HomeMy WebLinkAbout2013-05-02 Architectural Review Board Agenda Packet
City of Palo Alto Page 1
=================MEETINGS ARE CABLECAST LIVE ON GOVERNMENT ACCESS CHANNEL 26======================
Thursday May 2, 2013
REGULAR MEETING - 8:30 AM
City Council Chambers, Civic Center, 1st Floor
250 Hamilton Avenue
Palo Alto, CA 94301
ROLL CALL:
Board members: Staff Liaison:
Clare Malone Prichard (Chair) Russ Reich, Senior Planner
Lee Lippert (Vice Chair)
Alexander Lew Staff:
Randy Popp Diana Tamale, Administrative Associate
Naseem Alizadeh Amy French, Chief Planning Official
Margaret Netto, Contract Planner
Elena Lee, Senior Planner
PROCEDURES FOR PUBLIC HEARINGS
Please be advised the normal order of public hearings of agenda items is as follows:
Announce agenda item
Open public hearing
Staff recommendation
Applicant presentation – Ten (10) minutes limitation or at the discretion of the Board.
Public comment – Five (5) minutes limitation per speaker or limitation to three (3)
minutes depending on large number of speakers per item.
Architectural Review Board questions of the applicant/staff, and comments
Applicant closing comments - Three (3) minutes
Close public hearing
Motions/recommendations by the Board
Final vote
ORAL COMMUNICATIONS. Members of the public may speak to any item not on the
agenda with a limitation of three (3) minutes per speaker. Those who desire to speak must
complete a speaker request card available from the secretary of the Board. The Architectural
Review Board reserves the right to limit the oral communications period to 15 minutes.
APPROVAL OF MINUTES.
April 4 & 18, 2013
ARCHITECTURAL REVIEW BOARD
AGENDA
City of Palo Alto Page 2
AGENDA CHANGES, ADDITIONS AND DELETIONS. The agenda may have additional
items added to it up until 72 hours prior to meeting time.
NEW BUSINESS:
Preliminary Reviews:
1. 2755 El Camino Real [13PLN-00138]: Request by the Hayes Group on behalf of Pollock
Financial Group, Inc. for preliminary Architectural Review of a new four story mixed use
building with three stories of below grade parking on a 19,563 square foot lot. The Council
conducted a preliminary review session in February 2013 regarding the potential project. The
Planning and Transportation Commission has not yet conducted the Planned Community (PC)
initiation. Zone District: Public Facility (PF).
2. 500 University Avenue [13PLN-00112]: Request by Thoits Bros. LLC for Preliminary
Architectural Review of a new three-story 26,806 square foot commercial building with below
grade parking, replacing the existing one-story commercial building. The concept design would
require a Design Enhancement Exception (DEE) to allow additional height over the limit for a
corner tower element. Zone: CD-C(GF)(P). This item is continued to the next regular
meeting on May 16, 2013.
Minor Review:
3. 180 El Camino Real [13PLN-00064]: Request by Fergus, Garber, Young Architects, on behalf
of the Leland Stanford Junior University, for a Minor Architectural Review of façade
improvements and signage for a commercial recreation use for SoulCycle at the Stanford
Shopping Center. Zone District: Per CEQA Guideline Section Community Commercial,
Environmental Assessment: Exempt from the provisions of the California Environmental
Quality Act (CEQA) 15301 (Existing Facilities) (CC).
BOARD MEMBER BUSINESS AND ANNOUNCEMENTS.
REPORTS FROM OFFICIALS.
Subcommittee Members: Naseem Alizadeh and Randy Popp
SUBCOMMITTEE:
4. 180 El Camino Real [12PLN-000532]: Request by FME Architecture and Design, on behalf of
Board of Trustees of the Leland Stanford Junior University for Architectural Review to allow
facade modifications to exisitng product display windows for Wilkes Bashford at the Stanford
Shopping Center. Zone District Community Commercial (CC). Environmental Assessment:
Exempt from the provisions of CEQA, Per CEQA Guideline Section 15311 (Accessory
Structures).
STAFF ARCHITECTURAL REVIEW:
Project Description: Removal of two cedar trees and the planting of 24” box Erect European
Hornbeans as replacement trees
City of Palo Alto Page 3
Applicant: Kyle Sager
Address: 1510 Page Mill Road [13PLN-00122]
Approval Date: 4/15/13
Request for hearing deadline: 4/29/13
Project Description: Review three non-illuminated free-standing signs for the temporary relocation site
of the Main Library
Applicant: Hung Nguyen, Public Works Department
Address: 1313 Newell Road [13PLN-00159]
Approval Date: 4/12/13
Request for hearing deadline: 4/25/13
Project Description: Review one halo-illuminated wall mounted sign for an existing retail use
Applicant: David Kim
Address: 250 University Avenue [13PLN-00052]
Approval Date: 4/12/13
Request for hearing deadline: 4/25/13
Project Description: Review of minor façade improvements for an existing restaurant use that include
non-illuminated signage and painting
Applicant: PJ Patton
Address: 452 University Avenue [13PLN-00139]
Approval Date: 4/16/13
Request for hearing deadline: 4/29/13
Project Description: Review for a façade improvement, new outdoor patio and landscaping
Applicant: Mr. Gary Semling
Address: 3375 El Camino Real [13PLN-00065]
Approval Date: 4/17/13
Request for hearing deadline: 4/30/13
Project Description: To hold a private only member pre-owned car sales event at the site
Applicant: Maureen Weneta
Address: 1860 Embarcadero Road [13PLN-0151]
Approval Date: 4/17/13
Request for hearing deadline: 4/30/13
Project Description: Removal of three planter boxes from the recessed area on private property on
University Avenue side of the restaurant
Applicant: Paul Shenckman
Address: 185 University Avenue [13PLN-00163]
Approval Date: 4/19/13
Request for hearing deadline: 5/2/13
Project Description: Landscape modification due to installation of electric vehicle charging stations
Applicant: David Ham
Address: 3333 Coyote Road [13PLN-00126]
Approval Date: 4/22/13
City of Palo Alto Page 4
Request for hearing deadline: 5/6/13
Project Description: Installation of one 24 sq. ft. illuminated wall sign on the East facade side of the
building wall
Applicant: Pro Sign Inc
Address: 3903 El Camino Real [13PLN-00038]
Approval Date: 4/22/13
Request for hearing deadline: 5/6/13
Project Description: Installation of two externally illuminated individual channel letter
Applicant: Bruce Schmidt
Address: 140 University Avenue [12PLN-0478]
Approval Date: 4/22/13
Request for hearing deadline: 5/6/13
Project Description: Addition of electrical substation and expansion of previously approved service
yard (permit# 11PLN-00336)
Applicant: John Ludlow
Address: 3251 Hanover [13PLN-00120]
Approval Date: 4/23/13
Request for hearing deadline: 5/6/13
Project Description: Replacement of nine building mounted wireless antennas with six new building
mounted wireless antennas
Applicant: Lisa Elliot
Address: 525 University Avenue [12PLN-00489]
Approval Date: 4/24/13
Request for hearing deadline: 5/7/13
Project Description: Improvement/maintenance of an existing bicycle trail that provides access from
Mitchell Park to Charleston Road
Applicant: Peter Jensen
Address: 600 E. Meadow Drive [13PLN-00173]
Approval Date: 4/25/13
Request for hearing deadline: 5/8/13
ADA. The City of Palo Alto does not discriminate against individuals with disabilities. To request accommodations to
access City facilities, services or programs, to participate at public meetings, or to learn more about the City’s compliance
with the Americans with Disabilities Act of 1990 (ADA), please contact the City’s ADA Coordinator at 650.329.2550 (voice)
or by e-mailing ada@cityofpaloalto.org.
Posting of agenda. This agenda is posted in accordance with government code section 54954.2(a) or section
54956.Recordings. A videotape of the proceedings can be obtained/reviewed by contacting the City Clerk’s Office at (650)
329-2571.
Materials related to an item on this agenda submitted to the Architectural Review Board after
distribution of the agenda packet are available for public inspection in the Planning and Community
Environment Department at 250 Hamilton Avenue, 5th floor, Palo Alto, CA. 94301 during normal
business hours.
