre‐Design Fall 2020
Project Status: This project upgrades and renovates safety and accessibility features at Cameron Park with a primary focus
on the park playground. The project is currently in the design and planning phase. A community meeting was held in May
2020.
Cubberley Field
Restroom
(CB‐17002)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$104,278 $681,546 Public Works Design Summer 2021
Project Status: This project will install a new restroom in the sports field area of the Cubberley Community Center. Design
for the project started in fall 2018 along with public outreach. A community meeting was held, and the Parks and
Recreation Commission reviewed the project in November 2018. The project is in design and needs to be reviewed by the
Architectural Review Board. Anticipated installation is in summer 2021.
Foothills Park
Boronda Lake
Dock
Replacement
(OS‐18000)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$0 $163,000 Public Works Pre‐design Spring 2021
Project Status: This project replaces an aged and deteriorating Boronda Lake Dock.
Foothills Park
Improvement
Project
(PE‐21000)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$0 $424,000 Public Works Pre‐design Fall 2023
Project Status: This project replaces the bridge to Sunfish Island and includes permitting and CEQA to address
replacement/improvements to the footbridge in Los Trancos Valley and the grade control structures along Buckeye Creek.
Parks and Open Space Projects Status as of June 2020
* ‐ Projects that were subject to funding reductions in the Fiscal Year 2021‐2025 CIP
Parks and Open Space Projects – Page 3 of 6
Foothills Park
Dam Seepage
Investigation
and Repairs
(PE‐20000)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$0 $36,000 Public Works Pre‐design Winter 2021
Project Status: This project will study a location of historic seepage from the Foothills Park Dam at the sharp bend in the
road on the face of the dam. The seepage is very minor, but it appears to be slowly worsening. The source of the seepage
is suspected to be the trench backfill around the pipe that returns shallow groundwater to Boronda Lake. This project will
locate and investigate the pipe and trench backfill material.
Johnson Park
Renovation
(PE‐21002)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$0 $1,194,000 Public Works Design Winter 2024
Project Status: This project includes the renovation of existing park elements, including asphalt concrete and brick
pathways, site furnishings, playground equipment and resurfacing, fencing, and improvements to irrigation and lighting.
This project has been delayed to FY 2024 due to staffing and funding impacts.
Ramos Park
Improvements
(PG‐14000)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$0 $271,000 Community Services Design Summer 2021
Project Status: This project includes safety and accessibility improvements at Ramos Park. The work includes replacing
the existing park playground, benches, drinking fountains, and resurfacing the basketball court playing surface. A second
community meeting has been planned for summer 2020 with construction planned for spring 2021.
Byxbee Park
Completion
(PE‐18006)*
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$ 367,192 $3,240,044 Public Works Pre‐Design Winter 2022
Project Status: This project allows for the remaining improvements to Byxbee Park that follows the completion of the
landfill capping work. The Baylands Comprehensive Conservation Plan (BCCP), which is currently undergoing CEQA
analysis, includes development of a conceptual plan for Byxbee Park. The BCCP and the conceptual plan for Byxbee Park
will be completed in summer 2020 and will be used to go out to bid for design and construction.
Rinconada Park
Improvements
(PE‐08001)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$2,280,051 $4,625,781 Community Services Design Spring 2021
Project Status: This project provides upgrades to safety, site amenities, playground facilities, a new restroom, irrigation,
drainage and ADA accessibility improvements at Rinconada Park. These improvements were identified in the Rinconada
Parks and Open Space Projects Status as of June 2020
* ‐ Projects that were subject to funding reductions in the Fiscal Year 2021‐2025 CIP
Parks and Open Space Projects – Page 4 of 6
Long Range Plan (LRP). The project schedule is currently being coordinated with the construction of the new Junior
Museum and Zoo Project. The Parks and Recreation Commission recommended a Park Improvement Ordinance (PIO) for
Council adoption in January 2020. Design and public outreach for the project has been performed by in house staff. The
project is anticipated to go out to bid in fall 2020. According to the LRP, future improvement phases would include
renovation to the eastern side of the park, arbor and pool areas, and development around the electrical substation.
Seale Park
Improvements
(PG‐14003)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$0 $400,000 Community Services Pre‐Design Summer 2024
Project Status: This project includes upgrades and renovations for safety and accessibility improvements. The project will
replace existing park amenities, picnic tables, and playground structures including a playhouse and swings; refinish the
playground perimeter fencing; and repair damaged decomposed granite and concrete pathways. Turf restoration and
irrigation renovations will also be included as well as replacement of bollards at the park entrances, the park sign, and a
small stone wall located in the middle of the park. This project has been delayed to FY 2024 due to staffing and funding
impacts.
Recurring Projects
Art in Public
Spaces
(AC‐86017)
Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion
$208,945 $1,349,443 Community Services N/A Recurring
Project Status: This project provides the ongoing temporary and permanent artworks throughout the City. FY 2020
funded temporary public artwork at King Plaza, Cubberley, the area surrounding California Avenue Garage
construction site, and for the upcoming Code: Art2 Festival. Additional funds were also used to hire a consultant to
create a California Avenue Public Art Plan. Some of the current Municipal Projects in process for FY 2021 include
artworks for the Charleston and Arastradero Corridor, the Highway 101 Bike and Pedestrian Bridge, the Public Safety
Building, and public programming for Code: ART2.
Benches, Signage,
Walkways,
Perimeter
Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion
$420,374 $207,000 Community Services N/A Recurring
Project Status: This project restores and replaces existing benches, signage, fencing, walkways, and landscaping at
Parks and Open Space Projects Status as of June 2020
* ‐ Projects that were subject to funding reductions in the Fiscal Year 2021‐2025 CIP
Parks and Open Space Projects – Page 5 of 6
Landscaping
(PG‐06003)
various City facilities. In winter 2020, wood fiber surfacing was installed at the small dog Park at Peers Park. In spring
2020, new bike racks were installed at Cubberley Community Center track and Mitchell Park pickleball courts.
Dog Park
Installation and
Renovation
(PG‐18001)
Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion
$15,746 $177,000 Community Services N/A Recurring
Project Status: This project enables building of dog parks at various City parks and facilities that currently do not have
dog parks, as well as renovating existing dog parks. The next dog park installation or renovation has not been
determined and several locations are under consideration. Staff is meeting with the Parks and Recreation Commission
to discuss location options and expansion of existing dog parks at Greer Park and Mitchell Park.
Off‐Road Pathway
Resurfacing and
Repair
(OS‐09001)*
Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion
$0 $455,000 Community Services N/A Recurring
Project Status: This project resurfaces failing and broken pathways within the City. Pathways are chosen based on
inspections and resident requests. The Adobe Creek Reach Trail will be built with the Highway 101 Pedestrian and
Bicycle Overcrossing Project that began in early 2020.
Open Space Lakes
And Pond
Maintenance
(OS‐00002)
Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion
$14,406 $102,800 Community Services N/A Recurring
Project Status: This project rehabilitates lakes and ponds in open space nature preserves to protect wildlife habitat
and recreational safety and to meet State Division of Safety of Dams requirements. A three‐year contract to clear
aquatic weeds at Boronda Lake is in progress and scheduled to be completed by September 2020.
Open Space Trails
and Amenities
(OS‐00001)
Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion
$286,674 $207,000 Community Services N/A Recurring
Project Status: This project restores unpaved trails, fences, picnic areas, and campgrounds at Foothills Park, the
Baylands, and the Pearson‐Arastradero Nature Preserves. A contract for trail maintenance was awarded in May 2018,
and the contractor has started the annual trail work. In spring 2020 the annual trail maintenance at Pearson
Arastradero Preserve and Foothills Park included 50 miles of trails, with heavy poison oak removal at the end of Steep
Hollow and Los Trancos trails, rail work on Redtail Loop Trail, and clearing of vegetation along the roadside in Pearson
Arastradero Preserve.
Parks and Open Space Projects Status as of June 2020
* ‐ Projects that were subject to funding reductions in the Fiscal Year 2021‐2025 CIP
Parks and Open Space Projects – Page 6 of 6
Park Restroom
Installation
(PG‐19000)
Prior Years Actuals Current Year Budget Implementing Department Project Phase Project Completion
$0 $414,000 Community Services N/A Recurring
Project Status: This project installs new restrooms at City parks that currently do not have restroom facilities. The
restrooms may be prefabricated, and each installation will require a Park Improvement Ordinance. Staff conducted a
community meeting in January 2020 to discuss adding a restroom at Ramos Park. Additional outreach is planned to
obtain community input.
Parks and Open
Space Emergency
Repairs
(PG‐09002)
Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion
$177,434 $142,000 Community Services N/A Recurring
Project Status: This project replaces or repairs playgrounds, play yard surfaces, wooden structures, park amenities,
and play equipment in the event of storms, fire, vandalism or structural failure. In winter 2020, arbor repairs occurred
at Greer Park. In spring 2020, rubber surfacing repairs to the Magical Bridge Playground were completed.
Athletic Courts
Resurfacing
(PG‐06001)
Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion
$55,378 $266,200 Community Services N/A Recurring
Project Status: This project repairs and resurfaces tennis and basketball courts in various Palo Alto parks.
Streets and Sidewalks Projects Status as of June 2020
* ‐ Projects that were subject to funding reductions in the Fiscal Year 2021‐2025 CIP
Streets and Sidewalks Projects – Page 1 of 3
One‐Time Projects
California Avenue
District Gateway
Signs
(PE‐17004)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$7,604 $176,999 Public Works Design Spring 2021
Project Status: This project includes the design and replacement of two existing gateway signs in the right‐of‐way
for the California Avenue business district. An application to the Architectural Review Board will be made in
summer 2020. The signs are expected to be replaced in spring 2021.
Newell Road/ San
Francisquito
Creek Bridge
Replacement
(PE‐12011)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$1,367,302 $4,831,256 Public Works Pre‐Design Spring 2022
Project Status: This project removes and replaces the Newell Road bridge over San Francisquito Creek with a clear
span to allow the channel to convey up to the natural capacity of the San Francisquito Creek, approximately 7,500
cfs, and will provide improved safety for vehicular, bicycle, and pedestrian traffic. The project is being closely
coordinated with the City of East Palo Alto, Santa Clara Valley Water District, and the San Francisquito Creek Joint
Powers Authority (JPA). The EIR was certified by Council in June 2020. The design of the preferred alternative will
be submitted to regulatory agencies for permits in fall 2020. Project construction is estimated to start by winter
2021.
Streetlights
Condition
Assessment
(PE‐13014)*
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$8,799 $241,481 Public Works Design Summer 2023
Project Status: This project assesses the condition and maintenance needs of the City’s streetlight system. This
project has been delayed to FY 2023 due to staffing and budgetary priorities.
Recurring Projects
Curb and Gutter
Repairs
(PO‐12001)
Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion
$450,166 $569,223 Public Works N/A Recurring
Project Status: This project repairs curbs and gutters uplifted by tree roots. For FY 2020, the curb and gutter
locations are selected from a list reported by the public and evaluated by Public Works staff. This project is
Streets and Sidewalks Projects Status as of June 2020
* ‐ Projects that were subject to funding reductions in the Fiscal Year 2021‐2025 CIP
Streets and Sidewalks Projects – Page 2 of 3
combined with the current year’s Sidewalk Repair Project (PO‐89003). Between January 1, 2020 and June 30, 2020,
there were 760 linear feet of curbs replaced and 2,500 square feet of gutter repaired at various locations
throughout the City. The FY 2019 Sidewalk, Curb and Gutter Repairs Project has been completed as of May 2020.
Sidewalk Repairs
(PO‐89003)*
Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion
$1,658,872 $1,455,975 Public Works N/A Recurring
Project Status: This project repairs and replaces broken and uplifted sidewalks. The program completed all twenty‐
three sidewalk districts in 2017, a thirty‐year (1986 – 2017) sidewalk repair district cycle. Council approved a
sidewalk assessment contract in November 2017 to evaluate the sidewalk program and assess potential
improvements to the current district‐based program. Staff used this assessment to compile a list of areas that
require prompt action at varying locations throughout Palo Alto. These priority locations were repaired in FY 2020.