Agenda Date:
To:
From:
Subject:
1 Architectural Review Board
Staff Report
May 2, 2013
Architectural Review Board
Margaret Netto, Contract Planner Department: Planning and
Community Environment
2755 El Camino Real [13PLN-00138]: Request by the Hayes Group on
behalf of the Pollack Financial Group, Inc., for preliminary Architectural
Review of the construction of a new four-story, mixed-use building with
three stories of below grade parking on a 19,563 square foot lot (formerly a
'park-and-ride' parking lot). The Council conducted a preliminary review
session in February 2013 regarding the potential project. The Planning and
Transportation Commission has not yet conducted the Planned Community
initiation. Zone District: PF.
RECOMMENDATION
Staff recommends that the Architectural Review Board (ARB) conduct a preliminary review of
the 2755 El Camino Real conceptual development plans, and provide comments on the design to
staff and the applicant. No formal action may be taken at a preliminary review public hearing.
Comments made at a preliminary architectural review public hearing are neither binding on the
City nor on the applicant.
SITE INFORMATION
The project site is a 19,563 square foot parcel, located on the northeast comer of El Camino Real
and Page Mill Road (see location map, Attachment A). The subject site is zoned Public Facilities,
and the Comprehensive Plan land use designation is Major Institution! Special Facilities. It is a
vacant surplus parking lot previously owned by Valley Transportation Authority (VT A) and
recently sold to the applicant.
Surrounding Sites
The southern comer (3000 Page Mill Road) of the Page Mill/EL Camino Real intersection is the
ten-story Palo Alto Square commercial complex (PC 4637), which includes at-grade landscaped
parking facilities located adjacent to the street frontage. The four-story Sunrise Assisted ~iving
Facility (a Planned Community, PC 4831) with one level of below grade parking facilities, is
located adjacent to and northwest of the subject property. Adjacent to and northeast of the subject
site is PC-4463, a three-story residential condominium complex (The Silverwood), which includes
13PLN-0138 Page 1 of6
one level of underground parking. The southeast comer of Page Mill Road and EI Camino Real is
developed with the two-story AT&T retail building and associated parking lot. The site is adjacent
to the AT&T on Page Mill Road (423-451 Page Mill Road) was recently amended from single
family residential zoning and land use designation to the Commercial Service (CS) zone and land
use designation. The AT&T building is adjacent to the three-story mixed-use building at 2825 EI
Camino Real, which is next to a vacant lot approved for development of a one-story commercial
building. The westerly comer of the intersection is the Mayfield Soccer Complex, on a 5.9 acre
site zoned PF (AS3).
BACKGROUND
On February 11, 2013, the City Council conducted a Preliminary Review (,Prescreening') of the
proposed rezoning of this site to a Planned Community (PC) zoning, for the proposed
development of a four-story commercial building with associated parking. The application for
Planned Community would also need to include a request for a Comprehensive Plan Amendment,
to change the site's Land Use Designation. The Council provided the following comments during
the Prescreening session:
• Additional analysis and quantification of the public benefits should be conducted;
• This is a highly visible location, therefore architecture and attention to massing are
particularly important;
• The relationship between the building and the sidewalk should be improved;
• The open space plaza does not appear to be designed for public use;
• Some Councilmembers expressed concern about the 50-foot tall, flat roof;
• Overall, the architecture should have a "warmer" feel.
PROJECT DESCRIPTION
The project is a new four-story, 31,740 square foot (sq. ft.) commercial building with three levels
of underground parking spaces, on a 19,563 sq. ft., comer site with a 1.62 Floor Area Ratio
(FAR). The applicant envisions a professional office and surface parking on the ground level as
well as below grade, and office use on the remaining three commercial floors.
The building concept includes a c~ncrete frame, cut stone, plaster finish and window glazing
system. Vehicular ingress to the site and garage would be provided via right tum only from EI
Camino Real, with right tum only onto EI Camino Real. The modem design includes two-story
tall, two-sided structural-glazed windows, with deep window shades fronting EI Camino Real and
Page Mill Road. At grade level, the building would be recessed back at the comer to provide a
connection between the sidewalk and the public plaza. A low planter wall with accent planting
provides a backdrop to the plaza space and screens the parking area. Integral planters at the street
level would form a building base, with clear, frameless glass windows allowing visual access into
the ground floor level, similar to the windows of the AT&T building across Page Mill Road.
The Landscape Plan includes a 12 foot wide public sidewalk along Oregon Expressway and a 15
foot wide sidewalk along EI Camino Real. Both streets include a series of street trees in tree
grates. The low planter wall is proposed at back of walk. The accent plant materials incorporate a
variety of color and texture to soften the edge between the building and sidewalk. The perimeter
planting provides screen planting.
13PLN-0138 Page 2 of6
The project would provide a total of 115 vehicle parking spaces where 134 parking spaces would
be the standard parking requirement for general office use. The project is potentially eligible for a
parking adjustment, up to a 20 percent reduction, if deemed appropriate by the Director of
Planning and Community Development (and in this case, the City Council). At the City Council
Study Session, Council suggested a 10% parking reduction would be appropriate, subject to
providing a Transportation Demand Management (TDM) plan. Assuming a 10% reduction, the
project would need to provide 121 parking spaces on site, if the building is to be entirely office
use. Short-term bicycle parking spaces are proposed near the main entrance of the building and
long-term bicycle parking would be provided in a secured portion in the basement parking area.
The project application would include a Design Enhancement Exception (DEE) request. The DEE
request is to allow the upper portion of the rear stair tower to encroach into a 45 degree daylight
plane from the northern rear property line (conlmencing at 10 feet above grade plane).
DISCUSSION
The plans incorporate some of the comments noted at the Council Prescreening session:
• The fourth story has been stepped back with an outdoor terrace area breaking up the
massing from the street;
• The fourth story terrace breaks up the flat roof appearance;
• The plaza area has been enlarged for public use. The area includes accent paving bands,
stainless steel bollards and decorative bike racks. These elements define the public space
and guide pedestrians to the building entry;
• The building is set back from the property line creating a relationship between the building
and the sidewalk. The deep window shades provide for a "warmer" feel to the building as
opposed to the original design with the elliptical wall shape with full height glass.
Building, Height, Mass
The plans indicate a building height of 50-feet above grade, generally consistent with the PF, CS
and PC zoning. The roof screen would extend an additional eight feet above the roof. The DEE
request is to allow the upper portion of the rear stair tower to encroach into a 45 degree daylight
plane from the northern rear property line (commencing at 10 feet above grade plane). Staff
requests the ARB to discuss how the building would fit into the existing street context, and the
DEE request.
Context-Based Design Criteria
According to Section 18.16.090 of the Palo Alto Municipal Code, "compatibility is achieved
when apparent scale and mass of new buildings is consistent with the pattern of achieving a
pedestrian oriented design, and when new construction shares general characteristics and
establishes design linkages with the overall pattern of buildings, so that the visual unity of the
street is maintained". The proposal does achieve a pedestrian-oriented design with floor to ceiling
storefront glazing, a recessed entry, and columns that would create a colonnade. The building
would be set back from the EI Camino ReallPage Mill Road comer. The Sunrise Assisted Living
Facility and Silverwood condominium complex is very similar in height, mass and articulation.
13PLN-0138 Page 3 of6
The scale of the street facing facades is generally pedestrian-oriented. One element that the
proposed building does have in common with the some of the taller buildings in close proximity is
a recessed entry.
The building in the concept plans generally appears to be compliant with the majority of the
Context-Based Design Criteria of the Zoning Code. However, a recent Council colleague's memo
requested the staff revise applicable guidelines relating to sidewalk widths and the pedestrian
relationship to buildings. One consideration is the use of landscaping to mitigate the size of
buildings and create greater pedestrian comfort.
The ARB is requested to discuss the project's compatibility in the areas of scale, mass, pedestrian
oriented design, given the site's context. The conceptual plans show an architectural style
compatible with some of the buildings on the street, intended to create a visual unity of the street's
buildings.
EI Camino Real Development
Three guidelines are applicable to this site: (1) EI Camino Real Design Guidelines (ECR
Guidelines), (2) South EI Camino Real Guidelines, recommended by ARB in 2002 (South ECR
Guidelines), (3) EI Camino Real Master Schematic Design Plan, 2003 Draft (Design Plan), and
(4) Context Based Guidelines found in the Palo Alto Municipal Code.
South ECR Guidelines: The project is located within the California Avenue Strategic Site
Pedestrian-Oriented Node, "the ,properties at the intersection of Page Mill Road and EI Camino
Real need to be architecturally prominent, with a strong street presence so that they serve as
anchors, for the southern end of the district". As defined on Page 14, the "VTA center at the
corner of Page Mill and EI Camino Real" -where a more intensive use of the site should be
designed -"to take advantage of the prominent location" and supports pedestrian activities. The
project would provide three levels of subsurface parking, which is desirable. Buildings should
face EI Camino Real parallel to the EI Camino Real right-of-way, but would need to provide a
prominent entry to reflect human scale. Also as noted, "The EI Camino Real frontage should
feature extensive windows." The project does provide extensive glazing on the favade, providing a
strong street presence. The ARB should consider the massing at the corner, which may dominate
the corner. Building "step-backs", or landscape "softening" may be desirable in order to mitigate
the size of the building favade as perceived from a pedestrian standpoint.
ECR Guidelines: The project is subject to the 1979 guidelines with respect to spacing of street
trees, signage, architecture and building colors. The applicable sections are as follows:
• The ECR Guidelines call for street tree spacing every 25 feet (Page 2, top) or 30
feet (page 2, bottom); whereas the ECR Master Schematic Design Plan calls for London
Plane street trees in this segment ofEI Camino Real, planted 22 to 23 feet on center, in 4'
x 6' tree wells, and pruned to provide 14' feet of clearance below to allow for truck and
bus traffic. The concept plan does indicate London Plane street trees.
Page 4 of6
• Signage: There are a few relevant statements, such as: "Signs on ECR are limited to Yz to
2/3 the maximum size permitted by the sign ordinance'; "Wall signs should appear as
though the building and the sign were designed together"; "The sign should not appear as
if it were attached as an afterthought"; "Three signs, one on each elevation, are usually not
approved." No signage is proposed at this time but the applicant should provide location(s)
of signage on the formal Planned Community plan set for formal ARB review, to ensure
integration with the "signature building" architecture.
• Architecture: "Buildings should not be overdesigned or decorated with superfluous details
or imitations of structural materials." Also "when possible, buildings should be set back
from the front property line, with landscaping or a people-oriented plaza in front." This is
something to keep in mind when comparing guidelines. Again, the massing of the building
near the comer should be discussed by the ARB.
• Colors: "More than three colors on a structure will make it incompatible with the
surroundings. Using bright colors, such as reds, yellows and purples and greens as
predominant color on a structure may it incompatible with the surroundings. The ARB
usually feels these colors are used to attract attention."
OTHER CITY DEPARTMENTS' REVIEWS
The applicant has received comments from the Utilities Department's Water;Gas & Wastewater
and Utilities' Electric Engineering Divisions, from Green Waste, from the Building Division, the
Public Works Engineering and Public Works Environmental Compliance Divisions, and the Fire
Department. The project will require review and approval by Caltrans and Santa Clara County for
review of the ingress/egress driveways off El Camino Real, as well as any installation of Traffic
Control devices as part of this project (see Attachment B -Departmental Review Comment
Letters).
ARCHITECTURAL REVIEW AND PC PROCESS
The purpose of this preliminary Architectural Review public hearing is to introduce the proj ect to
the ARB and to give the applicant feedback early in the design process.
An assessment of aesthetics would be provided within the anticipated environmental review
document associated with a formal application for Planned Community rezoning. The applicant
should submit solar studies, streetscape elevations, photometric plans and other visual information
to allow a full, formal review. Achievement of urban forestry goals on a densely designed site of
this nature would require creative and technological consideration. Staff is working with the
applicant to explore urban and pedestrian design features that would help improve the site
connections to services and create a greater sense of place for this area. Following submittal of an
application for PC rezoning and Land Use re-designation, staff would meet with the applicant
team to discuss the areas that need to be addressed and set next steps for environmental review,
including the aesthetics section.
Subsequent to this preliminary review, the applicant intends to submit a Planned Community
application including requests for land use re-designation and DEE, and documents to enable
13PLN-0138 Page 5 of6
environmental review. The Planning and Transportation Commission (PTC) would be requested
to review environmental documents and initiate the requested PC rezoning and land use re
designation. If the PTC initiates the PC application, formal plans would be prepared and
forwarded, along with an environmental analysis, to the ARB for review and recommendation.
Planning staff requires that all project applicants review and provide pertinent items required in
the City's 'Architectural Review submittal requirements' list available on the City's website for
formal Architectural Review and Environmental Review. Adherence to the submittal
requirements list facilitates timely review of projects.
GREEN BUILDING REQUIREMENTS
At the formal application stage, the applicant will be required to submit a Cal Green Tier 2
mandatory compliance worksheet. The project proposes to use both conventional and sustainable
materials, including concrete frame, high efficiency glazing systems, high recycled content metal
skin systems and an energy efficient cool roof. Electric vehicle charging stations are proposed on
grade and in the below grade parking garage.
ENVRIONMENTAL REVIEW
No environmental review is required for this preliminary architectural review application, as it is
not considered a project under California Environmental Quality Act (CEQA).
PUBLIC COMMENTS
Staff has not received any public comments as of the publication of this staff report. Neighboring
property owners within 600 foot radius will have received notice cards regarding the ARB public
hearing.
ATTACHMENTS
Attachment A:
Attachment B:
Attachment C:
Attachment D:
Project Location Map
Departmental Review Comments
Applicant's letter
Preliminary Development Plans (Board Members Only)
COURTESY COPIES
Ken Hayes, Hayes Group
khayes@thehayesgroup.com
Prepared by: >" Margaret Netto, Contract Planner
Reviewed by: Amy French, AICP, Chief Planning Official
13PLN-0138 Page 60f6
«
~ z UJ ~ J: U ~
0Id:I.
abc Zone District Labels
C::I Zone Districts c::::J Assessment Parcel (AP)
c=::J 2755EI Camino Real
:>!l~~IW')
IAttachmen(A]
The City of
Palo Alto
~ ~
8 -,..-4
m U
~ u:l
\.(')
IT)
t
N .s .~ rjJ
This map is a product of the
Cityof Palo Alto GIS
~
S9'
ATTACHMENT B
Public Works Department
Environmental Services Division
Watershed Protection Grqup
PROJECT REVIEW COMMENTS
Date: 4/8/2013
To: Margaret Netto .
From:
Phone:
Kirsten Struve, Manager, Environmental Control Programs
(650) 329 .. 2421
---------------------------~-~-------------------------------------------------~-.~------------------------------------------
Application Number:
Company Name
Projeet Address: 2755 EI Camino Real
Palo Alto, CA
_____ ~-_-_-------------------------------------------~------_________ ----____ ~_M _________ ~ ________________________ ~ ______ ~ ___
We have reviewed the site floor plans for this project. Please note the following issues must be
addressed in building'plans prior to 'final approval by·this department:
PAMe 16.09.170,16.09.040 Discharge of Groundwater
The project is located in an area of suspected or known groundwater contamination with Volatile Organic Compounds (VOCs).
If groundwater is encount~red then the plans must include the following procedure for construction dewatering:
Prior to discharge of any water from construction dewateringt the water shall be tested· for volatile organic compOl.mds (VOCs)
using EPA Method 60 11602 or Method 624. The analytical results of the VOC testing shall be transmitted to the Regional
Water Quality Control Plant (RWQCP) 650-.~29-2S98. Contaminated ground water that exceeds' state or federal requirements
for dis.charge to navigable waters may not be discharged to the stonn drain system or creeks. If the concentrations of pollutants
exceed the applicable limits for discharge to the storm drain system then an Exceptional Discharge' Pennit must be obtained
from the RWQCP prior. to discharge to the sanitary-sewer system. If the VOC concentrations exceed the toxic organics
discharge limits contained in the Palo Alto Municipal Code (16.09.040(m)) a treatment system for removal ofVOCs will also
be required prior to discharge to the sanitary sewer. Additionally, any water' discharged to the sanitary sewer system or storm .
drain system must be free of sediment.
PAMC 16.09.180(b)(9) Covered Parking
Drain plumbing for parking garage floor drains must be cOIll1ected to an oil/water separator with a minimum capacity of 100
gallons, and to the sanitary sewer system
PAMC 16.09.180(b)(lO) Dumpsters for New and Remodeled'Facilities
Page t of4
New buildings and residential developments providing centralized solid waste collection, except for single-family and duplex
residence~~ shall provide·a covered area for a dumpster. The area shall be adequately sized for all waste streams and designed
with grading or a berm system to prevent water ronon and nmoff from the area.