The project repaired 4,300 square feet of sidewalk, 2,750 square feet of driveways and brought 8 curb ramps up to
ADA compliance between January 1, 2020 and June 30, 2020. The FY 2019 Sidewalk, Curb and Gutter Repairs
Project has been completed as of May 2020. Funding was reduced in FY 2021 as part of the FY 2021 Capital
Improvement Program budget strategy. Remaining funding will be used to perform emergency maintenance and
spot repairs.
Sign Reflectivity
Upgrade
(PO‐11000)
Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion
$10,207 $132,263 Public Works N/A Recurring
Project Status: This project includes the annual inventorying, upgrading and maintaining of all traffic signs. A list of
signs not meeting the minimum requirement is derived from MUTCD approved Nighttime Visual Inspection surveys.
In the second half of FY 2020, 460 signs were identified for reflectivity replacements.
Street Lights
Improvements
(PO‐05054)*
Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion
$118,051 $374,352 Public Works N/A Recurring
Project Status: This project replaces street light poles, pole foundations, luminaires and wiring as needed to restore
or improve street lighting.
Street Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion
Streets and Sidewalks Projects Status as of June 2020
* ‐ Projects that were subject to funding reductions in the Fiscal Year 2021‐2025 CIP
Streets and Sidewalks Projects – Page 3 of 3
Maintenance
(PE‐86070)*
$5,353,373 $10,413,643 Public Works N/A Recurring
Project Status: This project includes the annual resurfacing, micro‐seal, crack seal and reconstruction of various city
streets. This project funds the street maintenance work that supports Council’s adopted goal of achieving a
citywide average pavement condition index (PCI) score of 85, representing very good or excellent conditions, by
2019. The citywide PCI goal of 85 was met at the end of calendar year 2018, and the emphasis will now shift to
maintaining the 85 score while addressing the remaining streets with PCI scores less than 60. The upcoming OBAG2
project will overlay approximately 4.8 lane miles of roads including Sand Hill Road from London Plane Way to Stock
Farm Road and the FY 2020 Street Resurfacing Project will overlay approximately 4 lane miles of roads. These
projects started in summer 2020. Funding was reduced for FY 2021 as part of the FY 2021 Capital Improvement
Program budget strategy. Street resurfacing projects will have reduced scope reducing the number of streets that
can be resurfaced over the next two years.
Thermoplastic
Lane Marking
and Striping
(PO‐11001)
Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion
$13,006 $231,455 Public Works N/A Recurring
Project Status: This project maintains the thermoplastic markings on roadways. Thermoplastic lane marking and
striping is incorporated into annual Pavement Preventive Maintenance Projects. In FY 2020, the project has
restriped 27,270 linear feet of thermoplastic striping ranging from lane striping, crosswalk striping, and bike lane
striping, and refreshed 381 thermoplastic paving legends.
Traffic and Transportation Projects Status as of June 2020
* ‐ Projects that were subject to funding reductions in the Fiscal Year 2021‐2025 CIP
Traffic and Transportation Projects – Page 1 of 6
One‐Time Projects
Charleston
Arastradero
Corridor Project
(PE‐13011)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$11,701,371 $19,554,490 Public Works Construction Winter 2021
Project Status: This project is part of the 2014 Council Infrastructure Plan. It will reconfigure the Charleston
Arastradero Corridor to provide new landscaped median islands, bulb outs, enhanced bike lanes and new street trees
to complement the new lane configurations that were approved for permanent retention. This project will be
constructed in three phases. Phases 1 and 2 were substantially completed in spring 2020. Phase 3 is expected to go
out to bid in fall 2020 and start construction in early 2021.
Churchill Avenue
Alma Street
Railroad Crossing
Safety
Improvements
(PL‐20000)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$0 $4,814,000 Office of Transportation Design Summer 2021
Project Status: This project will design and provide pedestrian and bicycle safety improvements on the east side of the
Churchill Avenue and Alma Street railroad crossing intersection. Design includes, but is not limited to, traffic signal
modifications, street lighting improvements, roadway resurfacing, sidewalk realignment and/or widening, drainage
improvements, utility relocations, signage and striping, innovative bicycle treatments, traffic calming elements, and
way‐finding improvements.
Churchill Avenue
Enhanced
Bikeway
(PL‐14000)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$247,905 $3,429,457 Office of Transportation Design Summer 2021
Project Status: This project includes the planning, design and construction of a shared‐use path along the north side
of Churchill Avenue between the existing shared‐use path at Castilleja Avenue and the Stanford Perimeter Trail. It
also includes intersection improvements at Churchill Avenue and El Camino Real, to include a new dedicated
westbound right‐turn lane. Design plans for the project are at 65% completion. Staff plans to finalize the design by
fall 2020 and begin construction soon after. An encroachment permit from Caltrans will need to be secured for the
work within the El Camino Real right‐of‐way.
Traffic and Transportation Projects Status as of June 2020
* ‐ Projects that were subject to funding reductions in the Fiscal Year 2021‐2025 CIP
Traffic and Transportation Projects – Page 2 of 6
Highway 101
Pedestrian
Bicycle Overpass
Project
(PE‐11011)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$7,182,628 $22,889,459 Public Works Construction Summer 2021
Project Status: This project, part of the 2014 Council Infrastructure Plan, includes the design and construction of a
new pedestrian bridge across Highway 101 at Adobe Creek. Council approved a contract with Granite Construction on
November 18, 2019. Construction began in January 2020 and is anticipated to be completed by summer 2021. The
project started with utility relocations, vegetation removal, and site preparation work. Currently in June 2020 there
are utility joint trench, concrete piles, and columns construction in progress.
Parking
Management and
System
Implementation
(PL‐16002)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$248 $ 1,287,123 Office of Transportation Design Spring 2022
Project Status: This project includes implementation and installation of equipment to implement the outcomes of the
paid parking study for downtown, including the Comprehensive Parking Permit and Citation System. Professional
Account Management (Duncan) was selected as the City’s service provider for the comprehensive permit and citation
management system. System design started in fall 2019, and the base system is on schedule to launch in select
districts in fall 2020.
El Camino Real
Pedestrian Safety
and Streetscape
Project
(PL‐18000)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$113,422 $6,481,553 Office of Transportation Pre‐Design Summer 2021
Project Status: The El Camino Real Pedestrian Safety and Streetscape Project will install complete streets
improvements focused on pedestrian safety at controlled and uncontrolled crosswalks, enhanced bus operations at
two existing major transit stops, and new urban design amenities between Stanford Avenue and Sheridan Avenue.
The project include: curb extensions, median refuges, median shade trees, pedestrian scale lighting, and potential
bus enhancement.
Quarry Road
Improvements
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$1,282,050 $5,148,378 Office of Transportation Design Fall 2022
Traffic and Transportation Projects Status as of June 2020
* ‐ Projects that were subject to funding reductions in the Fiscal Year 2021‐2025 CIP
Traffic and Transportation Projects – Page 3 of 6
and
Transit Center
Access
(PL‐16000)
Project Status: This project includes the planning, design, and construction of bicycle and pedestrian improvements
along Quarry Road between El Camino Real and Welch Road, including, but not limited to, upgraded bicycle lanes and
crosswalks, innovative intersection treatments for bicyclists, and improved access to transit stops. Planning, design,
and construction of a new bicycle, pedestrian, and transitway between the Palo Alto Transit Center bus depot and
the intersection of Quarry Road and El Camino Real has been completed. Implementation is timed to support
expanded operations of the hospital and the completion of Caltrain electrification in 2022.
Emergency
Vehicle Traffic
Signal
Preemption
System Pilot
(PL‐19000)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$0 $608,701 Palo Alto Fire Department Design Summer 2021
Project Status: This project will purchase and implement an emergency vehicle preemption system pilot project. The
system will integrate with the City’s current traffic signal management system and with the City’s computer‐aided
emergency response dispatch system to provide safer and quicker response times for emergency vehicles. Staff has
procured a cost estimate from one vendor and is finalizing a contract for sole source services. Project began in Spring
2020 and staff is working with our CAD vendor to prepare the system for the connection to the traffic management
system.
Railroad Grade
Separation and
Safety
Improvements
(PL‐17001)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$2,101,075 $12,401,7368 Office of Transportation Design Summer 2024
Project Status: This project is a community‐based process to advance the railroad grade crossing circulation study
and context sensitive solutions study envisioned by the City Council. It will also fund the preparation of a Project
Study Report and environmental analysis that will be required for the City to realize its goals of advancing grade
separations. This capital project provides funds for a contract with AECOM to do engineering support for the rail
grade separation studies. Funding for safety improvements at the railroad crossing at Alma Street and Churchill
Avenue has been moved into a separate project, Churchill Avenue/Alma Street Railroad Crossing Safety Improvement
Project (PL‐20001).
Traffic and Transportation Projects Status as of June 2020
* ‐ Projects that were subject to funding reductions in the Fiscal Year 2021‐2025 CIP
Traffic and Transportation Projects – Page 4 of 6
Downtown
Automated
Parking
Guidance
Systems, Access
Controls &
Revenue
Collection
Equipment
(PL‐15002)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$138,611 $2,857,336 Office of Transportation Design Fall 2021
Project Status: This project includes design and installation of new downtown parking guidance systems, access
controls and revenue collection equipment that will be coordinated with both the Downtown Parking Wayfinding, PL‐
15004 project and the 2016 Downtown Parking Management. Following City Council direction in April 2016, Staff has
advanced the design of the single space detection system with individual indicator lights. Staff contracted with Dixon
Resources for additional management support in design and procurement for the system installation in the
Downtown garages on University Avenue. Staff will be issuing a design build contract in fall 2020.
Recurring Projects
Bicycle and
Pedestrian
Transportation
Plan
Implementation
(PL‐04010)*
Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion
$2,367,931 $2,321,200 Office of Transportation N/A Recurring
Project Status: The Neighborhood Traffic Safety and Bicycle Boulevards Phase 1 Project along Amarillo
Avenue/Moreno Avenue, and Ross Road was completed in November 2018. Conceptual plans for the Neighborhood
Traffic Safety and Bicycle Boulevards Phase 2 Project along Bryant Street, Maybell Avenue, Stanford Avenue, and Park
Boulevard/Wilkie Way were adopted by City Council in 2015. Currently, Phase 2 is on hold at 75% design until a
community engagement process is identified to allow for community review in 2020/2021.
Safe Routes to
School
Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion
$89,373 $222,300 Office of Transportation N/A Recurring
Traffic and Transportation Projects Status as of June 2020
* ‐ Projects that were subject to funding reductions in the Fiscal Year 2021‐2025 CIP
Traffic and Transportation Projects – Page 5 of 6
(PL‐00026) Project Status: This project enables the City’s Safe Routes to School program, including school commute planning,
encouragement activities, and capital improvements along local and collector streets that may be impacted by school
commute activities. The capital improvements include traffic calming devices, enhanced crosswalks, and improved
signage along suggested safe routes to school. In FY 2020, traffic calming projects and traffic studies were pursued for
locations in need of traffic calming and other safety countermeasures. In FY 2020 and 2021, the project will
implement enhanced signage, striping and buffers on East Meadow Drive from Alma to Fabian Way, on Fabian Way
from East Meadow Drive to East Charleston Road, and the widening and repaving of the Waverley Bike Path between
East Meadow Drive and Charleston Road.
Parking District
Implementation
(PL‐15003)*
Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion
$32,760 $272,100 Office of Transportation N/A Recurring
Project Status: This project implemented the signage needs of the residential preferential parking program. Phase 1 of
the Downtown Residential Preferential Parking Program was implemented in October 2015, Phase 2 was implemented
in April 2016, and the program was made permanent in April 2017. The Evergreen Park‐Mayfield RPP program was
made permanent in April 2018. The Southgate RPP program was made permanent in October 2019. The Old Palo Alto
pilot was approved by Council and began in November 2019.