PAMC 16.09.180(b)(14) Architectural Copper
On and after January 1,2003, copper meta] roofing, copper metal gutters, copper metal down spouts, and copper granule
containing asphalt shingles shall not be permitted for use on any residential, commercial or industrial building for which a
building permit is required. Copper flashing for use under tiles or slates and small copper ornaments are exempt from this
prohibition. Replacement roofing, gutters and· downspouts on historic structures are exempt, provided that the roofing material
used shall be prepatinated at the factory. For the purposes of this exemption, the definition ofnhistoricll shall be limited to
structures designated as Category 1 or Category 2 buildings in the current edit~on of the Palo Alto Historical and Architectural
Resources Report and Inventory.
PAMC 16.09.175(k) (2) Loading Docks
(i) Loading dock drains to the storm drain system may be allowed if equipped with a fail-safe valve or
equivalent device that"is kept closed during the non-rainy season and during periods ofloading dock operation.
(ii) Where chemicals, hazardous materials., grease~ oil, or waste products are handled or used within the loading
dOCK area, a drain to the stonn drain system Shall not be allowed. A drain to the sanitary sewer system may be allowed if
equippec;l with a fail-safe valve or equivalent device that is kept closed during the non-rainy season and' during periods of
loading dock operation. The area in which the drain is located shan be covered or protected from rainwater run-on by berms
andlor grading. Appropriate wastewater treatment approved by the Superintendent shall be provided for all rainwater contacting
Ute loading dock site.
PAMC .16.09.180(b)(5) Condensate from HVAC .
Condensate lines shall not be connect~d or allowed to drain to the stonn drain system.
PAMC 16.09.180(b)(b) Copper Piping
Copper, copper alloys, lead and lead alloys, including brass, shall not be used in sewer lines, connectors, or seals coming in
contact with sewage except for domestic waste sink traps and short lengths of associated connecting pipes where alternate
materials are not practical. The plans must specifY that copper piping Will not be used for wastewater plumbing.
16.09.180(12) Mercury Switches
Mercury switches shall not be installed in sewer or storm drain sumps:
PAMC 16.09.205(a) Cooling Systems, Pools, Spas, Fountains, Boilers and Heat Exchangers
It shall be unlawful to discharge water from cooling systems, pools,. spas~ fountains boilers and heat exchangers to the storm
drain system.
PAMe 16.09.165(h) Storm Drain LabeJing
Storm drain inlets shaU be clearly marked with the words "No dumping -Flows to Bay," or equivalent.
Uudesignated Retall Space:
PAMC 16.09
Newly constructed or improved buildings with all or a portion of the space with undesignated tenants or future use will need to
meet ail requirements that would have been applicable during design and construction. If such undesignated retail space
becomes a food service facility the following requirements must be met: .
Designated Food Service Establishment (FSE) Project:
A. Grease Control Device (GCD) Requirements, PAMC Section 16.09.075 & cited BldgIPlumbing Codes
1. The plans shall specify the manufacturer details and installation details of all' proposed GCDs. (eBe 1009.2)
2. GCD(s) shall be sized in accordance with the 2007 California Plumbing Code.
3. 'GCD(s) shall be installed with a minimum capacity of 500 gallons.
4. GCD sizing calculations shall be included on the plans. See a sizing calculation example below.
P.age20f4
5. .The size of a11 GeDs installed shall be equal to or larger than what is specified on the plans.
6. OCDs larger than 50 gallons (100 pounds) shall not be installed in food preparation and storage areas. Santa Clara
County Department of Environmental Health prefers GCDs to be installed outside. GCDs shall be installed such that
all access points or manholes are readily accessible for inspection, cleaning and removal or' all contents. GCDs
located outdoors shall be installed in such a manner so as to exclude the entrance of surface and stormwater. (CPC
1009.5)
7. All large, in~ground interceptors shall have a minimum of three manholes to allow visibility of each inlet piping, baffle
(divider) waU, baffle piping and outlet piping. The plans shall clearly indicate the nwnber of proposed manholes on
the OCD. The Enviromnental'Compliance Division of Public Works Department may authorize variances which
allow GeDs with less than three manholes due to manufacture available options or adequate visibility.
8. Sample boxes shall be installed downstream of all GCDs.
9. All GCDs,sha1l be fitted with reliefvent(s). (CPC 1002.2 & 1004)
10. GCD(s) installed in vehicle traffic areas shall be rated and indicated on plans.
B. Drainage Fixture Requirements, PAMC Section 16.09.075 & cited BldgIPlumbing Codes
11. To ensure all FSE drainage fixtures are connected to the correct drain lines, each drainage fixture shall 'be clearly
labeled on the plans. A list of all fixtures and their discharge connection, i.e. sanitary sewer or grease waste line, shaH
be included on the plans.
12. A list indicating all connections to each proposed OeD shall be included on the plans. This can be incorporated into
the sizing calculation. ' " ,
13. All grease generat'ing drainage fixtures shall connect to a GeD. These include but are not limited to:
a. Pre-rinse (scullery) sinks
b. Three compartment sinks (pot sinks)
c. Drainage fixtures in dishwQshing room except for dishwashers shall connect to a OCD
d. Examples: trough drains (small drains prior to entering a dishwasher), small drains on busing counters
adjacent to pre-rinse sinks or silverware soaking sinks '
e. Floor drains in dishwashing area and kitchens
f. Prep sinks
g. Mop Ganitor) sinks
h. Outside areas designated f01' equipment washing shall be covered and any drains contained therein shall
connect to a GCD. ' ,
i. Drains in trash/recycling' enclosures
j. Wok stoves, rotisserie ovenslbroilers or ()ther grease generating cooking equipment with drip lines
k. Kettles and tlItibraising pans and associated floor drains/sinks
14 .. --The connection of-any high temperature discharge lines and non-grease 'generating'drainage fixtures to 'a GCD is
prohibited. The following shall not be connected' to aGeD:
a. Dishwashers
b. Steamers
c. Pasta cookers
d. Hot lines from buffet counters and kitchens
e. Hand sinks
f. Ice machine drip lines
g. Soda machine drip lines
h. Drainage lines in bar areas
15. No garbage disposers (grinders) shall be installed in a FSE. (PAMC 16.09.075(d)).
16. Plumbing lines shall not be installed above any cooking, food preparation and storage areas.
17. Each drainage'·fixture discharging into a oeD shaH be individually trapped and vented. ccpe 1014.5)
C. Covered Dumpsters, Recycling and Tallow Bin Areas PAMe, 16.09.075(q)(2)
18. Newly constructed and remodeled FSEs shall include a covered area for all dumpsters, bins, carts or container used for
the collection of trash, recycling, food scraps and waste cooking fats, oils and grease (FOG) or tallow.
19. The area shall be designed and shown OD, plans to prevent -water run-on to the area and runoff from the area.
20. Drains that are installed within the enclosure for recycle and waste bins, dumpsters and tallow bins serving FSEs are
optional. Any such drain installed shall be connected to a GCD.
Page 3 of4
21. If tallow is to be stored outside then-an adequately sized, segregated space for a tallow bin shall be included in the
covered area. -
22. These requirements shall apply to remodeled or converted facilities to the extent that the portion of the facility being
remodeled is related to the subject of the requirement.
D. Large Item Cleaning Sink, PAMC 16.09.075(m)(2)(B)
23. FSEs shall have a sink or other area drain which is connected to a OeD and large enouSit for cleaning the largest
kitchen equipment such as floor mats, containers, carts, etc. Recommendation: Generally, sinks or cleaning areas
larger than a typical mop/janitor sink are more useful. --
E. GCD sizing criteria and an example of a GCD sizing calculation (2007 CPC)
Sizing Criteria:
Drain Fixtures Pre-rinse sink "DFUs
4
3
3
3
3
2
2
-GCD Sizing:
TotalDFUs
8
21 35
90
172
216
GCD Volume (gallons)
500
750
1,000
1,250
1,500
2,000
Note:
3 compartment sink
2 compartment sink Prep smk:
Mop/Janitorial sink
Floor drain
Floor sink
ExampleGCD
Sizing Calculation: Quantity
1
1
2
1
1
1
1
4
Drainage Fixture & Item Number
Pre-rinse sinkt Item 1
3 compartment sink, Item 2
Prep sinks, Item 3 & Floor sink, Item 4
Mop sink, Item 5
Floor trough, Item 6 & tilt skillet, Item 7
Floor trough, Item 6 & steam kettle) Item 8
Floor sink, Item 4 & wok stove, Item 9,
Floor drains
1,000 gallon GeD minimum sized
DFUs Total
4 4
3 3
3 6
3 3
2 2
2 2
2 2
2 8
Total: 30
• All resubmitted plans to Building Department which include FSB projects shall be resubIl?-itted to Water Quality.
• It is frequently to the FSB~s advantage to install the next size larger OeD to allow for more efficient grease discharge
prevention and may allow for I01)ger times between cleaning. There are many manufacturers of GeDs which are available
in different shapes, sizes ana materials (plastic) reinforced fiberglass, reinforced concrete and metal)
• The requirements will assist FSEs with FOG discharge prevention to the sanita:o' sewer and storm drain pollution
prevention. The FSE at all times shaH comply with the Sewer Use Ordinance of the Palo Alto Municipal Code. The
ordinances include requirements for GeDs, oeD maintenance, dra'inage fixtures, record keeping and construction projects.
Page40f4 "
Hello Margaret,
The Fire Department is recommending approval for this project with the following conditions:
1. Plumbing designer shall coordinate with sprinkler designer to provide a sump with a
minimum of 300 gallons capacity to detain main drain test flow from ftre sprinkler
system. Pumps to sanitary sewer-shall be sized with the approval of the City of Palo Alto
Utilities Department.
2. Roof access for the rooftop mechanical enclosure shall be via a hatch with minimum
dimensions of 36 in. x 48 in.
Thanks,
Go~don Simpkinson
To: Margaret Netto
From: Woojae Kim
Date: April 11, 2013
PUBLIC WORKS ENGINEERING
REVIEW COMMENTS FOR
2755 EL CAMINO REAL, 13PLN-138 (ARB)
Here are the Public Works Engineering (PWE) review comments with more comments
that·may follow pending revised submittal:
CALTRANS: Caltrans review and approval of this project is required. Caltrans right ..
of-way across EI Camino Real extends from back-of-walk to back .. of walk. The City
has a maintenance agreement with Caltrans that requires the City to maintain the
sidewalk and to issue Permit for Street Work in the Public Right-of-Way ("Street
. Work Permits") for work done on the sidewalks by private contractors. Caltrans has
retained the right to review and permit new ingress/egress ,driveways off EI Camino
Real as welt as the installation of Traffic Contr~1 devices as part of this project.
SANTA CLARA COUNTY: Santa Clara County (County) review and approval of this
project is required. County right-of-way across Page Mill Road extends from
property line to property Une. Any work in the County right-of-way will require
Street Work Permit from the County. The County needs to review and permit new
Ingress/egress driveways off Page Mill Road as well as any installation of Traffic
Control devices as part of this project.
OFFSITE IMPROVEMENTS: As part of this project, the applicant, at minimum, will be
required to repave (2~inch grind and pave) the half-width of Page Mill Road along the
frontage of the project site, and install new public sidewalks, curbs, gutters, and
driveway approaches in the public right-of-way per the City Standards. The site plan
must show the extent of the offsite improvement work and note that any work in the
public right-of-ways must be done per City standards by a licensed contractor and
that a Street Work permits from appropriate agencies are required.
DEDICATION AND EASEMENT FOR PUBUC SIDEWALK: On Page Mill Road Side, a
minimum of five (5) feet of width of land from back of the curb to the property
shall be dedicated to the County/City as public right-of-way sld~walk., Subgrade
structure such as underground garage cannot be under this, dedication. On Page Mill
Road and EI Camino Real, any sidewalk for public usage within the property line shall
be granted a public access easement. All dedicationS and easements need to
recorded at the County Clerk .. Recorder's Office before a build'ing permit can be
issued for the project.
STREET TREES: The applicant may be required to replace existing and/or add new
street trees in the public right-of-way along the property's frontage. Cail Public
Works' arborlst at 650-496-5953 to arrange a site, visit so he can determine what
street tree work will be required for this project. The site or tree plan must show
street tree work that the ·arborist has determined Including the tree species, size,
location, staking and Irrigation requirements. Any removal, relocation or planting of
street trees; or excavation, trenching or pavement within 10 feet of street trees
must be approved by the Public Works' arborist. The plan must note that in order to
do street tree work, the applicant must first obtain a Permit for Street Tree Work in
the Public Right~of-Way C·Street Tree Permit") from ,Public Works' Urban Forestry.
STORM WATER RUNOFF SYNOPSIS: Provide a synopsis of pre and post-development
storm water runoff flows and drainage systems. Summarize existing storm water
Page 2 of 5
drainage patterns such as where the existing site runoff drains to. Explain the
Increase In the site storm water runoff flow for post-development. Show justification
that the existing City storm water drainage system has the capacity to handle the
increase in the flow.
STORM WATER TREATMENT: One of the requirements to qualify the project as a C.3
SpecIal Project Category A is that the project has to be in "a central business district,
downtown core area or downtown core zoning district or historic preservation site
and/or district". Planned Community Zonirig District does not qualify as one
of those districts; hence Low Impact Development Reduction Credit cannot
be applied.
This project must meet the latest State Regional Water Qua!.ity Control Board's
(SRWQCB) C.3 provisions. The applicant is required to satisfy all current storm water
discharge regulations and shall provide calculations and documents to verify
compliance. All projects that are required to treat storm water will need to treat the
permit-specified amount of storm water runoff with the following low Impact
development (LID) methods: rainwater harvesting and reuse, infiltration,
evapotranspiration, or biotreatment. However, biotreatment (filtering storm water
. through vegetation and soll$ before ,qischarging to the storm drain ,system) will be
allowed only where harvesting and reuse, infiltration and evapotranspiration are
infeasible at the project site. Complete the Infiltration/Harvesting and Use Feasibility
Screening Worksheet (Santa Clara Valley Urban Runoff Pollution Prevention Program
C.3 Stormwater Handbook -Appendix I). Vault ... based treatment will not be
allowed as a stand ... alone treatment measure. Where storm water harvesting
and reuse, infiltratio~, or evapotranspiration are infeaSible, vault*based treatment
measures may be used In series with blotreatment, for example, to remove trash or
other large solids.
Reference: Palo Alto Municipal Code Section 16,11,030(c)
.b.itQ;.ttww.Wu.s.~YUr'pQR=-w2k_.coJI!lp.1~r..mit c3 _s1.ocsLr~::')L_b(:1i).d.b..QqJ(. ;Z.sU;'~LAflP~n!.:H2LJ_~
i-.. em:i.iJ).Htl Y._.?J)}_4,·.PIt.f
The applicant must incorporate permanent storm water pollution prevention
measures that treat storm water runoff prior to discharge. The prevention measures
shall be reviewed by a qualified third-party reviewer who needs to certify that it
complies with the Palo Alto Municipal Code requirements. ThIs is required prior to
the Issuance of a building permit. The third"party reviewer shall be acquired by the
applicant and needs to be on the Santa Clara Valley Urban Runoff Pollution
Prevention Program/s (Program) list of qualified consultants. Any consultant or
contractor hired to destgn/and/or construct a storm water treatment system for the
project cannot certify the project as a third-party reviewer.
111tP';,ilYY.J.Nyv.sc:vurppp··w2k.c()m.ft..9-[lSlJJj;~m.ts.2.Ql.?tJ1t.!Ill?OO[IL.lJJi.tbl.Lqht::=:J:.9D.~~~ .. llt.9..nt;;
Within 45 days of the insta.llation. of the required storm water treatment measures
and prior to the issuance of an occupancy permit for the building, third-party
reviewer shall also submit to the City a certification for approval that the project's
permanent measures were constructed and installed in accordance to the approved
permit drawings. The project must" also enter into a maintenance agreement with
the City. to guarantee the ongoing maintenance of the permanent C.3 storm water
discharge compliance measures. The maintenance agreement shall be executed
prior to the first building occupancy sign-off.
BEST MANAGEMENT PRACTICES (BMP's): The applicant Is required to submit a
conceptual site grading and drainage plan that conveys site runoff to the nearest
adequate municipal storm drainage system. In order to address potential storm
Page 3 of 5
water quality impacts, the plan shall identify BMP's to be incorporated into the Storm
Water Pollution Prevention Plan (SWPPP) that will be required for the project. The
SWppp shall include permanent BMP's to be incorporated into the project to protect
storm water quality. (Resources and handouts are available 'from PWE. Specific.
reference Is made to Palo Alto's companion document to "Start at the Source",
entitled "Planning Your Land Development Project"). The elements of the PWE
approved conceptual grading and drainage plan shall be incorporated into the
building permit plans.