Traffic Signal and
Intelligent
Transportation
Systems
(PL‐05030)*
Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion
$368,200 $2,461,200 Office of Transportation N/A Recurring
Project Status: This project will include design and construction of traffic signals, traffic signal communications
networks, detection and data projects for transportation use, and maintenance of the City’s traffic signal Central
management system. The project includes the replacement of traffic signal controllers/cabinets, video detection
systems, and other related field equipment. The new controllers enable additional traffic signal timing strategies and
improve the reliability of the City's traffic signals.
Traffic and Transportation Projects Status as of June 2020
* ‐ Projects that were subject to funding reductions in the Fiscal Year 2021‐2025 CIP
Traffic and Transportation Projects – Page 6 of 6
Transportation
and Parking
Improvements
(PL‐12000)*
Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion
$290,303 $337,000 Office of Transportation N/A Recurring
Project Status: This project implements miscellaneous neighborhood traffic calming improvements including
neighborhood traffic studies and parking improvements. This project also funds the development of grant proposals
used to procure funding for future projects. Projects which are currently in progress include the Middlefield North
Traffic Safety Project, Crescent Park neighborhood safety improvement pilot, and Charleston/San Antonio Traffic Signal
Safety and Operations Improvement Project.
Airport Projects Status as of June 2020
* ‐ Projects that were subject to funding reductions in the Fiscal Year 2021‐2025 CIP
Airport Projects – Page 1 of 1
One‐Time Projects
Airport Apron
Reconstruction
(AP‐16000)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$13,499,947 $52,701,456 Public Works Construction Summer 2022
Project Status: This project includes the design and reconstruction of the Palo Alto Airport apron and is being
implemented in multiple phases. The pavement surfaces at the airport are failing and uneven. The need to
reconstruct the aircraft parking apron is critical to airport safety. Construction Phase I was completed in
November 2017. Construction Phase II was completed in winter 2020. Construction on Phase III is scheduled to
begin in FY 2021.
Airport Layout
Plan
(AP‐21000)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$0 $583,500 Public Works Design Spring 2022
Project Status: This project provides updates to the Airport Layout Plan (ALP), including a narrative report and
environmental study.
Airport
Facilities
Electrical
Improvements
(AP‐20000)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$0 $206,000 Public Works Design Fall 2020
Project Status: This project upgrades the outdated electrical panels for the Palo Alto Airport office rental spaces.
The project is designed and building permits are approved. The project is scheduled to go out to bid in August
2020 and construction will start in fall 2020.
Recurring Projects
2019‐2023 – Airport Capital Improvements Program Projects: There are no recurring projects scheduled at this time.
Electric Fund Projects Status as of June 2020
* ‐ Projects that were subject to funding reductions in the Fiscal Year 2021‐2025 CIP
Electric Fund Projects – Page 1 of 11
One‐Time Projects
230 kV Electric
Intertie
(EL‐06001)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$578,055 $440,040 Utilities Pre‐Design Summer 2022
Project Status: This project will perform a technical feasibility study to determine the general project
requirements to establish a 230 kV electric intertie line and construct a 230/60 kV substation to connect the
City's electric system directly to the 230kV transmission line. The City has presented its findings to Stanford
University and SLAC National Accelerator Laboratory (under the oversight of the Department of Energy), the two
other parties involved with facilitating this work. Stanford decided they do not want to participate in the project
so the 230 kV option is no longer viable. Staff will pursue other options to procure an alternative transmission
source to serve Palo Alto. This project will be renamed in the future.
Capacitor Bank
Installation
(EL‐16002)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$180,434 $186,298 Utilities Design Fall 2021
Project Status: This project installs capacitor banks at electric substations and on distribution lines to ensure
Northern California Power Association Power Factor requirements are met. Staff has performed an analysis
where capacitors are needed to provide VAR support to the system. Capacitor banks will be installed at Hanover
Avenue, Hansen Way, Quarry Road and Park Boulevard Substations. Progress on the project was delayed due to
restrictions posed by COVID‐19 and the installations are now expected to be completed by fall 2021.
Coleridge
Cowper
Tennyson
4/12kV
Conversion
(EL‐14000)*
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$29,827 $980,000 Utilities Design Summer 2022
Project Status: This project converts the primary electric distribution system in the Coleridge/Cowper/Tennyson
area from 4 kV to 12 kV. This project is a precursor to work being planned for Colorado/Hopkins Substations.
Design is at 90% completion and is delayed due to COVID‐19 restrictions. Construction of this project is deferred
to maintain zero rate increases to ease economic recovery because of COVID‐19.
Colorado Power
Station
Equipment
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$922,316 $2,762,500 Utilities Pre‐Design Fall 2021
Project Status: Staff is evaluating the need to replace the COP‐3 115 kV/60 kV transformer bank at Colorado
Electric Fund Projects Status as of June 2020
* ‐ Projects that were subject to funding reductions in the Fiscal Year 2021‐2025 CIP
Electric Fund Projects – Page 2 of 11
Upgrades
(EL‐19001)
Substation. Future project completion dates will be based on the outcome of this evaluation.
Colorado
Substation Site
Improvements
(EL‐19002)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$16,360 $500,000 Utilities Pre‐Design Fall 2022
Project Status: This project will make modifications to the substation driveways and fence to provide adequate
ingress and egress for utility vehicles used for maintenance and repair. Staff is preparing an overall masterplan
for Colorado Substation to include all proposed improvements. Preliminary designs for lighting, driveway, and
fence have been prepared but need to be incorporated together, and with other proposed improvements, to
ensure a cohesive design and plan for construction.
Colorado Hopkins
System
Improvement
(EL‐15000)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$0 $3,518,000 Utilities Pre‐Design Summer 2027
Project Status: This project will replace deteriorating equipment which will increase system capacity and
improve service reliability for the areas served by the Hopkins and Colorado substations and adjacent
substations. After performing the preliminary engineering analysis, it has been decided to rebuild Hopkins
substation to a 12kV substation. Design on this project will begin summer 2022. Because of the deferral of
related 4/12 kV conversion work the completion date of this project will need to be pushed out
East Meadow
Circles 4/12kV
Conversion
(EL‐17001)*
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$38,704 $1,014,993 Utilities Pre‐Design Spring 2022
Project Status: The project converts the primary electric distribution system in the East Charleston/Alma
Street/East Meadow Drive/Middlefield Road area from 4 kV to 12 kV and is challenging because of the
configuration of the streets and rear easement facilities. Engineering is continuing to work on a design that
should be completed September 2020. Construction of this project is deferred to maintain zero rate increases
to ease economic recovery because of COVID‐19.
Facility
Relocation for
Caltrain
Modernization
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$103,587 $3,061,999 Utilities Design Fall 2020
Project Status: The Utilities Department received approval from Caltrain to continue removal of the overhead
lines in October 2018. The installation of the Overhead Catenary System above the rails to power the trains will
Electric Fund Projects Status as of June 2020
* ‐ Projects that were subject to funding reductions in the Fiscal Year 2021‐2025 CIP
Electric Fund Projects – Page 3 of 11
(EL‐17007) cause conflicts with the City's overhead electric and communication lines, as well as those owned by others,
including AT&T and Comcast, which cross the railroad tracks. In June 2020, Council approved the contract for
construction of this project, in conjunction with EL‐19004. Wood Pole Replacement, and construction is
expected to start in July 2020.
Hopkins
Substation
4/12kV
Conversion
(EL‐20000)*
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$0 $5,693,000 Utilities Pre‐Design Spring 2026
Project Status: This project converts the distribution system connected to the Hopkins Sub‐station from 4kV to
12kV. Engineering design is to begin on this project in fall 2020 but the start of construction will be deferred to
maintain zero rate increases to ease economic recovery because of COVID‐19.
HCB Pilot Wire
Relay
Replacement
(EL‐17005)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$305,123 $819,647 Utilities Construction Summer 2022
Project Status: This project replaces the existing HCB pilot wire relays with a new microprocessor line
differential protective relay to protect the city’s 60kV sub‐transmission line sections and equipment from
damage due to faults (i.e. short circuits) on the 60kV line sections. This project is being done is phases, with
design and construction happening concurrently on the different phases. Construction of these improvements
rely on work completed by other projects to install fiber optic connections. Staff is working on the design for
the replacement of relays at Park Substation and Switching Station and between line sections COP‐PB, COP‐AC
and COP‐HO.
Rebuild
Underground
District 15
(EL‐11003)*
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$43,348 $506,107 Utilities Design Spring 2022
Project Status: This project rebuilds and replaces the underground electric system in Underground District 15,
the area bounded by Los Palos Avenue, Glenbrook Drive, Pomona Avenue, and Arastradero Road. This project is
in the preliminary stages of engineering design and work will be coordinated with EL‐16000 which is currently
rebuilding the electric system along Arastradero Road. Work on this project was delayed due to public input
regarding the design of the project. Changes to the Rules and Regulations will require property owners to pay
for the differential cost should they want submersible equipment instead of pad mount. Design of the project is
delayed as staff prepares cost information to present to affected property owners showing how much they will
Electric Fund Projects Status as of June 2020
* ‐ Projects that were subject to funding reductions in the Fiscal Year 2021‐2025 CIP
Electric Fund Projects – Page 4 of 11
have to pay. Construction of this project is also deferred to maintain zero rate increases to ease economic
recovery because of COVID‐19.
Rebuild
Underground
District 16
(EL‐13003)*
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$10,858 $398,252 Utilities Design Spring 2022
Project Status: This project rebuilds and replaces the underground electric system in Underground District 16,
the area along Louis Road between Greer Street and Loma Verde Avenue. This project design and cost estimate
is nearly complete and this project will be bundled with other similar type jobs for bidding to obtain more
favorable pricing. Construction of this project is deferred to maintain zero rate increases to ease economic
recovery because of COVID‐19.
Rebuild
Underground
District 19
(EL‐11008)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$149,023 $149,023 Utilities Completed Spring 2020
Project Status: This project rebuilt and replaced the underground electric system in Underground District 19,
the area bounded by Forest Avenue, Waverley Street, Addison Avenue, and Alma Street. This project is
completed.
Rebuild
Underground
District 20
(EL‐14002)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$9,969 $1,409,965 Utilities Design Summer 2025
Project Status: This project rebuilds and replaces the underground electric system in Underground District 20,
the area bounded by Channing Avenue; Center Street; Hamilton Avenue; and Lincoln Avenue. This project is in
the preliminary stages of assessment for engineering design. Design is 65% completed and has been hampered
by COVID‐19 restrictions. Construction of this project is deferred to maintain zero rate increases to ease
economic recovery because of COVID‐19.
Rebuild
Underground
District 23
(EL‐17000)*
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$0 $1,264,000 Utilities Pre‐design Summer 2025
Project Status: This project rebuilds and replaces the underground electric system in Underground District 23,
the area bounded by Chaucer Street; Hamilton Avenue; and Southwood Drive. This project is in the preliminary
stages of assessment for engineering design. Design on this project will begin spring 2021. Construction of this
Electric Fund Projects Status as of June 2020
* ‐ Projects that were subject to funding reductions in the Fiscal Year 2021‐2025 CIP
Electric Fund Projects – Page 5 of 11
project is deferred to maintain zero rate increases to ease economic recovery because of COVID‐19.
Rebuild
Underground
District 24
(EL‐10006)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$1,885,129 $2,529,195 Utilities Construction Spring 2021
Project Status: This project rebuilds and replaces the underground electric system in Underground District 24,
the area bounded by Lytton Avenue; Bryant Street; Forest Avenue; and Alma Street. Construction by city staff is
approximately 90% completed but is currently slowed due to a shortage of Operations staff and COVID‐19
restrictions. Work is being scheduled with Operations and to accommodate impacted customers as best as
possible.
Rebuild
Underground
District 25
(EL‐19000)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$9,266 $242,600 Utilities Design Summer 2022
Project Status: This project rebuilds and replaces the underground electric system in Underground District 25.