The developer shall require its contractor to incorporate BMP's for storm water
po)Jution prevention in all construction operations, in conformance with the SWPPP
prepared for the project. It Is unlawful to discharge any construction debris (5011,
asphalt, sawcut slurry, paint, chemicals, etc.) or other. waste materials into gutters
or storm drains .. (PAMC Chapter 16.09).
The applicant is required to paint the "No Dumping/Flows to Matadero Creek" logo In
blue color on a white background, adjacent to all storm drain Inlets. Stencils of the
logo are available from the Public Works Environmental Compliance Division, which
may be contacted at (650) 329-2598. A deposit may be required to secure the
return of the stencil. Include the instruction to paint the logos on the construction"
grading and drainage plari. Include maintenance of these logos in the Hazardous
Materials Management Plan, if such a plan is part of this project.
DRAINS FOR PARKING STRUCTURE: Any -drains within the covered floors of the
parking structures shall be connected to an 011 separator then to sanitary sewer lines.
Storm water runoff from any exposed surface without canopies need to be treated as
per C.3 requirements.
The fonowing comments are provided to assist the applicant at the building permit
phase. You can obtain various plan set details, forms and guidelines fr.om Public
Works at the City's Development Center (285 Hamilton Avenue) or on Public Works'
we bsite: tlltg~LLw.\tYjL\I-!..~:ltYQfllfll(,m"ttQ .. .orgLQ.epj;r;;Lpw..g IfJ)JITlli_J2r.UIUtfJ !"tl.~r·
Include In plans sub"mitted for a building permit:
GRADING & EXCAVATION PERMIT: Since more than 10,000 square feet of the land
area on the project site is peing disturbed, a Grading and Excavation Permit needs to
be obtained from PWE at the Development Center before the building permit can be
Issued. Refer to the Public Works' website for "Excavation and Grading Permit
Instructions." For the Grading and Excavation Permit application, various documents
are required Including a grading and drainage plan, soils report~ Interim and Final
erosion and sediment' control," storm water pollution prevention plan (SWPPP),
engineer-stamped and signed shoring plan, and a copy of the Division of
Occupational Safety and Health (DOSH) excavation permit. Refer to our website for
"Grading and Excavation Permit Application" and guidelines. Except for the soils
report and the POSH permit, Include the requlr~d documents and drawings In the
building permit set drawings. Indicate the amount of soil to be cut and filled for the
project.
;HJP.;/ I.'!'1YJ.w.dtY9..fnglocllt.Q.! .. 9JJJ1dvic:m~l.f!j0.pankLQ"Q~~I::I!YJ.e.u~it!.1~9;i
GRADING AND DRAINAGE PLAN: " The plan set must include a grading and drainage
plan prepared by a licensed professional that Includes eXisting and proposed spot
elevations and showing drainage flows to demonstrate proper drainage of the site.
Other site utllit1es may be shown on the grading plan for reference only, and should
Page 4 of 5
be so noted. No ,utility infrastructure should be shown inside the building footprint.
Installation of these other utilities will be approved as part of a subsequent Build,log
Permit application.
Site gradlngl excavation,and other site Improvements that disturb large soil areas
may only be performed during the regular construction season (from April 16
through October 15th) of each year the permit is active. The site must be stabilized
to prevent soU erosion during the wet season. The wet season· Is defined as the
period from October 15 to April 15. Methods of stabilization are to be Identified
within the Civil sheets of the improvement plans for approval.
SOILS REPORT: A detailed site-specific soil report prepared by a licensed soils or
geo,-technlcal engineer must be submitted which inCludes information on water table
and sub-grade construction issues. Measures must be undertaken to render the
basement waterproof and able to withstand .all projected hydrostatic and soil
pressures. No pumping of groundwater is allowed. In general, PWE recommends
that structures be constructed in such a way that they do not penetrate existing or
projected ground water levels.
DEWATERING: Excavation for sub-grade structures may require dewatering. PWE
only allows groundwater drawdown well' dewatering. Open pit groundwater
dewatering Is not allowed. If dewatering is required, the dewatering plan must be
submitted to Public Works at the Development Center as Street Work Perm'lt.
Dewatering is only allowed from April through October due to inadequate capacity in
our storm drain system. The geotechnical report for this site must list the highest
anticipated groundwater level. If the deepest excavation is expected to be within 3
feet of the highest anticipated groundwater level, the contractor can determine the
actual groundwater depth immediately prior to excavation by installing piezometers
or by drilling exploratory holes. Alternatively, the contractor can excavate and hope
not to hit groundwater, but if he does, he must immediately stop excavation and
submit a dewatering plan to PW.E for approval and install a drawdown well system
before he continues to' excavate. Public Works may require the water to be tested for
contaminants prior to initial discharge and at intervals during dewatering. If testing
is required, the contractor must retain an Independent testing firm to test the
discharge water for the contaminants as specified by Public Works.
BA~EMENT DRAINAGE: Due to high groundwater throughout much of the City, PWE
prohibiting the pumping and discharging of groundwater. Sub-grade drainage
systems such as perforated pipe drainage systems at the exterior of the basement
walls or under the slabs are not allowed. PWE recommends that a waterproofing
consultant be retained to desjgn and inspect the vapor barrier and waterproofing
systems for the basement.
BASEMENT SHORING: Shoring for the basement excavation, including tiebacks,
must not extend onto adjacent private property or into the City right-of-way without
having first obtained written permission from the private property owners and/or an
encroachment permit from PWE at the Development Center.
STORM WATER POLLUTION PREVENTION: The City's full--sized "Pollution Prevention
-It's Part of the Plan" sheet must be included In the plan set. Copies are available
,from pevetopment Center or on our website. Also, the applicant must provide a site
specific storm water pollution control. plan sheet in the plan set.
b tt fl.;.l Lwww . citvofpa I oalto. 0 rg.L <':1VJ.k9..~LfU§.b.Qnl\LO ocu nJ.fJJJ.ts! 2:Z:1:'
Page 5 of 5
IMPERVIOUS SURFACE AREA: Since the project will be creating or replacing 500
square feet or more of impervious surface, the applicant shall provide calculations of
the existing and proposed impervious surface. areas. The calculations need to be
filled out in the Impervious Area Worksheet for Land Developments form which is
available at the Development Center or on our website, then submitted with the
buHding permit application.
!JJJ;.r.Elbt:JY:lw.!~(~itY(lfp.qJ9.~:lI~.9~f2nJ1~jJ£k~nxJf.llebilll!~iJJoc::.! .. j.u.u}nt~/2Z_U~
WORK IN THE RIGHT-OF-WAY -If any work Is proposed In the public right-of-way,
such as sidewalk repl'acement, driveway approach, curb Inlet, storm water
connections or utility laterals, the followtng note shall be included on the Site Plan
next to the proposed work:
"Any construction within the public right-of-way must have an approved Permit ·for
Cons.truct/on In the Public Street prior to commencement of this work. TH E
PERFORMANCE OF THIS WORK IS NOT AUTHORIZED BY THE BUILDING PERMIT
ISSUANCE BUr SHOWN ON THE BUILDING PERMIT FOR INFORMATION ONLY."
LOGISTICS PLAN: The contractor must submit a logistics plan to PWE prior to
commencing work that addresses all impacts to the City's right-of-way, 'includlng,
but not limited to: pedestrian control, traffic control, truck routes, material
deliveries, contractor's parking, concrete pours, crane lifts, work hours, noise
control, dust control, storm water pollution prevention, ·contractor's contact, noticing
of affected businesses, and schedule of work. The plan will be part of the buildIng
permit submittal. .
.t}t~ll;/L.'A!..VY:M .:J;J.tY9fl.)(.~ I.~~{.l !.tJ).~f)r9b;jy:.tGH~LfjlC?JJ.~J.!lkb;t9 .. Gl:IJnmlt~!.I.?7 J..!J.
FINALIZATION OF BUILDING. PERMIT: The Public Works Inspector shall sign off the
building permit prior to the finalization of thl's permit. All offMsite improvements shall
be finished prior to this sign-off. Similarly, all as-bullts, on-site grading, drainage
and post-developments BMP's shall be completed prior to sign-off.
March 28th, 2013
City of Palo Alto
ATTACHMENT C
Department of Planning & Community Environment
250 Hamilton Avenue, 5th floor
Palo Alto, CA 94303
Re: 2755 EI Camino Real ARB Preliminary Review Project Description
To Planning Staff and ARB Members:
HAYeS
GROUP
ARCH!