District 25 includes Orme Street between Los Robles Avenue and Juana Briones School. Engineering design is
currently in progress and is awaiting the procurement of an easement on private property. Construction of this
project is deferred to maintain zero rate increases in an effort to ease economic recovery because of COVID‐19.
Rebuild
Underground
District 26
(EL‐16000)*
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$4,800 $945,827 Utilities Design Spring 2022
Project Status: This project rebuilds and replaces the underground electric system in Underground District 26
the area along Arastradero Road between El Camino Real and Hillview Avenue. This project is in design and will
be designed in conjunction with, and eventually bid with, EL‐11003 which is rebuilding the electric system on Los
Palos Avenue, Glenbrook Drive, and Pomona Avenue. This project will be bundled with other similar type jobs
for better bid results. Construction of this project is deferred to maintain zero rate increases to ease economic
recovery because of COVID‐19.
Rebuild
Underground
District 30
(EL‐19003)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$0 $1,556,000 Utilities Pre‐Design Summer 2025
Project Status: This project will rebuild and replace the underground electric system in the area bounded by San
Francisquito Creek, Edgewood Drive, Island Drive, Hamilton Avenue, Center Drive, Dana Avenue, Alester Avenue
Electric Fund Projects Status as of June 2020
* ‐ Projects that were subject to funding reductions in the Fiscal Year 2021‐2025 CIP
Electric Fund Projects – Page 6 of 11
and Jackson Drive. Design on this project is delayed due to COVID‐19 restrictions and will begin July 2022.
Reconfigure
Quarry Feeders
(EL‐14005)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$469,506 $1,036,754 Utilities Construction Winter 2021
Project Status: This project reconfigures how distribution circuits are connected to each substation transformer
at Quarry Substation. While phases of this project have been completed in construction, others phases still
need to be designed and constructed. Design of the final phase of this project is being estimated and the
drawings and job package prepared. Construction will be delayed due to the impact of COVID‐19 restrictions.
Smart Grid
Technology
Installation
(EL‐11014)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$736,960 $13,366,104 Utilities Pre‐Design Fall 2024
Project Status: Council approved proceeding with Advanced Metering Infrastructure (AMI) and associated smart
grid investments in December 2018. AMI is a foundational technology that is becoming a standard in the
utilities industry and will improve customer experience while enabling CPAU to operate more effectively. An
AMI‐based smart grid system will empower customers to more efficiently utilize utility supplies, facilitate
customer adoption of distributed energy resources (DER) such as solar photovoltaics (PV) and electric vehicles
(EV), and enable the timely detection of water leaks. AMI will also enable CPAU to optimize operations and
improve reliability by reducing restoration time for outages. Staff has gone out to bid for procurement of an
AMI system and the bids are being evaluated.
Substation 60kV
Breaker
Replacement
(EL‐17002)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$248,238 $3,413,169 Utilities Construction Summer 2025
Project Status: This project replaces high voltage circuit breakers that interconnect the nine electric substations
and two power switching stations that are reaching the end of their useful life and/or are now underrated for
the use. This project is being done is phases, with design and construction happening concurrently on the
different phases. Staff completed the first phase of procurement and is negotiating a contract with a contractor
to complete the design and replacement of the remaining breakers.
Substation
Physical Security
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$212,719 $2,139,773 Utilities Construction Winter 2025
Electric Fund Projects Status as of June 2020
* ‐ Projects that were subject to funding reductions in the Fiscal Year 2021‐2025 CIP
Electric Fund Projects – Page 7 of 11
(EL‐16003)* Project Status: This project installs facilities providing physical protection of electric substations from vandalism
and intrusion. A professional services contract was awarded to Burns & McDonnell and the study is complete
and staff implements recommendations from the study each Fiscal Year. Bids are being reviewed for
improvements at Hanover Avenue and Hansen Way substations.
Utility Site
Security
Improvements
(EL‐04012)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$1,539,560 $1,644,681 Utilities Completed Spring 2020
Project Status: This project adds electronic security systems at utility sites to protect equipment at electric
substations, water pumping plants, reservoirs, and gas stations from intrusion and vandalism. To date, cameras
and detection systems have been installed at nine electric substations, three water stations, and one natural gas
station to monitor facilities. Staff is working on standardizing equipment and video management software
across departments. This project is completed. Any additional video equipment will be incorporated as part of
the work under EL‐16003 – Substation Physical Security.
VA Hospital –
Customer Load
Requirements
(EL‐17003)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$84,984 $84,984 Utilities Completed Spring 2020
Project Status: This project met the growing electric needs of the VA Hospital. Staff has had numerous
discussions with VA Hospital on electric load growth at the hospital and anticipated needs from the utility. Much
of the cost is reimbursed to the City by the VA Hospital. Staff has prepared preliminary designs for interim
solutions and is awaiting additional information from VA to develop long range plans to meet their future needs.
Because a majority of the construction work will be completed by VA Hospital, this WBS was closed and any
remaining work will be charged against EL‐89028 – Electric Customer Connections.
Underground
District 42 –
Embarcadero
Road, Emerson,
Middlefield
EL‐08001
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$0 $2,050,000 Utilities Pre‐Design Spring 2026
Project Status: This project will replace the existing overhead electrical distribution system with an under‐
ground system along Embarcadero between Emerson and Middlefield. This project involves creating an
Underground Utilities District and performing the work on a general benefit basis under the provisions of Utility
Rule 17 which requires the Utility to bear the cost of the distribution system and the property owners to bear
the cost of undergrounding their services. This project is deferred due to higher priority work.
Electric Fund Projects Status as of June 2020
* ‐ Projects that were subject to funding reductions in the Fiscal Year 2021‐2025 CIP
Electric Fund Projects – Page 8 of 11
Underground
District 46 –
Charleston/El
Camino Real
(EL‐12001)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$2,328,463 $3,499,983 Utilities Construction Fall 2021
Project Status: This project undergrounds the existing overhead utility systems in the area along the 400 block
of West Charleston and El Camino Real. Underground substructures have been installed. A shortage of
Operations staff has caused a review and revision of construction plans. Staff is now working on a bid package
to complete the reconstruction of the 60kV line, installation of steel poles, and removal of the overhead wires,
while internal electric operations staff schedules the installation of a new underground electric system.
Underground
District 47 –
Middlefield,
Homer, Webster,
Addison
(EL‐11010)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$3,190,128 $3,649,356 Utilities Construction Summer 2020
Project Status: This project undergrounds the existing overhead distribution system in the area bounded by
Middlefield Road, Homer Avenue, Webster Street, and Addison Avenue. Installation of substructures and utility
electric system is completed. There is only one customer who has not converted their service and they have
been given a deadline of July 14 to complete their conversion work. Where possible, the overhead electric lines
are being removed and poles cut down to the level of the communication lines.
Recurring Projects
Communications
System
Improvements
(EL‐89031)
Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion
$800,766 $100,000 Utilities N/A Recurring
Project Status: This project installs copper wire cable systems, high frequency coaxial cable, fiber optic cable,
and related equipment to provide communications services for traffic signal coordination, telephone links,
computer data transmission, and the Electric Supervisory Control and Data Acquisition (SCADA) system. This
project is funding a portion of the design phase of an expanded Utilities fiber optic network. The contract for
design of this network was approved by Council in June 2020.
Electric Fund Projects Status as of June 2020
* ‐ Projects that were subject to funding reductions in the Fiscal Year 2021‐2025 CIP
Electric Fund Projects – Page 9 of 11
Electric Customer
Connections
(EL‐89028)
Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion
$2,648,995 $2,400,000 Utilities N/A Recurring
Project Status: This project installs services, transformers, and meters for new customers; upgrading of existing
services; temporary service connections; and overhead and underground extensions for new or existing
customers. Projects are in various stages of design and construction to provide temporary and permanent
power to residential and commercial customers in Palo Alto.
Electric System
Improvements
(EL‐98003)
Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion
$2,414,005 $1,500,000 Utilities N/A Recurring
Project Status: This project consists of various projects that replace deteriorated facilities or install protective
devices that improve the Electric Distribution System. Projects are in various stages of development to replace
transformers, replace poles, replace overhead wires, and install protective devices to improve service reliability.
Electric Utility
Geographic
Information
System
(EL‐02011)
Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion
$68,904 $326,000 Utilities N/A Recurring
Project Status: This project enhances the citywide Geographical Information System (GIS). The primary
emphasis will be to provide a compatible user interface and estimating software, to edit and update data which
will reside in the citywide GIS. This funding is also being used to pay for Utilities Electric Division’s share of cost
for the implementation of new city‐wide GIS system (ESRI) led by IT. Staff is also working directly with IT to
assess GIS needs and the transition of the mapping information to ESRI.
SCADA System
Upgrades
(EL‐02010)
Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion
$63,805 $265,000 Utilities N/A Recurring
Project Status: This project upgrades the Supervisory Control and Data Acquisition (SCADA) system hardware.
Staff completed upgrade of the servers used for monitoring the utility substations and equipment in 2014.
Vendor delays due to COVID‐19 restrictions postponed the server upgrade till 2021.
Substation
Facility
Improvements
Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion
$375,144 $327,800 Utilities N/A Recurring
Project Status: This project makes improvements to facilities at the electric substations in Palo Alto. Staff is
Electric Fund Projects Status as of June 2020
* ‐ Projects that were subject to funding reductions in the Fiscal Year 2021‐2025 CIP
Electric Fund Projects – Page 10 of 11
(EL‐89044) working on the replacement of Remote Terminal Units (RTU) at various substations, upgrading gravel and
grounding, and reconfiguring steel trusses and associated devices.
Substation
Protection
Improvements
(EL‐89038)
Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion
$690,592 $300,000 Utilities N/A Recurring
Project Status: This project makes improvements to equipment used at electric substations to protect the
substation equipment and circuits emanating from the substation from damage due to faults (i.e. short circuits)
on the electric system.
Underground
System Rebuild
(EL‐16001)*
Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion
$22,478 $350,000 Utilities N/A Recurring
Project Status: This project replaces underground electric equipment in areas that were originally installed
underground, that are not part of an Underground District. Staff is working to identify areas where the age of
the existing cables are a high priority for cable replacement. To date, this includes areas in the Stanford
Research Park, Arastradero Road, and along East Bayshore Road. New areas have been identified but no
progress has been made on development of the project as staff are currently working on other projects with
higher priorities.
Wood Pole
Replacement
(EL‐19004)
Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion
$26,395 $1,500,000 Utilities N/A Recurring
Project Status: This project will fund the annual replacement of deteriorated wood power poles. Staff has
identified 84 wood poles for the pole replacement contract. In June 2020, Council approved the contract for
construction of this project, in conjunction with EL‐17007 ‐ Facility Relocation for Caltrain Modernization and
construction is expected to start in July 2020.
Upgrade Electric
Estimating
System
(EL‐13008)
Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion
$23,148 $23,148 Utilities N/A Recurring
Project Status: This project upgrades the existing Electric estimating software used for preparing job estimates
by integrating engineering analysis, adding predefined standards and templates, and by integrating
documentation, materials ordering, and work management functions. Staff completed the underground
Electric Fund Projects Status as of June 2020
* ‐ Projects that were subject to funding reductions in the Fiscal Year 2021‐2025 CIP
Electric Fund Projects – Page 11 of 11
construction standards and the draft of the overhead construction standards for electric installations. The
software used for project estimating was upgraded to the latest version. Staff will work with IT to assess a
possible transition of the estimating software from AME to ESRI.
Fiber Optics Fund Projects Status as of June 2020
* ‐ Projects that were subject to funding reductions in the Fiscal Year 2021‐2025 CIP
Fiber Optics Fund Projects – Page 1 of 1
One‐Time Projects
Fiber Optic
System Rebuild
(FO‐16000)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$167,167 $1,292,156 Utilities Design Spring 2021
Project Status: This project is for the System Capacity Improvement that rebuilds portions of the "dark" fiber optic
network around Palo Alto. The first phase of this project has been constructed. Additional work is being assessed
and will be coordinated with the project to expand the Utilities Fiber Optic Network (EL‐89031).
Recurring Projects
Fiber Optics
Network
System
Improvements
(FO‐10001)
Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion
$1,009,942 $500,000 Utilities N/A Recurring
Project Status: This project improves the reliability within the fiber optic network system. A project to install a
new fiber optic cable from Park Substation to the Stanford Research Park to enhance capabilities and reliability is
identified and waiting for availability of staff to design
Fiber Optics
Customer
Connections
(FO‐10000)
Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion
$133,326 $250,000 Utilities N/A Recurring
Project Status: This project enables the installation of fiber optic infrastructure for new service connections.
Projects are developed as needed to meet customer requests for leasing of fibers on the Dark Fiber system. Staff
have processed and completed nine customer connection projects since the last update, in addition to several
smaller projects involving existing fiber optic cable connections that did not require additional engineering design
and were handled directly by Operations staff. The number of projects was likely impacted by COVID‐19 work
restrictions.
Gas Fund Projects Status as of June 2020
* ‐ Projects that were subject to funding reductions in the Fiscal Year 2021‐2025 CIP
Gas Fund Projects – Page 1 of 3
One‐Time Projects
Gas Main
Replacement
Project 23
(GS‐13001)*
Prior Years Actuals Total Project Budget Implementing
Department
Project Phase Project
Completion
$1,935,021 $11,124,279 Utilities Design Winter 2021
Project Status: This project enables the design and construction to replace approximately 21,700 linear feet (which
represents 1.9% of the City's Gas distribution main system) of distribution main and 320 gas service laterals
constructed mainly of PVC material on various streets within the Midtown, Evergreen Park, Ventura, College
Terrace, Charleston Terrace, and Research Park neighborhoods. The design is expected to be completed in
summer 2020 with construction beginning in late fall 2020.
Gas
ABS/Tenite
Replacement
Project
(GS‐18000)
Prior Years Actuals Total Project Budget Implementing
Department
Project Phase Project
Completion
$0 $2,615,100 Utilities Construction Summer 2020
Project Status: This project replaces approximately 130 gas services laterals constructed of Acrylonitrile‐butadiene‐
styrene (ABS) or Tenite material on various streets. Council approved funding in June 2019. Construction began in
fall 2019 and will be completed in summer 2020. After this project, there will be approximately sixteen known ABS
services remaining in the gas system. Ten services will be replaced as part of GMR 23 in FY 2021, one service will
be replaced when RWQCP retires the plant burner, and five services will be scheduled for replacement once the
five‐year moratorium ends on those streets.
Recurring Projects
Gas System,
Customer
Connections
(GS‐80017)
Prior Year Actuals Current Year Budget Implementing
Department
Project Phase Project Completion
$1,039,110 $1,342,415 Utilities N/A Recurring
Project Status: This project enables the Gas Distribution System to be extended in order to provide gas service
to new customers and augment service to customers with increased natural gas demands. Improvements
include new mains, services, valves, regulators, meters, and accessories. This project upgrades infrastructure to
Gas Fund Projects Status as of June 2020
* ‐ Projects that were subject to funding reductions in the Fiscal Year 2021‐2025 CIP
Gas Fund Projects – Page 2 of 3
provide gas service connections to new customers, meet changes in existing customer service demands, and
respond to changes in gas service requirements due to new development or redevelopment. This project is
funded partially from reimbursements by customers. City crews completed sixty‐five new gas services between
January 2020 and June 2020.
Gas Distribution
System
Improvements
(GS‐11002)
Prior Year Actuals Current Year Budget Implementing
Department
Project Phase Project Completion
$9,600 $500,000 Utilities N/A Recurring
Project Status: This project enables Gas Distribution System improvements. Typical activities include: increasing
distribution system capacity for load growth, replacing deteriorated capital facilities, reconfiguring/adding to the
system to improve service reliability, conducting research related to performance of the gas distribution system
or its various components, and making general improvements to the system. The City must continuously
evaluate service reliability needs and make improvements to the system to maintain top level service to City
customers and to minimize potential economic losses due to service interruptions. In the second half of FY 2020,
approximately one hundred feet of natural gas mains identified in non‐standard locations were either upgraded
or replaced.
Gas Equipment
and Tools
(GS‐13002)
Prior Year Actuals Current Year Budget Implementing
Department
Project Phase Project Completion
$117,005 $100,000 Utilities N/A Recurring
Project Status: This project purchases polyethylene (PE) fusion equipment and tools, directional boring/locating
equipment and tools, and general shop equipment and tools. The equipment needs to be upgraded on an
annual basis to safely operate and maintain a natural gas distribution system and to ensure operators’ safety and
productivity. Some recent purchases include large diameter tapping, stopping machines, and a pressure
recording chart.
Gas Meters and
Regulators
(GS‐80019)*
Prior Year Actuals Current Year Budget Implementing
Department
Project Phase Project Completion
$45,551 $250,000 Utilities N/A Recurring
Project Status: This project provides replacement of the existing gas meters and regulators annually. The
Gas Fund Projects Status as of June 2020
* ‐ Projects that were subject to funding reductions in the Fiscal Year 2021‐2025 CIP
Gas Fund Projects – Page 3 of 3
coordination of gas meter and regulator replacements with gas meters identified to be replaced under the AMI
contract, which is generally gas meters that are 25 years or older. The gas meter replacement program ensures
the accuracy of gas consumption measurement, reduces possible revenue loss due to under‐registered gas, and
provides customers with accurate monthly bills.
Storm Drain Projects Status as of June 2020
* ‐ Projects that were subject to funding reductions in the Fiscal Year 2021‐2025 CIP
Storm Drain Projects – Page 1 of 2
One‐Time Projects
Corporation Way
System Upgrades
and Pump Station
(SD‐21000)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$0 $3,166,000 Public Works Design Spring 2022
Project Status: This project incorporates a design of a new small pump station with 25 cubic feet per second
capacity and upgrades 700 linear feet of storm drain pipe to 30 inch High Density Polyethylene. The existing
system does not have the force needed to discharge storm flows into the Adobe Creek. Adding a pump station
in advance of the outfall and upsizing the storm drain pipe will eliminate the routine flooding along East
Bayshore Road and convey runoff from a 10‐year storm event. The design consultant contract was awarded in
June 2020. Final design is anticipated to be complete in spring 2021. Construction is anticipated to be
completed in spring 2022.
Loma Verde
Avenue Trunk
Line
Improvements
(SD‐19000)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$45,028 $2,976,813 Public Works Construction Fall 2020
Project Status: This project replaces 1,750 linear feet of storm drain pipe with 48‐inch High Density Polyethylene
and replaces associated catch basins, laterals and manholes. This project was dependent on completion of the
Matadero Creek Storm Water Pump Station Project, located downstream from Loma Verde Avenue storm drain
improvements. The construction contract was awarded in June 2020 with work planned to begin in summer
2020 and to be completed by fall 2020.
West Bayshore
Road Pump
Station
(SD‐20000)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$2,624 $1,339,400 Public Works Design Spring 2023
Project Status: This project incorporates design and construction of a new small pump station with 15 cubic feet
per second capacity. The Storm Drain Master Plan identifies this as a high priority project. Installing a new
pump station will allow storm flows to be pumped into the Adobe / Barron Creek confluence while adding a
pump station in advance of the outfall would eliminate the routine flooding along West Bayshore Road and
allow the system to convey runoff from a 10‐year storm event. The design consultant contract was awarded in
June 2020. Final design is anticipated to be complete in spring 2021. Construction is planned to be completed
by spring 2023.
West Bayshore Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
Storm Drain Projects Status as of June 2020
* ‐ Projects that were subject to funding reductions in the Fiscal Year 2021‐2025 CIP
Storm Drain Projects – Page 2 of 2
Road and Fabian
Way Capacity
Upgrades
(SD‐23000)
$0 $2,109,000 Public Works Design Spring 2024
Project Status: This project incorporates design and construction of a new small pump station with 15 cubic feet
per second capacity. The Storm Drain Master Plan identifies this as a high priority project. Installing a new
pump station will allow storm flows to be pumped into the Adobe / Barron Creek confluence while adding a
pump station in advance of the outfall would eliminate the routine flooding along West Bayshore Road and
allow the system to convey runoff from a 10‐year storm event. Proposals were received in November 2019 for a
design contract. The consultant contract was awarded in June 2020. The design is anticipated to be complete in
spring 2021. Construction is planned to be completed by spring 2024.
Recurring Projects
Storm Drainage
System
Replacement and
Rehabilitation
(SD‐06101)
Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion
$461,993 $2,159,481 Public Works N/A Recurring
Project Status: This project provides for annual replacement and rehabilitation to maintain the integrity of the
storm drain system, including deteriorated storm drain pipes, manholes, and storm drain inlets. The current
project to rehabilitate an existing box culvert over Oregon Expressway is underway. The design was finalized in
December 2019. The project will go out to bid and staff anticipates awarding a construction contract in fall 2020
with construction completing in late 2020.
I I I I
Wastewater Collection Fund Projects Status as of June 2020
* ‐ Projects that were subject to funding reductions in the Fiscal Year 2021‐2025 CIP
Wastewater Collection Fund Projects – Page 1 of 3
One‐Time Projects
Wastewater
Collection
System
Rehabilitation
Augmentation
Project 28
(WC‐15001)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$478,178 $5,665,897 Utilities Completed Spring 2020
Project Status: This project enabled the design and construction of a high priority wastewater main and lateral
replacement work to reduce inflow of rainfall and ground water into the collection system. The project replaced or
rehabbed a total of 7,655 linear feet of wastewater mains located in the Leland Manor/Garland, Midtown West,
and Lower Page Mill/Los Altos Hills areas of the City. Project Notice of Completion was effective June 15, 2020.
Wastewater
Collection
System
Rehabilitation
Augmentation
Project 30
(WC‐17001)*
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$0 $6,921,684 Utilities Design TBD
Project Status: This project funds the design and construction of high priority main and lateral replacement work,
which reduces inflow of rainfall and groundwater into the collection system. The project replaces approximately
21,000 linear feet (which represents 1.8% of the City's Wastewater Collection System) for various streets in the
City, including Ventura, Charleston Meadows, and Research Park neighborhoods. The project will be comprised of
pipes identified in video inspection work or through maintenance records as deficient and in need of replacement.
Priority will be given to areas identified by Public Works as targeted work zones ensuring coordination between
departments.
Wastewater
Collection
System
Rehabilitation
Augmentation
Project 29
(WC‐16001)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$113,466 $4,434,839 Utilities Construction Summer 2020
Project Status: This project currently in construction replaces of 8,972 linear feet of wastewater mains. The
sanitary sewer mains, laterals, and manholes to be rehabilitated or replaced in this project are located in the
Charleston Meadows neighborhood. Construction started in February 2020 and was suspended due to COVID‐19
County’s Shelter‐in‐Place Order. The completion date is delayed till September 2020.
Recurring Projects
Sewer System, Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion
Wastewater Collection Fund Projects Status as of June 2020
* ‐ Projects that were subject to funding reductions in the Fiscal Year 2021‐2025 CIP
Wastewater Collection Fund Projects – Page 2 of 3
Customer
Connections
(WC‐80020)
$301,755 $445,000 Utilities N/A Recurring
Project Status: This project installs sewer lateral connections and additions or extensions of existing mains to
serve new customers and to respond to changes in sewer requirements due to redevelopment. Old existing
non‐plastic sewer laterals with condition deficiencies per Utilities Operations’ criteria are required to be
replaced. Other revenue includes customer connection and capacity fees for connecting to the wastewater
collection system.
Sewer
Lateral/Manhole
Rehabilitation
and Replacement
(WC‐99013)
Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion
$802,497 $825,000 Utilities N/A Recurring
Project Status: This project replaces defective sewer laterals, cleanouts, manholes, install backwater devices,
and purchase equipment to support these activities to maintain the Wastewater Collection System. Information
collected during routine annual maintenance activities is used to prioritize work. The work performed will help
reduce both the backflow of sewage onto private property and the City's treatment expenses. This project also
cleans and video‐inspects sewer collection mains and laterals as necessary.