TEeTS
Attached Is Hayes Group Architect's submittal package for 2755 EI Camino Real for ARB
preliminary review. The project applicant is Hayes Group Architects on behalf of Pollock
Financial Group, Inc. This package includes 8 sets of half size drawings and 8 sets of full size
drawings illustrating contextual photos, proposed site plan, floor plans, elevations, section, and
perspectives.
1. EXISTING CONDITIONS
The site is located at the corner of Oregon Expresswayl Page Mill Road and EI Camino Real. It
is currently a PF zoned surplus parking lot for the VT A (Valley Transportation Authority)
oommuters. VTA has determined that 2755 EI Camino has not been used by a significant
nu mber of VTA commuters, and as a result of a high level of disuse. VT A has declared 2755 EI
Camino to be a surplus site for sale for which the Pollock Financial Group has been chosen as
the qualified purchaser of the property.
The property abuts a four-story senior housing project on the west and a three-story
condominium project on the north. Retail buildings of one and two-story heights are situated
across Page Mill Road. A collegiate soccer playing field and a parking lot of a large-scale
commercial development sits immediately across EI Camino Real.
2. PROPOSED PROJECT
We propose to demolish and recycle,·'n accordance with Palo Alto's waste and recycling
requirements, the existing parking facll1ty and rezone the property to a Planned Community (PC)
zoning designation. A new, four-slory, 31,740 SF, commercial building with three levels of
underground parking is proposed for the 19,563 SF, corner site. A square footage analysis and
2657 Spring Street, Redwood City, CA 94063 Phone 650.365.0600 Fax 650.365.0670 thehayesgroup.com Architecture and Interiors
supporting parking. facility calculations are provided in the submittal documents. The F.A.R. for
the proposed project is 1.62/1.0.
With Stanford Research Park and the original Hewlett Packard facility up the street from the
project site, the northeastern corner of Page Mill Road s.nd EI Camino Real serves as an
entrance to Silicon Valley and to the California Avenue neighborhood of Palo Alto. As an
important gateway, the building form needs to respond to the corner.
As one approaches Page Mill from EI Camino Real, the eastern elevation draws inspiration
from 'Ihe landmark saw-tooth HP building but reinterpreted as array of vertical faces that are
slanted in plan to establish a language in the facade. Solid panels on the southeast faces shade
the fa9ade from the sun. The building engages the street corner with two-story two-sided
structural glazed glass windows with deep window shade fronting EI Camino Real and Page Mill
Road, adding light and depth to enrich the street context while also contributing to the visual
Interest of the gateway intersection. On grade, the building is recessed back at the corner to
draw an inviting connection between the sidewalk and the public plaza. Integral planters along
the street level form a building base with clear, frameless glass windows allowing visual access
into the ground floor like the AT&T building across the street.
3. D.E.E. REQUEST
Day Light Plane: A D.E.E. is requested for the upper portion of the rear stair tower that
encroaches into a 45 degree day-light-plane projected from the northern rear property line
commencing at 10 ft above grade plane. Functionally, the stair tower must extend the full four
stories of the building. Aesthetically, the top of ·the stair tower ties In with the roof plate to create
a coherent elevation along the northern and eastern bulldlng faQada.
4. PARKING & BICYCLE SPACES
'A combination of onwgrade and below grade parking facilities supply 115 parking stalls total. At
City Council study session, council endorsed a 10% parking reduction with a TOM plan. We plan
to provide a TOM plan satisfying council in exchange for a parking reduction of between 5 and
10%.
Short-term bicycle parking spaces are located near the main entrance of the building. Long-term
bicycle parking spaces are provided in a secured area in the basement parking area.
5. TRASH/RECYCLING
A trash and recycling faoility is accessible via the vehicular driveway that serves the project.
6. GREEN BUILDING STANDARD
In accordance with the oity's Green Building Ordinance, this project will comply with California·
Green Building Code (CalGreenl Tier 2) with Local Amendments. The building seeks to use bolh
conventional as well as sustainable materials, including a concrete frame, high efficiency glazing
systems, high recycled content metal skin systems, cut stone, plaster finishes, abundant day
lighting and sun-shading systems as well as an energy efficient cool roof. Electric vehicle
charging stations are proposed at the oniJrade and below grade parking garages.
We look forward to a staff review and scheduling of an ARB Preliminary hearing so that we can
proceed with the development of this project.
Please call me at (650) 365-0600 x15 if you have any questions.
Sincerely,
Ken Hayes, AlA
Principal
cc: Jeff Pollock, Pollock Financial Group, Inc.
THE
GUZZARDO
PARTNERSHIP INC.
Landscape Architects • Land Planners
181 Greenwich Street
San francisco, CA 94111
T 41 5 4334672
F 4154335003
www.tgp-lnc.com
2755 EI Camino Real
Landscape Statement of Design Intent
March 28, 2013
The landscape plan establishes a prominent landmark at the intersection of EI Camino Real and
Oregon Expressway. By incorporating contemporary materials and finishes, the landscape design
provides an urban streetscape that uni'fies the landscape and site.
The landscape plan includes an entry plaza at the buildingls lobby entrance off EI Camino Real. This
entry plaza includes a series of accent paving bands, stainless steel bollards and decorative bike
racks. These elements serve to de'fine the plaza and guide pedestrians to the building entry_ A low
planter wall with accent planting will provide a backdrop to the plaza space and likewise screen the.
parking area.
The landscape plan also includes a 12' wide public walk along Oregon Expressway and a 15' wide
public walk along EI Camino Real. Both streets include a series of street trees in tree grates. Th~
pedestrian concrete paVing, selected street tree varieties and tree grates are to be as approved by
the City of Palo Alto.
A low planter wall with accent planting is proposed at the back of public walk. The accent plant
materials incorporate a variety of color and texture for a soft edge condition between the building
and public walk.
The perimeter planting areas include screen planting. Where possible, upright plant materials are
used to provide a sense of scale at the pedestrian level. Stormwater treatment will be provided
within the north perimeter planting area as· well asthe low planter at the back of public walk. All
selected plant materials are appropriate to the specific site and microclimate conditions.
The Guzzardo Partnership, Inc.
~r~
Paul T. Le'ttieri, A.S.LA.
Principal
California Registered Landscape Architect #1918
~ v
CITY 0 F
L
ALT
3 Architectural Review Board
Staff Report
Agenda Date: May 2, 2013
To: Architectural Review Board
From:
Subject:
Elena Lee
Senior Planner
Department: Planning and
Community Environment
180 EI Camino Real [12PLN-00064]: Request by Fergus, Garber, Young
Architects, on behalf of the Leland Stanford Junior University, for a Minor
Architectural Review of fa9ade improvements and signage for a commercial
recreation use for Soulcyc1e at the Stanford Shopping Center. Zone District:
CC (Community Commercial). Enyironmental Assessment: Exempt from the
provisions of CEQ A, 15301 (Existing Facilities).
RECOMMENDATION
Staff recommends that the Architectural Review Board (ARB) recommend the Director of Planning
and Community Environment approve the proposed project based upon the Architectural Review
Findings (Attachment A) and conditions of approval (Attachment B) attached to the staff report.
PROJECT DESCRIPTION
The project is a fa9ade remodel of an existing one story tenant space (plus a partial mezzanine) and
the installation of signage to establish a commercial recreation use, "SouICycle" at the eastern
portion of the Stanford Shopping Center. The storefront is approximately 24 feet 1 Y2 inches in
length and faces El Camino Real across a surface parking lot. The vacant tenant space was most
recently occupied by Hlaska, a retail tenant. Adjacent stores are the "Pink Berry" store to the right
and "The Body Shop" to the left. This fa9ade remodel is presented to the ARB for its review and
recommendation because significant changes are proposed for a substantial frontage along El
Camino Real and the proposed signage, although consistent with the City's sign ordinance, is not
consistent with the Stanford Shopping Center Master Sign Program. Associated with this
Architectural Review application is a request for a Conditional Use Permit. The proposed use is
considered commercial recreation, which may only be approved via a conditional use permit in the
Community Commercial (CC) zoning district. The proposed use is compatible with the shopping
center and adequate parking is provided.