Wastewater
General
Equipment and
Tools
(WC‐13002)
Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion
$0 $50,000 Utilities N/A Recurring
Project Status: This project includes the acquisition of new fusion equipment and other associated tools. The
equipment is used to fuse together pipe joints in the City's wastewater collection system. As the equipment
ages, the quality of the fusion joints begins to decline, and the operators must spend more time scraping,
aligning, and fusing construction joints to maintain a high quality of standards for the installation of City's
wastewater collection mains, along with the associated service standards and worker safety and productivity
measures, equipment and tools require continuous upgrades. In the second half of FY 2020, a transporter was
purchased for the wastewater CCTV van camera.
Wastewater
System
Improvements
(WC‐15002)
Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion
$ 0 $260,000 Utilities N/A Recurring
Project Status: This project implements improvements to the Wastewater Collection System. Typical activities
include: increasing system capacity for growth, flow monitoring, hydraulic modeling and system analysis, load
simulations, asset management analysis and assessment, system inflow/infiltration analysis, and sanitary sewer
Wastewater Collection Fund Projects Status as of June 2020
* ‐ Projects that were subject to funding reductions in the Fiscal Year 2021‐2025 CIP
Wastewater Collection Fund Projects – Page 3 of 3
overflow monitoring and reduction. Mainline sewer backups and overflows into homes and businesses are
costly and create a health risk. Reducing the losses associated with these backup claims requires a continuous
evaluation of system needs and making improvements to maintain a high level of service. Replacement of the
City’s legacy wastewater maintenance and asset management software (ICOM) will begin in summer 2020.
Sedaru’s wastewater collection system soft‐water and implementation project was approved by Council in June
2020. The project kick‐off meeting is scheduled for early July 2020.
Wastewater Treatment Fund Projects Status as of June 2020
* ‐ Projects that were subject to funding reductions in the Fiscal Year 2021‐2025 CIP
Wastewater Treatment Fund Projects – Page 1 of 2
One‐Time Projects
Advanced
Water
Purification
Facility
(WQ‐19003)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$0 $23,246,073 Public Works Pre‐Design Winter 2024
Project Status: This project enables the design and construction of an Advanced Water Purification Facility to further
improve the quality of the tertiary‐treated recycled water by microfiltration or ultrafiltration followed by reverse
osmosis to reduce the level of total dissolved solids. The water reuse partnership agreement with Valley Water and
Mountain View provides $16 million in funding from Valley Water for this project. Design is expected to be
completed in FY 2021 with project completion in FY 2024.
Outfall Line
Construction
(WQ‐19000)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$0 $8,219,000 Public Works Design Winter 2023
Project Status: This project consists of the construction of a new parallel outfall pipe to convey final plant effluent to
San Francisco Bay. Design is 99% complete, awaiting FAA approval. The City is expecting a State low‐interest loan to
be awarded for the construction phase.
Secondary
Treatment
Upgrades
(WQ‐19001)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$483,059 $30,763,109 Public Works Design Fall 2024
Project Status: This project upgrades the Secondary Treatment process at the Regional Water Quality Control Plant.
The existing Secondary Treatment process has two main components; the Fixed Film Reactors (FFR) and the
Activated Sludge (AS) Process. This project includes the reconstruction of the AS process, rehabilitation of the AS
Aeration Basins, and the elimination of the FFRs. The design contract began in October 2018. Staff is pursuing a
State low‐interest loan or bond for the construction phase.
New
Laboratory and
Environmental
Services
Building
(WQ‐14002)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$76,175 $22,767,993 Public Works Design Fall 2024
Project Status: This project replaces the existing Plant lab and environmental services offices. This building will
consolidate staff from the current four separate buildings and will provide a larger and updated lab. In February
2019 a consultant began the design. Staff is pursuing a State low‐interest loan or bond for the construction phase.
Wastewater Treatment Fund Projects Status as of June 2020
* ‐ Projects that were subject to funding reductions in the Fiscal Year 2021‐2025 CIP
Wastewater Treatment Fund Projects – Page 2 of 2
Plant Master
Plan
(WQ‐10001)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$3,024,494 $3,024,494 Public Works Construction Fall 2021
Project Status: This project enables the ongoing program management support for major capital projects. Current
tasks include developing scopes of work, evaluating consultant proposals, coordinating project management
activities, pursuing State low‐interest loans for multiple projects, and updating partner agreements. The consultant
continues to provide support for the tasks associated with this project.
Primary
Sedimentation
Tank
Rehabilitation
(WQ‐14003)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$653,663 $20,389,640 Public Works Design Spring 2023
Project Status: This project enables the design and construction for new protective coatings on each of the four
concrete primary sedimentation tanks and replacement of worn rotating parts and mechanical and electrical
equipment. These tanks were installed in 1972 and the recoating project will extend the concrete life another 30
years. Design is complete and the construction project is in the solicitation process. The City is expecting a State
low‐interest loan be awarded for the construction stage.
Recurring Projects
Plant Repair,
Retrofit and
Equipment
Replacement
(WQ‐19002)
Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion
$327,099 $7,017,719 Public Works N/A Recurring
Project Status: This project enables the assessment, repair, and retrofit of the Plant's concrete and metal
structures; the replacement of necessary Plant equipment and ancillary facilities to maintain treatment reliability
and existing infrastructure; and the replacement of large diameter flow meters built into the wastewater
treatment system on sewers, pipes, and water lines.
Water Fund Projects Status as of June 2020
* ‐ Projects that were subject to funding reductions in the Fiscal Year 2021‐2025 CIP
Water Fund Projects – Page 1 of 5
One‐Time Projects
Mayfield
Reservoir
Subgrade and
Venting Repair
(WS‐19000)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$0 $600,000 Utilities Construction Summer 2020
Project Status: This project is part of the City’s recent Seismic Upgrade and Emergency Water Supply and Storage
Projects. The reservoir was drained in 2012 for approximately two years to allow extensive seismic rehabilitation
work to be performed and construction of a new pump station. Subsequently hairline cracks were sealed in the
reservoir. A geotechnical consultant was hired to evaluate the tank foundation. This study was completed and
there were several options identified. Staff has completed the design of the vent screen replacement and crack
sealing. The Notice of Award was issued in February 2020. The Notice to Proceed with construction was delayed
until the start of July 2020 due to Covid‐19.
Water Main
Replacement
Project 27
(WS‐13001)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$148,886 $ 7,786,998, Utilities Completed Spring 2020
Project Status: This project replaced approximately 9,600 linear feet of structurally deficient, aging, or corroded
water mains and services along the mains on Sand Hill Road, Oak Creek Drive (5%) and Fulton Avenue. The
project is currently complete except for the Oak Creek Drive (95%) portion of the work that should be done after
Stanford’s bank stabilization project is completed.
Water
Regulation
Station
Improvements
(WS‐07000)*
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$ 1,476,112 $ 1,474,455 Utilities Design Fall 2020
Project Status: This project for Water Regulation Station Improvements includes seismic upgrades, piping
improvements and other various upgrades to increase the structural reliability of three of the City’s turnouts with
SFPUC. Work under this project was included in the Seismic Upgrade of four Steel Tanks and three Turnouts’
Project and the project was completed and closed out. Due to multiple existing issues at the California Turnout,
upgrade work at this facility has been removed from the contract. The Water Configuration Study was
terminated and staff will review the needs at a Pre‐Design level. Additionally, new issues with the pressure
reducing valves in the Page Mill and Arastradero regulating stations were found and will be addressed.
Water Recycling
Facilities
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$ 705,477 $ 852,697 Utilities Pre‐Design Fall 2023
Water Fund Projects Status as of June 2020
* ‐ Projects that were subject to funding reductions in the Fiscal Year 2021‐2025 CIP
Water Fund Projects – Page 2 of 5
(WS‐07001)* Project Status: This project allows the City to hire a consultant to prepare a business plan, prepare preliminary
design, and secure funding options for an expansion of the existing recycled water delivery system in the City.
The pipeline will primarily serve the Stanford Research Park and provide an alternative supply source of 435,600
cubic feet per year, roughly 10% of Palo Alto’s total water consumption in 2015. The environmental impact
report was completed in September 2015. The expansion pipeline is one of several water reuse projects being
considered in the Northwest County Recycled Water Strategic Plan. This, or one of the other projects, may be
recommended to Council for design and construction. The earliest that work would commence is in FY 2022.
Water Reservoir
Coating
Improvements
(WS‐08001)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$ 1,624,519 $ 2,141,1782 Utilities Completed Spring 2020
Project Status: This project for Water Reservoir Coating Improvements included the recoating of four steel tanks.
Work under this project was included in the Seismic Upgrade of four Steel Tanks and the three Turnout Projects.
Once construction started, it was found that the Montebello Reservoir was in very poor condition. Due to
escalating costs associated with roof replacement, staff decided to complete construction of the Montebello
Reservoir and re‐evaluate the remaining three tanks for replacement. Coating work at the three remaining steel
tanks (Dahl, Park and Corte Madera Reservoirs) was removed from the construction contract. The City
contracted with an engineering consultant to study the water system as a whole and make recommendations for
upgrades and/or improvements. During the Water Configuration Study, the Corte Madera Reservoir was found
to be in critical condition and was recommended to be replaced. Part of the funding for the new reservoir will
come from this task. The Water Configuration Study contract was terminated due to Consultant’s staffing
inability to complete the project. This CIP is scheduled to be closed and the remaining funds are to be returned
to reserves.
Water Tank
Seismic Upgrade
and
Rehabilitation
(WS‐09000)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$ 3,617,775 $ 11,728,033 Utilities Design Summer 2022
Project Status: This project for Seismic Water System Upgrades includes seismic upgrades at the Montebello,
Mayfield, Corte Madera, Park, Boronda, and Dahl Reservoirs in compliance with the American Society of Civil
Engineers (ASCE 7) seismic codes. Work at the steel tank sites includes the installation of new concrete footings,
anchor chairs and tie‐downs, installation of seismic shut off valves and control valves, flexible joints at the
inlet/outlet piping connections, relocation of various inlet and outlet piping, backup power supplies, and
Water Fund Projects Status as of June 2020
* ‐ Projects that were subject to funding reductions in the Fiscal Year 2021‐2025 CIP
Water Fund Projects – Page 3 of 5
reinforcement and/or replacement of interior tank columns. Seismic upgrade work at the Mayfield Reservoir was
completed in summer 2013 and work on the Boronda Reservoir was completed in summer 2016. All remaining
reservoirs were to be seismically upgraded as part of the Seismic Upgrade of four Steel Tanks and three Turnouts’
Project. However, during construction at the Montebello Reservoir, it was found that the existing roof, support
columns and support beams, and floor coating needed total replacement due to their poor condition. Given that
all four tanks were constructed at the same time, staff assumes that the remaining three tanks are in the same
condition. During the Water Configuration Study the Corte Madera Reservoir was found to be in critical condition
and was recommended to be replaced. Most of the funding for the new reservoir will come from this task.
Design‐Build proposals were received and evaluated and the contract phase is in progress.
Water Main
Replacement
Project 28
(WS‐14001)
Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion
$0 $ 9,085,107 Utilities Design Winter 2021
Project Status: This project will replace approximately 14,985 linear feet (which represents 1.2% of the City's
water distribution system) of mains and services on various streets within the City, including areas in the
Duveneck/St. Francis, Barron Park and Charleston Meadows neighborhoods. The recently approved capital
improvement plan increases the scope of each project and staggers construction projects to every other year.
Design is currently underway.
Recurring Projects
Water Service
Hydrant
Replacement
(WS‐80014)
Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion
$72,158 $400,000 Utilities N/A Recurring
Project Status: This project replaces system control valves, deteriorated galvanized service lines, lead goose‐
necks, and fire hydrant valves and assemblies per the Fire Department’s flow testing; upgrades fire hydrants in
main line replacement project areas; and replaces existing undersized or deteriorated copper water services.