DISCUSSION
Fas-ade Improvements
The project would involve the removal of an existing awning and storefront system and refinishing
of the remainder of the fa9ade. The proposed elevation would consist of an approximately 9~foot tall
glass and white aluminum frame store front system, with a bi-part sliding door system having fixed
sidelights. On either side of the sliding door system would be display windows that measure 9 feet
Page 1
tall by 5 feet 1 Yz inches wide. Directly above these windows, a white wood frame and aluminum
header would be installed. The upper part of the storefront is proposed to be finished with plaster.
The height of the fa9ade is being increased by one foot, as measured to the top of the taller parapet.
In the center of the new plaster fa9ade, an approximately 13 feet tall by 20 feet wide plaster finished
plywood box is proposed to be mounted. The additional plywood fa9ade is proposed to be
approximately 6 inches in depth and would be illuminated by a perimeter cove with continuous LED
lighting. All of the plaster is proposed to be painted a soft white (RAL #9003). A 3/4 inch aluminum
reveal and top cap are proposed to finish the edges. The proposed new storefront finishes reflect a
limited color palette. The majority of the fa9ade would be painted white. Accent colors would be
provided by the gray wall sign and white, yellow and gray vinyl graphics in the storefront.
Although the proposed storefront is significantly more streamlined in appearance from adjacent
storefronts, its proportions are consistent with and do not detract from the neighboring tenants. A
color and material sample board will be provided at the ARB hearing.
Signs
The signage proposal includes one primary wall sign and window signage. The wall sign would be
located at the top of the building and would consist of cutout letters on the additional plywood
fa9ade. The wall sign would measure 1 foot 6 inches in height and 12 feet 'l4 inch in length for a
total of 18.03 square feet. The sign would be externally illuminated with concealed LED lighting at
the base of the sign, directly in front of the recessed plywood panel that forms the body of the sign
letters. The cutout letters would have depth of 1 foot 3/8 inches and would be a cool gray color
(Pantone #11 C).
The applicant also proposes additional vinyl window graphics and signage. They would consist of a
17.5-square foot yellow and gray bicycle wheel on the right, a white band extending along the entire
bottom of the store front and text covering a 2-square foot area on the far left stating, in dark gray
letters, "SOlTLCYCLE".
The Stanford Shopping Center is subject to both the City'S Sign Ordinance and a master sign
program. While the signs conform to the City's Sign Ordinance in terms of maximum size, they
would not conform to the Center's master sign program. The program stipulates only one wall sign
per storefront and limits the letter height to 10 inches. The proposed letter height would be 18 inches,
exceeding the maximum height by 8 inches. The master sign program also prohibits window signs
unless they are safety graphics. The shopping center management has approved of the proposed
signage. Signage that is compliant with the City's Sign Ordinance but not the master sign program
can be approved if reconunended by the Architectural Review Board. There have now been several
signs, approved through the ARB process, that do not meet the master sign program. Recent
shopping center sign approvals recommended by the ARB include signs with letter heights of
approximately 16 inches, and storefronts having more than one sign per storefront.
Staff is concerned about the location of the proposed wall sign relative to the heights of the
adjacent tenant signage. As illustrated on page A240 of the plan set,the tenants along this
frontage have various signs at different heights. Staff would recommend that the proposed wall
sign be lowered so that it is more in line with the adjacent signage, and has placed a draft
Page 2
condition reflecting staff recommendation (condition of approval #6) for ARB consideration of
the project's compatibility with recent ARB approvals.
ENVIRONMENTAL REVIEW
The project would be an alteration to an existing facility and new construction not exceeding
10,000 square feet qualifying for a Class 3 Categorical Exemption per section 15301 of the
California Environmental Quality Act.
ATTACHMENTS
A. Architectural Review Findings
B. Draft Conditions of Approval
C. Project Plans (Board members only)
COURTESY COPIES
Fergus, Garber, Young
Simon Property Group
Prepared by: Elena Lee, Senior Planner
Reviewed by: Amy French, AICP, Chief Planning Official
Page 3
ATTACHMENT A
FINDINGS FOR APPROVAL
ARCHITECTURAL REVIEW BOARD STANDARDS FOR REVIEW
180 El Camino Real, Soul cycle
File No. 13PLN-00064
The design and architecture of the proposed improvements, as conditioned, furthers the goals and
purposes of the ARB ordinances as it complies with the Architectural Review findings, as
required in Chapter 18.76.020 of the PAMC.
1) The design is consistent and compatible with the applicable elements of the city's
Comprehensive Plan, particularly: Policy L-18: Encourage the upgrading and
revitalization of selected Centers in a manner that is compatible with the character of
surrounding neighborhoods; Policy L-26: Maintain Stanford Shopping Center as one of
the Bay Area's premiere regional shopping centers. Encourage any new development at
the center to occur through infill, including development on existing surface parking lots;
and Policy B-22: Work with Stanford University to ensure that the Stanford Shopping
Center is sustained as a distinctive, competitive, high quality regional shopping center.
2) The design is compatible with the immediate environment of the site, namely, with the
architecture of other storefronts within the Stanford Shopping Center.
3) The design is appropriate to the function of the project in that it accommodates a retail
use while encouraging the pedestrian attributes of the mall.
4) In·areas considered by the Board as having a unified design character, the design is
compatible with such character, in that the remodeled storefront will be consistent with
other recently remodeled storefronts within the mall.
6) The design is compatible with approved improvements both on and off the site; both with
the newly designed storefronts and original storefronts still in place in the mall.
12) The materials, textures, colors and details of construction and plant materials are an
appropriate expression to the design and function and whether the same are compatible
with the adjacent and neighboring structures, landscape elements and functions in that the
materials are of high quality and appropriately express the use of the space. The space
incorporates similar details and colors of the surrounding spaces while still maintaining a
unique design.
ARB standards #5, 8-11 and 13-15 are not applicable to the project.
ATTACHMENT B
CONDITIONS OF APPROVAL
180 EI Camino Real (Soulcycle)/File No. 13PLN-00064
PLANNING DIVISION
1. The project shall be implemented and shown on the plans dated received April 24, 2013
on file with the City of Palo Alto Planning Division except as modified by these approval
conditions.
2. A copy of the ARB approval letter shall be printed on the plans submitted for building
permits.
3. Construction activities and all noise producing equipment shall comply with Chapter 9.10
(Noise) of the Palo Alto Municipal Code.
4. During construction, the site shall be kept clear of debris on a daily basis.
5. All landscaping located around the building shall be protected and maintained.
6. The wall sign shall be lowered so it is better aligned with the adjacent tenant signs. Cycle
layout appears to leave inadequate aisle space beweent the two exits.
FIRE DEPARTMENT
7. Cycle layout appears to leave inadequate aisle space beweent the two exits. Applicant
should verify that Building Inspection Services does not view this as an, ,accessibility or
egress violation. ' .
UTILITIES ELECTRICAL ENGINEERING
8. The applicant shall comply with all the Electric Utility Engineering Department service
requirements noted during plan review.
9. Applicant/Developer must notify Utilities Engineering (Electric) if the proposed
renovation/change of use has any impact on the existing electrical service size, voltage,
or location. If there are any changes, the Utilities will provide comments and/or
conditions along with any applicable fees and cost estimate.
UTILITIES WATER, GAS, WASTEWATER
10. This space does not currently have separate water and gas meters. Separate metering of
this space will require the applicant to submit improvement plans for utility construction
and a completed water-gas-wastewater service connection application -load sheet for
City of Palo Alto Utilities. The plans must show the location of all the new meters and
underground mains connected to the meters including backflow preventers.
11. The applicant shall be responsible for installing and upgrading the existing utility mains
and/or services as necessary to handle anticipated peak loads. This responsibility includes
all costs associated with the design and construction for the installation/upgrade of the
utility mains and/or services.
12. An approved reduced pressure principle assembly (RPP A backflow preventer device) is
required for all existing and new water connections from Palo Alto Utilities to comply
with requirements of Cali fomi a administrative code, title 17, sections 7583 through 7605
inclusive. The RPP A shall be installed on the owner's property and directly behind the
water meter within 5 feet of the property line. RPP A's for domestic service shall be lead
free. Show the location of the RPP A on the plans.
13. Utility vaults, transformers, utility cabinets, concrete bases, or other structures can not be
placed over existing water, gas or wastewater mains/services Trees may not be planted
within 10 feet of existing water, gas or wastewater mains/services or meters: New water,
gas or wastewater services/meters nlay not be installed within 10' or existing trees.
Maintain 10' between new trees and new water, gas and wastewater
services/mains/meters.