Water System
Customer
Connections
Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion
$ 851,385 $ 750,000 Utilities N/A Recurring
Project Status: This project allows for improvements that include new main extensions, valves, domestic
Water Fund Projects Status as of June 2020
* ‐ Projects that were subject to funding reductions in the Fiscal Year 2021‐2025 CIP
Water Fund Projects – Page 4 of 5
(WS‐80013) services, meters on upgraded services, backflow devices, fire services, and fire hydrants. System extensions are
required to provide service to new customers and to serve existing customers requesting expanded service.
Water
Distribution
System
Improvements
(WS‐11003)
Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion
$148,016 $ 446,620 Utilities N/A Recurring
Project Status: This project enables improvements to water distribution system deliverability and reliability.
Typical activities include: installing restraining joints at critical pipelines and bridge crossings, increasing the size
of inadequate facilities, system leakage surveys, network modeling, and fire flow studies or other system
improvements as required. Continuous evaluation of system needs and making required improvements is
necessary to maintain adequate quantities of quality water, meeting local, state, and federal safe drinking water
standards. During the last six months the Mayfield Reservoir VFD replacement and back‐up controls were
completed. El Camino Pump Station pump programming was completed and tested to add the capability for the
El Camino Reservoir to pump into zone 1 in addition to zone 2. The 18”CCP repair and valve installation on Page
Mill Road was bid as part of the WMR 27 project which is under construction. Staff began the ACP pipe study
and is in the process of collecting pipe samples. The Water CAD modeling software was upgraded from 2000
pipe to 5000 pipe model.
Water General
Equipment/Tools
(WS‐13002)
Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion
$ 0 $ 50,000 Utilities N/A Recurring
Project Status: This project acquires new equipment and tools, the replacement of existing fusion equipment,
and other associated tools. The fusion equipment is used to fuse together pipe joints in the City's water
distribution system. Equipment and tools are required to be upgraded on an annual basis to maintain high
quality standards for the installation of the City's water distribution mains, along with the associated service
standards and worker safety and productivity measures. Staff did not purchase any equipment or tools in FY
2020.
Water Meters
(WS‐80015)*
Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion
$122,265 $ 1,292,700 Utilities N/A Recurring
Project Status: This project enables the purchasing of meters for new customers, upgrading meters for current
customers, installing meter bypasses, and replacing obsolete meters that are no longer repairable. This funding
Water Fund Projects Status as of June 2020
* ‐ Projects that were subject to funding reductions in the Fiscal Year 2021‐2025 CIP
Water Fund Projects – Page 5 of 5
also allows for annual testing and calibration of selected meters to maintain meter accuracy and reliability.
During the AMI implementation process approximately 25% of the meters will be replaced.
Water System
Supply
Improvements
(WS‐11004)
Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion
$61,673 $ 261,620 Utilities N/A Recurring
Project Status: This project evaluates and improves the City’s water distribution system on an as‐needed basis.
Typical activities performed under this project include: piping modifications, equipment replacements
associated with water delivery, Supervisory Control software upgrades, system modifications for water system
quality compliance, conditional assessment of the reliability of transmission mains, and security system
installations. The water system includes the connection facilities between the City’s and the San Francisco
Public Utility Commission’s pipelines, emergency water wells within the City, pumping stations, water reservoirs,
and pipelines. Procured SCADA switches and firewall components for the fiber connections to 27 water sites.
Software to control the system was purchased too. Staff installed the hardware and software. Staff is planning
SCADA controller upgrades for the water facilities in the foothills. This new project will be funded July 1, 2020.
Water, Gas,
Wastewater
Utility GIS Data
(WS‐02014)
Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion
$178,991 $ 736,399 Utilities N/A Recurring
Project Status: This project enables contracts related to Utilities GIS (Geographic Information System) needs.
AME database is heavily utilized by Utilities Engineering staff to update the utility information in GIS. The
updated information is used by various City staff, such as marking/locating underground utilities to comply with
USA (Underground Service Alert) requirements; developing design drawings for pipeline replacement projects;
verifying existing underground utilities during construction activities; creating customized utility map books for
field crews and on‐call personnel to meet their specific needs. Annual surveying contracts to collect GPS points
of existing above‐ground utility features within the CIP project areas. The data is used to correct the GIS
database. Accurate utility data helps the design of new pipe alignment to minimize construction conflicts.
Create synchronization and user interface between the upcoming Citywide ESRI GIS database and Utilities AME
database.
List of Completed Projects
CIP #Project Name Project Description Project Type Fund Source Department Season
Completed
Year
Completed
Total Project
Budget **
PF‐18000 Parking Lot J Elevator
Modernization
This project modernized the existing elevators at parking Lot J. The project
involves upgrading the interior of the elevators, elevator control interface, call
buttons, and meeting current ADA standards. Construction started in April
2019. Project is complete except for the State final inspection on the second
car. State is behind because of COVID, but the inspection should be done by
the end of July 2020.
Construction Buildings and
Facilities Public Works Spring 2020 $ 781,324.00
PE‐15003 Fire Station 3 Replacement
This project replaced the existing Fire Station at Embarcadero Road and Newell
Road with a new structure that meets essential services standards and current
program needs. Construction completed in March 2020.
Construction Buildings and
Facilities Public Works Winter 2020 $ 10,080,258.00
WS‐08001 Water Reservoir Coating
Improvements
This project included the recoating of four steel tanks. Work under this project
was included in the Seismic Upgrade of four Steel Tanks and the three Turnout
Projects. Once construction started, it was found that the Montebello Reservoir
was in very poor condition. Due to escalating costs associated with roof
replacement, staff decided to complete construction of the Montebello
Reservoir and re‐evaluate the remaining three tanks for replacement.
Construction Water Utilities Spring 2020 $ 2,141,172.00
WS‐13001 Water Main Replacement ‐
Project 27
This project replaced approximately 9,600 linear feet of structurally deficient,
aging, or corroded water mains and services along the mains on Sand Hill Road,
Oak Creek Drive (5%) and Fulton Avenue.
Construction Water Utilities Spring 2020 $ 7,786,998.00
WC‐15001
Wastewater Collection
System Rehabilitation
Augmentation Project 28
This project enabled the design and construction of a high priority wastewater
main and lateral replacement work to reduce inflow of rainfall and ground
water into the collection system. The project replaced or rehabbed a total of
7,655 linear feet of wastewater mains located in the Leland Manor/Garland,
Midtown West, and Lower Page Mill/Los Altos Hills areas of the City.
Construction Wastewater
Collection Utilities Spring 2020 $ 5,665,897.00
EL‐17003 VA Hospital ‐ Customer
Load Requirements
This project met the growing electric needs of the VA Hospital. Staff has had
numerous discussions with VA Hospital on electric load growth at the hospital
and anticipated needs from the utility. Much of the cost is reimbursed to the
City by the VA Hospital. Staff has prepared preliminary designs for interim
solutions and is awaiting additional information from VA to develop long range
plans to meet their future needs.
Design Electric Utilities Spring 2020 $ 84,984.00
1
List of Completed Projects
CIP #Project Name Project Description Project Type Fund Source Department Season
Completed
Year
Completed
Total Project
Budget **
EL‐04012 Utility Site Security
Improvements
This project added electronic security systems at utility sites to protect
equipment at electric substations, water pumping plants, reservoirs, and gas
stations from intrusion and vandalism. Cameras and detection systems have
been installed at nine electric substations, three water stations, and one
natural gas station to monitor facilities.
Construction Electric Utilities Spring 2020 $ 1,644,681.00
EL‐11008 Rebuild Underground
District 19
This project rebuilt and replaced the underground electric system in
Underground District 19, the area bounded by Forest Avenue, Waverley Street,
Addison Avenue, and Alma Street.
Construction Electric Utilities Spring 2020 $ 149,023.00
FD‐18000 Self Contained Breathing
Apparatus Replacement
This project replaced Self Contained Breathing Apparatus equipment (SCBA)
used by firefighters when entering hazardous conditions when responding to
fire and hazardous materials incidents. The SCBA provides breathable air for
firefighters when entering environments where the atmosphere is immediately
dangerous to life or health. The expected service life for SCBAs is 15 years.
Purchase Buildings and
Facilities Fire Department Spring 2020 $ 799,999.00
FD‐20000 Cardiac Monitor
Replacement
This project replaced the entire complement of twenty cardiac monitors in the
Department. Along with other tools needed for patient assessment and airway
verification, cardiac monitors assess cardiac activity in patients and provide
defibrillation and pacing.
Purchase Buildings and
Facilities Fire Department Spring 2020 $ 850,000.00
PL‐16001 Downtown Mobility and
Safety Improvements
This project included the construction of curb extensions and the installation of
new pedestrian signal heads and traffic signal modifications in 2019 as part of
the Upgrade Downtown project.
Construction Traffic and
Transportation
Office of
Transportation Fall 2019 $ 1,819,847
FD‐20002 Thermal Imaging Cameras
Replacement
This project replaced the Thermal Imaging Cameras (TICs) on all fire and
response vehicles used to help identify the location of victims; assess the
source of fires, smoke, and heat; to assist in creating a plan of action.
Purchase Buildings and
Facilities Fire Department Fall 2019 $ 99,000
WC‐11000
Wastewater Collection
System Rehabilitation
Augmentation Project 24
This project addressed areas that were identified in Wastewater Capital
Improvement Project 17 (Cleaning and Video Inspection of the Collection
System) as needing rehabilitation. This project was combined with Project 25
and 26(WC‐12001; WC‐13001).
Construction Wastewater
Collection Utilities Fall 2019 $ 3,131,595
WC‐13001
Wastewater Collection
System Rehabilitation
Augmentation Project 26
This project was combined with Project 24 and 25(WC‐11001; WC‐12001). All
new service laterals were installed from the new sewer main to the new sewer
cleanouts located in the City’s right‐of‐way.
Construction Wastewater
Collection Utilities Fall 2019 $ 3,309,998
2
List of Completed Projects
CIP #Project Name Project Description Project Type Fund Source Department Season
Completed
Year
Completed
Total Project
Budget **
CB‐19000 Cubberley Track and Field
Replacement
This project replaced the synthetic turf field, installed an all‐weather track and
a fitness area.Construction Parks and Open
Space Public Works Fall 2019 $ 1,851,708
PE‐14018 Baylands Boardwalk
Improvements
This project replaced the existing boardwalk with similar alignment and
configuration. Construction Buildings and
Facilities Public Works Winter 2019 2,123,681$
PE‐17009 City Hall Floor 4 Remodel This project improved the Administrative Services Department offices on the
fourth floor of City Hall.Construction Buildings and
Facilities Public Works Winter 2019 494,818$
PE‐14015
Lucie Stern Buildings
Mechanical and Electrical
Upgrades
This project replaced and upgraded the mechanical, electrical, and fire/life
safety systems at Lucie Stern Children’s Theater, Lucie Stern Community
Theater, and Lucie Stern Community Center.
Construction Buildings and
Facilities Public Works Spring 2019 6,142,607$
PL‐16000
Quarry Road
Improvements and Transit
Center Access
This project included planning, design and construction of bicycle and
pedestrian improvements along Quarry Road.Construction Traffic and
Transportation
Planning and
Community
Environment
Spring 2019 5,148,378$
EL‐17008 Utility Control Center
Upgrades This project upgraded the Utility Control Center working environment. Construction Electric Utilities Winter 2019 499,997$
GS‐12001 Gas Main Replacement
Project 22
This project replaced approximately 23,700 linear feet of gas mains and
services along University Avenue and other streets in the Downtown North
nieghborhood.
Construction Gas Utilities Spring 2019 11,658,997$
WC‐12001
Wastewater Collection
System Rehabilitation /
Augmentation Project 25
This project was combined with Project 24 and 26 (WC‐11001; WC‐13001)
replacing 45,294 linear feet of sanitary sewer mains in university South,
Professorville and Old palo Alto neigborhoods.
Construction Wastewater
Collection Utilities Spring 2019 3,211,998$
WQ‐14001 Dewatering and Loadout
Facility
This project provides funding for the design and construction of the sludge
dewatering facility and truck loadout to retire existing dewatering and sewage
sludge incinerators.
Construction Wastewater
Treatment Public Works Spring 2019 27,497,551$
WS‐12001 Water Main Replacement
– Project 26
This project replaced approximately 11,000 linear feet of aging water mains
and services which included water main replacement as part of the Upgrade
Downtown Project.
Construction Water Utilities Spring 2019 7,506,161$
PE‐17009 City Hall Floor 5 Remodel This project improved the Planning and Community Environment (PCE)
Department offices on the fifth floor of City Hall. Construction Buildings and
Facilities Public Works Summer 2018 525,000$
AC‐14001
Baylands Nature
Interpretive Center Exhibit
Improvements
This project replaced worn out or non‐functioning exhibits at the Baylands
Nature Interpretive Center.Construction Buildings and
Facilities
Community
Services Summer 2018 56,000$
3
List of Completed Projects
CIP #Project Name Project Description Project Type Fund Source Department Season
Completed
Year
Completed
Total Project
Budget **
PE‐17000 Mitchell Park Adobe Creek
Bridge Replacement This project replaced the existing bridge over Adobe Creek in Mitchell Park. Construction
Parks and Open
Space Public Works Summer 2018 250,000$
PD‐14000 Internal Alarm System
Replacement
This project replaced the citywide system of panic alarms from various
departments and the Council chambers.Construction Buildings and
Facilities Police Summer 2018 78,000$
EL‐14004 Maybell 1&2 4/12kV
Conversion This project converted circuits 1 & 2 at Maybell substation from 4kV to 12kV.Construction Electric Utilities Fall 2018 364,796$
GS‐15001 Security at City Gas
Receiving Stations
This project equiped the City’s four Gas Receiving Stations with video
surveillance systems. Construction Gas Utilities Summer 2018 150,000$
SD‐13003
Matadero Creek Storm
Water Pump Station and
Trunk Line Improvements
This project upgraded the capacity to the Matadero Creek Storm Water Pump
Station, which serves a low‐lying 1200‐acre area of southeastern Palo Alto. Construction Storm Drain Public Works Summer 2018 6,685,317$
AP‐16002 Wildlife Hazard
Management Plan
The Wildlife hazard Management Plan identified the specific actions the airport
will take to mitigate the risk of wildlife strikes on or near the airport.Study Airport Public Works Summer 2018 63,415$
WC‐14001
Wastewater Collection
System Rehabilitation
Augmentation Project 27
This project replaced 16,859 linear feet of sanitary sewer mains of various sizes
on various streets.Construction Wastewater
Collection Utilities Winter 2018 4,022,455$
PG‐15000 Buckeye Creek Hydrology
Study
This project analyzed flooding conditions and recommended flood control
structures and drainage and erosion control solutions for the creek located
within Foothills Park.
Study Parks and Open
Space Public Works Spring 2018 167,741$
PE‐17004
CalTrain Corridor Video
Management System
Installation
This project replaced two existing gateway signs in the right‐of‐way for the
California Avenue business district. Construction Streets and
Sidewalks Public Works Spring 2018 1,550,000$
PF‐16003 Parking Lot Q Elevator
Modernization This project modernized the existing elevator at Parking Lot Q.Construction Buildings and
Facilities Public Works Fall 2017 170,608$
PE‐13003
Parks, Trails, Open Space,
and Recreation Master
Plan
This master plan provided guidance on the recreation and improvement needs
for Palo Alto’s parks, trails, open space and recreational programs. Study Parks and Open
Space
Community
Services Fall 2017 627,057$
4
List of Completed Projects
CIP #Project Name Project Description Project Type Fund Source Department Season
Completed
Year
Completed
Total Project
Budget **
PE‐12003 Rinconada Park Master
Plan
This project developed a plan for short, medium and long range improvements
to the regional park including the consideration of pathways, new restrooms
and playgrounds, new landscaping, and revitalization of underutilized areas
within the park.
Study Parks and Open
Space
Community
Services Fall 2017 541,355$
PE‐13012 Structural Assessment of
City Bridges
The project developed an inventory of all City‐owned bridges and culvert
structures, condition assessment, cost estimate for rehabilitation, and
recommendation for future inspection frequencies, assessment and
improvements.
Study Buildings and
Facilities Public Works Fall 2017 198,529$
WC‐11000
Wastewater Collection
System Rehabilitation /
Augmentation Project 24
Combined with Project 25 and 26 (WC‐12001; WC‐13001), this project replaced
and/or rehabilitated approximately 42,398 linear feet of sanitary sewer mains
of various sizes, 779 sewer laterals, and 121 sewer manholes.
Construction Wastewater
Collection Utilities Fall 2017 3,119,806$
WC‐13001
Wastewater Collection
System Rehabilitation /
Augmentation Project 26
Combined with Project 25 and 26 (WC‐12001; WC‐13001), this project replaced
and/or rehabilitated approximately 42,398 linear feet of sanitary sewer mains
of various sizes, 779 sewer laterals, and 121 sewer manholes.
Construction Wastewater
Collection Utilities Fall 2017 3,361,118$
PG‐13003
Golf Reconfiguration and
Baylands Athletic Center
Improvements
This project completed the rehabilitation of the Palo Alto Municipal Golf
Course, including a new layout for the course, new prefabricated restroom,
new water‐saving turf and irrigation system, and rebranded the course as the
Baylands Golf Links.
Construction Parks and Open
Space Public Works Fall 2017 13,675,177$
GS‐11000 Gas Main Replacement –
Project 21
This project combined with GWR 19B & GMR 20 and replaced ABS gas mains
and services. Construction Gas Utilities Winter 2017 2,364,937$
WS‐11000 Water Main Replacement
– Project 25
This project provided installation of approximately 11,869 linear feet of new
High Density Polyethylene (HDPE) water mains, 232 new HDPE water services,
and 15 new fire hydrants within the City limits.
Construction Water Utilities Winter 2017 5,445,069$
WS‐15004 Water System Master Plan
The 2015 Water System Master Plan identified present capital improvements
and replacement rates required to ensure optimal reliability levels of service to
the existing distribution and transmission systems.
Study Water Utilities Spring 2017 500,000$
WC‐10002
Wastewater Collection
System Rehabilitation /
Augmentation Project 23
Combined with Project 22 (WC‐09001). This project replaced and/or
rehabilitated approximately 33,497 linear feet of sanitary sewer mains of
various sizes, 554 sewer laterals, and 102 sewer manholes.
Construction Wastewater
Collection Utilities Winter 2017 1,272,289$
EL‐10009
Street Light System Street
Light System Conversion
Project
This project converted HPS streetlights to LED and the conversion of
approximately 4500 cobrahead streetlight fixtures. Construction Electric Utilities Spring 2017 696,918$
5
List of Completed Projects
CIP #Project Name Project Description Project Type Fund Source Department Season
Completed
Year
Completed
Total Project
Budget **
EL‐13006 Sand Hill / Quarry 12kV
InterTie
This project installed new wire to connect circuits QR‐24 and QR‐27 in the Sand
Hill/Quarry area. Construction Electric Utilities Winter 2017 208,648$
EL‐15001 Electric Substation Battery
Replacement This project replaced the batteries in all nine of the City's electric substations. Construction Electric Utilities Winter 2017 400,000$
PG‐13001
Stanford/Palo Alto Playing
Fields Soccer Turf
Replacement
This project replaced the synthetic turf at the Stanford/Palo Alto Playing Fields. Construction Parks and Open
Space
Community
Services Fall 2016 1,499,979$
PG‐09003 Park Maintenance Shop
Remodel
This project renovated and remodeled the Parks maintenance shop for safety
and efficienciency upgrades.Construction Parks and Open
Space
Community
Services Summer 2016 94,419$
PE‐12017 City Hall First Floor
Renovations
This project installed new elevator control panels and replaced the gray‐painted
panels inside the elevators.Construction Buildings and
Facilities Public Works Summer 2016 3,974,963$
PE‐11012 Temporary Main Library This project created a temporary main Library to be used while the new one
was being constructed.Construction Buildings and
Facilities Public Works 156,254$
PE‐15029
Baylands Nature
Interpretive Center Facility
Improvement
The project replaced decking, railings, structural framing members, exterior
wood flooring, and cabinetry, restroom reconfiguration, and provided
Americans with Disabilities Act (ADA) improvements.
Construction Buildings and
Facilities Public Works Spring 2017 889,452$
PE‐13008 Bowden Park
Improvements
This project improved the children’s playground and included park amenity
upgrades such as new playground equipment, a new retaining wall, surfacing
and pathway upgrades, planting restoration and irrigation renovations, and
replaced of damaged wood benches and the playground perimeter fence.
Construction Parks and Open
Space
Community
Services Summer 2016 421,126$
PE‐13020 Byxbee Park Trails This project provided trail and site amenities over the remaining area of the
landfill cap. Construction Parks and Open
Space Public Works Fall 2016 334,607$
PE‐17002 City Hall Floor 3 Remodel
This project improved the Utilities Department administrative offices on the
third floor of City Hall. It included new carpet, wall reconfiguration, a
kitchenette, cabinets, paint, soundproofing, office furniture, doors, and
associated building systems.
Construction Buildings and
Facilities Public Works Spring 2017 440,000$
6
List of Completed Projects
CIP #Project Name Project Description Project Type Fund Source Department Season
Completed
Year
Completed
Total Project
Budget **
PE‐14015
Lucie Stern Buildings
Mechanical and Electrical
Upgrades – Phase 1
This project replaced and upgraded the mechanical, electrical, and fire/life
safety systems at Lucie Stern Children’s Theater, Lucie Stern Community
Theater, and Lucie Stern Community Center.
Construction Buildings and
Facilities Public Works Summer 2016 3,247,248$
PG‐12004 Sarah Wallis Park
Improvements
This project improved site amenities with new concrete pathways, replaced old
furnishings, and upgraded landscape with drought tolerant species. Construction Parks and Open
Space
Community
Services Winter 2017 65,000$
AP‐16003 Airport Perimeter Fence
This project replaced the perimeter fencing and gates surrounding the Palo Alto
Airport boundaries to prevent unauthorized access to the airport runway in
accordance with Federal and State standards.
Construction Airport Public Works Spring 2017 2,003,540$
SD‐11101
Channing Avenue/Lincoln
Avenue Storm Drain
Improvements
This project installed of 5,800 linear feet of 36‐inch to 60‐inch diameter storm
drain along Channing and Lincoln Avenues over three project phases to
increase drainage system capacity.
Construction Storm Drain Public Works Winter 2016 7,676,275$
GS‐14004 Gas Distribution System
Model
This project included the development, model installation, testing,
documentation, and staff training of a natural gas distribution system model. Study Gas Utilities Summer 2016 149,500$
AC‐14000
Art Center Auditorium
Audio, Visual and
Furnishings
This project replaced outdated audio visual equipment and furnishings
following the auditorium’s use as a temporary library. Construction Buildings and
Facilities
Community
Services Winter 2016 150,000$
PF‐15000 Rinconada Pool Locker
Room
This project renovated the Rinconada Pool locker room including the changing
area, restrooms, and showers in the women's and men's locker rooms. Construction Buildings and
Facilities Public Works Winter 2016 464,433$
PE‐13016 El Camino Park
Restoration
This project installed new athletic fields, synthetic turf, field lighting, fencing, a
new restroom, scorekeeper booth and storage buildings, an expanded parking
lot, new bike and pedestrian pathways, landscaping, benches, and other
amenities.
Construction Parks and Open
Space
Community
Services Fall 2015 5,611,122$
178,152,825$ Notes: ** Final Project Actuals may be different from Total Project Budget amounts Grand Total
7